plaintiff's first amended complaint and exhibits filed 8 5 09 - olsen f-22

Upload: imispgh

Post on 30-May-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    1/105

    567s9

    10111213

    14151617

    ..

    Samuel L. B o Lead C o ~ l s b o ~ d ~ b o < t d comTX sa : 27775006440 North Central Expressway 'J:$-

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    2/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    Sikorsky Aircraft Pays $2.9 Million to Settle False Claims Act Allegations,

    available at http://www.usdoj.gov/opa/pr/2009/March/09-civ-273.html (last

    visited July 18. 2009). The United States alleged that from 1991 to 2006,

    Sikorsky knowingly installed armored plates . . . that had not been ballistically

    tested as required under the contract. Id. "This settlement sends a message that

    fraud, especially when it concerns the safety of our men and women in uniform,

    cannot and will not be tolerated in Government contracts," said Michael F. Hertz,

    Acting Assistant Attorney General for the Department of Justices Civil Division.

    "As demonstrated here, the Department . . .[is] committed to rooting out such fraud

    and prosecuting it." Id.1

    On behalf of the United States of America, Relator Darrol O. Olsen

    (Olsen) files this Plaintiffs First Amended [qui tam] Complaint, pursuant to

    Federal Rule of Civil Procedure 15(a)(1)(A) against defendant LOCKHEED

    http://www.usdoj.gov/opa/pr/2009/March/09-civ-273.htmlhttp://www.usdoj.gov/opa/pr/2009/March/09-civ-273.html
  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    3/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    the United States Air Force (USAF) during production of the "F-22 Raptor" (F-

    22).

    I. PRELIMINARY STATEMENT

    1. In 1991, Lockheed entered into a contract with the USAF to produce

    the F-22.

    2

    StealthRADAR and visual non-observability--is a core feature of

    that aircraft. The entire aircraft is designed around that feature. Numerous

    components of the F-22 contribute to its planned stealth design, such as the

    fighters contours and the coatings applied to its skin. The low observable

    (LO) coatings applied to the F-22 are integral to its stealth, pilot safety, and

    mission accomplishment. Lockheed emphasizes the importance of very low

    observable stealth to the F-22 in materials such as the brochure attached hereto as

    Exhibit A, downloaded on July 15 30, 2009 from Lockheeds web site at

    http://www.lockheedmartin.com/data/assets/corporate/press-kit/F-22-Brochure.pdf.

    http://www.lockheedmartin.com/data/assets/corporate/press-kit/F-22-Brochure.pdfhttp://www.lockheedmartin.com/data/assets/corporate/press-kit/F-22-Brochure.pdf
  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    4/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    knowingly use defective coatings. Based upon third-party reports, it appears that

    the defective coatings have not been remedied through the present date, and that

    Lockheed has never fully disclosed the low observables system defects to the

    USAF.

    3. Moreover, during the September 1995 through June 1999 period,

    Lockheed misrepresented to the USAF that the coatings were passing stealth tests

    and, thus, meeting contract specifications. In addition, Lockheed actively

    concealed the stealth coatings failures from the USAF. For example, Lockheed

    management often directed Olsen not to speak with the USAF about the coatings

    problems. Indeed, on numerous occasions when Olsen protested the use of the

    failed coatings and stated that Lockheed had to tell the USAF about the problems,

    Lockheed manager David Trawinskis response was, Stay out of it." On one

    occasion when Olsen objected to wasting money by purchasing more of the same

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    5/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    4. All that mattered to Lockheed was that the USAF thought that the

    coatings were satisfactory, and that the F-22 program was timely proceeding so

    that the USAF would continue to pay Lockheeds progress and milestone bills. On

    information and belief, Lockheed continued to misrepresent and conceal the

    problems with the F-22's coatings through at least October 2004 and likely to the

    present date.

    5. In effecting its fraud, Lockheed falsely certified that the coatings were

    meeting stealth tests and, thus, meeting contract specifications, in order to get paid.

    Lockheed made those certifications when presenting the progress bills and

    milestone bills for payment to the USAF. In doing so, Lockheed presented false

    claims to an agency of the United States for payment in violation of 31 U.S.C.

    3729(a)(1)(A), (B), and (G), or former 31 U.S.C. 3729(a)(1)(2) and (7).

    6. Further, on information and belief, since the entire F-22 is designed

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    6/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    incurred by the USAF due to Lockheeds conscious or reckless use and application

    of known defective stealth coatings.

    7. Relator brings this lawsuit for damages suffered by the United States,

    including principal, interest and penalties as a result of Lockheeds false and

    fraudulent practices which violated the False Claims Act.

    II. PARTIES

    8. Relator Darrol O. Olsen is a Materials and Process Engineer

    specializing in composites and low observablesstealthmaterials. Olsen was

    employed in various capacities by Lockheed for a total of 18 years. 4 Because of

    his expertise in stealth technology, Olsen worked from September 1995 to July

    1999 on the F-22. In particular, Olsen worked nearly exclusively on the F-22's

    coatings, which are essential to that fighters stealth capability. Olsen lives at

    15205 South 4160 Road, Claremore, OK 74017.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    7/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    76108. (Lockheed Martin Corporation and its business unit(s), including LMAC,

    are collectively referred to as Lockheed.)

    III. JURISDICTION AND VENUE

    10. This is an action to recover damages and civil penalties on behalf of

    the United States for defendants violations of the False Claims Act, 31 U.S.C.

    3729 et seq. under the 1991 contract between Lockheed and the USAF, an

    agreement which continues through this date.

    11. The FCA provides the United States District Courts exclusive

    jurisdiction for actions brought thereunder.

    12. Section 3732(a) provides that, "Any action under section 3730 may be

    brought in any judicial district in which the defendant . . . can be found, resides,

    transacts business, or in which any act proscribed by section 3729 occurred."

    Lockheed, through its business unit LMAC, is the prime contractor for the 1991

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    8/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    be extended. 31 U.S.C. 3730(b)(3). If the United States declines to intervene,

    the Relator can proceed on the governments behalf. 31 U.S.C. 3730(b)(4).

    IV. FCA'S SUBSTANTIVE PROVISIONS

    14. Section 3729 of the FCA provides:

    (a) Liability for certain acts.

