piping installation works on pipe racks

38
Sadara Project ﻣﺷﺭﻭﻉ ﺻﺩﺍﺭﺓPolyethylene Envelope Transmittal Page: 1 of 1 Form Version: 23-Apr-2012 Sadara Unit(s) 455 460 470 Sadara Transmittal Sadara-L&T-T-1233 Issue Date 29 June 2013 Date Reply Needed N/A From Majid Al Majid To Mr. P. Sankaranarayanan Company L&T ATCO Subject SADARA Response to L&T-SADARA-T-882-13, Method Statement of Piping Installation Works on Pipe Racks (Rev.1) In respect of the above referenced transmittal; Accepted with comments. SADARA request L&T to resubmit the Method Statement after incorporating the comments in the attached file for our records. Subject File Name Date Rev Method Statement of Piping Installation Works on Pipe Racks (Rev.1) SA-RTIP-PEAAA-LTAT-50-5001- commented N/A N/A

Upload: hibari

Post on 10-Apr-2016

825 views

Category:

Documents


124 download

DESCRIPTION

aw

TRANSCRIPT

Sadara Project مشروع صدارة Polyethylene Envelope

Transmittal

Page: 1 of 1 Form Version: 23-Apr-2012

Sadara Unit(s) 455 460 470

Sadara Transmittal Sadara-L&T-T-1233

Issue Date 29 June 2013 Date Reply Needed N/A

From Majid Al Majid To Mr. P. Sankaranarayanan

Company L&T ATCO

Subject SADARA Response to L&T-SADARA-T-882-13, Method Statement of Piping Installation Works on Pipe Racks (Rev.1)

In respect of the above referenced transmittal;

Accepted with comments. SADARA request L&T to resubmit the Method Statement after incorporating the comments in the attached file for our records.

Subject File Name Date Rev Method Statement of Piping Installation Works

on Pipe Racks (Rev.1) SA-RTIP-PEAAA-LTAT-50-5001-

commented N/A N/A

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 1 of 12

PROJECT: SADARA POLYETHYELENE LSPB -1

CONTRACT NO: 10001 / 6600028371

CLIENT: SADARA

CONTRACTOR: LARSEN & TOUBRO ATCO SAUDI

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

(SA-RTIP-PEAAA-LTAT-50-5001)

1 28-May-13 Issued for Review and Approval KRK DKU CTK/PSN

0 21-Apr-13 Issued for Review & Comments KRK DKU CTK/PSN

Rev Date Description Prepared Reviewed Approved Approved

L&T L&T L&T SADARA

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 2 of 12

REVISION RECORD SHEET

Rev. No. Date Reason for

the revision Revision details/ Locations

0 21-Apr-13 Issued for

Review and Approval

Superseded

1 28-May-13 Issued for

Review and Approval All Sections has been modified

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 3 of 12

CONTENTS

1. PURPOSE……………………………………………………………………............................... 4

2. SCOPE……………………………………………………………………………………………… 4

3. REFERENCES………………………………………………………………............................... 4

4. RESPONSIBILITIES………………………………………………………………………………. 4

5. DEFINITIONS………………………………………………………………................................. 6

6. HSE REQUIREMENT……………………………………………………………………………....6

7. EQUIPMENT AND TOOLS……………………………………………………………………….. 7

8. MANPOWER……………………………………………………………………………………...... 7

9. GENERAL PREPARATORY WORKS…………………………………………………………… 8

10. WORK EXECUTION PROCEDURE………………………………………............................... 8

11. ATTACHMENTS…………………………………………………………………………………...12

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 4 of 12

1. PURPOSE

This method statement will serve as a guide line to carry out and complete the pipe installation works at pipe racks for Polyethylene SADARA Project.

2. SCOPE

This procedure will cover random pipes and pipe spools installation at pipe rack 640,565,500,440,305,350,400,235,200,220,150,700,750,775,825,850,905 for SADARA POLYETHYLENE LSPB PROJECT and to ensure that the entire recommendations are read and understood well prior to Start of erection works at site.

3. REFERENCES

� SADARA HSE Standard – A554-K-PRG-QM-GEN-PLN-004 � L&T ATCO HSE Standard – SA-RTIP-PEAAA-LTAT-50-9001 � Construction work detail procedure (Extra Length Management)- SA-RTIP-PEAAA-

LTAT-50-3047 � Construction work detail procedure (Welding Brazing) - SA-RTIP-PEAAA-LTAT-50-

3004 � Construction work detail procedure (spools cleaning) - SA-RTIP-PEAAA-LTAT-50-

0057 � Fabrication and Erection of On shore � ITP for AG Piping - SA-RTIP-PEAAA-LTAT-31-5001 � ASME B31.3 - Process piping � Shop Drawings & Erection Drawings � General welding requirements – RT85-6500-01

4. RESPONSIBILITIES

4.1 CONSTRUCTION MANAGER

� Schedule the project in logical steps and time required to meet deadlines. � Determine labor requirements and dispatch workers to construction sites � Inspect and review projects to monitor compliance with building and safety norms

and other regulations � Interpret and explain plans to staff and clients representing the L&T and SADARA

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 5 of 12

� Co-ordinate with all internal department and obtain necessary permit and licenses for smooth installation of structural activities

4.2 ENGINEERING DEPARTMENT

� Provide Technical Support to construction site execution section by providing drawings, procedures, material specifications, standard and technical specifications.

4.3 THE PIPING ENGINEER

� Piping Engineer is required to ensure that all the pipe installation works are carried out as per project specifications, approved drawings & HSE requirements.

� Conduct daily tool box talks, before the commencement of the scheduled work explain the hazards associated with the work and the mitigation measures.

� Strictly follow the project schedule and release of work front to other disciplines like E & I

� Responsible for taking and closure of required work permits from HSE.

4.4 QA/QC MANAGER

� Assist and coordinate with the construction manager and all personnel assigned to the project in establishing an overall Project Quality Management Plan based on approved standards.

� Responsible for ensuring that Project Quality Management policy, plans and procedures are implemented effectively and are suitable for the purposes and use for which they are intended.

� Coordinate and communicate with Client on Project Quality implementation � Coordination with QC-Inspectors(Piping and Welding)

4.5 THE PIPING QC INSPECTOR

� QC Inspector will ensure that all the line clearance activities that are required to be inspected have been inspected and approved as per the project requirements and QP.

� Accompany the company representative while carrying out inspections and release of hold points.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 6 of 12

� Qc Inspector will ensure that all fit-up’s inspection done and are according to Isometric and all supports are installed.

4.6 QC WELDING INSPECTOR

� Ensures Daily weld visual inspections are done, and monitor welder’s performance. � Ensures NDT offer are done as per specification requirements. � Ensures test packages NDT are cleared.

4.7 THE HSE SUPERVISOR

� HSE Supervisor will orient all erection people and provide sticker for competent people for identification & authorize to work at height.

� HSE Supervisor will ensure that the steel structural erection work is covered with valid elevated work permits including cold and hot work permit wherever applicable, and all permit & safety requirements are strictly followed.

� HSE Supervisor will ensure that daily tool box talks are carried out before the commencement of work, at all work locations, as per HSE Plan.

� HSE Supervisor will ensure that work locations are safe to work in & with appropriate safety signs and Barriers.

� Any unsafe act or conditions will be immediately stopped and reported to the HSE Manager and Construction Supervisor

� HSE Supervisor will Review and the implementation of Job Safety Analysis (JSA) and Method Statement.

5. DEFINITIONS

� Project - Sadara Polyethylene LSPB -1 � Company - Sadara Chemical Company � Contractor – L & T ATCO � Construction Supervisor - Contractor’s Supervisor � QC Inspector - Contractor’s Quality Control Inspector (Piping) � HSE - Health, Safety & Environment

6. HSE REQUIREMENT

� Safety goggles � Safety face shields

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 7 of 12

� Safety shoes � Dust masks � Safety helmet � Full body harness � Hand Gloves (Leather) � Reflecting Jacket � Ear Plugs

Client’s safety instruction & Project Safety regulations shall be strictly followed.

