physical unit operation-screening, grit removal,equalization

49
TOPIC- Physical Unit Operation- Screening, Grit Removal, Equalization NAME ENROLL NO. PATEL JIMI 131100106029 PATEL MILIND 131100106035 PATEL VIRAJ 131100106040 PATEL YASH 131100106042 SHAH ASHIT 131100106051 GUIDED BY: Prof. MANALI Prof. UTTEJANA A. CHAUDHARY

Upload: yash-patel

Post on 12-Apr-2017

587 views

Category:

Engineering


8 download

TRANSCRIPT

Page 1: Physical Unit Operation-Screening, Grit Removal,Equalization

TOPIC- Physical Unit Operation-Screening, Grit Removal,

EqualizationNAME ENROLL NO.

PATEL JIMI 131100106029

PATEL MILIND 131100106035

PATEL VIRAJ 131100106040

PATEL YASH 131100106042

SHAH ASHIT 131100106051

GUIDED BY: Prof. MANALI Prof. UTTEJANA A. CHAUDHARY

Page 2: Physical Unit Operation-Screening, Grit Removal,Equalization

Physical Unit Operations - Screening

Page 3: Physical Unit Operation-Screening, Grit Removal,Equalization

Screening• Screening is the first Unit Operation employed in

wastewater treatment. • Screening is necessary to retain floating matter

and coarse solids as pieces of cloths garbage so as to protect pumps and other units from clogging.

• Thus retained material at screens is called as screenings.

• Screens may consist of vertical or inclined bars (bar racks or bar screens), wire mesh or perforated plates having either circular or rectangular openings.

Page 4: Physical Unit Operation-Screening, Grit Removal,Equalization
Page 5: Physical Unit Operation-Screening, Grit Removal,Equalization
Page 6: Physical Unit Operation-Screening, Grit Removal,Equalization

Design Criteria for Bar Screens

( Bar Racks)Design Parameters Manually Cleaned Mechanically Cleaned

1. Velocity through Rack ( m/s)

0.3- 0.6 0.6- 1.0

2. Bar SizeWidth (mm)Depth (mm)

4-825-50

8-1050-75

3. Spacing Between Bars (mm)

25-75 10-50

4. Slope from Horizontal Degrees

45-60 75-85

5. Allowable head loss in clogged condition mm

150 150

Page 7: Physical Unit Operation-Screening, Grit Removal,Equalization

Head Loss through the bar rack is calculated from the following formulae.• HL= • = 0.0728 (V2- v2)• HL= Hv. Sinθ………………..(2)• Where, • HL= Head Loss through bar rack in meters• V= Velocity through Rack, m/s• v= Velocity in upstream of bar Rack, m/s• G= Acceleration due to Gravity• = 9.81 m/sec2

Page 8: Physical Unit Operation-Screening, Grit Removal,Equalization

• W= Maximum Cross Sectional Width of bars facing the wastewater flow, meters

• b= minimum clear bar spacing• Hv= Velocity head of wastewater flow approaching the bar in

meters• = Bar Shape factor Value of Bar Shape factor for Clean Bar Rack

are Given Below• Sharp Edge Rectangular Bar- 2.42• Rectangular with Semi circular faceing Upstream- 1.79• Rectangular with both ends Semi-circular – 1.67• Circular Bars – 1.83

Page 9: Physical Unit Operation-Screening, Grit Removal,Equalization

Characteristics Quantity & Composition of Screenings

• Quantity of Screenings depends upon the type of screen, weather, & Characteristics of wastewater.

• Narrow opening will collect more screenings & hot weather shall increase the use of water & Wastewater formation shall be more thereby increasing screenings.

Page 10: Physical Unit Operation-Screening, Grit Removal,Equalization

• Quantity of screenings may be 0.03 to 0.08 m3/ ML with an average of around 0.05 m3/ML

• Screening contain approximately 80 % moisture and has a normal wt. density of 960 kg/ m3.

• Screening are odorous and attract flies.