    (1) In general. Subject to paragraph (2), any person who--

    (A) knowingly presents, or causes to be presented, a

    false or fraudulent claim for payment or approval;

    (B) knowingly makes, uses, or causes to be made or

    used, a false record or statement material to a false

    or fraudulent claim;

    * * *

    (G) knowingly makes, uses, or causes to be made or

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    9/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    is liable to the United States Government for a civil penalty of not less

    than $5,000 and not more than $10,000, as adjusted by the Federal

    Civil Penalties Inflation Adjustment Act of 1990 (28 U.S.C. 2461

    note; Public Law 104-410), plus 3 times the amount of damages

    which the Government sustains because of the act of that person.

    31 U.S.C. 3729(a)(1)(A), (B), and (G) (As amended May 20, 2009,

    FRAUD ENFORCEMENT AND RECOVERY ACT OF 2009, 111 P.L. 21

    4(a); 123 Stat. 1617 [S. 386]).5

    15. Pursuant to Section 3729(b)(2) of the FCA, a "claim":

    (A) means any request or demand, whether under a contract or

    otherwise, for money or property and whether or not the United

    States has title to the money or property, that--

    5

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    10/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    (i) is presented to an officer, employee, or agent of the

    United States; or

    (ii) is made to a contractor, grantee, or other recipient, if the

    money or property is to be spent or used on the

    Government's behalf or to advance a Government

    program or interest, and if the United States

    Government

    (I) provides or has provided any portion of the money

    or property requested or demanded; or

    (II) will reimburse such contractor, grantee, or other

    recipient for any portion of the money or property

    which is requested or demanded; and

    (B) does not include requests or demands for money or property

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    11/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    31 U.S.C. 3729(b)(2) (As amended May 20, 2009, FRAUD

    ENFORCEMENT AND RECOVERY ACT OF 2009, 111 P.L. 21 4(a);

    123 Stat. 1617 [S. 386]).6

    V. REGULATIONS

    16. Government contracting is controlled by the Federal Acquisitions

    Regulation (FAR) promulgated by the Federal Acquisition Regulatory Council. 41

    U.S.C. 421(c)(1). FAR sets forth the requirements binding the executive

    agencies of the United States and all contractors that provide goods and services to

    those agencies. 48 C.F.R. 1.101 et seq. Defendants violations of the FCA

    specifically involve defense contracting, making relevant the Defense Federal

    Acquisition Regulation Supplement (DFARS), promulgated by the Department of

    Defense (DoD). 41 U.S.C. 421(c)(2); see also 48 C.F.R. 201.301(a) (DoD

    implements and supplements the FAR through the DFARS).

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    12/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    a) 48 C.F.R. 52.212-4(q) ("the Contractor shall comply with all

    applicable Federal . . . laws . . . and regulations applicable to its

    performance under this contract.");

    b) 48 C.F.R. 52.212-4(a) ("The Contractor shall only tender for

    acceptance those items that conform to the requirements of this

    contract.");

    c) 48 C.F.R. 52.246-1 ("the Contractor is responsible for

    performing . . . all inspections and tests necessary to

    substantiate that the supplies or services . . . conform to contract

    requirements . . . .");

    d) 48 C.F.R. 52.212-4(o) ("the Contractor warrants and implies

    that the items delivered hereunder are merchantable and fit for

    use for the particular purpose described in this contract."); and

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    13/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    manner consistent with the need to fulfill the production

    plan]).7

    18. Similarly, on information and belief, Lockheed certified as required

    by 48 C.F.R. 52.232-5(c) in each progress bill that:

    I hereby certify, to the best of my knowledge and belief, that

    (1) The amounts requested are only for performance in

    accordance with the specifications, terms, and conditions

    of the contract; . . . . 8

    19. Further, on information and belief, each progress bill submitted by

    Lockheed to the USAF for payment was subject to certain other regulations,

    including, but not limited to:

    a) 48 C.F.R. 52.232-16(a) (each progress payment will not be

    more frequently than monthly and will be computed "as 80% of

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    14/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    b) 48 C.F.R. 53.301-1443 (Form 1443: certifying that a progress

    bill had been prepared "in accordance with" the subject

    contract, "work reflected [in the progress bill had] been

    performed" and "the quantities" of work done were "consistent

    with the requirements" of the subject contract); and

    c) 48 C.F.R. 52.232-16(c) (Contracting Officer "may reduce or

    suspend progress payments" for the Contractors "failure to

    comply with any material requirement of [the] contract").

    20. On information and belief, upon purportedly achieving contract

    milestones (or subparts thereof), Lockheed submitted milestone bills to the USAF

    for payment that contained certifications similar to those required for progress

    bills.

    VI. FACTS

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    15/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    22. After active duty, Olsen returned to his clerical position at Lockheed

    from 1975-79, with educational leaves of absences. In 1979, Olsen received a B.S.

    in biosciences with a minor in chemistry.

    23. In 1979, Lockheed hired Olsen as an engineer in Research

    Engineering at its Burbank, California facility. There, Olsen performed R&D on

    items supporting numerous programs,

    24. Olsen worked in the nonmetallics (or composites) materials area in

    research and development. In this capacity he developed new, advanced

    composites materials (nonmetallics) and processes. Among other responsibilities,

    he performed numerous types of materials testing. Olsen worked on new, state-of-

    the-art technologies for existing and future programs.

    25. From 1982-88, Olsen worked for Northrop Grumman Corporation

    (Northrop). Olsen was assigned to the F-18 fighter and the B-2 stealth bomber,

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    16/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    27. In 1990, Olsen once again took a job with Northrop, focusing full-

    time on the B-2 at the B-2 production facility in Palmdale, California.

    Subsequently, he performed work at Edwards Air Force Base for B-2 flight tests.

    Olsen worked on all stealth aspects of the B-2, including the LO coatings system

    and repairs, composites structures, all materials and processes, testing, RCS issues

    and diagnostics including off-site RCS testing, and research and development.

    28. Olsen became an Engineer Specialist at Northrop. Due to his work

    experience, Olsen had become a recognized expert on stealth coatings. While

    Northrop had roughly 10,000 employees assigned to the B-2 program, only about

    20 had Olsens level of knowledge about stealth materials. In fact, Northrop chose

    Olsen out of approximately 3,000 engineer-candidates to be its Military Corporate

    Field Representative and Advisor to the USAF on the B-2's stealth coatings,

    advanced composites materials, repairs, all materials and processes, and on other

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    17/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    Northrops integrity in ensuring the B-2's stealth, when he witnessed a radically

    different attitude and conduct upon returning to Lockheed.