7. EQUIPMENT AND TOOLS

� Mobile/ Crawler cranes � Welding Machines � Pulley � Pulling cable � Chain block 2T,3T, 5T. � Man lift � Lifting Accessories � Trolley assembly � Nylon/ Teflon pipe rollers � Hand tools & fixtures as required

8. MANPOWER

� Piping superintendent � Piping supervisor � Rigger Foreman � Piping foreman � Riggers � Pipe fitters � Permit receiver � Fire watcher � Scaffolders � Crane operators � Welders � Mechanic technicians

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 8 of 12

� Man lift operators � Safety Supervisors

9. GENERAL PREPARATORY WORKS

� Pipe rack sections (640 ,565 ,500 ,440 ,305 ,350 ,400 ,235 ,200 ,220 ,150 ,700 ,750 ,775 ,825 ,850 ,905) should first be turned-over for pipe installation. Secure work transfer sheet from structural group.

� Scaffolding and access are ready for use. Major pipe rack will be provided with mat type scaffolds at elevations where most work will be done. Others will be provided with scaffold individually at work locations.

� Walkway outside the pipe rack shall be provided along with scaffolds. � Manpower, equipment, tools and other logistics are ready and prepared for

installation. � Lifeline to be provided for full length of working platform. � The delivered spools, random length and other materials for erection shall be

verified and checked as follow � Verify piping spools are as per required ISO drawing and check for any damages. � All spools shall be painted prior to erection. � All spools shall be internally cleaned prior to erection.

10. WORK EXECUTION PROCEDURE

10.1 PIPING INSTALLATION USING NYLON ROLLERS ON PIPE RACKS

� Pipe will be loaded using cranes into the extended scaffoldings at designated/ end of pipe rack.(Attached typical lift plan for PipeRack-640)

� Loading of spools on scaffolds is not allowed. � Install extended scaffolding at designated loading area at first level. Once the

erection of pipes at this level was completed, additional extended scaffold will be installed for the next elevation. Additional hanging scaffold with access walkway will be installed for fit-up and full welding of pipe joints and supports not accessible by the hanging mat scaffold.

� Install, align and fix the roller assemblies at rack beams. Nylon rollers will be employed primarily to move random lengths along the racks.

� Install required pulleys to complete with Chain block. The pulley and cable will be used to pull the pipes from loading end, along the rollers and to its final position

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 9 of 12

� Cranes will pick-up the pipes either directly from trailers or from temporary lay down nearby the pipe rack.

� Pipes will be lifted by cranes using correct nylon slings and will be rigged to position at rollers in working platform.

� Once the pipe is initially positioned at rollers (on two spans), hook the pipe to a Chain block. Pipe should be tied in such a way so as not to damage bevel at pipe end.

� When the pipe is being pulled, a watcher will check the travel of pipe such that it will safely and correctly ride the succeeding rollers. A signaling system for safe execution and control of pulling will be employed.

� Once the length of pipes reaches its destination, it will be removed from rollers using chain blocks.

� Pipe spools such as expansion loops, branch take offs and others will be placed directly in position using cranes or chain blocks where required. Fit up and welding of spooled pieces will be done in place utilizing the mat type scaffold or localized scaffold.

� For pipeline without attachments, a double ended welding execution will be adopted i.e. the first two random length rigged to positioned will be fitted up and full welded together. The succeeding lengths will be installed in the same manner. The double ended lengths are then welded together until the entire run is completed.

� Random Pipes will also be placed from selected intermediate columns also and will be pulled to their places and Aligned.

� During the installation process, if the gap between Grids is less, for erection feasibility chain block pulley will be used for the balancing of the spool in one end and the other end belt will used.

� At interconnecting pipe racks the same roller system will be utilized where new steel works is installed and when there are no obstructions.

� Other areas will utilize cranes or manual rigging method (sticking-out method) to directly install the spools and straight lengths into positions.

� Prior to full welding works, check the fitted up spool/ pipe joint for the following: � The surface is clean and free from paint, oil, dirt, scale, oxides and other foreign

materials. � The bevel angle, weld joint, root opening and alignment as per Isometric drawing

approved WPS. � Flange face is free from damage and scratches. � Weld seam is staggered so that longitudinal joint and also joints shall not touch the

bearing surfaces (structural steel) � Re-in forcing pad is provided with 6mm vent hole as per specification.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 10 of 12

� Socket welding gap is in accordance with specification. � Welding consumables should be in accordance with approved WPS. � All fit-ups shall be inspected by contractor or sub-contractor Piping inspector. � Submit request for inspection (RFI) of the fitted spool/ piping. � When fit-up is accepted, proceed full welding. � Welding process shall be as per approved WPS. Only qualified welders can do

welding works. Documents such as welding procedures and specification (WPS) and welders performance qualification record (WPQR) should be made available at site.

� All welding electrodes shall be backed and in site shall be stored in portable oven and shall have continuous power supply.

� During welding process, in-process inspection will be done by welding inspector and will be verifying the following items

� Welding consumables are in accordance with the approved WPS. � Required pre-heat/ inter-pass temperature requirements are done as per approved

WPS. � Purging requirement, as applicable, is being maintained as per approved WPS.

10.2 AFTER WELDING WAS COMPLETED, VISUAL INSPECTION WILL BE DONE CHECKING THE FOLLOWING ITEMS, AS APPLICABLE

� Inside surface of orifice flanges welded joints is ground or machined smooth. � Threaded joints must be checked for fit and roundness as per spec. no. � Weld surface reinforcement in accordance with ASME B31.3 table 341.3.2 � Dimensions of fillet weld in-accordance with ASME B31.3 fig.328.5.2B and

328.5.4D � Root pass in accordance approved WPS. � Arc strikes in areas not covered by the finished weld and grounds. � Temporary materials used are already removed as per spec. � Cleanliness of pipe shall be maintained as per spec. no. The weld spatter, slag,

flux and other foreign materials are removed. � Welders ID, Weld no., and line no & WPS. Shall be marked with permanent marker

on the pipe next to the weld. � Completed weld shall be subjected to require NDE as per line Class. � PMI as required shall be conducted. And marking shall be done as per PMI

procedure PWHT.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 11 of 12

� Hardness test as required on some joints shall also be conducted as required by line class. As per approved weld repair procedure.

� Rejected weld will be repaired and will under-go visual inspection as per above mentioned and required NDE as per above

� For threaded line installation, refer specification, method statement of Deluge piping system specification no only gasket installation and inspection.

� Bolt Tightening shall be done by trained persons, in sequence to produce even compression and uniform bolt loads Torque wrench used shall be calibrated valves shall be set daily When using stud tensioner, the manufacturer’s procedure must be followed. The bolt used shall be checked for conformance with the ISO drawing.

� For pipelines with shoes, saddle, others, this attachment will be Tac weld to the pipe after being rigged to position. Shoes and saddle shall be positioned such that it will align and rest properly at beams or supports. Prior to full welding the alignment, support location and orientation must be checked and verified with latest approved drawings. The supports used should be in accordance with the latest approved IFC drawings.

� Pipe Supports to be Over Head welded by only trained welders and cleaning will by means mechanical cleaning.

� For supports directly weld to Alloy pipes, PMI (If Required) shall also be conducted � Pipe stoppers and guides shall be full welded and painted. � Prior to closure of piping section, full compliance with internal cleanliness

inspection and documentation shall be ensured in. � Piping installation at pipe rack areas

640,565,500,700,445,305,440,235,350,400,200,150,905,850,etc., will be done as applicable.

10.3 SAFETY PRECAUTIONS

� Obtain the approval of the work permit from the concerned PERMIT department before starting any work.

� Fire watcher with fire extinguisher shall be at work area whenever there is hot work.

