pja design presentation

Upload: andymiller4

Post on 06-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 PJA Design Presentation

    1/21

    Pipe Jacking Design and Best Installation PracticePrepared by the

    Pipe Jacking Association

  • 8/3/2019 PJA Design Presentation

    2/21

    Key Considerations

    Pipe Jacking is an integrated system linking:

    soils

    jacking shafts

    pipes

    shields

    jacking loads

    engineering

  • 8/3/2019 PJA Design Presentation

    3/21

    Soils Investigation

    Soils investigation is key:

    This influences

    excavation method

    temporary works

    length

    pipes

    ground stabilisation

  • 8/3/2019 PJA Design Presentation

    4/21

    Differing ground needs to be assesed as appropriate:

    Non-cohesive soils

    Cohesive soils

    Mixed soils

    Fill

    Rock

    Water presence is a key factor

    Soils Data Requirements

  • 8/3/2019 PJA Design Presentation

    5/21

    Unstable Ground Conditions

    Tunnelling methods depend on

    the stability of the ground

    Solutions to instability are

    either geotechnical processesor physical constraint

    Geotechnical options are extensive

  • 8/3/2019 PJA Design Presentation

    6/21

    Excavation: Open Face

    Hand shields

  • 8/3/2019 PJA Design Presentation

    7/21

    Excavation: Open Face

    Hand shields

    Backacter

  • 8/3/2019 PJA Design Presentation

    8/21

    Excavation: Open Face

    Hand shields

    Backacter

    Cutter boom

  • 8/3/2019 PJA Design Presentation

    9/21

    Excavation: Closed Face

    Pressurised slurry

    Compressed air

    Earth pressure balance

  • 8/3/2019 PJA Design Presentation

    10/21

    Temporary Works: Shafts and Shield Entry

    Segmental

    Precast or insitu

    Piled

    Sheeted or timbered

    Battered

    Anchorages

    Shield entry and exit

  • 8/3/2019 PJA Design Presentation

    11/21

    Temporary Works: Thrust Walls

    The thrust wall takes the full jacking load

    Spreaders distribute the load

    Thrust wall failure key risk

  • 8/3/2019 PJA Design Presentation

    12/21

    Temporary Works: Manholes

    Manhole requirements vary

    Shafts bases can be enlarged

    Caissons can fulfil mutiple roles

    Manhole utilisation impacts on

    project costs

  • 8/3/2019 PJA Design Presentation

    13/21

    Jacking Lengths and Friction Loads

    Design variables include:

    thrust walls

    pipe design

    interjacks

    friction lubricants

    spoil removal

    engineering

  • 8/3/2019 PJA Design Presentation

    14/21

    Jacking Loads

    Jacking loads comprise:

    face loads

    pipe string weight

    friction

    misalignment

    time delays

    Frictional forces 0.5 to 2.5 tonnes per square metre

  • 8/3/2019 PJA Design Presentation

    15/21

    Lubrication

    Bentonite

    Soil type dependent

    Foams

  • 8/3/2019 PJA Design Presentation

    16/21

    Pipe Jacking Pipes

    Concrete jacking pipes: EN 14457

    Installation forces are key

    Follow manufacturers recommendations

  • 8/3/2019 PJA Design Presentation

    17/21

    Best Installation Practice: Loading

    Thrust load and anchorage

    Load transfer

    Control/failsafe

    Interjacks

  • 8/3/2019 PJA Design Presentation

    18/21

    Best Installation Practice: Steering

    Tolerances: 75mm for line, 50mm for level

    Setup and shield entry

    Regular checks

    Cautious realingment

  • 8/3/2019 PJA Design Presentation

    19/21

    Best Installation Practice: Records

    Monitoring

    Main survey checks

    Line and level

    Shield position

    Pipe rolling Main jacking load

    Interjack load

    Shield load

    Total load

    Surface checks

  • 8/3/2019 PJA Design Presentation

    20/21

    Summary

    Design: Ground

    Excavation method

    Temporary works

    Jacking loads

    Lubricants

    Pipes and joints

    Installation: Steering

    Loading Records

  • 8/3/2019 PJA Design Presentation

    21/21

    Pipe Jacking Association10 Greycoat Place, London SW1P 1SB

    Tel: 0845 070 5201 Fax: 0845 070 5202

    Email: [email protected]

    Website: www.pipejacking.org