    B. The F-22's Background

    30. In the early 1970s, the USAF began studying concepts for an

    Advanced Tactical Fighter (ATF) to replace the F-15. The ATF concept would

    evolve into the F-22. After a concept investigation phase, the USAF requested

    proposals for the F-22 design in the autumn of 1985. Seven aerospace defense

    contractors responded, including Lockheed. Each contractor was required to

    include in its proposal a description of its stealth skills and experience.

    31. Prior to selecting the winning design, the USAF suggested that the

    contractors form teams so that the best industry expertise could be brought to bear

    on such a technologically challenging project. Lockheed, Boeing and General

    Dynamics formed one team. The Lockheed group agreed that each contractor

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    18/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    assigned the work, giving itself the lions share. Lockheed assumed responsibility

    for most of the F-22's stealth capability, including the coatings.

    C. The 1991 Lockheed Contract

    33. On information and belief, Lockheed and the USAF in 1991 entered

    into a fixed price contract that required Lockheedsubject to USAF approval and

    consistent with the contract specificationsto deliver 648 F-22s at a cost of $86.6

    billion or about $134 million per fighter.10

    34. On information and belief, Lockheed submitted a certification with

    the 1991 contract attesting that it would comply with the "Statement of Work,"

    which was part of that agreement, including all low observables engineering

    specifications. On information and belief, the "Statement of Work" set forth the

    requirements for reflectivity (RCS signature) and reparability, among other

    specifications.11

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    19/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    35. Further, on information and belief, Lockheed certified in the 1991

    contract that it would comply with all applicable laws and regulations, including

    those set forth in the Section V, supra.

    D. The Importance of Stealth to the F-22

    36. Stealth capability is a core feature of the F-22. The purpose of stealth

    is to prevent the aircraft from being detected by ground-to-air or air-to-air

    RADAR. The entire F-22 is designed around its stealth capability.

    37. The observability of an aircraft by RADAR is referred to as its

    RADAR Cross Section (RCS) or RADAR signature. The F-22's RCS should, at

    most, indicate to a RADAR sender or yield a RADAR signature about the size of a

    bumblebee.

    38. The key to stealth is to minimize the RADAR return to the RADAR-

    emitting source either by conducting, dissipating and reflecting the RADAR wave

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    20/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    15

    12

    13

    14

    16

    17

    39. The F-22's design requires the use of electrically conductive coatings

    on its skin to conduct, dissipate and reflect away or absorb the RADAR waves.

    40. In addition, RADAR absorbing material (RAM) is also used on the

    F-22 to absorbrather than reflectRADAR waves; RAM component materials

    include metallic particles that absorb electrical energy. RAM is typically applied

    to "hot spots" on the structure and structural flex points, such as around antennas

    and vertical supports.

    41. The F-22 requires several different LO coatings to be applied to theskin of the aircraft. The initial F-22 requirement was for three primary layers of

    coatings to be stacked together (before other LO materials were applied) in the

    following order: The first coating is a primer designed to smooth and seal the

    surface of the skin and promote adhesion of the second, conductive coating. The

    second coating is a conductive coating consisting of metallic flakes intended to

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    21/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    weight severely impacts the F-22 and obstructs its mission capabilities by

    impacting its range, speed, maneuverability, and its overall performance for

    combat capabilities.

    43. The proper functioning of the coatings and their respective repairs are

    absolutely essential to the F-22's stealth capability. If not all coatings and their

    repairs are effective, the stealth measures of the aircrafts design are negated,

    resulting in serious compromise to the radar cross section. The F-22 then becomes

    a highlighted target.

    E. 1995-2004: Continuous and Undisclosed Coatings Problems

    44. In September 1995, Olsen returned to Lockheed in the Materials and

    Processes Engineering Group in Marietta, Georgia as a Senior Engineering

    Specialist, the highest engineering grade below management. Olsen eventually

    reported to Supervisor Richard Morrison and Manager David Trawinski. The

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    22/105

    1

    2

    4

    5

    6

    3

    7

    8

    10

    11

    12

    13

    14

    15

    16

    17

    9

    materials, their respective repairs, the effects of defects, assist in the collection of

    RCS data for the SAS database, develop standard repairs specifications (these

    documents would become the Air Force technical manual specifications in the

    field), and formally validate and verify the F-22 Low Observables System to the

    U.S. Air Force.

    46. By late 1995, Olsen observed that the conductive coatings providedby CAAP CO. had significant widespread and visible problems, such as:

    1. inconsistent batches (viscosity and weight inconsistency);2. clumping of metallic flakes;3. metallic flakes not binding and resulting in separating from the paint resin;4. paint resin with improper chemistry remaining soft;5. abrading damaged conductivity; and6. water or jet-related fluids damaged the coatings properties and RCS

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    23/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    resulting in significant RADAR cross section impacts. Olsen learned that those

    coatings had not been formally tested according to industry protocols to thoroughly

    identify their properties and verify acceptability for production.

    47. The normal stages of formal testing are:

    1) Lockheeds Engineering Testing Laboratory (ETL)

    tests the coatings viscosity, weight and composition.

    Additionally, ETL applies coatings to panels and checks

    materials properties; including, but not limited to,

    conductivity, thickness and smoothness;

    2) Lockheeds RCS department tests reflectivity and

    reparability by directing RADAR at the coatings on 6' x

    3' football panels.12 Additionally an RCS signature is

    captured at this point.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    24/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    testing from the compact range. RCS oversees the tests

    and interprets the data.

    4) RCS department tests reflectivity and reparability of the

    coatings on mock-up sections of the F-22;

    5) RCS department tests the reflectivity and reparability of

    the coatings on an F-22 in a hanger; and

    6) RCS department tests the reflectivity and reparability of

    the coatings on an F-22 during ground and flight tests at

    Edwards Air Force Base.

    Under no circumstances should testing proceed to a subsequent stage if the

    coatings have not passed the preceding stage. As Olsen would soon learn,

    Lockheed paid no heed to that fundamental protocol.