� All electrical tools shall be checked and color-coded. � Continuous monitoring and inspection shall be implemented to detect and correct

unsafe practices while performing the work activities. � Provide warning signs and sufficient barricade on working area and only assigned

personnel will be allowed in the area.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 12 of 12

� Welding location shall be enclosed with wind barrier and provided with non-asbestos fire blanket to prevent spread of any welding sparks.

� Safety officer shall monitor the work activities to help and to protect all assigned workers against exposure to safety hazards. He shall ensure that personnel protection equipment (PPE’S) are supplied and used and comply with L & T/SADARA applicable general instruction and standards.

� Safety harness with double lanyards shall be used all the time when working at elevated temporary platforms.

� Man-lift users shall be trained and certified to operate.

11. ATTACHMENTS

� JSA for AG Piping Installation works � Lifting plan of AG Piping

460 470

The Following Drawings Specification Schedule

Data Sheets Calculation Material Requisition

Are Transmitted TBE Vendor Document MOM

Acceptance/Approval Review Information

This is Record Quatation Construction

Original Revision Final

Size No. of Copies

Receipt Not RequiredReceipt Required (Please Acknowlegde the Receipt of the Duplicate and Return)The Above Documents Received By:

Signature: Name:

John HufnagelJulian Archer

Drawings / File Name Description

To Majid Al Majid

Rev. No.

cc Mark Williams

455

L&T-Sadara-T-882/13

29-May-13 Date Reply Needed 30-May-13

Date:

Alshobber Khalid

1 Method Statement of Piping Installation Works on Pipe Racks

Transmittal

Subject

C.T KuriakoseD.K UpadhayM.K Sankar

Sadara Unit (s)

L&T Transmittal

Issue Date

From

cc

Company

Method Statement of Piping Installation Works on Pipe Racks (Revision 1)

P.Sankaranarayanan

Sadara

*** Nothing Follows ***

SA-RTIP-PEAAA-LTAT-50-5001 A4 1

X

X X

X X

X

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 1 of 12

PROJECT: SADARA POLYETHYELENE LSPB -1

CONTRACT NO: 10001 / 6600028371

CLIENT: SADARA

CONTRACTOR: LARSEN & TOUBRO ATCO SAUDI

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

(SA-RTIP-PEAAA-LTAT-50-5001)

1 28-May-13 Issued for Review and Approval KRK DKU CTK/PSN

0 21-Apr-13 Issued for Review & Comments KRK DKU CTK/PSN

Rev Date Description Prepared Reviewed Approved Approved

L&T L&T L&T SADARA

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 2 of 12

REVISION RECORD SHEET

Rev. No. Date Reason for

the revision Revision details/ Locations

0 21-Apr-13 Issued for

Review and Approval

Superseded

1 28-May-13 Issued for

Review and Approval All Sections has been modified

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 3 of 12

CONTENTS

1. PURPOSE……………………………………………………………………............................... 4

2. SCOPE……………………………………………………………………………………………… 4

3. REFERENCES………………………………………………………………............................... 4

4. RESPONSIBILITIES………………………………………………………………………………. 4

5. DEFINITIONS………………………………………………………………................................. 6

6. HSE REQUIREMENT……………………………………………………………………………....6

7. EQUIPMENT AND TOOLS……………………………………………………………………….. 7

8. MANPOWER……………………………………………………………………………………...... 7

9. GENERAL PREPARATORY WORKS…………………………………………………………… 8

10. WORK EXECUTION PROCEDURE………………………………………............................... 8

11. ATTACHMENTS…………………………………………………………………………………...12

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 4 of 12

1. PURPOSE

This method statement will serve as a guide line to carry out and complete the pipe installation works at pipe racks for Polyethylene SADARA Project.

2. SCOPE

This procedure will cover random pipes and pipe spools installation at pipe rack 640,565,500,440,305,350,400,235,200,220,150,700,750,775,825,850,905 for SADARA POLYETHYLENE LSPB PROJECT and to ensure that the entire recommendations are read and understood well prior to Start of erection works at site.

3. REFERENCES

� SADARA HSE Standard – A554-K-PRG-QM-GEN-PLN-004 � L&T ATCO HSE Standard – SA-RTIP-PEAAA-LTAT-50-9001 � Construction work detail procedure (Extra Length Management)- SA-RTIP-PEAAA-

LTAT-50-3047 � Construction work detail procedure (Welding Brazing) - SA-RTIP-PEAAA-LTAT-50-

3004 � Construction work detail procedure (spools cleaning) - SA-RTIP-PEAAA-LTAT-50-

0057 � Fabrication and Erection of On shore � ITP for AG Piping - SA-RTIP-PEAAA-LTAT-31-5001 � ASME B31.3 - Process piping � Shop Drawings & Erection Drawings � General welding requirements – RT85-6500-01

4. RESPONSIBILITIES

4.1 CONSTRUCTION MANAGER

� Schedule the project in logical steps and time required to meet deadlines. � Determine labor requirements and dispatch workers to construction sites � Inspect and review projects to monitor compliance with building and safety norms

and other regulations � Interpret and explain plans to staff and clients representing the L&T and SADARA

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 5 of 12

� Co-ordinate with all internal department and obtain necessary permit and licenses for smooth installation of structural activities

4.2 ENGINEERING DEPARTMENT

� Provide Technical Support to construction site execution section by providing drawings, procedures, material specifications, standard and technical specifications.

4.3 THE PIPING ENGINEER

� Piping Engineer is required to ensure that all the pipe installation works are carried out as per project specifications, approved drawings & HSE requirements.

� Conduct daily tool box talks, before the commencement of the scheduled work explain the hazards associated with the work and the mitigation measures.

� Strictly follow the project schedule and release of work front to other disciplines like E & I

� Responsible for taking and closure of required work permits from HSE.

4.4 QA/QC MANAGER

� Assist and coordinate with the construction manager and all personnel assigned to the project in establishing an overall Project Quality Management Plan based on approved standards.

� Responsible for ensuring that Project Quality Management policy, plans and procedures are implemented effectively and are suitable for the purposes and use for which they are intended.

� Coordinate and communicate with Client on Project Quality implementation � Coordination with QC-Inspectors(Piping and Welding)

4.5 THE PIPING QC INSPECTOR

� QC Inspector will ensure that all the line clearance activities that are required to be inspected have been inspected and approved as per the project requirements and QP.

� Accompany the company representative while carrying out inspections and release of hold points.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 6 of 12

� Qc Inspector will ensure that all fit-up’s inspection done and are according to Isometric and all supports are installed.

4.6 QC WELDING INSPECTOR

� Ensures Daily weld visual inspections are done, and monitor welder’s performance. � Ensures NDT offer are done as per specification requirements. � Ensures test packages NDT are cleared.

4.7 THE HSE SUPERVISOR

� HSE Supervisor will orient all erection people and provide sticker for competent people for identification & authorize to work at height.

� HSE Supervisor will ensure that the steel structural erection work is covered with valid elevated work permits including cold and hot work permit wherever applicable, and all permit & safety requirements are strictly followed.

� HSE Supervisor will ensure that daily tool box talks are carried out before the commencement of work, at all work locations, as per HSE Plan.

� HSE Supervisor will ensure that work locations are safe to work in & with appropriate safety signs and Barriers.

� Any unsafe act or conditions will be immediately stopped and reported to the HSE Manager and Construction Supervisor

� HSE Supervisor will Review and the implementation of Job Safety Analysis (JSA) and Method Statement.

5. DEFINITIONS

� Project - Sadara Polyethylene LSPB -1 � Company - Sadara Chemical Company � Contractor – L & T ATCO � Construction Supervisor - Contractor’s Supervisor � QC Inspector - Contractor’s Quality Control Inspector (Piping) � HSE - Health, Safety & Environment

6. HSE REQUIREMENT

� Safety goggles � Safety face shields

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 7 of 12

� Safety shoes � Dust masks � Safety helmet � Full body harness � Hand Gloves (Leather) � Reflecting Jacket � Ear Plugs

Client’s safety instruction & Project Safety regulations shall be strictly followed.

