planning and executing fast-track projects › scv-tems › files › 2016 › 12 › tems... ·...
TRANSCRIPT
Planning and Executing Fast-Track Projects
Dr. Raymond LevittProfessor of Civil & Environmental EngineeringAcademic Director, Advanced Project Management ProgramStanford University
Presentation to IEEE SCV Engineering Management Society October 29, 2003
2
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
3
Planning and Executing Fast Track Projects
Converting Strategy into Action
Fast-Track Project Case Study: Lockheed Martin Launch Vehicle
Goal: Shrink time-to-market for LMLV by 80% vs. Trident missile!Highly Concurrent: many interdependent activities must be scheduled concurrentlyKey components will be outsourced to minimize cost
4
Planning and Executing Fast Track Projects
Converting Strategy into Action
Organization of Avionics PDT
P ow er D ist.P anel
S ub Team (3)
F iring U n itS ubT eam (3)
O peratio nalIn terlocks
S ub Team (4)
F ligh t B o xes S u b Team
P rogramM anager
S E & IP ro ject
M anager
P ropu ls ionP ro ject
M anag er
N G & CP ro ject
M anager
Facilities& S E
E ngineeringM anager
B usin essD evelopm ent
M anager
O perationsM anager
TestE ng ineerin g
M anager
S tructu resP ro ject
M anager
T otal: (15)
O ff-shelf D epartm ent
C ab les C o ntractor
P ackag ing D epartm ent
E lectron ics D epartm en t
F ligh t B oxesD epartm ent
P rocesso r fo rP ackage
S ub Team (5 )
C ab lesS ubT eam
(3)
O ff-sh elfS ub Team
(5)
P ackag ingS u bTeam
(1.5)
E lectron icsP arts
S ubTeam (6)
A vion icsP ro ject
M anager
Fu nctio nal G u idance
P ro ject O vers igh t- M on ito ring-E xception H and ling
Fu nctio nal G u idance
P ro ject O vers igh t- M on ito ring-E xception H and ling
S T S ubT eamP D T P roduct D evelopm ent T eamS E & I S yste m s E ng ineering and In teg ra tionN G & C N av iga tion , G u idance and C ontro lS E S upport E qu ipm ent
(Actor N am e) A cto r N o t R epresen tedin A vio n ics M od el
(Actor N am e)(# FTE s) A ctor R ep resen ted
in A vion ics M o del
5
Planning and Executing Fast Track Projects
Converting Strategy into Action
Activity Workflow for Avionics PDT
P re d ec es so r -S u cc es so rre la tio n sh ip
A c tiv ity
(T o ta l H o u rs )
A c tiv ity
(T o ta l H o u rs )
(s ta rt)m ile s to n e
m ile s to ne(fin is h )V e h ic le
A v io n ic sC o n c e p t
S ys te mIn te g ra tio n a n d
T e s t
Id e n tify P a rtsR e q u ire d
S e a rc h fo rV e n d o rs
P ro c u re m e n tS u p p o rt
P re p a reD o c u m e n ta tio n
P rin te d W irin gB o a rd D e s ig n
P rin te d W irin gA s s e m b ly
E n c lo s u reD e s ig n T o p A s s e m b ly
P ro c u re m e n t
D e ve lo p in gS u b -c o n tra c ts
T e a m in gA g re e m e n ts
R a n g eR e q u ire m e n ts
V e h ic leIn te rc o n n e c t
L a yo u t
D e fin eIn te rfa c e s
D e ta ile dC a b le D rw .
F a b ric a te a n dT e s t C a b le s
D e fin eR e q u ire m e n ts
N ewE n g in e e rin g
(C a b le s )
R e e n g in e e rin gE x p e rie n c e s
P ro d u c tio nE n h a n c e m e n ts
B u ild a n d T e s tF lig h t U n its
B re a d B o a rdA n d P h ys ic a l
M o c k u p
A p p ly in gE x is tin g
A p p lic a tio n s
O ffs h e lf S u b T ea m (S T ) (5 )
C a b les S T (3 )
F lig h t B o x es S T (15 )
E le c tro n ic P arts S T (6 )
P a cka g in g S T (1 .5 )
P ro jec t M a n a g er (1 )
C a b le s S u b Tea m (3 F T E )
F lig h t B o x e s S T (1 5 F T E )
E le c tro n ic P a rts S u b T e a m (6 F TE )
P a ck a g in g S u b T ea m (1 .5 F TE )
P h ys ic a lM o c k u p
A v io n ic sD raw in g s
O ffs h e lf S u b Te a m (5 F T E )
6
Planning and Executing Fast Track Projects
Converting Strategy into Action
Case Study Results :Lockheed Martin Launch Vehicle
LMLV1 launched in mid-April 1996 – almost 4 months later than plannedLaunch vehicle “departed controlled flight” and had to bedetonated by AF safety officerAnalysis of telemetry data indicated most likely cause of failure to be a misrouted cablethat shorted out!
