Page 1: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Pixel Upgrade Status and Plan

G.M. Bilei

Firenze Mar. 6th 2013

Page 2: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Introduction and news

• The Pixel project is progressing pretty much according to the plan

• ROC PSI46dig / TBM08 submission was done in early January 2013.- expect wafers (6) back in first half of April 2013

- plan to order 24 additional wafers (delivery mid May)

(enough for 3-4 wafers for each production center)

• Digital Test Boards will be produced by PSI (requested 15 for INFN)- Need to identify for each consortium one contact person to become

expert in maintaining them and support the consortium. Look for volunteer

• High rate Test Beam at FNAL with digital ROC this summer- Good opportunity to contribute and learn. As INFN we should participate..

• Pixel TDR Document now available, one per institute.

Firenze 6.3.2013

G.M. Bilei 2

Page 3: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

2013 Pixel activities and goals

Many tasks to accomplish in 2013:

• CO2 cooling plant & piping

• Install extra LV-power cables for BPIX layer 1 (CAENPP1)

• Submission of digital TBM & ROC (PSI46dig) for Pilot System

• Production masks for PSI46dig ROC (BPIX Layer 2-4, FPIX)

• Production of Pilot System and integration into present FPIX

• Production of BPIX Supply Tubes & Mechanics for installation tests

• Installation test without beam pipe

• BPIX Supply Tube protoytpe with sector test of all electrical boards

• Preseries digital pixel modules with full functionality (sensor, HDI, cables, BB)

• High rate test pixel test beam at FNAL

Firenze 6.3.2013

G.M. Bilei 3

Page 4: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

INFN plan and objectives for 2013

• Complete construction of 8 old modules with analog ROC at IZM- All parts are available. IZM delivery very soon- Complete setups and qualification of INFN production centers

• Evaluate, qualify together with KIT the Selex BB process and reassess cost.

• Select Bump Bonding vendor (IZM, Selex) by September at latest.

• Set up new readout systems for digital ROC in the lab and get experience

• Construction of few prototypes of new digital pixel modules

• Preparation for mass construction (new readout cards, database, software analysis etc.)

• Possibly participate to the FNAL high rate test beam in summer

Firenze 6.3.2013

G.M. Bilei 4

Page 5: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

INFN draft Pixel schedule 2013

2013 INFN Pixel activities

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

                       

Analog Module Bump Bonding at IZM                        

Construction and qualification 8 Analog Modules                        

INFN and KIT Bump Bonding R&D at SELEX                        

Qualification of Selex modules                        

INFN Selection of Bump Bonding Vendor                        

Digital Module Bump Bonding                        

Construction and qualification of 10 digital modules                        

Digital ROC and TBM                        

HDI for digital modules                        

Sensors                        

Digital Test Boards                        

Test Beam FNAL                        

Firenze 6.3.2013

G.M. Bilei 5

Milestone INFN Gruppo I Pixel Upgrade1/12/2013 Realizzazione primi prototipi nuovi moduli Pixel Upgrade con ROC Digitale

Page 6: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Overall schedule Pixel Construction

6Firenze 6.3.2013

G.M. Bilei

Page 7: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Pixel Construction TDR milestones

7Firenze 6.3.2013

G.M. Bilei

Page 8: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Firenze 6.3.2013

G.M. Bilei 8

Half Layer 22 faces 8 modules/faces =176 modulesNeeds 250 modules allowing for 80% yield and 15% spares

Contribution to 50% of BPix layer 3

Draft INFN Plan2011 Start setting up2012-13 Production ~ 8 old analog modules2013 Production of few new modules2014 Start mass production2015 End module prod & integration2016 Commissioning and Installation

Page 9: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Module construction flow chart

Sensors test

ROC Test after dicing

TBM and HDI testing

Company Bump bond

Glue/bond TBM to HDI

Test before glue HDI to sensor

module characteri-

zation

Burn-in

X-ray calibration

PisaPisa

Catania

Bari

Perugia

Perugia/Pisa

Half LayerAssembly

and testing

Bare Moduletest

SiN-railsglue

Bond ROCs to HD

Glue HDI to bare module

Module testing

Padova

Page 10: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

Pixel Construction Costs as TDR

Firenze 6.3.2013

G.M. Bilei 10

INFN contribution to construction 803 Ke (963 KCHF)

UK contribution on FED withdrawn. Currently 690 KCHF are missing

Page 11: Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013

INFN Pixel Upgrade spending profile

11