Page 1: Pipe Support

9/19/2006 1

Welcome

to

Presentation on

PIPE SUPPORT SYSTEMS & PIPING FLEXIBILITY(03-Feb-2005)

Page 2: Pipe Support

9/19/2006 2

Program Objectives

1. To create a sense of appreciation for compliance of best engineering practices , and improve understanding of piping through preliminary knowledge of Pipe supports.

2 To enable faster & better interpretation of engineering deliverables by working knowledge of these Pipe supports .

3 To enable maintenance engineers to take preventive action in case of exceptions.

Page 3: Pipe Support

9/19/2006 3

INDEX

PARTPART--I Overview.I Overview.PARTPART--II Support Basics. II Support Basics. PARTPART--III Support Classification. III Support Classification. PARTPART--IV Support Detailing. IV Support Detailing. PARTPART--V Support Design.V Support Design.PARTPART--VI Line Designation VI Line Designation PARTPART--VII Piping Flexibility VII Piping Flexibility PARTPART--VIII Sample Drawings .VIII Sample Drawings .

Page 4: Pipe Support

9/19/2006 4

OVERVIEW

Page 5: Pipe Support

9/19/2006 5

THE CODE ASME B 31.3 SPECIFIES UNDER CLAUSE 321.1.1, THE OBJECTIVE OF THE SUPPORT DESIGN AS PREVENTION OF

Piping stress in excess of those permitted in the code.Leakage at joints due to misaligned flanges.Excessive thrust and moments on connected equipment (such as pumps and turbines).Excessive stresses in the supporting (or restraining) elements.

Resonance with imposed fluid induced vibrations.Excessive interference with thermal expansion and contraction in a piping system, which is otherwise adequately flexible.(No unwanted rigidity). Unintentional disengagement of piping from its supports.Excessive piping sag in systems requiring drainage slope.

Page 6: Pipe Support

9/19/2006 6

PIPE SUPPORTS STANDARDS

1. ANSI31.1 &31.3 ie Power Piping & Process Piping 2. *MSS –SP 58 Pipe Hangers and Support : Materials, Design &

Manufacturers3. *MSS –SP 69 Pipe Hangers and Support : Selection & Application.4. *MSS –SP 77 Guidelines for Pipe Support Contractual

Relationships.5. *MSS –SP 89 Pipe Hangers and Supports: Fabrication &

Installation Practises.6. MSS –SP 90 Guidelines on Terminology of Pipe Hangers &

Supports.

* These are advisory standards recommending standard practices.

Page 7: Pipe Support

9/19/2006 7

SUPPORT OR SUPPORTING ELEMENTS

The term “supports” or “supporting elements” encompasses the entire range of various methods of carrying the weight of pipeline and the contents. It therefore includes “hangers” which generally carry the weight from above, with the supporting members being mainly in tension. Likewise, it includes “supports” which on occasion are delineated as those which carry weight from below,with supporting member being in compression.

Pipe supports refer to the physical structural elements such as pre- engineered structural steel along with suitable springs, snubbers, fixed on pipes to reduce or nullify the forces created in piping systems due to self weight, thermal expansion or contraction, shock load, etc.

Page 8: Pipe Support

9/19/2006 8

Basic Terminology

•Pipe : Pressure tight cylinder to convey fluid/fluid pressure

•Pipe Support Elements: Transmit the load from pipe to structures& /or pressure equipment Ex. Spring Hangers, Guides, Hangers. These are called Fixtures. Attachment like clips, clamps, strips etc. are called Structural Attachments.

•Piping Components: Joining/Assembling Mechanical elements for pressure tight piping etc. like Flanges, Gaskets, Valves, Expansion Joints, Hoses, Traps Strainers etc.

•Piping: Assemblies of piping components used to convey, distribute, mix etc. flows. Also includes piping elements.

•Piping Elements: Any material or work required to plan & install piping system is called piping elements. Specs, Materials, components, supports inspection etc.

•Piping System : Interconnected piping subjected to same set or varying sets of Design conditions.

Page 9: Pipe Support

9/19/2006 9

Continued…..

Hot load / Hot setting / Operating loadThe weight that the spring has to support while the pipe line system is in operation. This is also called Operating load.

