piles supported embankment.pdf

Upload: thadikkaran

Post on 04-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Piles supported embankment.pdf

    1/20

    Pile-Supported Highway Embankment 5 - 1

    5 Pile-Supported Highway Embankment

    End-bearing piles can be used to support highway embankments constructed over soft foundationmaterials. This method of support can reduce the potential for excessive deformations and failure

    during the undrained stage of construction when excess pore pressures are induced in the foundationmaterials by the embankment loading.

    This example presents a FLACanalysis of the initial (undrained) construction stage for a highwayembankment built over soft saturated foundation clay and muck, using timber piles to supportthe embankment.* The piles extend through the soft materials and into underlying silty sands.The embankment includes foamed concrete engineered fill as part of the embankment materials.The light-weight foamed concrete is placed in lifts of approximately 0.6 m thickness. The firstlift is placed over a wire mesh directly in contact with the top of the timber piles. Earth fill andpavement material are placed as cover over the foamed concrete. The analysis also includes atraffic surcharge of 11,500 Pa (240 psf). Figure 5.1 shows a section view of the embankment andfoundation materials. The groundwater surface is at the top of the foundation materials.

    Figure 5.1 Half-section view of foamed concrete embankment on timberpiles

    * This analysis is based on information provided by K. J. Kim of the North Carolina Department ofTransportation on the design of a foamed concrete embankment supported on timber piles for theU.S. 64 widening project in Tyrrell County, North Carolina.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    2/20

    5 - 2

    The properties assumed for the foundation and embankment materials are listed in Tables 5.1and5.2. Note that both saturated and dry densities are shown for the foundation materials. Theembankment materials are assumed to remain dry. TheFLACsimulation is an undrained analysisusing the groundwater configuration mode. Consequently, the drained material bulk modulus and

    strength properties and the dry mass densities are input for this calculation mode, because the effectof water is incorporated in the FLACcalculation.

    Table 5.1 Properties for Foundation Soils

    muck very soft clay silty sand

    Saturated unit weight (N/m3) 11,100 13,560 18,840

    Porosity (%) 90 80 30

    Dry density (kg/m3) 231 582 1620

    Drained Youngs modulus (MPa) 0.3 0.5 15.0

    Drained Poissons ratio 0.49 0.45 0.3

    Drained Bulk modulus (MPa) 5.0 1.67 12.5

    Shear modulus (MPa) 0.1 0.17 5.77

    Drained Cohesion (Pa) 3500 5000 0

    Drained Friction angle (degrees) 0 0 32

    Dilation angle (degrees) 0 0 0

    Horizontal permeability (m/day) 0.003 0.0003 2.4

    Vertical permeability (m/day) 0.001 0.0001 0.8

    Table 5.2 Properties for Embankment Materials

    foamed concrete earth fill

    Dry density (kg/m3) 640 1920

    Porosity (%) 30 30

    Drained Youngs modulus (MPa) 600.0 10.0

    Drained Poissons ratio 0.15 0.3

    Drained Bulk modulus (MPa) 286.0 8.33

    Shear modulus (MPa) 261.0 3.85

    Drained Cohesion (Pa) 50,000 2400

    Drained Friction angle (degrees) 0 30

    Dilation angle (degrees) 0 0

    Horizontal permeability (m/day) 1.2 1.2Vertical permeability (m/day) 0.4 0.4

    Treated timber piles are located on a 2.5 m by 2.5 m rectangular spacing beneath the embankmentmaterials. The length of each pile is 12.8 m (42 ft), and the average pile diameter is 0.3048 m (12in). The properties of the timber piles are listed inTable 5.3.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    3/20

    Pile-Supported Highway Embankment 5 - 3

    Table 5.3 Properties for Treated Timber Piles

    Elastic modulus (GPa) 10.0

    End-bearing capacity (KN) 250.0

    This analysis is performed as a parametric study to compare the deformation of an unsupportedembankment to that of a pile-supported embankment. In both cases, we first determine the initialequilibrium state of the saturated foundation soils. Then, for the unsupported case, we add theembankment materials and monitor the vertical displacement along the foundation surface directlybeneath the embankment. For the pile-supported case, we install the timber piles and then add thelayers of embankment materials while monitoring the vertical displacements in the same locationsas those for the unsupported case.