    48. In February 1996, Olsen directed that formal testing commence

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    25/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    repairs. For repairs, ETL would use the spray repair method or the brush/roller

    repair method on damaged areas of the CAAP CO. and Boeing coatings. If the

    original baseline coatings met required specifications, repairs using the same

    coatings should have met the designated RCS signatures and other specifications.

    49. Olsen witnessed each 1996 test. The repairs failed every time. The

    initial baseline coatingsbefore any repairfailed by giving heightened RCS

    signatures. In addition, coatings visibly degraded when exposed to fluids, such as

    aircraft fuel, cleaning solvents and even waterto all of which an operational F-22

    would routinely be exposed, destroying the conductivity resulting in unfavorable

    RADAR signature impacts. The coatings also disfigured when touched. In

    addition, repairs to those coatings failed. For instance, the repaired coatings

    registered heightened RCS signatures as bad as the damaged, unrepaired coatings.

    Despite those first-stage failures, Morrison and Trawinski directed, improperly,

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    26/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    51. On occasion, USAF personnel would attend the weekly, or other,

    meetings; Lockheed knew when Air Force personnel would attend. On some such

    occasions, a weekly meeting was specifically designed to mislead the Air Force by

    a charade or false demonstration. When Air Force personnel attended meetings,

    Morrison and Trawinski instructed Olsen not to speak with the USAF; nor did

    Lockheed management disclose anything negative about the baseline coatings

    materials. Rather, if discussing the coatings at all, Lockheed management falsely

    reported to the USAF that the coatings were satisfactory and that any problems

    were repairable.

    52. Lockheed continued to order defective coating materials from CAAP

    CO. and Boeing. Notably, and contrary to industry standards, Lockheed had no

    back-up materials to consider as substitutes for the failing materials.

    2. 1997: The Cycle Continues

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    27/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    media has reported that F-22 adhesivesthe glue intended to bind RAM to the

    aircrafthave separated at engine inlets and been ingested into the aircraft

    causing damage to or destroying engines of as many as 30 of the fighters. As the

    project fell further behind schedule and tests were failed or skipped and test results

    falsified, Mr. Olsen was forced to sign off on incomplete or completely blank F-22

    Standard Repair Specifications. For instance, an aircraft accident investigation

    report released March 27, 2008 indicated the separation of a six-by-eight-inch

    piece of low observable material ingested into the right engine of an F-22 at Nellis

    Air Force Base, Nevada on November 1, 2007 caused extensive damage to the

    engine, totaling about $1.2 million. The separated piece included several layers of

    coatings, which detached from the engines inlet during takeoff. This caused

    pieces of first-stage engine fans to break away, causing additional damage to the

    engine. The report cited the use of adhesives with poor cohesive strength and lack

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    28/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    54. Olsen expressed concern to Morrison and Trawinski that problems

    with the CAAP CO. and Boeing coating materials and the low observables

    materials system could not be corrected. Large orders of multiple batches for all

    LO materials were purchased numerous times, but were not tested due to the

    failures of the initial coatings, resulting in most of those materials expiring on the

    shelf and then being discarded by special HazMat handling and disposal teams.

    Olsen was ordered to stay the course. Further, Morrison and Trawinski

    reemphasized that Olsen was never to discuss the coatings problems with the

    USAF. Indeed, they instructed Olsen to have no communications at all with the

    USAF.

    55. On information and belief, Lockheed wanted to isolate Olsen and his

    written and vocalized concerns about the coatings. On numerous occasions when

    Olsen told Morrison and Trawinski that the coatings were failing, he was told to:

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    29/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    Olsen) for an award due to purportedly demonstrating that "the brush and roll

    restoration process meets the RCS requirements," and Lockheed presented this

    award at a ceremony on November 11, 1997. See Exhibit B, 11/27/97 Brush

    and Roll Repair Paint Team Memo from Trawinski to N.F. Kavanaugh.

    However, the restoration process did not, and it never had met RCS requirements.

    57. Just two weeks earlier, Olsen had informed Lockheed management of

    the failing conductive coatings test results from the engineering laboratory:

    1) The resin system shows dissolution with light wiping using the

    [CAAP CO. conductive coating] spec cleaning solvent . . . .

    2) Metal flakes do not bind to the resins system. Flakes are easily

    removed when wiped with a cloth or abraded.

    3) Light abrading with very fine sandpaper/polishing abrasives

    remove the surface metal and affects electrical/RCS properties.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    30/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    concerned that the coatings and repairs were working, when they were

    actually in a complete failure mode. In fact, five months later, Morrison

    instructed Olsen to start over the process, for which Lockheed had given

    Olsen the award, because the process continued to fail. See Exhibit D,

    3/26/98 Smart Silver Paint Repair Plan Memo from Morrison to

    Olsen.

    58. On information and belief, the USAF attended the award ceremony.

    Olsen was present, as required, but he refused to participate in the sham ceremony,

    declining to go forward to accept the award.

    59. Sham awards notwithstanding, the stealth coatings project continued

    its failures.

    3. 1998: "No One Cares. We've Got to Meet Milestones."

    60. The coatings problems did not abate. On information and belief,

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    31/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    61. In early 1998, Olsen was directed to make a large order of all Low

    Observables materials in sets of about 10 to 20 each, to support the

    S.M.A.R.T Low Observables Testing Program. Olsen went to Trawinski to

    again press his concerns about the inability of the initial first coatings to

    satisfy the contract specifications. Trawinskis response was: "No one cares.

    We've got to meet the milestones. Olsen was ordered to purchase these

    massive amounts anyway. In other words, Trawinski was only interested in

    the flow of payments from the USAF and the appearance of timely project

    progress.13 Olsen stated he would make these purchases only if ordered to

    do so. Trawinski said, That is an order.

    62. Olsen persisted. In a March 1998 meeting with Morrison and

    Trawinski, Olsen told them that: "If you dont allow me to fix it [the coating

    problem by replacing the vendors], then a year from now the plane will be in the

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    32/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    addition to continuing to order, purchase and test materials Lockheed knew had

    and would continue to fail, Lockheed ordered and purchased costly, short shelf-life

    low observables materials prematurely in order to provide misleading documentary

    support for false progress and milestone claims. That is, even though Lockheed

    had not progressed to the stage where it needed these materials, and even though

    the shelf life of the materials would expire before Lockheed was ready to use

    themif ever, Lockheed ordered and purchased such materials in order to falsely

    appear to have reached the milestone accomplishment.