Cold load / Cold setting / Installed loadThe weight that the spring has to support while the pipe line system is NOT in operation. This is also called pre-set load.

Travel stopsLimit the spring travel at the top and bottom to a small percentage beyond the specified range. In addition, they prevent the spring form moving while the spring is not in operation (in pre-set mode) or in hydrostatic testing phase.

TravelCompression or expansion of spring in “mm” from Hot to Cold or vice versa load variation.

Page 10: Pipe Support

9/19/2006 10

Elements Of Pipe Support

1. Fixtures:a. Hanger Rodsb. Spring hangersc. Turn Bucklesd. Chainse. Anchorsf. Bracketsg. Guidesh. Saddles

2. Structural Attachments:a. Clipsb. Lugsc. U-boltsd. Straps

Page 11: Pipe Support

9/19/2006 11

Classification of Pipe Supports1. Rigid or Weight Supports (Rod Hangers, Sliding supports, VS & CS Supports)

2. Rigid Restraints & Anchors (Supplementary Steel or Structural Members )

3. Snubbers (Hydraulic & Mechanical )

4. Sway Braces

Page 12: Pipe Support

9/19/2006 12

Rigid Type Supports (Weight supports)

All sliding type supports: Bare, Clamped, Shoe, Dummy supports, bracket supports, etc. (supported from bottom). In this the supports members are in compression.

Hangers rods (without spring): Will be supported from top. (Designed on the basis of max. weight carrying conditions, including Hydro test). In this the supports are in tension.

Page 13: Pipe Support

9/19/2006 13

SHOE SADLE CLAMP SHOE BASE SUPPT BASE ADJ.SPT

Page 14: Pipe Support

9/19/2006 14

BASE ELL SPT BASE ADJ SPT DUMMY SPT DUMMY SPT SHOE VERT DUMMY

Page 15: Pipe Support

9/19/2006 15

ADJ. ELL. SPT ADJ. SPT. ADJ.GUIDE ADJ. GUIDE SPT. NO WELD

Page 16: Pipe Support

9/19/2006 16

TRUNNION ELL.SPT. SUPPORT SUPPORT CLAMP ELL.SPT

Page 17: Pipe Support

9/19/2006 17

ROD HANGER

THE ROD HANGERS ARE USED FOR NON CRITICAL SUPPORTS.

DIFFERENNT ATTACHMENTS LIKE EYE-NUTS,TURNBUCKLES,RODS HEX

NUTS & BOLT CLAMPS ARE USED IN CONJUNCTION WITH HANGER RODS.

TURNBUCKLES ARE FOR ADJUSTMENT IN THE SUSPENDED LENGTH FROM

THE PIPE.

Page 18: Pipe Support

9/19/2006 18

ROD HANGERS

Offset Limitation of rod hangers

a) Pipe With Movement In Axial Direction

b) Cold Pipe Positioning

– 1) Offset,Cold

-- 2) Operating Position Hot

Permissible horizontal movement not to exceed +4° for Rod hangers .

Page 19: Pipe Support

9/19/2006 19

Anchors & Guides (Restraint Type)

Anchors & Guides are provided to restrict movement of pipe in any one or all 6 freedom of movements.

1. They are provided to restrain, direct or absorb piping movements.

2. Their design takes into account forces/moments at these elements caused by internal pressure and thermal expansion/contraction.

Supplementary Steel

To attach the pipe with various type of supports mentioned above we need to tie it with the existing structure. To achieve this we either weld structural members to the supporting elements or supporting brackets on to the existing structure.

Page 20: Pipe Support

9/19/2006 20

PIPE SUPPORT MATERIAL FOR COLD SERVICES

1. Natural seasoned wood – IS 3629 Gr.I

• Along the grain cutting & across the grain loading

• Timber group A

1. HDPUF – Compressive Strength 70000 Kpa OR 70 KG per cm 2

• Loyde grade 320 – 82000 KPa - Standard

• Loyde grade 250 – 49000 KPa - Standard

• Loyde grade 300 – 70000 KPa – (IPCL Customized)

Page 21: Pipe Support

9/19/2006 21

Variable & Constant Supports (Flexible Supports)

Variable Spring Supports:

Variable spring supports are so called because they provide variable supporting forces as the pipe moves vertically due to contraction or elongation. Maximum variation in load is 25%.

