pipeline route selection. safety minute what is a typical pipeline project? there is no typical...

17
Pipeline Route Selection

Upload: neil-stevenson

Post on 29-Dec-2015

229 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Pipeline Route Selection

Page 2: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Safety Minute

Page 3: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

What is a Typical Pipeline Project?

There is no typical pipeline project since each pipeline project takes on its own unique challenges based on location, size of pipe, product to be transported and proposed schedule. What are the most important aspects of planning a successful pipeline project when project scheduling and budgeting are the overriding concerns of the client?

ROUTING→ENGINEERING→RIGHT-OF-WAY→SURVEY→MAPPING→ GIS→ENVIRONMENTAL→CONSTRUCTION

 

MOST IMPORTANT - ROUTING

Page 4: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

What is a Typical Pipeline Project?

Page 5: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

What is a Typical Pipeline Project?

Page 6: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

What is a Typical Pipeline Project?

Page 7: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Planning Phase

Project Kick-off

The routing team is usually comprised of an Engineering Project Manager, a Design Engineer, a Right-of-Way representative, an Environmental representative, a GIS representative, a Survey representative and a Construction representative.

By involving all groups impacted by the pipeline route selection to participate in the routing of the pipeline itself, each group is allowed the opportunity to look at issues and problems with a proposed route and suggest specific routing changes that may mitigate those issues or problems and avoid the need for expensive and time consuming re-routing of the pipeline later in the project.

In the initial stages of route selection, most of the basic routing is done in the office by the GIS specialist utilizing a Web based viewer that is customized for that specific project. This step requires the GIS specialist to download all publically available information that might have an impact on each of the project’s disciplines.

Page 8: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Planning Phase

Examples of information that might be searched out and made into data layers are as follows:

Recent aerial photography

All federal, state and local parks, wildlife management areas, forests, public lands

Tax maps and associated landowner information

Foreign pipelines and other utilities that cross the proposed route

Road, railroad and water body crossings

Jurisdictional boundaries of states, counties, cities

Native American ownership or interests

Federal and state threatened and endangered species

Wetlands and other environmentally sensitive properties

Page 9: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

GIS Viewer

The previous listing is a sample of the information that may be developed into data layers for eventual incorporation into the GIS viewer to use in preparing the desktop routing study.

In addition to specific data layers, there may also be functional attributes that impact the final selection of a pipeline’s route. An example of this would be if the new pipeline needs to loop or parallel an existing pipeline, the location and number of tie-ins with existing pipelines, or if the client wishes to avoid routing the pipeline in greenfield or environmentally sensitive areas.

In many instances, regulatory and resource management agencies can dictate the complete avoidance of impacts to environmentally sensitive areas in the development of the route. In most cases, when complete avoidance of environmentally sensitive areas is not possible, such regulatory and resource management agencies will request routing that minimizes and mitigates those impacts.

Page 10: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

GIS Viewer

When preparing the desktop routing study, these impacts are weighed and route deviations are developed, or construction techniques such as horizontal directional drills are used to avoid or minimize the impacts.

In addition to environmental factors, engineering and design issues such as the future location of pump/compressor stations, valve sites, storage yards, inter-connects, meter sites, temporary and extra temporary workspace, drill layouts, access roads, topography, hydraulics and numerous other variables are all taken into account in the selection of a successful pipeline route.

Page 11: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Areas of Concern

In the development of any pipeline route there are certain natural and man-made features that should be identified and avoided if at all possible.

The potential for coming into contact with these features increases depending on the location where the proposed pipeline will be built. Features such as Native American and federal lands are more common in the southwestern and western United States, while critical wetlands and Wetland Reserve Program (WRP) properties are more commonly found in the southeastern United States.

Man-made structures such as rivers and hurricane protection levees can require a large amount of engineering and planning prior to obtaining approval from those jurisdictions to cross land and features that those authorities own or manage.

Highways and railroads always have their own specific crossing requirements that need to be taken into consideration during the planning stage.

Page 12: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Areas of Concern

In recent years nature conservancy programs have increased in numbers and level of activity and can create a natural barrier to the pipeline’s routing depending on the language in the conservation easement and whether a utility corridor might have been reserved for such potential crossings.

In all cases, it is important to identify these potential barriers early in the routing process so they can be investigated to determine the best way to traverse the properties or decide if a re-route or slight route deviation will be required.

Page 13: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

To the Field

Once the route has been identified on the GIS viewer, and all the disciplines have provided input into the routing process, the routing team often travels to the actual site of the selected route to perform route verification by “ground-truthing” the route.

As with the desktop process, a core team will be selected to participate in this phase of the routing study as sending a large group of routing team members is not possible due to prohibitive travel costs or time constraints.

If the proposed pipeline route is a long cross country pipeline it might be more cost efficient to fly the route with either a helicopter or fixed winged aircraft and utilize video which can be used as a means of tying the route to fixed points using GPS. In this way the video can be reviewed and specific areas of concern can be visited on the ground.

Page 14: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

To the Field

In most cases the route verification by ground will be limited to looking at the proposed pipeline route from public roads.

When examining a route from public roads is the only alternative, the best practice is to take pictures at each public access points both upstream and downstream of the proposed route utilizing a GPS camera. The GPS identified pictures may then be downloaded at a later date and be made a part of the GIS database for the proposed route.

Page 15: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Important to Remember

In many cases the proposed pipeline project is still in the confidential stage and has not been introduced to the local residents, local governments or other local stakeholders. In such instances, special precautions must be taken to minimize any attention that would result in being questioned by potential stakeholders. Experienced route selection personnel have the skill to tell the truth, and be polite, but to also be as vague as possible so as not to divulge the name of the client or any information that may give details about the size or product to be transported by the proposed pipeline. If the initial contact with these stakeholders is a negative or intrusive, then future issues may arise with those same stakeholders when they are approached once again during the survey permission and acquisition stages of the project. Also, it is important to remember that any information provided to governmental agencies can become a matter of public record and can be requested through the Open Records Act. Therefore, inquiries to such agencies are handled much the same way as with private stakeholders, that is, with discreet and vague inquiries that will not unwittingly destroy the confidential nature of the project.

Page 16: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Using the Information

Once the proposed route has been defined and reviewed in the field the information is now ready to use in developing detailed cost estimates, routing maps for meetings, engineering studies and other project activities that will facilitate the authorization and approval of the pipeline project.

It is suggested that once the route is developed and the operating company is prepared to go public with the proposed project, a public relations plan be developed prior to any meetings with major stakeholders who may significantly affect the successful outcome of the project.

The acceptance, and approval of the proposed selected route by federal, state and local leaders is an important component to helping sell the project to the local communities and landowners impacted by the proposed pipeline themselves.

Page 17: Pipeline Route Selection. Safety Minute What is a Typical Pipeline Project? There is no typical pipeline project since each pipeline project takes on

Using the Information

A well selected route, chosen with input from all disciplines and proofed both in the office and the field can save money both in the time and labor to acquire that route, as well in the cost of the actual construction and materials used to build the pipeline itself. As mentioned above, there are literally hundreds of factors and variables that go into the selection of a pipeline route. How all these factors are taken into consideration during the routing phase of the project can often dictate the success or failure of the project itself.