pgp1 om1 app
TRANSCRIPT
1
11/20/2010 PGP1-OM 1-S Venkat 1
Dr. S.Venkataramanaiah (S Venkat)OM & QT Area
IIM IndorePrabhandh Shikhar
Rau-Pithampur RoadIndore- 453 331
Email: [email protected]
11/20/2010 PGP1-OM 1-S Venkat 2
Aggregate Planning
2
11/20/2010 PGP1-OM 1-S Venkat 3
To understand
• Importance of Business Plan
• Planning Activities and their relation
• Planning for Sales and Operations
• The Aggregate Operations Plan
• Approaches for AP- Chase and Level Strategies
OBJECTIVES
11/20/2010 PGP1-OM 1-S Venkat 4
Business Plan- Importance § BP strategic in nature and addresses the following:§ Should we meet the projected demand entirely or a
portion of the projected demand?§ What are the implications of this decision on the overall
competitive scenario and the firm’s standing in the market?
§ How is this likely to affect the operating system and planning in other functional areas of the business such as marketing and finance?
§ What resources should we commit to meet the chosen demand during the planning horizon?
§ APP seeks to translate business plans to operational decisions
3
11/20/2010 PGP1-OM 1-S Venkat 5
Why APP?• Demand fluctuations• Capacity fluctuations • Difficulty level in altering production or output rates
– Production systems are complex and varying the rate of production requires prior planning and co-ordination with supplier and distributor
• Benefits of multi-period planning
Aggregate Planning is done in an organisation to match the demand with the supply on a period-by-period basis in a cost effective manner
11/20/2010 PGP1-OM 1-S Venkat 6
The Aggregate Plan• Main purpose is to specify optimal
combination of– Production rate (units completed per unit of
time)– Workforce level (number of workers)– Inventory on hand (inventory carried from
period to period)• Product group or broad category
(Aggregation)• This planning is done over an intermediate-
range planning period of 6 to 18 months
4
11/20/2010 PGP1-OM 1-S Venkat 7
Aggregate Demand- Components
Time
AGGREGATE DEMANDFor PSEUDO PRODUCT
ITEM 3 DEMANDITEM 2 DEMAND
ITEM 1 DEMAND
11/20/2010 PGP1-OM 1-S Venkat 8
Production Planning System- Inputs
Planning for
production
External capacity
Competitors’behavior
Raw material availability
Market demand
Economic conditions
Currentphysical capacity
Current workforce
Inventory levels
Activities required for production
External to firm
Internal to firm
5
11/20/2010 PGP1-OM 1-S Venkat 9
ForecastingAggregateProduction
Planning
MasterProductionScheduling
Materials PlanCapacity Plan
Actual Production
Market
Labour & Resources Vendors
Material Inflow
Order Inflow
Resource availability
MPS Linkages with APP & Forecasting
11/20/2010 PGP1-OM 1-S Venkat 10
Business Plan
Marketing Plan Financial Plan
Production Plan(rough cut capacity)
Master Production Schedule
Materials Requirement
Plan
Capacity Requirement
Plan
Detailed Scheduling
Shop Floor Control
Level 1
Level 2
Level 3
Hierarchical Approach to Planning
6
11/20/2010 PGP1-OM 1-S Venkat 11
APP Decision Variables: An illustration
• The decisions involve – Amount of resources (productive capacity and
labour hours) to be committed – Rate at which goods and services needs to be
produced during a period – Inventory to be carried forward from one
period to the next
11/20/2010 PGP1-OM 1-S Venkat 12
APP Decision Variables: An illustration
• An example from Garment Manufacturing– Produce at the rate of 9000 metres of cloth everyday
during the months of January to March – Increase it to 11,000 metres during April to August – Change the production rate to 10,000 metres during
September to December – Carry 10% of monthly production as inventory during
the first 9 months of production. – Work on a one-shift basis throughout the year with 20%
over time during July to October
7
11/20/2010 PGP1-OM 1-S Venkat 13
Aggregate Units for Capacity-Examples
Sl. No Product Aggregate Unit of capacity1 Acetic Acid Metric tonnes2 Data Entry Systems Numbers3 Mini computer Value (ex-factory) in Rs.4 Printed Circuit Board Square Metres5 Alloy Iron Castings Metric tonnes6 Cement Metric tonnes
11/20/2010 PGP1-OM 1-S Venkat 14
Aggregate Planning Framework
Targeted Demandto be fulfilled
Arriving at effectivePeriod-by-period
Demand to be met
Arriving at Period-by-PeriodSupply Schedules
-Actual period-by-period
Supply Schedules
ForecastingAlternatives for
Modifying demand
Alternatives forModifying supply
8
11/20/2010 PGP1-OM 1-S Venkat 15
Alternatives for managing demand
• Reservation of Capacity• Influencing Demand
– Special Tariffs– Differential Discount Structures– Limited period special offers
11/20/2010 PGP1-OM 1-S Venkat 16
Alternatives for Managing Supply
• Inventory Based Alternatives– Stock out, Backordering/Backlogging– Carrying Inventory
• Capacity Adjustment Alternatives– Hiring/Lay-off of workers– Varying shifts– Varying Working Hours (OT,UT)
• Capacity Augmentation Alternatives– Sub-contracting/Outsourcing– De-bottlenecking– Addition of new capacity
9
11/20/2010 PGP1-OM 1-S Venkat 17
APP-Example
Any Observations?