7. EQUIPMENT AND TOOLS

� Mobile/ Crawler cranes � Welding Machines � Pulley � Pulling cable � Chain block 2T,3T, 5T. � Man lift � Lifting Accessories � Trolley assembly � Nylon/ Teflon pipe rollers � Hand tools & fixtures as required

8. MANPOWER

� Piping superintendent � Piping supervisor � Rigger Foreman � Piping foreman � Riggers � Pipe fitters � Permit receiver � Fire watcher � Scaffolders � Crane operators � Welders � Mechanic technicians

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 8 of 12

� Man lift operators � Safety Supervisors

9. GENERAL PREPARATORY WORKS

� Pipe rack sections (640 ,565 ,500 ,440 ,305 ,350 ,400 ,235 ,200 ,220 ,150 ,700 ,750 ,775 ,825 ,850 ,905) should first be turned-over for pipe installation. Secure work transfer sheet from structural group.

� Scaffolding and access are ready for use. Major pipe rack will be provided with mat type scaffolds at elevations where most work will be done. Others will be provided with scaffold individually at work locations.

� Walkway outside the pipe rack shall be provided along with scaffolds. � Manpower, equipment, tools and other logistics are ready and prepared for

installation. � Lifeline to be provided for full length of working platform. � The delivered spools, random length and other materials for erection shall be

verified and checked as follow � Verify piping spools are as per required ISO drawing and check for any damages. � All spools shall be painted prior to erection. � All spools shall be internally cleaned prior to erection.

10. WORK EXECUTION PROCEDURE

10.1 PIPING INSTALLATION USING NYLON ROLLERS ON PIPE RACKS

� Pipe will be loaded using cranes into the extended scaffoldings at designated/ end of pipe rack.(Attached typical lift plan for PipeRack-640)

� Loading of spools on scaffolds is not allowed. � Install extended scaffolding at designated loading area at first level. Once the

erection of pipes at this level was completed, additional extended scaffold will be installed for the next elevation. Additional hanging scaffold with access walkway will be installed for fit-up and full welding of pipe joints and supports not accessible by the hanging mat scaffold.

� Install, align and fix the roller assemblies at rack beams. Nylon rollers will be employed primarily to move random lengths along the racks.

� Install required pulleys to complete with Chain block. The pulley and cable will be used to pull the pipes from loading end, along the rollers and to its final position

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 9 of 12

� Cranes will pick-up the pipes either directly from trailers or from temporary lay down nearby the pipe rack.

� Pipes will be lifted by cranes using correct nylon slings and will be rigged to position at rollers in working platform.

� Once the pipe is initially positioned at rollers (on two spans), hook the pipe to a Chain block. Pipe should be tied in such a way so as not to damage bevel at pipe end.

� When the pipe is being pulled, a watcher will check the travel of pipe such that it will safely and correctly ride the succeeding rollers. A signaling system for safe execution and control of pulling will be employed.

� Once the length of pipes reaches its destination, it will be removed from rollers using chain blocks.

� Pipe spools such as expansion loops, branch take offs and others will be placed directly in position using cranes or chain blocks where required. Fit up and welding of spooled pieces will be done in place utilizing the mat type scaffold or localized scaffold.

� For pipeline without attachments, a double ended welding execution will be adopted i.e. the first two random length rigged to positioned will be fitted up and full welded together. The succeeding lengths will be installed in the same manner. The double ended lengths are then welded together until the entire run is completed.

� Random Pipes will also be placed from selected intermediate columns also and will be pulled to their places and Aligned.

� During the installation process, if the gap between Grids is less, for erection feasibility chain block pulley will be used for the balancing of the spool in one end and the other end belt will used.

� At interconnecting pipe racks the same roller system will be utilized where new steel works is installed and when there are no obstructions.

� Other areas will utilize cranes or manual rigging method (sticking-out method) to directly install the spools and straight lengths into positions.

� Prior to full welding works, check the fitted up spool/ pipe joint for the following: � The surface is clean and free from paint, oil, dirt, scale, oxides and other foreign

materials. � The bevel angle, weld joint, root opening and alignment as per Isometric drawing

approved WPS. � Flange face is free from damage and scratches. � Weld seam is staggered so that longitudinal joint and also joints shall not touch the

bearing surfaces (structural steel) � Re-in forcing pad is provided with 6mm vent hole as per specification.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 10 of 12

� Socket welding gap is in accordance with specification. � Welding consumables should be in accordance with approved WPS. � All fit-ups shall be inspected by contractor or sub-contractor Piping inspector. � Submit request for inspection (RFI) of the fitted spool/ piping. � When fit-up is accepted, proceed full welding. � Welding process shall be as per approved WPS. Only qualified welders can do

welding works. Documents such as welding procedures and specification (WPS) and welders performance qualification record (WPQR) should be made available at site.

� All welding electrodes shall be backed and in site shall be stored in portable oven and shall have continuous power supply.

� During welding process, in-process inspection will be done by welding inspector and will be verifying the following items

� Welding consumables are in accordance with the approved WPS. � Required pre-heat/ inter-pass temperature requirements are done as per approved

WPS. � Purging requirement, as applicable, is being maintained as per approved WPS.

10.2 AFTER WELDING WAS COMPLETED, VISUAL INSPECTION WILL BE DONE CHECKING THE FOLLOWING ITEMS, AS APPLICABLE

� Inside surface of orifice flanges welded joints is ground or machined smooth. � Threaded joints must be checked for fit and roundness as per spec. no. � Weld surface reinforcement in accordance with ASME B31.3 table 341.3.2 � Dimensions of fillet weld in-accordance with ASME B31.3 fig.328.5.2B and

328.5.4D � Root pass in accordance approved WPS. � Arc strikes in areas not covered by the finished weld and grounds. � Temporary materials used are already removed as per spec. � Cleanliness of pipe shall be maintained as per spec. no. The weld spatter, slag,

flux and other foreign materials are removed. � Welders ID, Weld no., and line no & WPS. Shall be marked with permanent marker

on the pipe next to the weld. � Completed weld shall be subjected to require NDE as per line Class. � PMI as required shall be conducted. And marking shall be done as per PMI

procedure PWHT.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 11 of 12

� Hardness test as required on some joints shall also be conducted as required by line class. As per approved weld repair procedure.

� Rejected weld will be repaired and will under-go visual inspection as per above mentioned and required NDE as per above

� For threaded line installation, refer specification, method statement of Deluge piping system specification no only gasket installation and inspection.

� Bolt Tightening shall be done by trained persons, in sequence to produce even compression and uniform bolt loads Torque wrench used shall be calibrated valves shall be set daily When using stud tensioner, the manufacturer’s procedure must be followed. The bolt used shall be checked for conformance with the ISO drawing.

� For pipelines with shoes, saddle, others, this attachment will be Tac weld to the pipe after being rigged to position. Shoes and saddle shall be positioned such that it will align and rest properly at beams or supports. Prior to full welding the alignment, support location and orientation must be checked and verified with latest approved drawings. The supports used should be in accordance with the latest approved IFC drawings.

� Pipe Supports to be Over Head welded by only trained welders and cleaning will by means mechanical cleaning.

� For supports directly weld to Alloy pipes, PMI (If Required) shall also be conducted � Pipe stoppers and guides shall be full welded and painted. � Prior to closure of piping section, full compliance with internal cleanliness

inspection and documentation shall be ensured in. � Piping installation at pipe rack areas

640,565,500,700,445,305,440,235,350,400,200,150,905,850,etc., will be done as applicable.

10.3 SAFETY PRECAUTIONS

� Obtain the approval of the work permit from the concerned PERMIT department before starting any work.

� Fire watcher with fire extinguisher shall be at work area whenever there is hot work.

� All electrical tools shall be checked and color-coded. � Continuous monitoring and inspection shall be implemented to detect and correct

unsafe practices while performing the work activities. � Provide warning signs and sufficient barricade on working area and only assigned

personnel will be allowed in the area.