    The model is created using FLACs graphical interface, the GIIC. Upon entering the GIIC, thegroundwater flow option and structural elements are activated in the Model Options dialog. TheSave Project Asmenu item is then selected from the Filemenu in order to set up a project fileto save the model state at various stages of the simulation. We click on ? in this menu dialog toselect a directory in which to save the project file. A record of the FLACcommands used to createthis model is saved after the analysis is complete, using the File/Export Recordmenu item. Alisting of the record created for this model is given inExample 5.1.

    We generate the grid using the Build/Block tool to create a two block by two block grid. Then, we usethe Alter/Shape tool to generate lines defining the excavation slope and the excavation and foundationmaterial boundaries. The embankment is 3 m high and the pavement half-width is 12 m. Theresulting grid is shown inFigure 5.2and coincides with the half-section shown inFigure 5.1. Thegrid before alteration is saved as state P1.SAV, and after alteration as P2.SAV.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    4/20

    5 - 4

    FLAC (Version 4.00)

    LEGEND

    11-Sep-01 20:14 step 0

    -7.860E+00

  • 8/14/2019 Piles supported embankment.pdf

    5/20

    Pile-Supported Highway Embankment 5 - 5

    Figure 5.3 Groups defined for embankment and foundation materials

    After all the material groups are assigned, the foamed concrete lifts and earth fill groups are exca-vated using the Material/Cut&Fill tool. The initial stress state for the saturated foundation soils is thencalculated. We use the ININV.FIS FISHfunction provided in the FISHLibrary (see ININV.FISinSection 3in the FISHvolume). This function automatically calculates the pore pressures and

    total stresses that are compatible for a model containing a phreatic surface. The groundwater densityand water bulk modulus are specified before applying this FISH function. We use the Settings/GW

    tool to set the groundwater density to 1000 kg/m3 and the groundwater bulk modulus to 10,000Pa (to speed convergence to steady-state flow). We then use the Utility/FishLib tool to access theININV.FISFISHfunction. We enter the phreatic surface elevation (wth= 0) and the Ko ratios(k0x = 1.0 and k0z = 1.0) in the dialog, and press OK . TheFISHfunction is called intoFLACandexecuted. The pore pressure distribution and total stress adjustment are then calculated automati-cally. We now solve for the new equilibrium state, using the Run/Solve tool and running in coupledmechanical-groundwater flow mode. The pore-pressure distribution is shown inFigure 5.4. Themodel is saved at this state as P4.SAV.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d418.pdf/http://f2d418.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    6/20

    5 - 6

    FLAC (Version 4.00)

    LEGEND

    14-Sep-01 16:02 step 2392

    Cons. Time 2.1748E+06

    -5.513E+00

  • 8/14/2019 Piles supported embankment.pdf

    7/20

    Pile-Supported Highway Embankment 5 - 7

    Figure 5.5 Addition of first embankment lift foamed concrete1

    Vertical displacement histories are recorded at four locations along the base of the embankment, at(x=0,y=0), (x=5,y=0), (x=11,y=0) and (x=16,y=0). The displacements are monitored throughoutthe embankment construction; the results are shown in Figure 5.6. The extent of the displace-ments induced by the unsupported construction is shown in Figure 5.7. The maximum vertical

    displacement beneath the embankment is approximately 0.6 m (2 ft).The displacements are associated with excess pore pressures that develop in the muck and verysoft clay. This is evident from the pore pressure histories recorded along the centerline of theembankment at y=0 and y=-6 (in the muck) and at y=-10 (in the very soft clay). The plots ofpore-pressure histories are given inFigure 5.8.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    8/20

    5 - 8

    FLAC (Version 4.00)

    LEGEND

    15-Sep-01 13:34 step 75594

    Cons. Time 2.1748E+06

    HISTORY PLOT

    Y-axis :

    Y displacement( 1, 41)

    Y displacement( 6, 41)

    Y displacement( 12, 41)

    Y displacement( 17, 41)

    X-axis :

    Number of steps

    10 20 30 40 50 60 70

    (10 )+03

    -5.000

    -4.000

    -3.000

    -2.000

    -1.000

    0.000

    (10 )-01

    JOB TITLE : .

    Itasca Consulting Group, Inc.