0
200
400
600
800
1000
1200
1400
1 2 3 4 5 6 7 8 9 10 11 12
Total-lbr hrs Total-m/c hrs
11/20/2010 PGP1-OM 1-S Venkat 18
APP-Example
Any Observations?
0
2000
4000
6000
8000
10000
12000
1 2 3 4 5 6 7 8 9 10 11 12
Cumulative labr hrs Cumulative m/c hrs
10
11/20/2010 PGP1-OM 1-S Venkat 19
APP-Example
Any Observations?
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
1 2 3 4 5 6 7 8 9 10 11 12
Total-lbr hrs Total-m/c hrs Total-Fin Rs
11/20/2010 PGP1-OM 1-S Venkat 20
APP-Example
Any Observations?
0
5000
10000
15000
20000
25000
30000
35000
1 2 3 4 5 6 7 8 9 10 11 12
Cumulative labr hrsCumulative m/c hrsCumulative fin res Rs
11
11/20/2010 PGP1-OM 1-S Venkat 21
Balancing Aggregate Demandand Aggregate Production Capacity
0
2000
4000
6000
8000
10000
Jan Feb Mar Apr May Jun
45005500
7000
10000
8000
6000
0
2000
4000
6000
8000
10000
Jan Feb Mar Apr May Jun
4500 4000
90008000
4000
6000
Suppose the figure to the right represents forecast demand in units
Now suppose this lower figure represents the aggregate capacity of the company to meet demand
up
What we want to do is balance the production rate, workforce levels, and inventory to make these figures match up
Avg demand= 41000/6
Avg Capacity= 35500/6; what is the gap?
11/20/2010 PGP1-OM 1-S Venkat 22
APP-Demand and Capacity
Any Observations?
0
2000
4000
6000
8000
10000
12000
1 2 3 4 5 6
Demand Cap
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
1 2 3 4 5 6
Cum Dmd
Cum Cap
12
11/20/2010 PGP1-OM 1-S Venkat 23
APP Examples: Unit Demand and Cost Data
Materials Rs5/unitHolding costs Rs1/unit per mo.Marginal cost of stockout Rs1.25/unit per mo.Hiring and training cost Rs200/workerLayoff costs Rs250/workerLabor hours required 0.15 hrs/unitStraight time labor cost Rs8/hourBeginning inventory 250 unitsProductive hours/worker/day 7.25Paid straight hrs/day 8
Suppose we have the following unit demand and cost information:
Month Jan Feb Mar Apr May Jun Total
Demand 4500 5500 7000 10000 8000 6000 41000
11/20/2010 PGP1-OM 1-S Venkat 24
Jan Feb Mar Apr May JunDays/mo 22 19 21 21 22 20Hrs/worker/mo 159.5 137.75 152.25 152.25 159.5 145Units/worker 1063.33 918.33 1015 1015 1063.33 966.67Rs/worker 1,408 1,216 1,344 1,344 1,408 1,280
Productive hours/worker/day 7.25Paid straight hrs/day 8
Given the demand and cost information below, whatare the aggregate hours/worker/month, units/worker, and Rs/worker?