7
Planning and Executing Fast Track Projects
Converting Strategy into Action
Analysis Tools Can Enable “Project Design”Conceptual
DesignDetailed Design and Execution
Closeout &Learning
Level of InfluenceLevel of Influence
Expenditure of Funds Expenditure of Funds
OutcomeKnowledgeAnalysis ToolsOutcome
Predictions
100%
0%
8
Planning and Executing Fast Track Projects
Converting Strategy into Action
Fast Track Projects Are Information-Intensive
High performance,complex product has
high level of inter-dependency between
its subsystems
Fast-track schedule triggers unplanned coordination and rework for project
organization
Process OrganizationProduct
Project team must process large amount of information under
extremely tight time constraints
9
Planning and Executing Fast Track Projects
Converting Strategy into Action
The Challenge of Fast-Track Projects:“Concurrent Engineering” Incurs Large Overheads
CPM view of traditional project work – Sequential ActivitiesCPM View of Fast-Track Project work—Overlapped Activities
Reality of fast-track project work!
Increased CoordinationIncreased Rework
10
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
11
Planning and Executing Fast Track Projects
Converting Strategy into Action
PERT SimulationAssume each activity has a variable duration that is described by a probability distribution (Gamma) as follows:
Perform a large number of PERT simulations (~1,000)Independently sample each activity’s durationPerform a standard CPM analysis, using the sampled duration for each activityUse multiple (~1,000) CPM analyses to compute probability distributions of project duration and activity criticality
moml
mp Project Duration
12
Planning and Executing Fast Track Projects
Converting Strategy into Action
Nov95 Dec95 Jan96 Feb96 Mar96 Apr96
100%
0%
Probability ofCompletion 50%
What Would PERT Simulation Have Told Lockheed Managers?
“There is uncertainty in project completion time”
“Some near-critical activities may become critical”Fast-track projects usually have multiple near-critical pathsA “criticality index” is computed for each activity, equal to the % of simulation trials in which it was critical
13
Planning and Executing Fast Track Projects
Converting Strategy into Action
& of PERT Simulation for Fast-Track ProjectsShows how uncertainty in task durations affects uncertainty of project completion date
A straightforward extension of CPM approach and tools
Assumes that activity durations vary independently Does not model fundamental causes of variation in activity durations (e.g., poor designs, key skill deficits, bad weather, …)Does not reflect that fact that positive or negative risk factors (“knights and villains”) will impact multiple activitiesGives managers no guidance about where/how to intervene
Assumes no effects of executing activities in parallel vs. in sequence
Provides no insights about the hidden cost of more aggressive fast-tracking (concurrent task scheduling)
14
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
15
Planning and Executing Fast Track Projects
Converting Strategy into Action
Critical Chain* Concepts—1Remove hidden safety from task estimates
Eliminate multitasking
* Sources: Eliyahu Goldratt, “The Critical Chain,” and Scitor Corporation Web Site)
16
Planning and Executing Fast Track Projects
Converting Strategy into Action
Critical Chain* Concepts—2Plan backward from required completion date Calculate the Critical Chain (the resource constrained critical path)
* Source: Eliyahu Goldratt, Scitor Corporation Web Site)
17
Planning and Executing Fast Track Projects
Converting Strategy into Action
Critical Chain* Concepts—3Insert Project Buffer at end of critical chain; and insert Feeding Buffer at end of all non-critical chains
Track consumption of buffers during project
* Source: Eliyahu Goldratt, Scitor Corporation Web Site)
18
Planning and Executing Fast Track Projects
Converting Strategy into Action
What Could Critical Chain Analysis Have Told Lockheed Managers?
During the Planning Stage“Start some project activities earlier!” Earlier start time may not have been feasible.