Constant Spring Supports:

Constant spring supports are used where thermal movements are too large (over 2 inches & max 6% load variation is allowed). Such spring supports are used to restrict the loads created in piping systems on to critical equipment nozzles.

NOTE: (In Spring Supports springs are not designed for Hydrotest loads, howeversupports members are designed to take hydro-test loads.)

Page 22: Pipe Support

9/19/2006 22

Spring Hanger in four different load conditions

a) Unloaded Position

b) Loaded in Hot position

c) Pipe moves down from cold to hot position

d) Pipe moves up from cold to hot position

Page 23: Pipe Support

9/19/2006 23

TYPES OF VARIABLE –SPRING HANGERS

Page 24: Pipe Support

9/19/2006 24

Variable Spring Supports (Flexible Supports)

Page 25: Pipe Support

9/19/2006 25

SELECTION OF FLEXIBLE SUPPORTS

CONSTANT SPRING : Constant spring hangers are selected where absolutely necessary, when the percentage variation of load from cold to hot should be less than ± 6% for critical pipelines, which give the lowest %, load variation. The geometry & kinematics of these constant spring hangers is such that theoretically and constant supporting force can be achieved throughout its full range of expansion and contract.

Page 26: Pipe Support

9/19/2006 26

Constant Effort Spring support

Page 27: Pipe Support

9/19/2006 27

CONSTANT-SPRING SUPPORT

Page 28: Pipe Support

9/19/2006 28

Constant Spring Supports (Flexible Supports)

Page 29: Pipe Support

9/19/2006 29

VARIABLE SPRING

Variable spring hangers are recommended for general use on non-critical piping systems & where constant supports are not required. The inherent characteristic of a variable spring is such that its supportings force varies with spring deflection and spring scale. The vertical expansion of piping causes a corrresponding compression or extension of spring & causes a change in the actual supporting force is equal to the product of amount of vertical expansion & the spring scale.

Page 30: Pipe Support

9/19/2006 30

Comparison of variable support & constant support Springs

Particular Variable Spring Support Constant Spring Support

Design Simple design with Helical spring

Sophisticated design with Spring & Bell Crank Lever

Application Non critical applications – Ex. Heat Exchangers, Vessel, ordinary piping etc.

Critical applications – Ex. Steam piping near steam turbines , Steam Headers ,Boilers etc.

Movement Applicable for Low thermal movements (upto 50 mm)

Applicable for large thermal movements (above 50 mm)

Space Less space for installation Large space for installation

Cost Low cost High cost

Page 31: Pipe Support

9/19/2006 31

Formulas And Calculations

Upward movement - If Cold load is greater than Hot load

Downward movement - If Hot load is greater than Cold load

Movement = (Cold load - Hot load) / Spring rate.If result > 0 then movement direction is up. Otherwise, it's down.

Variability = ((Movement x Spring rate) / Hot load) x 100 (% load change)

Page 32: Pipe Support

9/19/2006 32

SNUBBERS

Rigid restraints are usually necessary when the pipe is strong to survive loads such as earthquake or high winds or other dynamic loads such as fluid hammer. But when these restraints are used in high temperature piping at some location it may develop elevated stress levels. In these casessnubbers are used.

Page 33: Pipe Support

9/19/2006 33

SNUBBER ASSEMBLY

Page 34: Pipe Support

9/19/2006 34

Mechanical Snubber

a) Photograph b) Schematic

Page 35: Pipe Support

9/19/2006 35

Hydraulic Snubber

a) Schematic b) Photograph

Page 36: Pipe Support

9/19/2006 36

SWAY BRACES

Sway braces are used to limit the effect of pipe vibration. These are little more than variable springs acting in horizontal plane. When sway brace is installed, the spring preload is adjusted to be zero when pipe is in the operating

position. Sway braces, like variable springs, do add some expansion stresses in the pipe.

Page 37: Pipe Support

9/19/2006 37

A) Vibration Control & Sway Brace.