7.25x22
7.25/0.15=48.33 & 48.33x22=1063.3322x8hrsxRs8=Rs1408
Cut-and-Try Example: Determining Straight Labor Costs and Output
Month Jan Feb Mar Apr May Jun Total
Demand 4500 5500 7000 10000 8000 6000 41000
13
11/20/2010 PGP1-OM 1-S Venkat 25
Chase Strategy(Hiring & Firing to meet demand)
JanDays/mo 22Hrs/worker/mo 159.5Units/worker 1,063.33Rs/worker 1,408
JanDemand 4,500Beg. inv. 250Net req. 4,250Req. workers 3.997HiredFired 3Workforce 4Ending inventory 0
Lets assume our current workforce is 7 workers.
First, calculate net requirements for production, or 4500-250=4250 units
Then, calculate number of workers needed to produce the net requirements, or 4250/1063.33=3.997 or 4 workers
Finally, determine the number of workers to hire/fire. In this case we only need 4 workers, we have 7, so 3 can be fired.
11/20/2010 PGP1-OM 1-S Venkat 26
Jan Feb Mar Apr May JunDays/mo 22 19 21 21 22 20Hrs/worker/mo 159.5 137.75 152.25 152.25 159.5 145Units/worker 1,063 918 1,015 1,015 1,063 967Rs/worker 1,408 1,216 1,344 1,344 1,408 1,280
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250Net req. 4,250 5,500 7,000 10,000 8,000 6,000Req. workers 3.997 5.989 6.897 9.852 7.524 6.207Hired 2 1 3Fired 3 2 1Workforce 4 6 7 10 8 7Ending inventory 0 0 0 0 0 0
Below are the complete calculations for the remaining months in the six month planning horizon
14
11/20/2010 PGP1-OM 1-S Venkat 27
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250Net req. 4,250 5,500 7,000 10,000 8,000 6,000Req. workers 3.997 5.989 6.897 9.852 7.524 6.207Hired 2 1 3Fired 3 2 1Workforce 4 6 7 10 8 7Ending inventory 0 0 0 0 0 0
Jan Feb Mar Apr May Jun CostsMaterial 21,250.00 27,500.00 35,000.00 50,000.00 40,000.00 30,000.00 203,750.00Labor 5,627.59 7,282.76 9,268.97 13,241.38 10,593.10 7,944.83 53,958.62Hiring cost 400.00 200.00 600.00 1,200.00Firing cost 750.00 500.00 250.00 1,500.00
260,408.62
Below are the complete calculations for the remaining months in the six month planning horizon with the other costs included
11/20/2010 PGP1-OM 1-S Venkat 28
Level Workforce Strategy (Surplus and Shortage Allowed)
JanDemand 4,500Beg. inv. 250Net req. 4,250Workers 6Production 6,380Ending inventory 2,130Surplus 2,130Shortage
Lets take the same problem as before but this time use the Level Workforce strategy
This time we will seek to use a workforce level of 6 workers
15
11/20/2010 PGP1-OM 1-S Venkat 29
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250 2,130 2,140 1,230 -2,680 -1,300Net req. 4,250 3,370 4,860 8,770 10,680 7,300Workers 6 6 6 6 6 6Production 6,380 5,510 6,090 6,090 6,380 5,800Ending inventory 2,130 2,140 1,230 -2,680 -1,300 -1,500Surplus 2,130 2,140 1,230Shortage 2,680 1,300 1,500
Note, if we recalculate this sheet with 7 workers we would have a surplus
Below are the complete calculations for the remaining months in the six month planning horizon
11/20/2010 PGP1-OM 1-S Venkat 30
Jan Feb Mar Apr May Jun4,500 5,500 7,000 10,000 8,000 6,000
250 2,130 10 -910 -3,910 -1,6204,250 3,370 4,860 8,770 10,680 7,300
6 6 6 6 6 66,380 5,510 6,090 6,090 6,380 5,8002,130 2,140 1,230 -2,680 -1,300 -1,5002,130 2,140 1,230
2,680 1,300 1,500
Jan Feb Mar Apr May Jun8,448.00 7,296.00 8,064.00 8,064.00 8,448.00 7,680.00 48,000.00
31,900.00 27,550.00 30,450.00 30,450.00 31,900.00 29,000.00 181,250.002,130.00 2,140.00 1,230.00 5,500.00
3,350.00 1,625.00 1,875.00 6,850.00
241,600.00
Below are the complete calculations for the remaining months in the six month planning horizon with the other costs included
Note:Total costs under this strategy are less than Chase at Rs260.408.62
LaborMaterialStorageStockout
16
11/20/2010 PGP1-OM 1-S Venkat 31
Some Observations
• Which strategy is better and why?
