  • 7/24/2019 Planning and Scheduling - CPM

    1/30

    Planning and Scheduling

    Dr. Ir. HM. Agung Wibowo, MM, MSc

    Jati Utomo Dwi Hatmoko, ST, MM, MSc, PhD

  • 7/24/2019 Planning and Scheduling - CPM

    2/30

    Gantt Chart(Mawdesley, 1997)

  • 7/24/2019 Planning and Scheduling - CPM

    3/30

    Linked Bar Chart(Mawdesley, 1997)

  • 7/24/2019 Planning and Scheduling - CPM

    4/30

    Techniques of Scheduling

    List of Activities

    Bar chart / Gantt Chart

    Critical Path Method (CPM)

    Precedence Diagram Network (PDM)

    PERT (Programme Evaluation & ReviewTechnique)

    Line of Balance Method

    Time Chainage Diagram (Mass HaulDiagram)

  • 7/24/2019 Planning and Scheduling - CPM

    5/30

    Network

    A network is a diagram showing allactivites which are needed to complete aproject and the order of which theymust be done.It therefore comprises two parts :

    The activitiesSome method of displaying thetechnological logic of construction.

  • 7/24/2019 Planning and Scheduling - CPM

    6/30

    Scheduling techniques

    1. Bar chart (Gantt chart)2. Network Activity on Arrow (CPM - Critical Path Method)

    Arrow Diagramming Method (ADM)

    Activity on Node (PDMPrecedence DiagramMethod)

  • 7/24/2019 Planning and Scheduling - CPM

    7/30

    Network (Mawdesley, 1997)Activity on Arrow

  • 7/24/2019 Planning and Scheduling - CPM

    8/30

    Activity on Arrow (CPM - Critical Path Method)

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

  • 7/24/2019 Planning and Scheduling - CPM

    9/30

    N & S

    bases

    N

    stem

    N

    wwall

    S

    stem

    S

    wwall

    S

    b/fill

    Deck

    KerbsSur-

    facing

    12

    15 12

    15 12 6 2 21

    2

    3

    4

    5

    6 20

    7 9 10

    0

    6

    activity

    name

    durationactivity

    reference

    earlieststart

    earliest

    finish

    KEY

    N

    b/fill

    68

    12

    6 21 21 33

    21 36 36

    33 39

    48 48 54 56 58 58 60

    5636

    N

    b/fill

    68

    33 39

    0

    6 21

    21 36

    26 38

    38 50

    36 56

    50 56 56 58

    50 56

    58 6021

    latest

    start

    latest

    finish

    50 56

    12

    Activity on Node

    (PDMPrecedence Diagram Method)

  • 7/24/2019 Planning and Scheduling - CPM

    10/30

    Project Scheduling

    Steps

    Define activities

    Sequence activities

    Estimate time /duration

    Develop schedule

    Excavate base

    Blind base

    Formwork

    Reinforcement

    Concrete

    (4d)

    (2d)

    (5d)

    (4d)

    (1d)

    Excavate base Blind base Formwork Reinforcement Concrete

    4 d 2d 5d 4d 1d

  • 7/24/2019 Planning and Scheduling - CPM

    11/30

    Linking Activities in the project

    A B

    A

    B

    Bar ChartActivity on the arrow

    network

    A B

    Precedence diagram

    Activity on B depends on activity A

    predecessor successor

  • 7/24/2019 Planning and Scheduling - CPM

    12/30

    Bar ChartActivity on the arrow

    networkPrecedence diagram

    AC

    A

    B

    A

    CCB B

    Activity on C depends on activities A and B

    Linking Activities in the project

  • 7/24/2019 Planning and Scheduling - CPM

    13/30

    Bar ChartActivity on the arrow

    networkPrecedence diagram

    A CA

    B

    A C

    C

    B BDD D

    Activity on C and D depends on activities A and B

    Linking Activities in the project

  • 7/24/2019 Planning and Scheduling - CPM

    14/30

    Bar ChartActivity on the arrow

    networkPrecedence diagram

    A C

    A

    B

    A C

    C

    B BDD D

    Activity on C depends on activity A and D depends on both activities A and B

    Linking Activities in the project

    Dummy

  • 7/24/2019 Planning and Scheduling - CPM

    15/30

    Only one activity is allowed for two events

  • 7/24/2019 Planning and Scheduling - CPM

    16/30

    Copyright 2006 John Wiley& Sons, Inc. 9-16

    Concurrent Activities

    2 3

    Lay foundation

    Order material

    (a) Incorrect precedencerelationship

    (b) Correct precedencerelationship

    3

    42

    DummyLay

    foundation

    Order material

    1

    2 0

  • 7/24/2019 Planning and Scheduling - CPM

    17/30

    Using dummies in the network

    Excavate (A) Foundation (B) Wall (C)

    The Project : 100 m Brickwall

    Excavate (A)

    Foundation (B)

    Wall (C)

  • 7/24/2019 Planning and Scheduling - CPM

    18/30

    A1 = Excavate base (40m)A2 = Excavate base (30m)A3 = Excavate base (30m)

    B1 = Foundation (40m)

    B2 = Foundation (30m)B3 = Foundation (30m)

    C1 = Wall (40m)C2 = Wall (30m)C3 = Wall (30m)

    Activity A(Excavate base 100m)

    Activity B(Foundation 100m)

    Activity C(Wall 100m)

    Excavate (A)

    Foundation (B)

    Wall (C)