SADARA Polyethylene LSPB-1 Project

METHOD STATEMENT FOR PIPING INSTALLATION WORKS ON PIPE RACKS

Date Doc. No Rev. No Page

28-May-13 SA-RTIP-PEAAA-LTAT-50-5001 1 Page 12 of 12

� Welding location shall be enclosed with wind barrier and provided with non-asbestos fire blanket to prevent spread of any welding sparks.

� Safety officer shall monitor the work activities to help and to protect all assigned workers against exposure to safety hazards. He shall ensure that personnel protection equipment (PPE’S) are supplied and used and comply with L & T/SADARA applicable general instruction and standards.

� Safety harness with double lanyards shall be used all the time when working at elevated temporary platforms.

� Man-lift users shall be trained and certified to operate.

11. ATTACHMENTS

� JSA for AG Piping Installation works � Lifting plan of AG Piping

LA

RSE

N A

ND

TO

UB

RO

ATC

O

JOB

SA

FETY

AN

ALY

SIS

(JSA

)

JSA

No:

66

DA

TE :

26

-05-

2013

R

EVIS

ION

NO

: 0

4 A

UTH

OR

ISA

TIO

N:

(Te

am L

eade

r /

Coo

rdin

ator

/ S

uper

viso

r)

Sign

ed :

____

____

____

____

____

____

____

____

JSA

TEA

M M

EMB

ERS

1. D

K U

padh

ya

2.

Ram

a kr

ishn

a

3.

Chris

tian

4. M

ahes

h pi

ngal

i

Sign

ed :

(

JSA

Team

Lea

der)

JOB

LO

CA

TIO

N:

Sada

ra, P

olye

thel

ene

Pro

ject

– A

G P

ipin

g In

stal

lati

on w

ork

JOB

DES

CR

IPTI

ON

: P

ipin

g Er

ecti

on &

fab

rica

tion

wor

ks –

Gas

cut

ting

, gri

ndin

g, w

eldi

ng

W

OR

K T

EAM

MEM

BER

S

P

ERSO

NA

L P

RO

TEC

TIV

E EQ

UIP

MEN

T R

EQU

IREM

ENTS

P

LAN

T, E

QU

IPM

ENT

&

TOO

LS

IS

OLA

TIO

N, T

AG

GIN

G,

BA

RR

ICA

DES

, SIG

NS

&

LIC

ENSE

S

En

viro

nm

enta

l Con

trol

s (B

un

din

g, W

aste

D

ispo

sal,

Dis

char

ge

Pre

ven

tion

, etc

) N

AME

(prin

t)

SIG

NAT

URE

Sa

fety

Hel

met

H

andt

ools

Pe

rmit

( H

ot w

ork)

W

aste

Bin

Sa

fety

gla

sses

( C

lear

/ B

lack

) Po

wer

too

ls

Barr

icad

es

Fire

figh

ting

equi

pmen

ts

Safe

ty S

hoes

( w

ith s

teel

toe

s)

Wel

ding

Gen

erat

or

Sign

Boa

rds

H

and

glov

es (

Leat

her/

wel

ding

) O

xy-A

cety

lene

cut

ting

set

Fire

wat

cher

Dus

t m

ask

, Wel

ding

Hel

met

Ai

r Co

mpr

esso

r Ce

rtifi

ed f

lagm

an

H

i viz

ves

t, f

ace

shie

ld

Fire

Ext

ingu

ishe

r Sc

affo

ld t

ags

H

earin

g Pr

otec

tion.

Fi

re B

lank

et

Leat

her

Apro

n,Le

g gu

ard

Pipe

Sup

port

s

PE

RMIT

S Pi

pe A

djus

tabl

e st

and

Conf

ined

Sp

aces

Cold

W

ork

D

PT, M

PT t

ool k

it

Exca

vatio

n

Gas

Fork

lift

Is

olat

ion

H

ot W

ork

Ch

ain

bloc

ks

Nyl

on B

elts

JOB

HAZ

ARD

AN

ALYS

IS (

JSA)

WO

RKSH

EET

SL

. No

JOB

STEP

H

AZAR

D

RISK

RE

QU

IRED

CO

NTR

OL

MEA

SURE

S 01

Pe

rmit

to w

ork

/ Pr

e -st

art

mee

ting

Inco

rrec

t I n

form

atio

n In

jury

/ D

amag

e a

s a

resu

lt of

in

corr

ect

info

rmat

ion

Obt

ain

corr

ect

hot

wor

k pe

rmit.

Dai

ly b

asis

Pre

sta

rt m

eetin

g an

d S

TART

car

d

02

Mob

iliza

tion

of

man

pow

er a

nd

equi

pmen

t.

Inco

mpe

tenc

y or

lack

of

tra

inin

g.

Equi

pmen

t co

llisi

on.

Pers

onal

Inj

ury

Prop

erty

dam

age

Enga

ge c

ompe

tent

man

pow

er.

HSE

Ind

uctio

n of

em

ploy

ees

to b

e co

mpl

eted

. Pe

rmit

to W

ork

to b

e ob

tain

ed for

the

spe

cific

job.

Ar

ea t

o be

cor

done

d of

f to

pre

vent

ent

ry o

f th

e un

auth

oriz

ed

pers

ons.

Ac

cess

to

emer

genc

y ve

hicl

e sh

all n

ot b

e bl

ocke

d.

Man

dato

ry P

PE (

Cove

rall,

Har

d ha

t, S

afet

y Sh

oes.

Saf

ety

spec

tacl

e G

love

s) t

o be

use

d.

Rout

e su

rvey

to

be d

one

befo

re t

rans

port

atio

n.

Trai

ned

flag

man

sha

ll be

ass

igne

d to

con

trol

the

T

raff

ic &

veh

icle

s w

ith f

luor

esce

nt ja

cket

. 03

Fo

rklif

t m

ovem

ent

with

Mat

eria

ls.

(Str

uctu

ral,

Pipe

s Sp

ools

& P

roje

ct

mat

eria

ls e

tc.)

Stru

ck b

y lo

ads.

Ro

llove

r of

pip

e fr

om

the

fork

. Fa

ll of

load

s.

Vehi

cula

r co

llisi

on

equi

pmen

t

Tum

ble

dow

n.

Pers

onne

l Inj

ury

/ A

sset

s D

amag

e Al

l mov

emen

ts t

o be

mad

e sl

owly

, sm

ooth

ly &

with

out

jerk

ing.

W

hile

tra

velli

ng w

ith t

he lo

ad, k

eep

the

mas

t til

ted

back

and

low

w

ith t

he fo

rks

15cm

to

20cm

abo

ve t

he g

roun

d.

Don

’t ra

ise

or lo

wer

the

load

whi

le m

ovin

g. (

This

effe

cts

stab

ility

of

mac

hine

) Tr

aine

d fo

rklif

t op

erat

or o

nly

to u

se fo

rklif

t.

Ensu

re F

lagm

an is

qua

lifie

d an

d at

tend

ed t

he t

rain

ing

for

Flag

man

. Fla

gman

ens

u res

tha

t un

auth

oriz

ed p

erso

nals

are

aw

ay fr

om t

he r

oute

. Fl

agm

an s

hall

be e

quip

ped

with

hig

h vi

sibi

lity

vest

, whi

stle

&

flags

(red

& g

reen

) To

pics

on

safe

lift

ing

and

fork

lift

mov

emen

t sh

all b

e di

scus

sed

regu

larly

dur

ing

daily

too

l box

tal

k G

roun

d so

il sh

all b

e le

velle

d co

mpa

cted

. Ens

ure

that

gro

und

soil

to b

e re

-leve

lled

com

pact

ed if

it w

as s

poile

d /d

istu

rbed

by

rain

. Li

ftin

g ap

plia

nce

mus

t no

t be

allo

wed

to

be o

pera

ted

in u

neve

n su

rfac

e W

here

/whe

n po

ssib

le s

ecur

e le

vel w

hen

mov

ing.