• What is the impact of cost structure and level of workforce on total cost?
LaborMaterialStorageStockout
48,000.00181,250.005,500.006,850.00
241,600.00
LaborMaterialHiringFiring
53,958.62203,750.00 1,200.001,500.00
260,408.62Chase Strg
11/20/2010 PGP1-OM 1-S Venkat 32
APP- Alternatives
Description of the alternative Costs
Reservation of capacity Planning and Scheduling costs
Influencing Demand Marketing oriented costs
Inventory based alternatives(a) Build Inventory Inventory holding costs(b) Backlog/Backorder/Shortage Shortage/Loss of goodwill costsCapacity adjustment alternatives(a) Over Time/Under Time OT premium, Lost productivity(b) Vary no. of shifts Shift change costs(c) Hire/Lay-off workers Training/Hiring costs, Morale issuesCapacity augmentation alternatives(a) Sub-contract/Outsource Transaction costs for sub-contract(b) De-bottleneck Annualised de-bottlenecking cost(c) Add new capacity Annualised cost of new capacity
Alternatives for managing demand
Alternatives for managing supply
17
11/20/2010 PGP1-OM 1-S Venkat 33
APP-Generic strategies
APP Strategy APP alternatives applicable Key featuresInventory based alternatives
(a) Build Inventory
(b) Backlog/Backorder/ShortageCapacity adjustment alternatives(a) Over Time/Under Time(b) Vary no. of shifts(c) Hire/Lay-off workersCapacity augmentation alternatives(a) Sub-contract/Outsource(b) De-bottleneck
No inventory carried from one period to another; Made-to-order and project environments; Several service systems
Inventory as the critical link between the periods; Made-to-stock environments; Products with low risks of obsolescence
Chase Strategy
Level Strategy
§ In level strategy, the emphasis is not to disturb the existing production rate at all § In chase strategy, no effort is made to carry inventory from one period
to another; the supply – demand mismatch is addressed during each period by employing a variety of capacity related alternatives
11/20/2010 PGP1-OM 1-S Venkat 34
Key Strategies for Meeting Demand
• Chase- hiring and layoff – need easily trained pool of workers-match bet production and order
• Stable workforce-variable work hours-vary output by flexible work schedules or OT
• Level – maintain constant workforce with constant output, variations are addressed using inventories
• Pure and mixed strategies
• Subcontracting
18
11/20/2010 PGP1-OM 1-S Venkat 35
Relevant cost components• From Agg production plan- production cost,
inventory cost, backorder cost, cost due to variations in production
• Basic production cost-Fixed and variable cost includes direct and indirect material and labour cost, OT cost etc
• Costs associated with changes in production rate- training, hiring and firing, subcontracting etc
• Inventory holding cost- cost of capital tied up, storing, insurance, taxes, spoilage and obsolescence
• Backordering cost-hard to measure- cost of follow up, loss of goodwill, loss of sales revenue etc
11/20/2010 PGP1-OM 1-S Venkat 36
APP-DensePack Inc Problem Densepack is to plan workforce and production levels for the six-month period January to June. The firm produces a line of disk drivesfor mainframe computers that are plug compatible with severalcomputers produced by major manufacturers. Forecast demands overthe next six months for a particular line of drives produced in theXYZ plant are 1280, 640, 900, 1200, 2000 and 1400. Numbers ofworking days are respectively 20, 24, 18, 26, 22, and 15. There arecurrently (end of December) 300 workers employed in theDensepack plant. Ending inventory in December is expected to be500 units, and the firm would like to have 600 units on hand at theend of June.
