CROSSTOWN LRTCLC Pharmacy – KennedyMeeting #3July 25, 2017

Page 2: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

2

Agenda

• East At-Grade (Pharmacy to Rosemount) Update

• Kennedy Station Update

Page 3: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

3

What Are We Building

• 15 underground stations and 10 surface stops – 9 km below ground and 10 km above ground

• A maintenance and storage facility

• A 19-kilometre route separated from regular traffic

• Transit communications system

• Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station

Page 4: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

4

East At-Grade (Pharmacy to Rosemount) Update

July 2017

• Preparatory works continue

– Tree Protection and Removals

• Median Removals underway

Summer 2017

• Utility Relocations

• Road Work

Page 5: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

5

Kennedy Station Concept

Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Page 6: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

6

How we’re building: Interchange Stations

• Eglinton, Cedarvale & Kennedy are “Interchange Stations”

• Interchange stations connect to the subway, and at Kennedy Station with GO Transit, allowing riders to seamlessly transfer between systems

• Interchange stations will be built using the Cut and Cover method.

Kennedy Station

Page 7: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

7

2017

• Dry utility relocations (Telecommunications)

• Toronto Hydro relocations

• Wet utility relocations (Water, Sanitary Sewer, Storm Sewer)

• Road works around TTC’s Kennedy Station

• Demolition of Existing TTC North Entrance

• Eglinton Ave road widening

• Start of support of excavation activities

Additional Notes• Nearby residents and businesses can expect noise and vibration in the area

caused by a pile drill, crane, loaders, trucks and other construction equipment, as well as dust from drilling activity and debris removal.

• In general, haul routes to and from the site will travel along Kennedy Road to and from Highway 401.

What to expect in 2017: Kennedy Station

Page 8: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

8

Kennedy Station Update

• Preparatory works are underway or complete

• Enbridge Gas Line Replacements nearing completion

• Parking reductions are underway. Parking lots at Kennedy Station are being used to support construction activities.

• Pending permits, the existing bus loop and passenger platform will be relocated to the South Parking Lot to allow for construction of the new bus loop and platform. Work is scheduled to begin in summer 2017.

• Pending permits, the North Entrance will be closed and demolished to make room for the new Main Entrance. Work is scheduled to begin in summer 2017.

• Pending permits, the existing passenger tunnel will be closed to allow for Support of Excavation to be installed. A new pedestrian tunnel will be constructed as part of the new Kennedy Station infrastructure. Work is scheduled to begin in summer 2017.

Page 9: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

9

Kennedy Station Update

July 2017

• Preparatory works continue

– Installation of the construction compound

– Hydro relocations between Kennedy and Birchmount underway

– Enbridge work continues

Summer 2017

• Utility Relocations – Telecommunications

– THESL at Kennedy Station

• Road Work

Page 10: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

10

What to Expect in 2017

Stage 1: Summer 2017

Page 11: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

11

What to Expect in 2017

Stage 1B: Summer 2017

Page 12: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

12

What to Expect in 2017

Stage 2: Summer/Fall 2017

Page 13: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

13

What to Expect in 2017

Stage 3: Fall 2017/Winter 2018

Page 14: Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017

14

GO Transit Improvements Update

• A new west platform

• Rebuild entire existing east platform

• Build new entrance for Go Station