    63. As part of the LO materials protocol, Lockheed was required to

    Validate and Verify the reparability of the LO materials. This protocol,

    generally, required that the repairs be successfully conducted under laboratory

    conditions twenty (20) times in sequence, without a single failure. When Air Force

    representatives attempted to repair LO defects, they consistently failed in their

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    33/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    64. On July 2, 1998, ETL issued another test report of coatings failures on

    football panel tests.15 Olsen wrote a note on the report and forwarded it to

    Morrison: "Rich- Another report showing flake loss & resin softening. Does this

    bother you? Morrison responded: "No - because RCS of repair OK & Yes -

    because we need to soak a spot on football panel w/topcoat & measure RCS. See

    Exhibit F, 7/2/98 Testing of Lot OP-91 5PTMRL04 __ Paint, SEM

    Evaluation Memo from L.M. Campbell to Olsen. Besides misstating what the

    report showedthe RCS of the repairs were not OKMorrison did not address

    the basic problem that the coatings were bad out of the suppliers drums. Repairs

    to a coating are made with the same coating material. The problems with the

    coatings were the coatings themselves, not application processes. Thus, repair

    applications of the same bad coatings could not remedy problems with the bad

    coatings, which had failed all materials testing. An obvious solution was to look

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    34/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    recounted that: "Per Rich Morrisons direction, I have asked RCS Engineering to

    determine how much degradation to the coating electricals is acceptable. Their

    response was no degradation can be permitted. See Exhibit G, 8/11/98

    Engineering Test Lab Results on 5PTMRL04 TY-1 Conductive Paint Memo

    from Olsen to Trawinski and Morrison. Rich Morrison had directed Olsen to

    ask RCS Engineering to reduce the RCS signature requirements below contractual

    requirements, so that the Low Observables materials would appear to pass.

    Morrison wanted to modify the RCS requirement so that the failing coatings and

    repairs would pass. Instead of using a Low Observable material that performed as

    intended and required, Morrison wrongfully pressured RCS Engineering to change

    the RCS signature [test] requirement so the failing, defective LO materials would

    falsely appear to be within specifications.

    66. Notwithstanding the consistent stream of failures and the lack of

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    35/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    L.O. Maintainability Group Brush/Roll Status, Presentation, Rich

    Morrison. Morrisons presentation showed the coatings meeting requirements

    with optimized products, and passing most tests. Afterwards, Olsen spoke with

    Ryan and Michael and asked how Morrison could report that the coatings were

    passing. They jointly responded that they were going to "let Morrison hang

    himself".

    67. As they had before, the coatings failed after that meeting. CAAP

    CO.s conductive coating remained inconsistent in makeup, weight, viscosity and

    visual characteristics from batch to batch. Metallic flakes clumped together.

    Rubbing with a soft cloth abraded the conductive coating, released the metallic

    flakes, destroyed the coatings electrical properties and left a gummy resin. F-22

    specification cleaning solvents, jet fuel, cooling fluids, water, and other liquids all

    similarly damaged the coating. Boeings topcoat coating was unstable as to its

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    36/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    such a conclusion was false, and not supported by the test. Morrison told him: "It

    is all political, stay out of it."

    69. No matter how many tests were performed or at what stage they were

    performed, the coatings continued to fail tests. In a December 9, 1998, work

    schedule entitled "[redacted] Paint & Topcoat Repair Schedule - No. 13", Olsen

    noted that "BASELINE COATINGS FAILED RCS RANGE TESTING" AND

    "[redacted] PAINT MATL. PROBLEMS. ALL TESTING ON HOLD FOR

    TESTING OF PRODUCTION MATL." See Exhibit I, 12/09/98 __ Paint and

    Topcoat Repair Schedule No. 13.

    70. On information and belief, throughout 1998, Lockheed continued to

    defraud the USAF about the coatings failures to keep progress and milestone

    payments flowing, and continued to convey the misimpression that the F-22 was

    making timely progress in the stealth coatings issues. In fact, rather than moving

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    37/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    the same failing results. See Exhibit K, 2/4/99 5PTMRL04 TY-1 __Paint

    Repair History. A February 11, 199 schedule directly shows that the F-22 L.O.

    baseline coatings and repairs continued to fail all tests. See Exhibit L, 2/11/99

    __ Paint and Topcoat Repair Schedule No. 15. Indeed, the coatings failures

    were so undeniable that even a Trawinski schedule entitled "F-22 [redacted] Paint

    Implementation," dated April 1, 1999, records numerous failed tests. See Exhibit

    M. On information and belief, Lockheed never shared those failed test results with

    the USAF.

    72. In 1999, Lockheed began using more conductive coatings from its

    LMAC business unit. By June of that year, Lockheed ceased using the CAAP CO.

    conductive coating altogether. On information and belief, the problems with that

    defective product had become so obvious that Lockheed believed that it could not

    hide its failures any longer.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    38/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    pounds to an aircraft designed to be ultra-light, in which mere ounces can make a

    significant difference. Moreover, with reparability failures unabated, additional

    layers of primers and other coatings dramatically increase reliability and

    maintainability (R&M) problems. Unsurprisingly, the media have reported, at

    least as late as 2006 that R&M man-hours and materials for the aircrafts crucial

    low observables characteristics have increased to as much as three times acceptable

    rates.

    74. In an attempt to make the conductive coating work, Lockheed

    increased its thickness, adding, on information and belief, 200 pounds to the

    aircraft. This new, thicker conductive coating was also found to be easily damaged

    by fluids and therefore, was over coated with several layers of primer (which did

    not meet engineering requirements), adding even more weight.

    75. Until Olsen took medical leave in July 1999, the CAAP CO.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    39/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    ever truthfully disclose to the USAF that the coatings were defective, rendering the

    stealth attribute a failure.

    76. In addition, the LO materials contained hazardous chemicals

    forbidden by the contract and by law, and such hazardous materials were handled

    irresponsibly and even illegally. The composition of LO materials contravened

    the F-22 contract, because they contained Diisocyanate chemicals which were not

    permitted by the contract.16 Isocyanates are harmful to living tissue. They are

    16Diisocyanates are a group of low-molecular-weight aromatic and aliphatic

    compounds. The most common of these are toluene diisocyanate (TDI),methylene bisphenyl isocyanate (MDI), and hexamethylene diisocyanate (HDI). .. . They are widely used in the manufacture of flexible and rigid foams, fibers,coatings such as paints and varnishes, and elastomers. Diisocyanates areincreasingly used in the automobile industry, auto body repair, and building

    insulation materials. In this report, diisocyanates as a group will be referred to asisocyanates. . . .