During the Execution Stage“ Cable team project and feeding buffers are being consumed by activity overruns!” Analysis could have alerted managers earlier in the project to bring in extra cable resources
19
Planning and Executing Fast Track Projects
Converting Strategy into Action
& of Critical Chain for Fast-track ProjectsHighlights latest startsShows impact of eliminating multi-taskingTracks impact of activity delays on buffersDoes not relate size of buffer in Feeder Chain or Critical Chain to degree of complexity or interdependence of activities in that chain Does not predict relative schedule risks of particular activities or chains in advance—vs. “task criticality” in PERT Simulation
20
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
21
Planning and Executing Fast Track Projects
Converting Strategy into Action
System Dynamics ApproachesModel projects as “stocks and flows” of work, resources, information, motivation, etc.Express relationships between variables as arbitrarily simple or complex finite difference equations
* Source: “The Rework Cycle: Why Projects Are Mismanaged” by Kenneth Cooper, PMNet, 1993
22
Planning and Executing Fast Track Projects
Converting Strategy into Action
What Would a System Dynamics Model Have Told Lockheed Managers
Showed impacts of positive and negative feedback loops on performanceShow impacts of delayed feedback loops—(oscillation)
Could provide insights about overall schedule risks due to fast-tracking this projectUnlikely to have identified specific problems in this case
* Source: “The Rework Cycle: Why Projects Are Mismanaged” by Kenneth Cooper, PMNet
23
Planning and Executing Fast Track Projects
Converting Strategy into Action
& of System Dynamics for Fast-Track Projects
System Dynamics is a broadly applicable simulation language
SD has been applied to problems as diverse as business supply chains (e.g., “The Beer Game”) and natural ecosystems (e.g., sustainability of fisheries, forests, …)
System Dynamics is a broadly applicable simulation language
No built-in objects or behaviors to model projects in detail
Insights it can provide about projects tend to be generic and high level (e.g., rework example)
“Stocks & flows” architecture is ideally suited for modeling flows of goods & info in ecosystems or supply chains
24
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
25
Planning and Executing Fast Track Projects
Converting Strategy into Action
Project Design ApproachModel planned fast-track work process and proposed organization realisticallySimulate organization executing work process to predict schedule/quality risksCompare predicted performance vs.plan, and “intervene” to mitigate risksIterate to find “optimal” project design
VDT Project Design Case Study: Lockheed Martin Launch Vehicle
26
Planning and Executing Fast Track Projects
Converting Strategy into Action
LMLV Project Avionics Team: VDT/SimVision Model
EngineeringManager
0.515
15
15
15
1515
5
5
5
5
5
3
3
32
2
1
11
1
1
1
11
1
0.4
5
Start
Finish
Vehicle AvionicsConcept Re-engineering
ExperiencesApply ExistingApplications
Bread Board andPhysical Mockup
Avionics Drawings
ProductionEnhancements
Build and TestFlight Units
DefineRequirements
DevelopingSubcontracts
TeamingAgreements
RangeRequirements
Physical Mock up
Procurement
New Engineering
Vehicle InterconnectLayout
Define Interfaces
Detailed CableDrawings
Fabricate andTest Cables
Identify PartsRequired
Search forVendors
PrepareDocumentation
ProcurementSupport
Printed WiringBoard Design
Printed WiringAssembly
Enclosure design
Top Assembly
System Integration& Test
ProjectManagement
Avionics PM
Packaging ST Flight Box ST ElectronicParts ST Cables ST Off-Shelf ST
27
Planning and Executing Fast Track Projects
Converting Strategy into Action
LMLV Project Avionics Team: Gantt Chart
1995 1996
28
Planning and Executing Fast Track Projects
Converting Strategy into Action
LMLV Project: Actor Backlogs
29
Planning and Executing Fast Track Projects
Converting Strategy into Action
LMLV Project: Process Quality Risks
Project Design Guides Managerial Interventions
“What-if Analysis” of LMLV Avionics Team
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
Increase Cable Subteam staffing
from 3-5 engineers
Replace 3 Cable Subteammembers with 3 more
experienced engineers
Cost
Duration
Except's
Bet
ter
Wor
se
31
Planning and Executing Fast Track Projects
Converting Strategy into Action
Lockheed Martin Launch Vehicle: Project Design Results
Simulated organization executing work process to predict schedule and quality risks
VDT/SimVision predicted launch date delay to within a few days, one year ahead!VDT/SimVision identified cable team quality risk that ultimately caused LMLV to fail!