B) Cutaway Section

C) Deflection of Spring when Thrust Exceeds Pre-compression

D) Tension Causes deflection of Spring in Opposite Direction

SWAY BRACES

Page 38: Pipe Support

9/19/2006 38

LOAD COMBINATIONS

Pipe supports must be designed to withstand any combination of loading which is postulated to occur simultaneously. Normal operating loads are either deadweight or deadweight plus thermal. These loads may be combined with occasional loads, as required by the design criteria of the specific project.Under certain conditions, capacities of materials may be increased for occasional loads. E.g. is the concept of service level instituted by ASME Boiler & Pressure Vessel Code, Section III. A typical spec for design load combination is as follows:-

Page 39: Pipe Support

9/19/2006 39

Load Cases

Normal I Deadweight II Deadweight + Thermal

Upset I Normal + relief valve dischargeII Normal + earthquake(DBE) +relief valve discharge.III Normal + water hammer

Emergency Normal + earthquake (DBE)+ Relief valve discharge.

Faulted Normal + earthquake (DBE) + pipe rupture.

These loads may be added either algebraically to arrive at realistic values or absolutely for added conservatism, according to the design criteria requirements.

Page 40: Pipe Support

9/19/2006 40

MAXIMUM SPAN BETWEEN TWO SUPPORTSAs per ASME B31.1 Table 12.5 adopted from MSS-SP-69

Suggested Maximum SpanPipe (NB)

Water mtr. (ft) Air /Steam mtr. (ft)1 2.1 (7) 2.7 (9)

2 3.0 (10) 4.0 (13)

3 3.7 (12) 4.6 (15)

4 4.3 (14) 5.2 (17)

6 5.2 (17) 6.4 (21)

8 5.8 (19) 7.3 (24)

12 7.0 (23) 9.1 (30)

16 8.2 (27) 10.7 (35)

20 9.1 (30) 11.9 (39)

24 9.8 (32) 12.8 (42)

Page 41: Pipe Support

9/19/2006 41

GUIDELINES FOR LOCATION OF SUPPORTS

Support should be located at near as possible to concentrated loads as valves, flanges etc. To keep the bending stress to the minimum.When changes of direction in a horizontal plane occur, it is suggested that the spacing be limited to 75% of the tabulated values to promote stability and reduce eccentric loadings.

Page 42: Pipe Support

9/19/2006 42

The standard span does not apply to vertical run pipes (risers) since no moment and no stress will develop due to gravity load in the riser. The support should be located on the upper half of a riser to prevent instability in overturning of pipe under its own weight. Support location should be selected near the existing building steel to minimize the use of supplementary steel.

Page 43: Pipe Support

9/19/2006 43

SPECS FOR ORDER

o The exact hot or operating load required to be supported during the working condition.

o Hydrostatic test load.o The total travel.o The direction of travel either upwards or downwards from the

erected position. o The set pin locking position (top, middle, bottom or as required).o The basic model.o Requirement of bottom accessory components such as rods,

clamps etc.o Any hazardous environmental conditions. o Any special finish on the body such as galvanizing etc.

Page 44: Pipe Support

9/19/2006 44

Phenomenon in Piping Flexibility

CREEP RUPTURE STRENGHTTime dependant stress is usually related to the “Creep Rupture Strength” at high temperature. At temperature above 1/3 of the melting point most metals will exhibit creep in standard tensile test. If the load is kept constant the specimen will continue to deform and subsequently fail. Hence considering this creep, the allowable stresses are 62.5% of the yield stress. Hence taking a conservative estimate the limit of the bending stress at which plastic flow starts is 1.6 times the allowable cold or hot stress.

FATIGUE ON PIPING

ARC Markl investigated the phenomenon of fatigue in piping. He observed that the fatigue failure occurred not in the middle of his test spans, but in the vicinity of fittings and that also at a lower stress than that for pipes. This lead to a factor called “Stress Intensification Factor”.

Page 45: Pipe Support

9/19/2006 45

Piping Support Design Tips

1. Since most piping systems are not made strictly of straight horizontal runs, the standard support spacing may not be applied uniformly throughout. Locations of supports should consider the following guidelines.

2. Pipe supports should be located as near as possible to concentrated weights such as valves, flanges, etc. From a pipe stress point of view, the best location for support attachment is directly on the equipment.

3. When changes of direction in a horizontal plane occur between the pipe and associated supports, such as with pipe elbows, it is suggested that the spacing be limited to three-fourths of the standard span shown in table.