    Minneapolis, Minnesota USA

    Figure 5.6 Vertical displacements along base of embankmentfor unsupported embankment construction

    FLAC (Version 4.00)

    LEGEND

    15-Sep-01 13:34

    step 75594

    Cons. Time 2.1748E+06

    -3.588E+00

  • 8/14/2019 Piles supported embankment.pdf

    9/20

    Pile-Supported Highway Embankment 5 - 9

    FLAC (Version 4.00)

    LEGEND

    15-Sep-01 13:34 step 75594

    Cons. Time 2.1748E+06

    HISTORY PLOT

    Y-axis :

    Grid-point pp ( 1, 40)

    Grid-point pp ( 1, 30)

    Grid-point pp ( 1, 23)

    X-axis :

    Number of steps

    10 20 30 40 50 60 70

    (10 )+03

    0.200

    0.400

    0.600

    0.800

    1.000

    1.200

    (10 )+05

    JOB TITLE : .

    Itasca Consulting Group, Inc.

    Minneapolis, Minnesota USA

    Figure 5.8 Pore pressures beneath center of embankmentfor unsupported embankment construction

    The pile-supported embankment construction is simulated by first installing pile elements in theFLACmodel. The model state at P4.SAV (the initial equilibrium state) is restored, and sevenpiles of 12.8 m length are positioned at a 2.5 m spacing within the foundation soils. Before thepiles are placed in the model, the first foamed concrete lift is added. This is done so that the top ofthe piles can be connected to the embankment materials. Then, the piles are positioned as showninFigure 5.9.

    In order to represent the three-dimensional effect of the 2.5 m pile spacing, we scale the pileproperties by dividing by the pile spacing. It is only necessary to scale the elastic modulus (to4 GPa) and the end-bearing capacity (to 100 KN) to account for the spacing. (Note that in thisanalysis, we neglect the weight of the piles; the density should also be scaled if this were included.)

    The properties of the pile coupling springs are selected to simulate an end-bearing capacity andzero skin friction. The cohesive strengths of the shear coupling springs at the top and bottomelements of each pile are set to 130,000 N/m, while all other shear and normal coupling-springstrength values are set to zero. The value for cohesive strength is derived from an axially loaded

    single-pile simulation to produce an end-bearing ultimate capacity of 100 KN in the silty-sandfoundation material. The value for coupling-spring shear stiffness is selected at approximately tentimes the equivalent stiffness of the stiffest neighboring zone. By doing this, the deformability atthe pile/soil interface will have minimal influence on both the compliance of the total model andthe calculational speed (seeSection 4.4.1in Theory and Background). The properties used forthe pile elements in this model are summarized in Table 5.4. The model is saved at this stage asP11.SAV.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d415.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d415.pdf/http://f2d415.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    10/20

    5 - 10

    Figure 5.9 Location of piles in FLAC model

    Table 5.4 Properties for Pile Elements

    middle segments top & bottom segments

    Elastic modulus (GPa) 4.0 4.0

    Radius (m) 0.1524 0.1524

    Perimeter (m) 0.976 0.976

    Shear coupling spring stiffness (GN/m/m) 0.0 1.0

    Shear coupling spring cohesion (N/m) 0.0 130,000

    Shear coupling spring friction (degrees) 0.0 0.0

    Normal coupling spring stiffness (GN/m/m) 0.0 0.0

    Normal coupling spring cohesion (N/m) 0.0 0.0

    Normal coupling spring friction (degrees) 0.0 0.0

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    11/20

    Pile-Supported Highway Embankment 5 - 1 1

    The embankment construction steps are now performed following the same sequence as for theunsupported case. Each of the pile-supported stages are saved as separate save states in P12.SAVthrough P17.SAV.

    The vertical displacements are monitored as before; the histories are shown inFigure 5.10. Themaximum vertical displacement beneath the embankment is approximately 0.03 m (1 in).

    Also, we note that for this case there is an insignificant change in pore pressures in the muck andvery soft clay, as seen inFigure 5.11.

    FLAC (Version 4.00)

    LEGEND

    15-Sep-01 16:11

    step 71593

    Cons. Time 2.1748E+06

    HISTORY PLOT

    Y-axis :

    Y displacement( 1, 42)

    Y displacement( 6, 42)

    Y displacement( 12, 42)

    Y displacement( 17, 42)

    X-axis :

    Number of steps

    10 20 30 40 50 60 70

    (10 )+03

    -2.500

    -2.000

    -1.500

    -1.000

    -0.500

    (10 )-02

    JOB TITLE : .