04

Grin

ding

job

by

usin

g of

Ang

le

grin

der

and

penc

il gr

inde

r w

ith 1

10V

Dis

c br

eaka

ge

Inha

latio

n H

azar

d(Fu

mes

& D

ust)

Fi

re H

azar

ds

Pers

onne

l inj

ury

Grin

ding

Dis

c sh

ould

hav

e hi

gher

RPM

rat

ing

than

the

grin

ding

m

achi

ne’s

RPM

. En

sure

the

dis

c is

tho

roug

hly

insp

ecte

d ag

ains

t an

y da

mag

es

prio

r to

inst

alla

tion.

En

sure

insp

ectio

n/co

lour

cod

e (F

it to

use

) M

ake

sure

tha

t th

e di

sc g

uard

is in

sou

nd c

ondi

tion

and

in p

lace

. En

sure

dis

c is

wel

l tig

hten

ed t

o gr

inde

r En

sure

onl

y tr

aine

d pe

rson

sha

ll op

erat

e th

e gr

indi

ng m

achi

ne.

Airb

orne

dus

t an

d bi

ts

of m

etal

par

ticle

s co

min

g fr

om t

he

stru

ctur

es

Pers

onal

inju

ry

Ensu

re t

he d

isc

is t

horo

ughl

y in

spec

ted

agai

nst

any

dam

ages

pr

ior

to in

stal

latio

n.

M

ake

sure

tha

t th

e di

sc g

uard

is in

sou

nd c

ondi

tion

and

in p

lace

. W

ear

Han

d an

d ey

e pr

otec

tion.

En

sure

han

dles

are

use

d as

grin

ders

.

Noi

se a

nd v

ibra

tion

Hig

h le

vel o

f no

ise

can

resu

lt in

te

mpo

rary

or

perm

anen

t he

arin

g da

mag

e.

Expo

sure

to

vibr

atio

n ca

n ca

use

wor

k re

late

d up

per

limb

diso

rder

s

Appr

opria

te h

earin

g pr

otec

tion

mus

t be

wor

n at

all

times

. Al

tern

ate

war

ning

sys

tem

to

be p

ut in

pla

ce.

Wea

r sa

fety

gog

gles

& e

ar p

lugs

Safe

ty g

uard

s to

be

fitte

d En

sure

sig

nage

is in

pla

ce.

Rota

ting

whe

el/

Dam

age

to w

heel

Clot

hing

, hai

r or

lim

bs c

an b

ecom

e en

tang

led

in e

quip

men

t re

sulti

ng in

in

jury

Insp

ect

the

grin

der

befo

re u

se.

Onl

y tr

aine

d an

d co

mpe

tent

per

sons

to

oper

ate

equi

pmen

t

Spar

ks a

nd f

lyin

g de

bris

Flyi

ng d

ebris

can

cau

se s

erio

us

dam

age

to e

yes.

Wea

r sa

fety

gog

gles

& f

ace

shie

ld.(

Dou

ble

eye

prot

ectio

n)

Prov

ide

Fire

Ext

ingu

ishe

r En

sure

tha

t th

ere

is n

o co

mbu

stib

le m

ater

ial i

n w

ork

area

. En

sure

fire

wat

cher

insp

ect

the

area

,30-

60 m

inut

es a

fter

wor

k is

fin

ishe

d.

Dis

inte

grat

ion

of

whe

els

or a

cces

sorie

s in

chu

ck o

f too

ls

Serio

us in

jury

to

pers

onne

l

Ensu

re p

rope

r w

heel

of co

rrec

t si

ze a

nd s

peed

. W

ear

prop

er P

PE, e

spec

ially

for

the

eyes

, N

ever

use

cut

ting

whe

els

for

grin

ding

, nev

er r

emov

e gu

ards

, dr

op w

heel

, etc

.

Elec

tric

sho

ck fr

om

dam

aged

too

l or

cabl

e

Dea

th o

r se

rious

inju

ry

Insp

ect

equi

pmen

t/ c

able

s be

fore

use

. O

nly

110V

equ

ipm

ent

is a

llow

ed f

or H

and

Tool

s D

o no

t us

e eq

uipm

ent

in w

et c

ondi

tion

No

conn

ectio

n/jo

int

cabl

e no

t al

low

ed.

Ensu

re o

ver

ride

switc

h is

rem

oved

.

05

Wel

ding

of

Pipe

s &

str

uctu

res

Fire

Burn

, Pro

pert

y D

amag

e

All p

erm

it re

quire

men

t sh

all b

e in

pla

ce b

efor

e st

art

the

hot

wor

k,

Area

HSE

sha

ll in

spec

t th

e w

ork

area

bef

ore

star

t an

y ho

t w

ork

activ

ity. R

emov

e fla

mm

able

mat

eria

ls.

Ensu

re p

rope

r su

perv

isio

n is

in p

lace

. En

sure

cor

rect

usa

ge o

f man

dato

ry P

PE's

(Fi

re R

etar

dant

Co

vera

ll/Ap

ron,

Har

d ha

t, S

afet

y Sh

oes,

Saf

ety

spec

tacl

e,

Glo

ves)

and

spe

cific

PPE

suc

h as

, w

elde

r’s le

athe

r gl

oves

,

Splin

ters

/sla

g

Burn

s in

jury

to

the

skin

wel

ding

hel

met

etc

: En

sure

pro

per

hous

e ke

epin

g al

l the

tim

e.

Ensu

re p

rope

r ea

rthl

ing

conn

ectio

ns.

Ensu

re t

hat

all c

able

s, e

lect

rode

hol

der,

ele

ctro

de o

vens

are

in

good

con

ditio

ns

Ensu

re a

dequ

ate

fire

fight

ing

equi

pmen

t an

d fir

e bl

anke

ts a

nd

fire

wat

ch a

re in

pla

ce.

Ensu

re t

he w

eldi

ng g

ener

ator

s ar

e eq

uipp

ed w

ith E

LCB

DB.

N

ever

pla

ce e

lect

rode

ove

n on

woo

den

surf

ace

whe

n in

use

. El

ectr

ode

stub

s sh

all b

e pr

oper

ly c

olle

cted

in c

onta

iner

s, t

ins.

Be

fore

sta

rtin

g th

e jo

b en

sure

tha

t al

l cab

les

& e

quip

men

t ar

e in

go

od c

ondi

tion

Ensu

re t

hat

all c

able

s ar

e ro

uted

pro

perly

and

pro

tect

ed f

rom

sh

arp

edge

Ca

ble

join

t is

not

allo

wed

. Tr

aine

d Fi

re w

atch

er s

hall

mon

itor

the

wor

k ac

tiviti

es a

nd

ensu

re t

hat

all t

he s

afet

y de

vice

s ha

s be

en in

spec

ted

and

in

wor

king

con

ditio

n 30

-60

min

utes

aft

er w

ork.

Re

mov

e al

l the

fla

mm

able

mat

eria

ls w

ithin

the

50

feet

of ho

t w

ork

activ

ities

. En

sure

tha

t th

ere

is n

o co

mbu

stib

le in

wor

k ar

ea w

ithin

50

feet

pe

rimet

er, P

rovi

de f

ire e

xtin

guis

her.

W

elde

rs w

ear

clea

r sa

fety

gla

sses

und

er fo

ods.

In

spec

t w

ork

plac

e fo

r an

y fla

min

g ite

ms

at t

he e

nd o

f th

e sh

ift

Fire

pro

of a

pron

/ gl

oves

/ sc

reen

. Re

mov

e th

e RE

FLEC

TIVE

JAC

KET,

is f

lam

mab

le!

DPT

& M

PT T

estin

g on

w

eld.

Pe

rson

al in

jury

Ensu

re c

orre

ct u

sage

of m

anda

tory

PPE

's S

afet

y Sh

oes,

Saf

ety

spec

tacl

es, G

love

s, M

asks

etc

.