4. The standard span does not apply to vertical runs of pipe (risers) since no moment (and therefore no stress, as defined by the piping codes) will develop owing to gravity loads in riser.

5. Support locations should be selected near existing building steel to maximize ease of design & construction and to minimize the supplemental structural materials used to transmit the pipe loading back to the building structure.

Page 46: Pipe Support

9/19/2006 46

Key Maintenance Tips

• Adequately designed piping and support systems are absolutely critical & important.

• Major failure of supports can be catastrophic.

• It becomes absolutely necessary for maintenance engineers to be very vigilant towards critical support systems and check for following common piping support problems :

1. Shoe not resting on the sleepers.2. Shoe twisted.3. Support weathered away.4. Trunnion / Dummy bent on vertical lines.5. Structural members bent near loops.6. LPDs embedded in soil thus turning it into an anchor

support.

Page 47: Pipe Support

9/19/2006 47

Key Maintenance Tips

Continued….

• Wooden blocks placed under elbow dummies weathered off.

• Guide plates in guided supports missing.• Pipe stops in axial restraint broken / bent.• Blocks attached to these pipe stops weathered off.• Variable Spring Supports Corroded.• Variable Spring Supports locks not removed.• Due to displacement Variable spring supports not

operational.• Pipe is corroded where it is directly resting on sleeper

rod.• Line is not supported adequately, high cantilever.

Page 48: Pipe Support

9/19/2006 48

PIPING CLASS CODING3-Character System : X - X - XXXX - XXX - XX1st Slot/Character :Line size in inches2ND Slot/Character :P-Process ; CWS-Cooling Water Supply ;CWR-CW Return; N2-Nitrogen; H2-Hydrogen; AS-Service Air; AI-Instrument Air; AP-Plant Air; FW-Fire Water; DMW-DM Water, etc.3rd Slot/Character :4 Digit Line Sr.No.4th Slot/Character :Piping Classa) First Character specifying : A-150# B-300# D-600 # E-900 # F-1500 # G-2500 # b) Middle No. specifying variants. (1 2 3 4 5 7 8 9 10 13 19 20)c) Third Character specifying : A-CS, B-CS MOLY, C D E H K M N S-PVC, T Y-MSRL Z-HDPE(Ex: A1A, A2A A3A, A4A, B1A, B2A.., B1K, B2K, D1A,D2A, D5A, F2A, F2D, G2E)5th Slot/Character :Insulation TypeIH, IC, IS, ET

Page 49: Pipe Support

9/19/2006 49

Piping Flexibility An Introduction

Page 50: Pipe Support

9/19/2006 50

Expansion Loads

Piping system which is too well restrained will not be able to expand and large forces will develop at the points of lockup,causing large stresses to develop in the pipe.

The ideal restraint conditions for thermal considerations is a total lack of restraint. Since this is not feasible, given otherloads, some forces due to expansion will develop on restraints even in the most optimally supported system.

Hence it is necessary to determine piping thermal movements for use in spring hanger selection and design of clearances in restraints.

Page 51: Pipe Support

9/19/2006 51

THERMAL EXPANSION OF PIPING SYSTEM

(a) Loop without directed thermal growth

(b) Loop with directed thermal movement

Page 52: Pipe Support

9/19/2006 52

a.Poor Service/Piping Distortion.

b.Proper Service/Piping alignment & limited stresses through PSA .

c.Poor Service/ Unnecessary looping etc .

a.Good but Costly due to heavy design .

Page 53: Pipe Support

9/19/2006 53

Calculation of Pipe ExpansionA pipe will expand when heated up and contract when cooled. This can be expressed through the expansion formula.

The temperature expansion of pipes depends on the start and final temperature and the thermal coefficient of expansion of the piping material. The general expansion formula can be expressed as:

dl = ∝ x Lo x dt where:dl = expansion (inches) Lo = length of pipe (inch) dt = temperature difference (oF)

∝ = linear expansion coefficient (inch/inchoF) (available in 31.1, 31.3,etc)Example: Thermal expansion for 1 meter Carbon steel pipe at 100ºC.

dl = 6.38/10� x 1000 x (212 – 93) = 0.76 mm/meter

For Carbon Steel∝ = linear expansion coefficient (inch/inchoF) = 6.38/10�Remember

Expansion in SS pipe will be approx. 30- 50% more than in a carbon steel pipe.