    Itasca Consulting Group, Inc.Minneapolis, Minnesota USA

    Figure 5.10 Vertical displacements along base of embankmentfor pile-supported embankment construction

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    12/20

    5 - 12

    FLAC (Version 4.00)

    LEGEND

    15-Sep-01 16:11 step 71593

    Cons. Time 2.1748E+06

    HISTORY PLOT

    Y-axis :

    Grid-point pp ( 1, 40)

    Grid-point pp ( 1, 30)

    Grid-point pp ( 1, 23)

    X-axis :

    Number of steps

    10 20 30 40 50 60 70

    (10 )+03

    0.200

    0.400

    0.600

    0.800

    1.000

    (10 )+05

    JOB TITLE : .

    Itasca Consulting Group, Inc.

    Minneapolis, Minnesota USA

    Figure 5.11 Pore pressures beneath center of embankmentfor pile-supported embankment construction

    We are also interested in the axial loading that develops in the piles. We note that the axial forcescalculated in the piles are scaled values; the actual forces are found by multiplying the scaledvalues by the pile spacing. We create a FISHfunction, ACTUAL PILE LOAD.FIS, to calculatethe actual pile loads from theFLACscaled loads. This function is created in the Fish Editorwhichis accessed from the Show menu.Figure 5.12shows the function we have written in the Fish Editor.We use the STR.FIN file (available in the FLAC\FISH\FIN directory) to access the structuralelement data structure (seeSection 4in the FISHvolumefor information on .FIN files). Thisfunction is executed by pressing the Run button in the Fish Editor, and the scaled values for pileaxial forces are overwritten by actual values. We can now create a plot of the actual axial forces inthe piles, as shown inFigure 5.13. (The pile numbers shown in the plot legend correspond to thetop, middle and bottom pile segments, which are assigned different material property numbers.)The maximum pile loading is approximately 210 KN. Please note that care must be taken whenusing thisFISHfunction. The results that are now stored in the structural element array for axialforces are not the correct FLACvalues, and subsequent simulations should not be done from thisstate.

    Finally, we note that this project can be re-created by importing the data file PEMBANK.DATlisted inExample 5.1, using the File/Import Recordmenu item. After the record is imported totheGIIC, each save state can be created by first clicking on that state in the Recordpane and thenclicking on the restore state button at the top of the pane. The commands associated with that statewill then be called into FLAC. Note that theProject Tree Recordformat must be enabled (from the

    Model Options dialog) to import this record.

    FLAC Version 4.0

    http://f2d495.pdf/http://f2d401.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d495.pdf/http://f2d401.pdf/http://f2d401.pdf/http://f2d495.pdf/http://f2d495.pdf/
  • 8/14/2019 Piles supported embankment.pdf

    13/20

    Pile-Supported Highway Embankment 5 - 1 3

    Figure 5.12 Fish Editor showing ACTUAL PILE LOAD.FIS function

    Figure 5.13 Actual loads in piles for pile-supported embankment construction

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    14/20

    5 - 14

    Example 5.1 PEMBANK.DAT

    ;Project Record Tree export

    ;Title: Piled Embankment

    new

    ;Branch 1: p1.sav

    config gwflow

    grid 60,45

    gen 0.0,-40.0 0.0,-15.0 30.0,-15.0 30.0,-40.0 rat 1.0,0.9 i 1 31 j 1 16

    gen 0.0,-15.0 0.0,3.0 30.0,3.0 30.0,-15.0 i 1 31 j 16 46

    gen 30.0,-40.0 30.0,-15.0 80.0,-15.0 80.0,-40.0 rat 1.02,0.9 i 31 61 j 1 16

    gen 30.0,-15.0 30.0,3.0 80.0,3.0 80.0,-15.0 rat 1.02,1.0 i 31 61 j 16 46

    model elastic i 1 60 j 1 45

    save p1.sav

    ;Branch 2: p2.sav

    gen line 11.75,3.0 20.75,0.0gen line 0.0,-9.0 20.0,-5.0

    gen line 0.0,-12.0 20.0,-10.5

    mark i 21 61 j 41

    mark i 20 61 j 32

    mark i 20 61 j 23

    mark i 1 20 j 41

    model null i 21 j 41 45

    model null i 20 j 42 45

    model null i 19 j 42 45

    model null i 18 j 43 45

    model null i 17 j 43 45

    model null i 16 j 44 45model null i 15 j 44 45

    model null i 14 j 45

    model null region 45 43

    gen line 0.0,2.5 11.0,2.5

    ini x 12.543801 y 2.0714378 i 13 j 44

    ini x 13.681461 y 1.5236754 i 14 j 43

    ini x 15.619698 y 0.84950686 i 16 j 42

    ini x 14.187088 y 1.3551335 i 15 j 43

    ini x 16.336002 y 0.63882875 i 17 j 42

    save p2.sav

    ;Branch 3: p3.sav

    group silty sand region 55 5

    model mohr group silty sand

    prop density=1620.0 bulk=1.2499999E7 shear=5770000.0 cohesion=0.0 &

    friction=32.0 dilation=0.0 tension=0.0 group silty sand

    group very soft clay region 59 29

    model mohr group very soft clay

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    15/20

    Pile-Supported Highway Embankment 5 - 1 5

    prop density=582.0 bulk=1669999.9 shear=172000.0 cohesion=5000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group very soft clay