Fall

of jo

b pi

ece

(the

jo

b be

ing

wel

ded)

In

jury

to

the

pers

onne

l/ cr

ash

inju

ry

Prov

ide

prop

er c

lam

p an

d su

ppor

t.

Ensu

re w

eldi

ng e

quip

men

t in

spec

ted.

Elec

tric

al S

hock

.

Elec

tric

sho

ck/

serio

us in

jury

/ fa

tal

inci

dent

El

ectr

ic B

urns

/ S

hock

Prop

er m

aint

enan

ce

Ensu

re w

eldi

ng m

achi

ne is

bei

ng e

arth

ed.

Ensu

re t

hat

elec

trod

e ho

lder

is in

sula

ted

Ensu

re t

hat

ther

e ar

e no

exp

osed

wire

s.

GFC

I Re

quire

d.

Usi

ng U

- Fo

ams

for

S.S.

wel

ding

U

se d

oubl

e in

sula

ted

or p

rope

rly g

roun

ded

equi

pmen

t .E

nsur

e al

l ele

ctric

al t

ools

and

cab

les

are

chec

ked

and

tagg

ed.

Do

not

touc

h el

ectr

ical

ly h

ot p

arts

or

elec

trod

e w

ith b

are

skin

or

wet

clo

thin

g.

Insu

late

cre

w f

rom

wor

kpla

ce a

nd g

roun

d us

ing

dry

insu

latio

n.

Rubb

er m

at o

r dr

y w

ood

in c

ase

of w

et w

orki

ng a

rea.

U

se c

orre

ct v

olta

ge t

ools

and

circ

uit

brea

kers

. All

wel

ding

ho

lder

s, c

able

s an

d co

nnec

tions

mus

t be

che

cked

on

daily

bas

is.

Har

mfu

l fum

es

Poor

ven

tilat

ion

Resp

irato

ry il

lnes

s D

erm

atiti

s.

Use

ven

tilat

ion

or e

xhau

st t

o k e

ep a

ir-br

eath

ing

zone

cle

ar a

nd

com

fort

able

. Cr

ew w

hile

wor

king

mus

t pl

ace

them

in t

he w

ind

dire

ctio

n, s

o th

e fu

mes

and

gas

es a

re b

low

n aw

ay fr

om t

hem

. Ex

trac

tion

syst

ems

mus

t be

pro

vide

d to

rem

ove

smok

e/ f

umes

if

natu

ral v

entil

atio

n is

inad

equa

te.

Ultr

a vi

olet

rad

iatio

n.

Pers

onne

l Inj

ury

Use

cor

rect

filt

er le

ns a

nd a

lway

s us

e he

lmet

. Pr

ovid

e no

n -fla

mm

able

shi

eldi

ng (

Fire

bla

nket

or

G.I

she

et)

to

prot

ect

othe

rs.

Trip

ping

Haz

ards

Elec

tric

sho

ck/

serio

us in

jury

/ fa

tal

inci

dent

All c

able

s, h

oses

, and

oth

er p

orta

ble

equi

pmen

t sh

ould

be

plac

ed in

a s

afe

area

. All

cabl

es a

nd h

oses

mus

t be

abo

ve h

ead

heig

ht.

Cann

ot I

mpo

se a

ny t

rip o

r en

tang

lem

ent

Haz

ards

.

Fire

haz

ard

Burn

and

per

sona

l inj

ury

The

foam

sha

ll be

sto

red

in a

des

igna

ted

area

, aw

ay f

rom

hot

w

ork.

M

ake

sure

tha

t th

e he

at fr

om w

eldi

ng w

ill n

ot r

each

up

to t

he

foam

in u

se.

0 6

Gas

Cut

ting

Back

Fire

, Fla

sh B

ack

Hig

h Te

mpe

ratu

re

Flyi

ng m

etal

s, s

park

s G

as L

eaka

ge

Maj

or f

ire, E

xplo

sion

B

urn

Inju

ries

to t

he e

ye

Suff

ocat

ion,

Fire

. M

etal

fum

e fe

ver,

diz

zine

ss, n

ause

a

Use

fla

sh b

ack

arre

stor

s an

d re

gula

tor

and

ensu

re it

is r

egul

arly

m

aint

aine

d. F

abric

ator

s sh

all c

heck

the

cut

ting

set

befo

re u

se.

Onl

y us

e fli

nt s

tone

s to

sta

rt f

lam

e U

se w

eldi

ng g

love

s (R

ed c

olou

r) a

nd A

pron

U

se s

afet

y gl

asse

s, f

ace

shie

ld m

ust

also

be

used

whi

le u

sing

po

rtab

le t

ools

. Ch

eck

regu

lato

r, h

ose,

hos

e co

nnec

tion

and

join

ts in

spec

tion

and

colo

ur c

oded

. St

ore

cylin

ders

sec

urel

y in

ope

n ai

r an

d in

upr

ight

Posi

tion,

shi

elde

d fr

om d

irect

sun

light

or

othe

r he

at s

ourc

e.

Posi

tion

the

body

with

the

win

d di

rect

ion

or in

suc

h a

man

ner

that

har

mfu

l gas

es a

re b

low

n aw

ay fr

om t

he b

ody.

Ar

ea m

ust

be w

ell v

entil

ated

. Kee

p ex

posu

re a

s lo

w a

s po

ssib

le.

Use

res

pira

tors

Tr

aine

d fir

e w

atch

man

sha

ll be

ass

igne

d to

con

trol

the

hot

w

ork

activ

ity

Flam

mab

le m

ater

ials

sha

ll be

rem

oved

with

in 5

0ft

vici

nity

Le

ak t

est

shou

ld b

e co

nduc

ted

with

hos

e co

nnec

tions

. Ac

etyl

ene

pres

sure

sho

uld

not

go m

ore

than

15

Psi.

All g

auge

s sh

all b

e pr

oper

ly c

alib

rate

d w

ith v

alid

dat

e.

Use

onl

y cr

impe

d ho

se c

onne

ctio

ns,(

jubi

lee

clam

ps s

hall

not

be

use)

D

o no

t la

ying

the

hos

es in

cut

ting

of f

lam

mab

le a

rea.

07

H

andl

ing

of

Com

pres

sed

Gas

Cy

linde

rs

Fire

P

erso

nal I

njur

y /

Prop

erty

dam

age

Mai

ntai

n th

e sa

fe d

ista

nce

from

the

hot

wor

k lo

catio

n fo

r th

e co

mpr

esse

d ga

s cy

linde

rs.

If it

is c

lose

to

the

hot

wor

k, c

ylin

ders

sha

ll be

pro

tect

ed w

ith

wet

fire

bla

nket

s.

Com

pres

sed

gas

cylin

ders

sha

ll be

pro

tect

ed

Prov

ide

cylin

der

caps

on

all c

ylin

ders

not

in u

se.

Prop

erly

sec

ure

cylin

ders

in a

n up

right

pos

ition

D

urin

g m

ovem

ent.

D

o no

t st

rike

cylin

ders

tog

ethe

r.

Use

cyl

inde

r tr

olle

ys t

o tr

ansp

ort

cylin

ders

. 08

W

orki

ng a

roun

d w

ith e

lect

ricity

as

soci

ated

by

an

elec

tric

al p

ower

dr

iven

too

ls

Pote

ntia

l for

ele

ctric

sh

ock

May

cau

se in

jury

, bur

ns o

r ev

en

deat

h

All e

lect

rical

equ

ipm

ent

shal

l hav

e gr

ound

faul

t ci

rcui

t in

terr

upte

rs a

nd a

ssur

ed e

quip

men

t gr

ound

ing

Mus

t en

sure

tha

t th

e el

ectr

ical

too

ls a

re in

spec

ted

for

wor

thin

ess

of u

se a

t si

te p

rior

to p

roce

ed o

f w

ork

activ

ities

U

se o

nly

non

– co

nduc

tive

ladd

ers

Co

nduc

tive

item

s of

jew

elle

ry o

r cl

othi

ng s

hall

not

be w

orn

durin

g th

e w

ork

activ

ity.