    TDI and other isocyanates are powerful irritants to the mucous membranes

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    40/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    toxic and exposure is known to result in hypersensitivity pneumonitis as well as

    occupational asthma in humans, both through inhalation exposure and dermal

    contact. Mr. Olsen was ordered to keep this fact secret from the Air Force, as the

    violation could lead to cancellation of the contract by the Air Force.

    77. In addition, hazardous materials were handled illegally. On

    information and belief, throughout the complete LO testing program, Morrison and

    Trawinski had numerous coatings shipments delivered to their homes and those of

    other employees. This was done to avoid any unexpected governmental inspection

    or discovery of the receipt and use of those defective, toxic materials.

    Management secretly circumvented the Lockheed company HazMat building

    which housed and controlled all toxic, controlled materials, thus avoiding

    documentation of Lockheeds receipt, its entry of the toxic substances in its books,

    and its assignment of the required company tracking and control of hazardous

    materials. Olsen refused to participate in that scheme which violated an assortmentof company policies and relevant laws dealing with dangerous, toxic substances.

    78 I f M i i f d Ol f h f h h h d d

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    41/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    HazMat LO coatings shipments would be delivered to Olsens home. Olsen

    immediately refused to participate in the illegal scheme and insisted that Morrison

    call and stop shipments to Olsens home. Morrison responded that Olsen was not

    a team player, and if youre not a team player you can be replaced. Morrison

    continued to have the toxic HazMat LO materials sent to his own and other

    employees homes. When they received the illegal materials, they smuggled them

    past the Lockheed company security guards and stored them in the engineering

    offices of the F-22 engineering building.

    79. The conductive coating had been modified numerous times and as a

    result was no longer in conformance with the Lockheed HazMat material control

    regulation requirements; the initial assigned Lockheed company HazMat control

    number was thus void, making this a nonconforming toxic HazMat material inside

    Lockheed Corporation facilities. In addition, the toxic HazMat LO materials were

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    42/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    in the emission of the toxic HazMat LO materials chemicals into the air, exposing

    countless people in the company and surrounding community to dangerous air.

    Lockheed management knew of the unlawful presence of mercury and

    diisocyanates and mercury in th4 components of the L.O. materials. Lockheed

    management concealed the unlawful presence of these controlled chemicals from

    the USAF, Lockheed employees, and the surrounding communities. Lockheed

    concealed this information because its disclosure would have resulted in the

    shutdown of the F-22 program, enormous expense, and significant delaylikely

    years.

    80. At no time during Olsens tenure at Lockheed did he see any

    indication that Lockheed informed the USAF about low observables baseline

    coatings failures or repairs failures. Further, during Olsens tenure at Lockheed,

    the LMAC coatings never satisfied or passed the reflectivity and reparability tests.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    43/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    82. By the time of Olsens termination, the stealth coatings project was

    secretly years behind schedule, poorly performing and out of specifications,

    without required waivers or tailorings.

    5. 2000-2004: Failures and Misrepresentations Continue [throughpresent]

    83. Following Olsens July 1999 departure and at least through October

    2004, if not through the present, the LMAC conductive coatings and the Boeing

    topcoat coatings have failed. The LMAC conductive coating failed, consistently,

    the reparability tests at least through October 2004.

    17

    By the same token, at least

    through October 2004, the Boeing topcoat coatings infrared properties continued

    to fail and its coloring, important for visual stealth, was inconsistent.18

    84. The LMAC conductive coatings only passed baseline coating

    reflectivity tests when Lockheed applied six (6) times the thickness, thereby adding

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    44/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    of the F-22s weight-gain. On information and belief, Lockheed has had to apply

    extra RAM (which is significantly heavier than conductive paint) to cover failing

    conductive gap filler and LO coatings over gaps, seams and structural flex points.

    On information and belief, the six (6) times additional thickness of conductive

    coating added hundreds of pounds to the super-cruiser, and the extra RAM has

    burdened the F-22 with approximately four hundred (400) more pounds, covering

    up failure and impacting the mission.

    85. The extremely thick coatings have proved brittle, resulting in

    cracking, fissures and heightened RCS. In short, the conductive coatingswhich

    were supposed to be paper thin and light by designhave so materially failed that,

    on information and belief, the F-22's velocity and maneuverability have been

    compromised by the added weight.

    86. The extra coatings were not merely inefficient cover-ups; they were

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    45/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    87. However, the LO conductive gap filler coatings were substandard,

    were cracking, and were failing relatively quickly in testingto the extent they

    were tested at all. Even though these coatings were not thoroughly tested to prove

    their integrity for aircraft service, and were failing when tested with aircraft fluids

    and water, they were put on production aircraft anyway.

    88. As a direct result of the expectation that the gap filler material would

    crack, Materials and Processes Engineering management decided to modify the

    formulation of the gap filler material by adding more conductive filler to the failing

    F-22 Specification gap filler material. Their reasoning was that adding excess

    filler would make it even more conductive and thus, when the material cracked, as

    Lockheed expected it would, the RCS signature would be less observable. The

    result, however, was that the extra conductive filler exacerbated cracking in the

    gap filler. The excessively thick LO coatings over the gap filler resulted in greater

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    46/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    would not approve adding even one pound to the aircraft. The F-22 was already

    overweight when these hundreds of pounds were added, and any additional weight

    would destroy the mission fitness and performance of this new advanced

    technology fighter. Moreover, the cracked primers/conductive coating/top coat

    paint system and the underlying cracked highly conductive gap filler destroys the

    low observability of the RCS signature, essentially painting a bulls-eye target on

    the aircraft in place of the intended low observable shroud. As a direct result,

    internal corrosion has occurred; the failure of the Low Observables System has

    allowed environmental exposure, resulting in internal corrosion. This has now

    been documented in the media, including the Salt Lake Tribune.