19
11/20/2010 PGP1-OM 1-S Venkat 37
APP-DensePack Inc Problem
Cost of hiring one worker = Rs. 500/-, cost of firing one worker =Rs. 1000/- and cost of holding one unit of inventory for one month= Rs. 80/-. The other costs of production in regular time, over timeand subcontract may be ignored.
In the past, the plant manager observed that over 22 workingdays, with the workforce level constant at 76 workers, the firmproduced 245 disk drives.
Solve the APP problem by Linear Programming.
11/20/2010 PGP1-OM 1-S Venkat 38
20
11/20/2010 PGP1-OM 1-S Venkat 39
11/20/2010 PGP1-OM 1-S Venkat 40
21
11/20/2010 PGP1-OM 1-S Venkat 41
11/20/2010 PGP1-OM 1-S Venkat 42
22
11/20/2010 PGP1-OM 1-S Venkat 43
11/20/2010 PGP1-OM 1-S Venkat 44
LINGO model Solution
Global optimal solution found at step: 13
Objective value: 379286.4
Workforce level
WT(0) 300.00
WT(T1) 273.0189
WT(T2) 273.0189
WT(T3) 273.0189
WT(T4) 273.0189
WT(T5) 737.8889
WT(T6) 737.8889
Production levelPT(T1) 800.00PT(T2) 960.00 PT(T3) 720.00PT(T4) 1040.00 PT(T5) 2378.378 PT(T6) 1621.622 Inventory levelIT(T1) 20.00 IT(T2) 340.00IT(T3) 160.00 IT(T4) 0.00 18.39849IT(T5) 378.37 IT(T6) 600.00
HT( T5) 464.8700 FT( T1) 26.98109
23
11/20/2010 PGP1-OM 1-S Venkat 45
Excel Model Solution
Any Observations?
Hiring cost layoff cost Inv cost total cost % Change Int Invent Final InvtBase case 232435.015 26981.0934 119870.2703 379286.38 ---- 500 600Case 1 227089.5131 34737.3129 119658.9685 381485.79 0.58 600 500Case 2 223211.4033 26981.0934 107113.5135 357306.01 -5.80 500 500Case 3 236313.1245 34737.3124 132415.7249 403466.16 6.38 600 600Case 4 68415.12458 37702.6095 275093.3331 381211.07 0.51 0 0Case 5 229762.2639 30859.2029 119764.6192 380386.09 0.29 550 550
11/20/2010 PGP1-OM 1-S Venkat 46
A SIMPLE EXAMPLE OF AGGREGATIONCAPACITY
MACHINE HRS. AVAILABLE/WK.
INDEX STD. M/C. HRS. AVAILABLE/WK.
1 36 0.5 18
2 54 1 (STANDARD) 54
3 80 0.8 64
4 33.5 0.6 20
156
24
11/20/2010 PGP1-OM 1-S Venkat 47
NEXT WEEK’S FORECASTED DEMAND
JOB A B C D E TOTAL
1. UNITS DEMANDED 300 210 240 1800 400
2. PRODN. RATE/SMH 6 7 6 30 25
3. DEMAND IN SMH = (1) / (2)
50 30 40 60 16 196
CAPACITY SHORTFALL 196 – 156 = 40 S.M.H.
11/20/2010 PGP1-OM 1-S Venkat 48
APP-Conclusions• Aggregate Planning (AP) serves to translate the business
plans into operational decisions• The decisions include
– amount of resources (productive capacity and labour hours) to commit, – rate at which to produce – inventory to be carried forward from one period to the next
• AP is done to match the demand and the available capacity on a period-by-period using a set of alternatives available to modify demand and/or the supply
• Alternatives for modifying demand include reservation of capacity and methods of influencing (changing) the demand during a period
• Alternatives for modifying the supply include inventory variations, capacity adjustment and capacity augmentation
25
11/20/2010 PGP1-OM 1-S Venkat 49
• AP exercise employs the two generic strategies; chase and level production.
• Chase strategy is often found to be expensive and hard to implement in organisations
• In reality a mixed strategy using a combination of alternatives is employed in an AP exercise. It uses a variety of alternatives for modifying supply.
• The structure of a transportation model lends itself to studying the AP problem
• Linear programming can also be used to model the AP problem
• MPS involves dis-aggregation of product information and ensuring the required capacity and material are available as per the plan
APP-Conclusions