09

Conn

ectin

g of

ca

bles

usi

ng

term

inal

lugs

or

conn

ecto

rs

Use

of

crim

ping

too

ls

may

cau

se in

jury

Pers

onne

l Inj

ury

Ensu

re p

rope

r us

e of

han

d to

ols

an a

dvic

e w

earin

g of

han

d gl

oves

at

all t

imes

. U

se a

ppro

ved

cabl

es.

No

splic

ing.

Con

nect

ors

only

we

can

use.

10

Air

Com

pres

sor

oper

atio

n (C

lean

ing

purp

ose)

Dus

t in

hala

tion

Eye

Irrit

atio

n H

ose

conn

ectio

n D

e -to

uchi

ng.

Hor

se P

layi

ng

Pers

onne

l Inj

ury

P ers

onne

l Inj

ury

Pers

onal

Inj

ury

/ Pr

oper

ty

dam

age/

Inju

ry t

o ot

hers

Pe

rson

al I

njur

y /

Prop

erty

da

mag

e/In

jury

to

othe

rs

Use

the

pro

per

resp

irato

ry p

rote

ctio

n.(N

-95

3M d

ust

mas

k)

Use

the

pro

per

PPE

with

dou

ble

eye

prot

ectio

n.(G

oggl

es &

face

sh

ield

) U

se t

he s

tand

ard

conn

ecto

r.

Fixe

d w

ire r

ope

conn

ecto

r w

ith e

ye b

oth

side

. M

ake

sure

tha

t ho

se is

in g

ood

cond

ition

. W

orki

ng a

rea

mus

t be

isol

ated

and

mak

e su

re n

o ot

her

job

in

that

isol

ated

are

a.

Enga

ged

expe

rienc

ed w

orke

r to

exe

cute

the

job.

M

ake

sure

the

re n

o ho

rse

play

ing

is h

appe

n.

Mak

e su

re t

he e

quip

men

t is

insp

ecte

d an

d co

lour

cod

ed.

11

Envi

ronm

ent

Ad

vers

e w

eath

er

cond

ition

H

eat

stre

ss

Cold

Sand

sto

rm

Hea

t cr

amps

, str

oke,

Exh

aust

ion

caus

ing

per

sonn

el in

jury

If v

isib

ility

bec

ame

poor

, wor

k w

ill b

e su

spen

ded

Dus

t m

ask

will

be

prov

ided

Pr

oper

res

t, H

eat

stre

ss in

dex

will

be

mon

itore

d an

d ac

t ac

cord

ingl

y D

rinki

ng w

ater

sta

tion.

Pr

oper

win

ter

PPE

12

Wor

king

in h

ot

envi

ronm

ent

Hea

t st

ress

H

eat

cram

ps

Hea

t st

roke

H

eat

exha

ustio

n Ca

usin

g pe

rson

nel’s

inju

ry

Ensu

re a

ll pe

rson

nel h

ave

corr

ect

PPE

such

as

hard

hat

, saf

ety

glas

ses,

cov

eral

l, sa

fety

sho

e, h

and

glov

es, &

ear

pro

tect

ion.

Re

st s

helte

r no

t to

be

mor

e th

an 5

0 fe

et a

way

from

the

wor

k.

Ensu

re p

lent

y of

drin

king

wat

er is

pro

vide

d.

Hea

t st

ress

aw

aren

ess

will

be

give

n to

all

wor

kers

prio

r to

sta

rt

tha

wor

k.

Regu

lar

mon

itorin

g of

hea

t in

dex.

13

Emer

genc

y re

spon

se

Fire

M

edic

al E

mer

genc

y

Prop

erty

dam

age

Fata

lity

Serio

us in

jurie

s

Mak

e su

re e

mer

genc

y co

ntac

t nu

mbe

rs a

re p

lace

d an

d Em

erge

ncy

Prot

ocol

to

be f

ollo

wed

En

sure

res

cue

equi

pmen

t are

ava

ilabl

e on

site

Ar

ea t

o be

bar

ricad

ed, n

o on

e w

ill b

e al

low

ed t

o en

ter

the

area

ER

P sh

ould

be

activ

ated

and

fol

low

ed.

In t

he e

vent

of

Emer

genc

y Ca

ll

Ambu

lanc

e -0

5943

3173

5 M

r. K

anna

n -

0505

6471

17

Mr.

D.K

. Upa

dhya

y-05

3530

0306

1

4 Fi

nish

ing,

ho

usek

eepi

ng

Mat

eria

ls le

ft o

n th

e gr

ound

unp

rote

cted

. Fu

mes

Air

bow

ls a

nd

part

icle

s

Slip

s tr

ips

and

falls

on

to u

npro

tect

ed

mat

eria

ls w

hich

may

cau

se p

erso

nal

inju

ry.

Ill h

ealth

Pe

rson

nel i

njur

y

Ens u

re t

hat

all w

aste

mat

eria

ls h

ave

been

rem

oved

from

the

w

ork

area

to

the

desi

gnat

ed w

aste

are

a.

Carr

ied

out

prop

er h

ouse

keep

ing

all t

he t

imes

Fi

re w

atch

er s

hall

mon

itor

the

wor

k ar

ea 1

5 m

inut

es a

fter

co

mpl

etio

n of

hot

wor

k an

d en

sure

wor

k lo

catio

n is

in s

afe

cond

ition

bef

ore

leav

e th

e si

te.

Revi

ew e

xplo

de u

nits

with

PPE

incl

ude

resp

ectiv

e.

15

Wor

king

at

Hei

ghts

w

ith H

ot w

orks

Fa

lling

from

Hei

ghts

Sl

ippa

ge o

f To

ols

and

tack

les

from

Wor

king

pl

atfo

rms

Hot

spl

atte

rs f

allin

g fr

om h

eigh

t Fi

re H

azar

d

Pers

onal

Inj

ury

and

may

cau

se t

o fa

talit

ies.

Se

rious

inju

ry.

May

cau

se in

jury

, bur

ns o

r ev

en

deat

h Pr

oper

ity D

amag

e/ I

njur

y to

oth

ers

Befo

re u

sing

sca

ffold

ing

for

heig

ht w

orks

, Ens

ure

that

“G

reen

Ta

g” s

houl

d be

pre

sent

. H

eigh

ts fr

om 1

.8 M

trs

and

abov

e ev

ery

pers

onne

l sho

uld

wea

r Fu

ll Bo

dy h

arne

ss (

It is

to

be in

spec

ted

and

mon

thly

col

or t

ag

shou

ld b

e m

aint

aine

d)

Ensu

re t

hat

full

body

har

ness

mus

t be

hoo

ked

to R

igid

pla

tfor

m

or L

ife li

ne.

Toe

guar

ds m

ust

be p

lace

d in

alig

ned

to p

latf

orm

. Fl

amm

able

mat

eria

ls s

houl

d be

rem

oved

fro

m t

he p

latf

orm

s an

d fir

e ex

tingu

ishe

rs m

ust

be d

uly

plac

ed n

ear

to t

he w

orki

ng a

rea.

H

ouse

kee

ping

sho

uld

be m

aint

aine

d on

wor

king

pla

tfor

ms

Fire

bla

nket

s sh

ould

be

prop

erly

pla

ced

bene

ath

the

Hot

wor

k ar

ea in

orde

r to

sto

p th

e sp

illag

e of

the

spl

atte

rs.

Usa

ge o

f pro

per

PPE

is w

hile

han

dlin

g th

e jo

b.

JO

B S

AFE

TY A

NA

LYSI

S A

TTEN

DA

NC

E SH

EET

JSA

No

: Jo

b D

escr

iptio

n :

Dat

e :

Supe

rvis

or:

Sr. N

o N

ame

Des

igna

tion

Sign

atur

e