    90. Olsen learned from Lockheed engineering test lab personnel and

    engineers in 2005 that LO coatings problems and failures were persisting. Olsen

    learned that despite increasing the LO conductive coating thickness to six times the

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    47/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    91 On information and belief, Lockheed at least through October 2004

    and likely to the present date has never truthfully disclosed to the USAF that the

    stealth coatings continually, for years, had failed the requisite tests. On

    information and belief, at least through October 2004, if not the present, the stealth

    coatings program had been delayed many years and hundreds of millions of dollars

    have been wasted (1) on the process and (2) on the defective aircraft. Our country

    does not have the stealth fighter for which it paid.

    F. Incentives to Deceive

    92. On information and belief, Lockheed knew that by fraudulently

    misleading the USAF about the coatings failures, it would continue to receive (1)

    progress and (2) milestone payments, and that the concealment would convey the

    impression that the F-22 program was timely progressing. On information and

    belief, Lockheed had substantial incentives to lie to the USAF about the defective

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    48/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    deployed field operations was a false claim, including but not limited to the

    following:

    a. From at least as early as late 1995, when Lockheed had not

    formally tested the coatings although it should have done so, and

    subsequently, when Lockheed falsely represented that the coatings had

    passed testing, each of Lockheeds certifications, pursuant to 48 C.F.R.

    52.232-5c, in each progress bill, that [t]he amounts requested are only for

    performance in accordance with the specifications, terms and conditions of

    the contract, constitutes a false statement, and each progress bill containing

    such certification constitutes a false claim and a false record under the False

    Claims Act. All progress payment requests since this time are affected

    because low observability is fundamental to the F-22s purpose and function.

    b. From at least as early as late 1995, when Lockheed had not

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    49/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    constituted a false claim under the False Claims Act. All progress payment

    requests since this time are affected because low observability is

    fundamental to the F-22s purpose and function.

    c. From at least as early as late 1995, when Lockheed had not

    formally tested the coatings although it should have done so, and

    subsequently, when Lockheed falsely represented that the coatings had

    passed testing, each milestone bill submitted by Lockheed constituted a false

    claim and each certification in support of such milestone bill, consistent with

    those described above in paragraphs 17-20, constituted a false statement and

    a false record pursuant to the False Claims Act. All milestone payment

    requests since this time are affected because low observability is

    fundamental to the F-22s purpose and function.

    94. Lockheeds statements to USAF representatives at weekly meetings of

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    50/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    95. Lockheeds public statements at the November 11, 1997 award

    ceremony attended by the USAF that the brush and roll restoration process meets

    the RCS requirements constitute false statements under the False Claims Act.

    96. Morrisons statement in his September 24, 1998 presentation to the

    Low Observables Steering Group, attended by the USAF, that the coatings were

    meeting specifications constituted false statements under the False Claims Act.

    See Exhibit H.

    97. Lockheeds statements made at the insistence of Morrison in the

    October 1, 1998 report that the coatings had registered stable on all tests

    constituted false statements and false records under the False Claims Act.

    98. Lockheeds failure to disclose the facts in the February 4, 1999

    Management Presentation Document entitled Items that Directly Contribute to

    [redacted] Restoration Problems and the April 1, 1999 document entitled F-22

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    51/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    100. Documents falsely stating or implying that Lockheed had used

    prematurely purchased, short shelf-life paints or other materials, which were in fact

    stored, discarded, or diverted to other uses, constitute false records and false claims

    pursuant to the False Claims Act. Additionally, requests for payment for such

    materials constituted false claims under the False Claims Act.

    101. Damages to the United States include all of the money expended

    for years in pursuing and testing wholly inappropriate, defective LO materials

    leading to defective LO stealth for the entire F-22 program. Because stealth is

    the primary, intrinsic advantage of the F-22 concept, and the defective stealth

    materials do not perform as required, damages should include the entire cost

    of the F-22 aircraft manufactured through this dateif not the entire cost,

    alternatively, the entire cost of incorporating the defective stealth materials

    into the aircraft structure and all of the related costs of the LO development

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    52/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    minimally, $50 million times the 183 aircraft acknowledged as manufactured

    or "in process." The LO materials didn't work in development phases, were

    falsely represented as performing and arent working per specifications today.

    The current LO materials are not spec for the program, dont work and will

    never perform as intended.

    103. If the damages include remediation of all F-22 aircraft, on

    information and belief the costs of disassembling each F-22, stripping off all

    LO materials, developing proper LO materials that would satisfy the

    specifications and the F-22 mission, reapplying a functional LO stealth

    externality, and reassembling each aircraft would cost no less than $50 million

    per F-22. This alternative damages calculation is in addition to the huge

    losses from the fraudulent R&D and processing of defective LO materials that

    currently plague the F-22 fleet.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    53/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    VIII. CAUSES OF ACTION

    COUNT ONE:

    False Claims Act, 31 U.S.C. 3729(a)(1)(A) (or former 31 U.S.C. 3729(a)(1))

    105. Relator re-alleges and incorporates the allegations contained in

    paragraphs 1 through 104 of this complaint.

    106. This is a claim for treble damages, civil penalties and other relief

    under the False Claims Act, 31 U.S.C. 3729 (a)(1)(A) (or former 31 U.S.C.

    3729(a)(1)).

    107. Defendant Lockheed used coatings on the F-22 that it knew were

    deficient. Olsen had direct, personal knowledge of that fact.

    108. Lockheed knowingly violated the regulations in FAR and DFARS, of

    certifications for the 1991 contract, of certifications in the progress bills, of

    certifications in the milestone bills and of representations in other documents and

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    54/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    milestone bills to the USAF for payment in violation of 31 U.S.C. 3729 (a)(1)(A)

    (or former 31 U.S.C. 3729(a)(1)).

    110. On information and belief, the USAF paid the false or fraudulent

    claims presented in the form of Lockheeds progress bills and milestone bills.

    111. By reason of these payments of false or fraudulent claims, the United

    States has been damaged in a substantial amount, entitling the United States to

    multiple damages, penalties, attorneys fees and other relief under the FCA.

    COUNT TWO:

    False Claims Act, 31 U.S.C. 3729 (a)(1)(B) (or former 31 U.S.C. 3729(a)(2))

    112. Relator re-alleges and incorporates by reference the allegations

    contained in paragraphs 1 through 111 of this complaint.

    113. This is a claim for treble damages and civil penalties under the False

    Claims Act, 31 U.S.C. 3729 (a)(1)(B) (or former 31 U.S.C. 3729(a)(2)).