Page 11: Physical Unit Operation-Screening, Grit Removal,Equalization

Design of BAR ScreensFollowing Information are Required for design:

• Peak Wet Weather flow.• Peak Dry Weather flow.• Hydraulic Design of Influent Conduit.• Treatment Plant Design Criteria Specified by Bureau of Indian

Standards or other Recognized agency.• Equipment Manufacturers, their specifications for equipment.• Velocity through bars• Information on Existing facility if plant is to be expanded.• Bar Spacing and head loss constrained through the rack & Through

entire plant.• Existing Site Plan with Contours.• Velocities through Screen Chamber.

Page 12: Physical Unit Operation-Screening, Grit Removal,Equalization

Design Example• Design Bar Screen for a Peak flow of 50 MLD.

Assume Other data, Maximum Rate of flow in m3/Sec = 50 x 10 6 x 10-3 = 0.5787 m3/sec

24 x 60 x 60 •Let Us Assume the velocity through the screen as 0.8 m/sec •Net Area of Screen= 0.5787 0.8

= 0.7234 m 2

Page 13: Physical Unit Operation-Screening, Grit Removal,Equalization

• Let us use bars of 10 mm x 50 mm with 10 mm dimensions facing the flow, at a spacing of 40 mm between the bars. So,

• Gross Area = s + t Net Area s

= Clear Spacing + Bar Thickness Clear Spacing

Therefore, Gross area in our Case

= Net Area x { Clear Spacing + Bar Thickness } Clear Spacing

Gross Area = 0.7234 x 40 + 10 40

= 0.9043 Keep Screen at 45 0 Inclination with horizontal then Gross Area required

= 0.9043 Sin 45

= 1.2788 m 2

Page 14: Physical Unit Operation-Screening, Grit Removal,Equalization

• Velocity in the approach Channel i.e. Slightly Upstream of Bar Rack

• = 0.8 x 40 50

= 0.64 m/secThus we have

V= 0.8 m/secv= 0.64 m/sec

Page 15: Physical Unit Operation-Screening, Grit Removal,Equalization

• Therefore,• HL= • = 0.0729 ( V2- v2)• = 0.0729 ( 0.8 2 – 0.64 2)• = 0.017 m• = 1.7 cm• This will be the head-loss when the screen is

clean • If it is half Clogged.

Page 16: Physical Unit Operation-Screening, Grit Removal,Equalization

• V= 2 x 0.8 = 1.6 m/sec

&• HL= 0.0729 ( 1.6 2 – 0.64 2)

= 0.157 m= 15.7 cm

• So to reduce the head loss frequently cleaning of screen is required.

Page 17: Physical Unit Operation-Screening, Grit Removal,Equalization

Physical Unit Operations - Grit Chamber

Page 18: Physical Unit Operation-Screening, Grit Removal,Equalization

Grit Removal in Grit Chamber

• Sand, ash, Cinder, Bone Chip, egg shells, etc., of size less than 0.2 mm are included in grit.

• It is therefore possible to remove grit from the waste water easily by reducing the wastewater velocity in long channel called as grit channel.

• The velocity is reduced to about 0.3 m/sec. • The settled grit is washed before its disposal.

Page 19: Physical Unit Operation-Screening, Grit Removal,Equalization

• Grit Chamber is provided for the purpose of removal of silt and sand particles mainly so that the same will not cause, the wear and tear of vanes of pumps, clogging of pipes, as well as, valve operation difficult.

• Cementing effects are also prevented in settling tanks and digester by removal of grit.

Page 20: Physical Unit Operation-Screening, Grit Removal,Equalization

• Grit Removal Unit may be a grit Channel, Grit Chamber or a Grit Basin.

• The Word grit chamber shall be used in subsequent discussion.

• There are two types of grit chambers 1. Horizontal flow Grit Chambers2. Aerated Grit Chamber

Page 21: Physical Unit Operation-Screening, Grit Removal,Equalization

• Horizontal flow grit chamber are designed to maintain a velocity of around 0.3 m/sec.

• Such a velocity falls then the organic particles also settle down and if velocity becomes high grit particles will not settle.

• The Waste water flow varies and therefore it is required to maintain the constant velocity by providing proportional flow weirs, partial flumes and palmer- Bowlup flumes.