Predicted performance impact of two potential managerial interventions(although these results were not used)
32
Planning and Executing Fast Track Projects
Converting Strategy into Action
“Exception”
(Jay Galbraith, 1974)
But Project Participants also Coordinate. And they Generate & Handle Exceptions
+
Project ParticipantsPerform Assigned Tasks
33
Planning and Executing Fast Track Projects
Converting Strategy into Action
Info. Volume is Derived from Project Tasks:Direct Work, Communications, Rework
Start
Ready toExcavate
ChooseConstruction
Methods
Long LeadPurchasing
Apply Exc Permit
Seek ZoningVariance
Provide GMP
SelectSubconsultants
Arch Program
Select Key Subs
Estimate Time
Define Scope
ProjectCoordination
Estimate Cost
Choose facadematerials
Choose Struct.System
GMPAccepted
DesignCoordination
Start
Ready toExcavate
ChooseConstruction
Methods
Long LeadPurchasing
Apply Exc Permit
Seek ZoningVariance
Provide GMP
SelectSubconsultants
Arch Program
Select Key Subs
Estimate Time
Define Scope
ProjectCoordination
Estimate Cost
Choose facadematerials
Choose Struct.System
GMPAccepted
DesignCoordination
Start
Ready toExcavate
ChooseConstruction
Methods
Long LeadPurchasing
Apply Exc Permit
Seek ZoningVariance
Provide GMP
SelectSubconsultants
Arch Program
Select Key Subs
Estimate Time
Define Scope
ProjectCoordination
Estimate Cost
Choose facadematerials
Choose Struct.System
GMPAccepted
DesignCoordination
34
Planning and Executing Fast Track Projects
Converting Strategy into Action
Team Information Processing Capacity is Derived From:# Actors; Skill Set; Experience; Structure; Policies
Client PM
Design PM Construction PM
ArchitecturalDesign Subteam
StructuralDesign Subteam
ProjectEngineers
ProcurementTeam
Client PM
Design PM Construction PM
ArchitecturalDesign Subteam
StructuralDesign Subteam
ProjectEngineers
ProcurementTeam
35
Planning and Executing Fast Track Projects
Converting Strategy into Action
VDT/SimVision Information Processing Model:Team IP Capacity >= Task IP Demand?
Client PM
Design PM Construction PM
ArchitecturalDesign Subteam
StructuralDesign Subteam
ProjectEngineers
ProcurementTeam
Start
Ready toExcavate
ChooseConstruction
Methods
Long LeadPurchasing
Apply Exc Permit
Seek ZoningVariance
Provide GMP
SelectSubconsultants
Arch Program
Select Key Subs
Estimate Time
Define Scope
ProjectCoordination
Estimate Cost
Choose facadematerials
1
1
1
Choose Struct.System
0.5
1
1.5
1
1.5
1
0.2
0.5
0.5
2
1GMP
Accepted
Design-Build Biotech Project
DesignCoordination
1
ProjectCoordination
Meeting
1
1 1
1
36
Planning and Executing Fast Track Projects
Converting Strategy into ActionPredictions from VDT/SimVision Project Design Approach
Backlog
Quality
Schedule
Cost
Start Fab Test& Deliver
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
Activities
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
Organization
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
Communication
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
Rework
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
ManagementMeeting
Architecture TeamMeeting
Foundry TeamMeeting
1
1 1 1 1
1
1
1
1
1
1
Meetings
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
0.8
4
4
4
4
1
1
1
1
1 1
1
1
1
1
1
Assignments 1
Start Fab Test& Deliver
Project Lead
Marketing Team Chip Architect TestEngineering St Foundry Lead
Logic DesignTeam 1 Foundry Test
EngineerFoundry Layout
Engineer
VerificationTeam
DesignCoordination
DevelopSpecification
Insert Scan
Partition Chip
Gen Test Suite
PlaceRoute
FullChipSynth
Verify RTL
FloorPlanning
Write B1RTL
Sim GatesAssemble RTL
PhysVerifn
Verify B1RTL
Generate TestVectors
Synth_B1RTL
0.8
4
4
4
4
1
1
1
1
1 1
1
1
1
1
ManagementMeeting
Architecture TeamMeeting
Foundry TeamMeeting
1
1 1 1 1
1
1
1
1
1
1
1
Model Simulation Results
37
Planning and Executing Fast Track Projects
Converting Strategy into Action
Steps in VDT/SimVision Project DesignIdentify client’s key business issues and risksDevelop Flexibility Matrix and trade-offsModel “Baseline Case”
Lay out 5-10 key business milestones per projectIdentify and sequence 5-10 activities per milestone
Lay out organization:– structure, positions, capacity, skills, decision making policies
Assign each task to one responsible position“Flight-simulate” Baseline Case
Diagnose backlogs, schedule and quality risksExplore potential interventions to mitigate risks
Choose a project design that is likely to succeed
38
Planning and Executing Fast Track Projects
Converting Strategy into Action
Level of Effort for Project/Program (Re)Design
Elements of Fast-Track ProgramDesign and Redesign
ClientEffort
(FTE-days)
AnalystEffort
(FTE-days)
Gather data from client about business objectives, 0.5 0.5milestones, tasks, costs, staffing, known risks, etc.