    group muck region 58 36

    model mohr group muck

    prop density=231.0 bulk=5.0002132E7 shear=100066.7 cohesion=3500.0 &friction=0.0 dilation=0.0 tension=0.0 group muck

    group foamed concrete1 i 1 17 j 41

    model mohr group foamed concrete1

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete1

    group foamed concrete2 i 1 15 j 42

    model mohr group foamed concrete2

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete2

    group foamed concrete3 i 1 13 j 43

    model mohr group foamed concrete3

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete3

    group foamed concrete4 i 1 12 j 44

    model mohr group foamed concrete4

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete4

    group earth fill i 20 j 41

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 19 j 41

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 18 j 41

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 18 j 42

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 17 j 42

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 16 j 42

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    16/20

    5 - 16

    group earth fill i 16 j 43

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 14 15 j 43model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill notnull i 13 14 j 44 45

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    group earth fill i 1 12 j 45

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group foamed concrete1

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group foamed concrete2

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group foamed concrete3

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group foamed concrete4

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group earth fill

    prop por=0.3 k11=2.83E-9 k22=9.44E-10 group silty sand

    prop por=0.8 k11=3.54E-13 k22=1.17E-13 group very soft clay

    prop por=0.9 k11=3.53E-12 k22=1.18E-12 group muck

    save p3.sav

    ;Branch 4: p4.sav

    model null group earth fill

    model null group foamed concrete4

    model null group foamed concrete3

    model null group foamed concrete2

    model null group foamed concrete1

    fix x y i 1 61 j 1

    fix x i 61 j 1 41

    fix x i 1 j 1 41

    set gravity=9.81

    water bulk 2e4

    water density=1000.0

    set echo off

    call Ininv.fis

    set wth=0.0 k0x=0.5 k0z=0.5

    ininv

    history 999 unbalanced

    solve

    save p4.sav

    restore p4.sav

    ;Branch 0: p5.sav

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    17/20

    Pile-Supported Highway Embankment 5 - 1 7

    model mohr group foamed concrete1

    prop density=640.0 bulk=2.85999936E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete1

    initial saturation 0.0 i 1 18 j 41 42

    fix saturation i 1 18 j 41 42set flow=off

    water bulk=2.0E8

    set =large

    fix x i 1 j 41 42

    history 1 ydisp i=1, j=41

    history 2 ydisp i=6, j=41

    history 3 ydisp i=12, j=41

    history 4 ydisp i=17, j=41

    history 5 gpp i=1, j=40

    history 6 gpp i=1, j=30

    history 7 gpp i=1, j=23

    solve

    save p5.sav

    ;Branch 1: p6.sav

    model mohr group foamed concrete2

    prop density=640.0 bulk=2.85999936E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete2

    fix x i 1 j 42 43

    fix saturation i 1 16 j 42 43

    initial saturation 0.0 i 1 16 j 42 43

    solve

    save p6.sav

    ;Branch 2: p7.sav

    model mohr group foamed concrete3

    prop density=640.0 bulk=2.85999936E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete3

    fix x i 1 j 43 44

    fix saturation i 1 15 j 43 44

    initial saturation 0.0 i 1 14 j 43 44

    solve

    save p7.sav

    ;Branch 3: p8.sav

    model mohr group foamed concrete4

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete4

    fix x i 1 j 44 45

    fix saturation i 1 13 j 44 45

    initial saturation 0.0 i 1 13 j 44 45

    solve

    save p8.sav

    ;Branch 4: p9.sav

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    18/20

    5 - 18

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    fix x i 1 j 45 46

    fix saturation i 1 19 j 42 46initial saturation 0.0 i 1 20 j 42 46

    solve

    save p9.sav

    ;Branch 5: p10.sav

    apply pressure 11500.0 from 1,46 to 12,46

    solve

    save p10.sav

    restore p4.sav

    ;Branch 0: p11.sav

    model mohr group foamed concrete1

    prop density=640.0 bulk=2.85999936E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete1

