planning and programmes gill proudbev lambert technical specialist planning liaison officer fcrm...
TRANSCRIPT
Planning and Programmes
Gill Proud Bev LambertTechnical Specialist Planning Liaison Officer FCRM Asset Investment and Planning Planning Liaison Team
6 October 2009
Outline
Programme planning for FCRM works
Funding and prioritisation
Procurement
Engagement with Spatial Planning
Environment Agency Powers
The EA has permissive powers with regard to flood defence under the Water Resources Act 1991 and the Land Drainage Act 1991
This means that we may act to carry out works, but we are not obliged to.
The new Floods and Water Bill will not affect these basic powers.
Flood Risk Management Planning
Flood Risk Management Planning
Making Space for Water - Government Policy
Catchment Flood Management Plans
Flood Risk Management Plans
Solutions
CFMPs
Set the strategic direction for managing
flood riskin a catchment
Strategies and other
Delivery Plans
Establish how toimplement
Projects and Actions
For example:Schemes and input
to spatial plans
Funding and prioritisation
Funding for Flood Risk Management
Main funding – FDGiA – £37.5M capital
£16.9M revenue
£54.4M total FDGiAInternal Drainage Boards precept £ 1.1M
Total Core Funding £55.5M
Also
- Local Levy (from Local Authorities) £1.15M
- Match funding from Yorkshire Forward £0.5M
Funding for 2009 – 2010 in Yorkshire Area
Constraints
We can only use public money to defend existing property
We cannot speculatively provide defences to allow development.
Under PPS25 if there is no land at lower risk of flooding on which to build, the developer may provide suitable defences.
Appraisal
HM Treasury – ‘Green Book’Best practice guide to carrying out the appraisal and evaluation of policies and projects funded by central government.
Preferred method of evaluation: cost benefit analysis.
Defra – Flood and Coastal Defence Project Appraisal Guidance 3 – Economic Appraisal (PAG3)
Guidance on the application of the ‘Green Book’ methodology to flood and coastal risk management schemes.
Outcome Measures
Purpose of OMs: to align programmes with Government objectives for FCERM
allow Operating Authorities to design programmes to deliver the objectives
establish consistency of reporting
efficiency - the right balance in the programme
Outcome Measures
OM1 Economic benefits *
OM2 Households at risk *
OM3 Deprived households at risk *
OM4 Nationally important wildlife sites
OM5 UK Biodiversity Action Plan habitats*
OM6 Flood warning
OM7 Contingency Planning
OM8 Inappropriate development
OM9 Long term policies and action plans
Prioritising Maintenance ExpenditureCONSEQUENCE OF FRMS FAILURE
Impact on
property and land
High density housing,
commercial and/or industrial
property(LU band A/B)
Internationally designated
sitesHIGHC01 HIGHC02 HIGHC03 HIGHC04
Medium density housing,
commercial and/or industrial
property(LU band C)
Nationally designated
sitesLOWC05 MEDC06 MEDC07 HIGHC08
Little or no housing,
commercial or industrial property
(LU band D & others)
No designations
LOWC09 LOWC10 LOWC11 MEDC12
HIGH
Negligible risk to life
Good warning(adequate
evacuation time)
Little warning (limited evacuation
time)
Little/no warning (no evacuation
time)
Impact on peopleNotes (1) The presence of vulnerable groups may increase consequence of failure.
(2) Warning time refers to failure of an asset, not flood warning time.
HIGH
Procurement
Key National Frameworks
Contract Annual Value
Expiry
National Contractor Framework (NCF2) £120m April 2011
National Engineering and Environmental Consultancy Agreement (NEECA2)
£50m Oct 2011
Strategic Flood Risk Management (SFRM)
£17m Sept 2012
National Cost Consultants Framework (NCCF2)
£3m Feb 2010
Under review
National Site Investigation Framework (NSIF2)
£2.5m Oct 2010
Global principals of the Frameworks
Procured using NEC form of Contract Developing collaborative but challenging supplier relationshipsEarly Contractor Involvement (ECI) / integrated teamsEncourage supplier interaction e.g. Framework Meetings, joint training initiativesProject Incentivisation - Pain/Gain shareRegularly review suppliers performanceDriving best practice Health & Safety and EnvironmentEncourage right behaviours with an Issue Resolution Protocol
Engagement with Spatial Planning
Environment Agency and Planning
Statutory (and non statutory) Consultee on Spatial Plans, certain applications and Environmental Assessment
Advice and evidence
Water quality, water resources, air quality, land contamination, waste management, biodiversity and flood risk
National & Regional Planning
Infrastructure Planning Committee
Statutory consultee for all applications
Permitting authority
Regional PlanningCommenting on Regional Spatial Strategies (& Regional Strategies) and SEA/SAEngage early - informal and formal stagesEnvironmental information for evidence base
Development Plans
Key Stakeholder
Respond to LDD consultations
Provide environmental data for evidence base
Encourage development of background evidence
documents, eg SFRAs, SWMPs
Highlight relevant EA plans/programmes
Local Level Engagement
Statutory consultee on applications and pre-
development proposals
Provide technical advice and information
Local Liaison meetings
Regular discussion with Officers
Training (eg FRSA)