Build “straw-man” as-planned, baseline model 0 1-2
Discuss and refine model 0.5 1-2
Diagnose risks with baseline case 0.25 0.5
Evaluate multiple potential interventions 0.25 0.5
Produce recommendations and report 0 1.0
Ongoing Redesign (Tracking) per cycle 0.5 1.0
39
Planning and Executing Fast Track Projects
Converting Strategy into Action
VDT Fast-Track Project Design: ExamplesReduce time to market for complex manufacturing facilities
Facilitate roll-out of new wireless telecom infrastructure across multiple regions
Develop best practices template toaccelerate factory start-ups
Identify and correct subcontractor management problem that would have delayed project 4 mo.
Help to meet ship milestone date required to close sale with large customer
Align goals and accelerate rollout of innovative consumer product by 3 months
Identify and mitigate critical quality risks to accelerate rollout of new server product
Help to define scope, schedule and organization for strategic IT projects
40
Planning and Executing Fast Track Projects
Converting Strategy into Action
& of VDT/SimVision for Fast-Track ProjectsVDT/SimVision uniquely highlights impact of fast-track work process on cost, schedule and process quality
VDT/SimVision shows impacts of differences in participants skills & experience on project outcomes
Small models and graphical inputs/outputs engage executives in project design process
Models only organizational risks—not technical or market risks (these risks require separate “scenarios”)
VDT organizational model assumes hierarchical exception handling
41
Planning and Executing Fast Track Projects
Converting Strategy into Action
Analysis Tools Can Support “Fast-Track Project Design”Conceptual
DesignDetailed Design and Execution
Closeout &Learning
0%
100%
Level of InfluenceLevel of Influence
Expenditure of Funds Expenditure of Funds
OutcomeKnowledge
OutcomePredictions
Analysis Tools- PERT Simulation- Critical Chain- System Dynamics- Virtual Design Team
42
Planning and Executing Fast Track Projects
Converting Strategy into Action
Outline
Fast Track Project Case Study: The Lockheed Martin Launch VehicleTechniques for Planning Fast Track Projects
PERT SimulationThe Critical ChainSystems Dynamics SimulationThe VDT/SimVision Project Design Approach
AppendixTrajectory of Ongoing Project Design Research
43
Planning and Executing Fast Track Projects
Converting Strategy into Action
Trajectory of Past VDT Project Design Research
99-02: LambertBuettner
97-00: Miller
96-99: Fridsma/Cheng
More Impact of IT/ Communication
technologies
More Impact of IT/ More Impact of IT/ Communication Communication
technologiestechnologies More Impact of Social ProcessesMore Impact of More Impact of
Social ProcessesSocial Processes
More Innovative Work ProcessesMore Innovative More Innovative Work ProcessesWork Processes
95-99: ThomsenSalazar-Kish
90-94: Cohen/Christiansen
Single Project
Program
Enterprise
Communities ofPractice, LearningOrganizations
Single Project
Program
Enterprise
Communities ofPractice, LearningOrganizationsMore Flexible
OrganizationsMore FlexibleMore FlexibleOrganizationsOrganizations
44
Planning and Executing Fast Track Projects
Converting Strategy into Action
Ongoing Stanford Project Design Research
Direct Costs
Complex, Fast-Track “Engineering Projects”
CoordinationCosts
* Effects of Coordination complexity
21 stCentury “Global Change” Projects
* Effects of Institutional Complexity
InstitutionalCosts
$, ¥, €, …
45
Planning and Executing Fast Track Projects
Converting Strategy into Action