  • 7/24/2019 Planning and Scheduling - CPM

    19/30

    Only one event at the start, and at the end of the network

  • 7/24/2019 Planning and Scheduling - CPM

    20/30

    PM

    Event i Eventj

    i j

    iES

    jEFActivity A

    Duration (d)LS LF

    (ES) Early start : the earliest the event i (activity A) can start

    (EF) Early finish : the earliest the event j can start or - the earliest the activity A can finish

    (LS) Latest start : the latest the event i (activity A) can start without delaying the project

    (LF) Latest finish : the latest the event j can start or the latest the activity A can finishwithout delaying the project

  • 7/24/2019 Planning and Scheduling - CPM

    21/30

    iES

    jEFActivity A

    Duration (d)LS LF

    (ES) Early start = EST (Early Start Time) = EETi (Early Event Time)

    (EF) Early finish= EFT (Early FinishTime) = EETj (Early Event Time j)

    (LS) Latest start = LST (Latest Start Time) = LETi (Latest Event Time i )

    (LF) Latest finish = LFT (Latest FinishTime) = LETi (Latest Event Time j )

  • 7/24/2019 Planning and Scheduling - CPM

    22/30

    Forward Pass

    iES

    jEFActivity A

    Duration (d)

    EF = ES + duration

  • 7/24/2019 Planning and Scheduling - CPM

    23/30

    Backward Pass

    i jActivity A

    Duration (d)LS LF

    LS = LF - duration

  • 7/24/2019 Planning and Scheduling - CPM

    24/30

    embankmentalready

    constructed

    existing ground

    profile

    existing ground

    profile

    finished ground

    profile

    NORTH ABUTMENT SOUTH ABUTMENT

    wingwalls stem

    base

    deck

    backfill

    embankmentalready

    constructed

    Activity Name Activity Reference Activity duration (days)

    North base 1 6

    South base 2 6North abutment stem 3 15

    South abutment stem 4 15

    North wingwalls 5 12

    South wingwalls 8 12

    North backfill 7 6

    South backfill 6 6

    Deck 9 20Kerbs 10 2

    Surfacing 11 2

    Resource constraint: only one set of formwork is available for

    base, one set for abutment stems and one set for wingwalls

    12

  • 7/24/2019 Planning and Scheduling - CPM

    25/30

    Activity on Arrow (CPM - Critical Path Method)

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

    FORWARD PASS

  • 7/24/2019 Planning and Scheduling - CPM

    26/30

    Activity on Arrow (CPM - Critical Path Method)

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

    BACKWARD PASS

  • 7/24/2019 Planning and Scheduling - CPM

    27/30

    Activity on Arrow (CPM - Critical Path Method)

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

    Free float (FF) : the maximum time an activity can be delayed without delaying any subsequent

    activities that are starting at their earliest times

    FF = EFjduration - ESi

    iES

    jEFActivity A

    Duration

    (d)LS LF

    FF = 0TF= 0

    FF =9TF=9

    FF =0TF=0

    FF =0TF=2

    FF =2TF=2

    FF =0TF =0

    FF =0TF=0

    FF =0TF =0

    FF =17TF=17FF =0

    TF=3FF = 0TF=0

  • 7/24/2019 Planning and Scheduling - CPM

    28/30

    Activity on Arrow (CPM - Critical Path Method)

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

    Total float (TF) : the maximum time an activity can be delayed without delaying the whole project

    TF = LFjduration - ESi

    iES

    jEFActivity A

    Duration

    (d)LS LFThe Total float is shared by activities in the network.

    FF = 0TF= 0

    FF =9TF=9

    FF =0TF=0

    FF =0TF=2

    FF =2TF=2

    FF =0TF =0

    FF =0TF=0

    FF =0TF =0

    FF =17TF=17FF =0

    TF=3FF = 0TF=0

    Interferent float (TF) = TF FF

  • 7/24/2019 Planning and Scheduling - CPM

    29/30

    Activity

    Name

    Activity

    Reference

    Activity

    duration

    (days)

    ES i LSi EFj LFj FF TF IF

    North base 1 6

    South base 2 6

    North

    abutment

    stem

    3 15

    South

    abutment

    stem

    4 15

    North

    wingwalls

    5 12

    South

    wingwalls

    8 12

    North

    backfill

    7 6

    South

    backfill

    6 6

    Deck 9 20

    Kerbs 10 2

    Surfacing 11 2

    We can use a table for this

  • 7/24/2019 Planning and Scheduling - CPM

    30/30

    Critical Path

    North

    base

    South

    base

    South

    stem

    North

    stem

    North

    wwalls

    North

    backfill

    South

    wwallsSouth

    backfill

    Deck

    KerbsSurfacing

    1 2

    3

    4

    5

    6 7 8 9 106 6

    15

    15

    12

    12

    6

    6

    20

    2 2

    0 6

    21

    21

    33

    36 48 56 58 60

    6058565036

    36

    21

    21

    60

    The longest path It determines the programme Any delay on the critical path means that the project will be delayed There could be > 1 critical path in the network

    Path 1 = NB+SB+SS+SW+SB+K+S = 49Path2 = NB +NS+NW+NB+K+S= 43Path 3 = NB+SB+SS+D+K+S=51Path 4 = NB+NS+SS+SW+SB+K+S=58Path 5 = NB+NS+NW+SW+SB+K+S=55Path 6 = NB+NS+NW+D+K+S=57

    Path 7 = NB+NS+SS+D+K+S=60 the critical path