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    55/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    reparability tests and had otherwise met the contract specifications for the F-22

    when in fact the coatings had continuously failed such tests and had not met

    contract specifications.

    116. On information and belief, by the wrongful uses of certifications in

    the 1991 contract, of certifications in the progress bills, of certification in the

    milestone bills and of representations in other documents and presentations,

    Lockheed knowingly made, used, or caused to be made or used false records or

    statements material to false or fraudulent claims, in the form of progress bills and

    milestone bills presented to the USAF for payment in violation of 31 U.S.C.

    3729 (a)(1)(B) (or former 31 U.S.C. 3729(a)(2)).

    117. On information and belief, the USAF paid the false or fraudulent

    claims presented in the form of defendants progress bills and milestone bills.

    118. On information and belief, by reason of these payments of false or

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    56/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    COUNT THREE:

    False Claims Act, 31 U.S.C. 3729 (a)(1)(G) (or former 31 U.S.C. 3729(a)(7))

    119. Relator re-alleges and incorporates by reference all the allegations

    made in paragraphs 1 through 118 of this complaint.

    120. This is a claim for treble damages and civil penalties under the False

    Claims Act, 31 U.S.C. 3729 (a)(1)(G) (or former 31 U.S.C. 3729(a)(7)).

    121. On information and belief, Lockheed used coatings on the F-22 that it

    knew were deficient.

    122. Lockheed knowingly violated the regulations in FAR and DFARS, of

    certifications in the 1991 contract, of certifications in the progress bills, of

    certifications in the milestone bills and of representations in other documents and

    presentations. Lockheed, in order to obtain payment from the United States,

    misrepresented to the USAF that the coatings had passed reflectivity and

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    57/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    the form of progress bills and milestone bills to the USAF for payment in violation

    of 31 U.S.C. 3729 (a)(1)(G) (or former 31 U.S.C. 3729(a)(7)).

    124. On information and belief, by those knowing violations, Lockheed

    knowingly made, used, or caused to be made or used false records and statements

    material to an obligation to pay or transmit money or property to the Government

    or knowingly concealed or knowingly and improperly avoided or decreased its

    obligation to the Government by concealing its existing, legal obligations to repay

    the United States for the unearned money from payments for the defective coatings

    from progress bills and milestone bills in violation of 31 U.S.C. 3729(a)(1)(G)

    (or former 31 U.S.C. 3729(a)(7)).

    125. On information and belief, by reason of Lockheeds conduct, the

    United States has been damaged in a substantial amount, entitling the United States

    to multiple damages, penalties, attorneys fees and other relief under the FCA.

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    58/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    or fraudulent information in connection with requests for

    payment [including progress bills and milestone bills],

    plus three (3) times the amount of the damages that the

    United States has sustained, because of Lockheeds

    unlawful actions from and after February 1996 when the

    F-22 stealth coatings failed reflectivity and reparability

    tests through the present date;19

    C. Defendant also be directed to disgorge all sums by which

    it has been enriched unjustly by its wrongful conduct;

    D. Defendant be enjoined from concealing, removing,

    encumbering or disposing of any assets which may be

    required to pay all civil monetary penalties imposed by

    the Court;

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    59/105

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    F. Relator be awarded all costs of this action, including

    statutory attorneys fees and costs pursuant to 31 U.S.C.

    3730(d).

    REQUEST FOR TRIAL BY JURY

    Pursuant to Rule 38 of the Federal Rules of Civil Procedure, Relator Darrol

    Olsen hereby demands a trial by jury.

    PRAYER

    WHEREFORE, Relator/Plaintiff prays that this District Court enter

    judgment on behalf of the Plaintiff and against the Defendant for the following:

    a. Damages in the amount of three (3) times the actual

    damages suffered by the United States Government as a

    result of the Defendants conduct which violated the

    False Claims Act, as well as all other relief available

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    60/105

    5

    10

    15

    1234

    6

    78

    9

    111213 14

    1617

    d. All other relief on behalf of the RelatorlPlaintiff or the

    United States Government to which either may be justlyentitled, whether at law or in equity, which the DistrictCourt deems just and proper.

    Dated: August 5, 2009UNITED STATES OF AMERICA, ex reI.Darrol OlsenRespectfully submitted:BoYD & ASSOCIATES AWGROUP

    Samuel L. Boyd PhilIp E. BensonTX SBN: 02777 00 CA SBN: 138933Catherine C. Jobe Donald R. WarrenTX SBN: 10668280 7825 Fay Ave., Ste. 2006440 North Central Expressway La Jolla, CA 92037Suite 600 Telephone (858) 454-2877Dallas, Texas 75206 Facsimile (858) 454-5878

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    61/105

    5

    10

    15

    1

    234

    6

    789

    11 12

    13

    14

    16

    17

    CERTIFICATE OF SERVICE AND DISCLOSUREOn or before September 27, 2007, a Disclosure Statement and exhibits were

    served upon Mr. Paul J. Wogaman, Trial Attorney, U.S. Department of Justice, 601D St., NW, #9006, Washington, D.C. 20004, regarding Relator's complaints, theDefendant's violations and Relator's intention to file suit.

    On this date, A u g u s t . . . . . . 5 ~ 2009, a copy of Relator's/Plaintiffs FirsAmended Complaint was formally served pursuant toCertified Mail, Return Receipt Requested, upon:Eric HolderAttorney General of the United StatesU.S. Department of Justice950 Pennsylvania Avenue NWWashington, DC 20530-0001Mr. Paul J. Wogaman (Via Federal Express)Trial AttorneyU.S. Department of Justice601 D St., NW, #9006Washington, D.C. 20004

    FRCP 4(i)(l )(b), vi

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    62/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    63/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    64/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    65/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    66/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    67/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    68/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    69/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    70/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    71/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    72/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    73/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    74/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    75/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    76/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    77/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    78/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    79/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    80/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    81/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    82/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    83/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    84/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    85/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    86/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    87/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    88/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    89/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    90/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    91/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    92/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    93/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    94/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    95/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    96/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    97/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    98/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    99/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    100/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    101/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    102/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    103/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    104/105

  • 8/14/2019 Plaintiff's First Amended Complaint and Exhibits Filed 8 5 09 - Olsen F-22

    105/105