pert - free pm study · pert calculations for the project term formula used pert value sum of pert...

2
Term Formula Used PERT Value (expected duration) (Pessimistic+ 4*(Most Likely) + Optimistic) 6 Standard Deviation (Sigma) Pessimistic Optimistic 6 Variance (Standard Deviation) 2 PERT Calculations for each task

Upload: vuongminh

Post on 28-Sep-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PERT - Free PM Study · PERT Calculations for the project Term Formula Used PERT Value Sum of PERT values of individual tasks Standard Deviation It is not correct to add standard

Term Formula Used

PERT Value

(expected duration)

(Pessimistic+ 4*(Most Likely) + Optimistic)

6

Standard Deviation (Sigma) Pessimistic – Optimistic

6

Variance (Standard Deviation)2

PERT Calculations for each task

Page 2: PERT - Free PM Study · PERT Calculations for the project Term Formula Used PERT Value Sum of PERT values of individual tasks Standard Deviation It is not correct to add standard

PERT Calculations for the project

Term Formula Used

PERT Value Sum of PERT values of individual tasks

Standard Deviation It is not correct to add standard deviations.

Thus, use sum of variances of all the tasks

Variance Sum of variances of all the tasks

To find duration and standard deviation for a project, you add PERT estimates for each activity on the critical path. Since you cannot add standard deviations, you must calculate variance, add the variances, and take the square root to obtain the project standard deviation.