Page 22: Physical Unit Operation-Screening, Grit Removal,Equalization

• Aerated Grit Chambers are Used for Selective Removal of Grit in medium and large sized wastewater treatment plants.

Page 23: Physical Unit Operation-Screening, Grit Removal,Equalization

Aerated Grit Chambers

Page 24: Physical Unit Operation-Screening, Grit Removal,Equalization

Grit Collection & Removal

• Mechanical Grit Collection in velocity controlled horizontal flow grit chambers and aerated grit chambers is achieved by the conventional equipment

• In some cases steep bottom slope is provided which will collect the grit at Central Point of Removal.

Page 25: Physical Unit Operation-Screening, Grit Removal,Equalization

• Grit Removal is achieved by air pumps for small aerated grit chambers.

• Grit can also be removed by tubular conveyors, buckets type collectors, elevators screws conveyors, grit pumps and clam shell buckets.

Page 26: Physical Unit Operation-Screening, Grit Removal,Equalization
Page 27: Physical Unit Operation-Screening, Grit Removal,Equalization

Quantity of Grit

• Grit Quantity varies greatly. It depends upon the following factors:

• Type of Sewerage System i.e. Separate or Combined Sewerage System

• Climate Condition• Soil Type• Sewer Grades• Type of Industrial Wastewaters• Relative Use of Garbage and grinders• The grit quantity may range from 5 to 200 m3/ Million Cubic

Meter of Wastewater. The typical Value can be Considered as 30 m3/ million Cubic meter of wastewater.

Page 28: Physical Unit Operation-Screening, Grit Removal,Equalization

Grit Disposal

• Various methods are Used for Grit Disposal

1. Sanitary Landfill: In low lying areas or large natural pits the grit is disposed. Such a method of disposal is preferred when site of disposal is far away from city or town.

2. Land Spreading 3. Incineration with Sludge: Incineration is burning at very

high temperature in excess Oxygen. City solid waste can be incinerated. Sludge and grit can be taken to the incinerator for burning. Grit can also be buried when its quantity is small.

Page 29: Physical Unit Operation-Screening, Grit Removal,Equalization

Sanitary Landfill

Page 30: Physical Unit Operation-Screening, Grit Removal,Equalization

Land Spreading

Page 31: Physical Unit Operation-Screening, Grit Removal,Equalization

Incineration with Sludge

Page 32: Physical Unit Operation-Screening, Grit Removal,Equalization

Design of Grit ChambersFollowing Information should be collected for designing of the grit chambers• Wastewater Characteristics and Size of Grit particles to be

removed. • Design average, peak and lowest flow.• Information about existing plant if it is to be expanded.• Type of Grit Chamber to be provided i.e. Horizontal flow,

aerated etc. • Influent pipe data and static head force main and hydraulic

grade line in case grit removal preceded pumping station.• Head loss constraints for Grit Removal Efficiency.• Treatment plant design criteria by Bureau of Indian Standards.

Page 33: Physical Unit Operation-Screening, Grit Removal,Equalization

Design Criteria for Horizontal Flow Grit Chambers• Detention Time = 40 to 60 Sec• Horizontal flow velocity = 15 to 30 cm/sec

approximately • = 4 • Where g= Acceleration due to Gravity= 9.81

m/sec2

• Ss= Sp Gravity of Grit= 2.65• D= dia of Grit in m.

Page 34: Physical Unit Operation-Screening, Grit Removal,Equalization

• Surface Overflow Rate (SOR) = 500-1500 m3/m2/day

• Length to Breadth Ratio = 6 to 15 • Length to depth Ratio = 10 to 30 • Depth= (1.5 to 2) + free board• Free Board = 0.75 to 1.0 m

Page 35: Physical Unit Operation-Screening, Grit Removal,Equalization

Design Example• Design a Suitable Grit Chamber to Cater a town of 2 Lakh

population with 150 l/capita/day Sewage Contribution • Assume Peak Factor = 1.5 • Maximum Sewage Contribution per day = Average Contribution x Peak factor = 150 x 200000 x 1.5 litres= 150 x 200000 x 1.5 m 3 1000 = 45000 m3