    struct node 1 1.251,0.01

    struct node 2 1.25,-12.8

    struct node 3 3.751,0.01

    struct node 4 3.75,-12.8

    struct node 5 6.251,0.01

    struct node 6 6.25,-12.8

    struct node 7 8.751,0.01

    struct node 8 8.75,-12.8

    struct node 9 11.251,0.01

    struct node 10 11.25,-12.8

    struct node 11 13.751,0.01

    struct node 12 13.75,-12.8

    struct node 13 16.251,0.01

    struct node 14 16.25,-12.8

    struct pile begin node 1 end node 2 seg 10 prop 3001

    struct pile begin node 3 end node 4 seg 10 prop 3001

    struct pile begin node 5 end node 6 seg 10 prop 3001

    struct pile begin node 7 end node 8 seg 10 prop 3001

    struct pile begin node 9 end node 10 seg 10 prop 3001

    struct pile begin node 11 end node 12 seg 10 prop 3001

    struct pile begin node 13 end node 14 seg 10 prop 3001

    struct prop 1001

    struct prop 2001

    struct prop 3001

    struct prop 3001 e 4e9 radius 0.1524 perimeter 0.976 cs ncoh 0 cs nfric 0 &

    cs nstiff 0 cs scoh 0.0 cs sstiff 0.0 cs sfric 0

    struct prop 3002 e 4e9 radius 0.1524 cs scoh 1.3e5 cs sstiff 1e9 per 0.976

    struct prop 3002 cs ncoh 0 cs nstiff 0

    struct chprop 3002 range 70 70

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    19/20

    Pile-Supported Highway Embankment 5 - 1 9

    struct chprop 3002 range 60 60

    struct chprop 3002 range 50 50

    struct chprop 3002 range 40 40

    struct chprop 3002 range 30 30

    struct chprop 3002 range 20 20struct chprop 3002 range 10 10

    struct chprop 3002 range 61 61

    struct chprop 3002 range 51 51

    struct chprop 3002 range 41 41

    struct chprop 3002 range 31 31

    struct chprop 3002 range 21 21

    struct chprop 3002 range 11 11

    struct chprop 3002 range 1 1

    water bulk 2e8

    set flow off

    fix x i 1 j 40 42

    save p11.sav

    ;Branch 1: p12.sav

    history 1 ydisp i=1, j=42

    history 2 ydisp i=6, j=42

    history 3 ydisp i=12, j=42

    history 4 ydisp i=17, j=42

    history 5 gpp i=1 j=40

    history 6 gpp i=1 j=30

    history 7 gpp i=1 j=23

    set large

    initial saturation 0.0 i 1 18 j 41 42

    fix saturation i 1 18 j 41 42

    solve

    save p12.sav

    ;Branch 2: p13.sav;

    model mohr group foamed concrete2

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete2

    initial saturation 0.0 i 1 16 j 42 43

    fix saturation i 1 16 j 42 43

    solve

    save p13.sav

    ;Branch 3: p14.sav

    model mohr group foamed concrete3

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete3

    fix x i 1 j 43 46

    initial saturation 0.0 i 1 19 j 42 46

    fix saturation i 1 19 j 42 46

    solve

    FLAC Version 4.0

  • 8/14/2019 Piles supported embankment.pdf

    20/20

    5 - 20

    save p14.sav

    ;Branch 4: p15.sav

    model mohr group foamed concrete4

    prop density=640.0 bulk=2.85999968E8 shear=2.61E8 cohesion=500000.0 &

    friction=0.0 dilation=0.0 tension=0.0 group foamed concrete4fix x i 1 j 43 46

    initial saturation 0.0 i 1 19 j 42 46

    fix saturation i 1 19 j 42 46

    solve

    save p15.sav

    ;Branch 5: p16.sav

    model mohr group earth fill

    prop density=1920.0 bulk=8330000.0 shear=3850000.0 cohesion=2400.0 &

    friction=30.0 dilation=0.0 tension=0.0 group earth fill

    fix x i 1 j 43 46

    initial saturation 0.0 i 1 19 j 42 46

    fix saturation i 1 19 j 42 46

    solve

    save p16.sav

    ;Branch 5: p17.sav

    apply pressure 11500.0 from 1,46 to 11,46

    solve

    save p17.sav

    FLAC Version 4.0