Page 54: Pipe Support

9/19/2006 54

CTE OF PIPING MATERIALS(Total linear Thermal Expansion in / 100’)

c -300 °F -100 °F - 25 °F 70 °F(ambient)

200 °F 400 °F

A 106 (CS) - 2.24 - 1.15 -0.32 0 0.99 2.70

A 312 – 304 (SS)

- 3.63 - 1.75 -0.46 0 1.46 3.80

CTE (At 1000F)

CS 6.13 micro in./In./ °F

SS 9.16 micro in./In./ °F

Page 55: Pipe Support

9/19/2006 55

PIPE UNDER STRESS

There are two types of loads which put a pipe under stress:

1. Primary Loads: These loads are typical loads such as internal pressure, external pressure, gravitational forces like the weight of pipe and fluid. These loads are generally called as sustained loads.Failure of the pipe due to any of the mentioned loads are called as catastrophic failures.

2. Secondary Loads: Just as primary loads have origin in some force, secondary loads are caused by displacement of some kind. e.g the pipe may be under load if the tank nozzle moves up or down. A pipe subjected to a cycle of hot and cold fluid similarly undergoes cyclic loads and deformation.

Page 56: Pipe Support

9/19/2006 56

PSA OBJECTIVE

Pipe Stress analysis is carried out to ensure safety against failure of the PIPING SYSTEM by verifying the structural integrity against the loading conditions, both external and internal during the life time of the system in the plant.

Hence the objectives can be stated as :1. Ensure that the stresses in the piping components in the system are

within the allowable limits.2. Solve dynamic problems developed due to mechanical vibration,

fluid hammer, pulsation, etc.3. Solve the problems associated due to higher or lower temperatures.

When piping is connected to strain sensitive equipment, the flexibility required to satisfy the acceptable limits of nozzle loading on the connected equipment overrides all other considerations.

The piping systems are mainly classified into 3 main categories and then again sub-categories. The main categories are HOT Systems, COLD Systems and CRYOGENIC Systems. In this the hot and cryogenic lines must undergo FLEXIBILTY ANALYSIS.

Page 57: Pipe Support

9/19/2006 57

• REQUIREMENT OF STRESS ANALYSIS

No formal stress analysis is required if:• The piping system is duplicate of successfully operating installations or

replacements.• Can be readily adjudged adequately by comparison with previously

analysed systems.• Satisfy equation Specified in the clause 119.7.1(A3) / 319.4.1(c).

Page 58: Pipe Support

9/19/2006 58

BASIC INFORMATION

A set of piping general (GAD)A Complete set of steel & structural drgs including the equipment foundation.A set of drgs showing the location of ventilating ducts, electrical trays, instrument trays etc.A set of piping spec and line list, which includes pipe sizes, M.O.C., thickness of insulation, operating temperatures etc.A copy of insulation spec. With densities.A copy of valve and specially list indicating weights.The movement of all critical equipment connections such as turbines, compressors, boilers etc.

Page 59: Pipe Support

9/19/2006 59

ON COLLECTION OF THE ABOVE DATA, THE STEPS IN WHICH THE PIPE STRESS ENGINEER WILL APPLY THIS BASICS TO DESIGN THE PIPING SUPPORT SYSTEM .

The determation of support location. The determination of thermal movement of the piping at each support location. The calculation of load at each support location.The selection of load at each support location.The selection of type of support i.e. Anchor, Guide, Rest, Constant or Variable Spring etc.Checking physical interference of the support with structures, trays, ducts eqpts etc

Page 60: Pipe Support

9/19/2006 60

• Excessive distortion subject to creep under conditions of repeated thermal cycling. • Excessive heat flow, exposing supporting elements to

temperature extremes outside their design limits.

Page 61: Pipe Support

9/19/2006 61

Support Drawing Samples

Page 62: Pipe Support

9/19/2006 62

Page 63: Pipe Support

9/19/2006 63

Page 64: Pipe Support

9/19/2006 64

Page 65: Pipe Support

9/19/2006 65

Page 66: Pipe Support

9/19/2006 66

Page 67: Pipe Support

9/19/2006 67

Thank you