Page 36: Physical Unit Operation-Screening, Grit Removal,Equalization

• 45000 m3 sewage produced daily i.e. in • 24 x 60 x 60= 86400 Seconds• Therefore Maximum Sewage Discharge • = 45000 m3/ Sec 86400 = 0.52 m3/Sec •Assume horizontal velocity 0.3 m/sec and detention time 50 sec•Therefore Length of the tank Required= Velocity x Detention Time = 0.3 x 50 = 15 m

Page 37: Physical Unit Operation-Screening, Grit Removal,Equalization

• Now Settling Velocity of Grit Particles are governed by Hazen’s Modified Equation as Given Below:

• Vs= 60.6 (Ss-1) d (3t + 70) 100Where, t= temp of Waste water 0 C d= dia of particle in cm Vs= Settling Velocity in cm/sec Ss= Sp Gravity of Grit, 2.65

If Ss= 2.65 above equation becomes Vs= d (3t + 70)Taking, t= 27 0C Vs= 3 m/sec

Page 38: Physical Unit Operation-Screening, Grit Removal,Equalization

• We want to remove 0.2 mm particle so Settling Velocity = 3 cm/sec

• Therefore Depth of Tank= 3.0 cm/sec x 50 sec.3 = 150 cm= 1.5 m

• Taking Length to Width Ratio as 10 : 1 • Width of the tank = 1.5m

Page 39: Physical Unit Operation-Screening, Grit Removal,Equalization

• Now, Check for SOR Surface Overflow Rate• Width= 1.5 m• Length=15 m• Plan Area= 1.5 x 15 = 22.5 m2 • Max Sewage flow = 45000 m3/day • Max SOR = 45000 m3/day 22.5

= 2000 m3/m2/day Which is higher than permitted as per Criteria

Page 40: Physical Unit Operation-Screening, Grit Removal,Equalization

So, take length: Width ratio as 6:1 Therefore Width= 2.5 m Therefore Plan Area= 2.5 x 15

= 37.5 m2

Therefore Max SOR= 45000 m3/ day 37.5 m2

= 1200 m3/m2/day

Which is less than 1500 therefore O.K.

Page 41: Physical Unit Operation-Screening, Grit Removal,Equalization

Grit Chamber

Page 42: Physical Unit Operation-Screening, Grit Removal,Equalization

Physical Unit Operations - Equalization

• Flow equalization is damping of flow rate variation so that a constant or nearly constant flow rate is achieved.

• This technique can be applied in a number of situation depending upon the characteristics of collecting system.

Page 43: Physical Unit Operation-Screening, Grit Removal,Equalization

Types of Equalization

1. In- line equalization• In this case, all the flow passes through the

equalization basin and helps in achieving reducing fluctuations in pollutant concentration and flow rate.

Page 44: Physical Unit Operation-Screening, Grit Removal,Equalization

2. Off- line equalization• In this case, only over-flow above a predetermined

value is diverted into the basin.• It helps in reducing the pumping requirements. • Off-line equalization is commonly used for the capture

of the “first flush” from combined collections systems.

Page 45: Physical Unit Operation-Screening, Grit Removal,Equalization

Location of Equalization Basin

• In some cases Equalization may be provided after primary treatment & before biological treatment.

• The design must provide for sufficient mixing to prevent solid deposition & concentration variation.

• It is also necessary to provide aeration system to avoid odour nuissance.

Page 46: Physical Unit Operation-Screening, Grit Removal,Equalization

Determination of the volume of flow equalization basin• It is determined by using an inflow mass diagram in

which cumulative inflow volume is plotted versus the time of day.

Page 47: Physical Unit Operation-Screening, Grit Removal,Equalization

Data requirement

1. Hourly flow data i.e. wastewater discharge during 0-1, 1-2, …, 23-24 hous of the day.

2. Design criteria of the component agency of state. (BIS, GPCB)

3. Location of equalization basin in the flow sheet.

4. List of manufacturers of equipments like pumps, pipe etc… price etc… of equipment.

Page 48: Physical Unit Operation-Screening, Grit Removal,Equalization

References

• Water & Waste WaterEngineering By Prof B.R.Shah

Prof A M Malek• Google Images

Page 49: Physical Unit Operation-Screening, Grit Removal,Equalization