planning & installation installing the system

134
MAGNETOM Register 8 English Print No.: M2-050.031.01.09.02 Doc. Gen. Date: 04/99 Replaces: M2-050.031.01.08.02 © Siemens AG 1998 The reproduction, transmission or use of this document or its contents is not permitted without express written authority. Offenders will be liable for damages. All rights, including rights created by patent grant or registration of a utility model _or_ design,_are_ reserved. Vision Vision plus MR Planning & Installation Installing the System

Upload: rass

Post on 17-Sep-2015

239 views

Category:

Documents


11 download

DESCRIPTION

Something for SMI Vision

TRANSCRIPT

  • MAGNETOM

    Register 8 EnglishPrint No.: M2-050.031.01.09.02 Doc. Gen. Date: 04/99Replaces: M2-050.031.01.08.02

    Siemens AG 1998The reproduction, transmission oruse of this document or its contentsis not permitted without expresswritten authority. Offenders will beliable for damages. All rights,including rights created by patentgrant or registration of a utilitymodel _or_ design,_are_ reserved.

    VisionVision plus

    MR

    Planning & Installation

    Installing the System

  • MAGNETOM Register 8 M2-050.031.01 Page 2 of 4 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

    0 - 2 Installing the System

    This page intentionally left blank.

  • Contents 0 - 31 _______General _______________________________________________________ 1 - 1

    Read this first . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 1Safety Note . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 2Magnet Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 4

    Transport dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 4Floor Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 5Magnet environment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 5Availability of LHe when the magnet is shipped cold . . . . . . . . . . . . . . . . . . 1 - 5Issuing orders and transport procedures . . . . . . . . . . . . . . . . . . . . . . . . 1 - 6

    Transport routes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 6Issuing the order . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 6

    Inspecting the magnet shock indicators . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 7Checking the shock indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 8

    Damage during system transport . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 8Important notes for the operation of the magnet . . . . . . . . . . . . . . . . . . . . 1 - 9Component Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 10

    System components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 10Explanation of the abbreviations used. . . . . . . . . . . . . . . . . . . . . . . 1 - 11

    2 _______Installation of the RF-room_______________________________________ 2 - 1

    Read this first . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 - 1Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 - 1General Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 - 2

    3 _______Unloading and positioning the magnet_____________________________ 3 - 1

    Additional information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 1Moving the magnet into the room (through the front) . . . . . . . . . . . . . . . . 3 - 1Moving the magnet into the room (through the back) . . . . . . . . . . . . . . . . 3 - 2Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 3

    Safety instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 4Installation Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 4

    Transport Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 4Completion of the MR suite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 5Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 5

    Tools required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 6Unloading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 6

    Unloading of a crated magnet . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 6Unloading a magnet without crate . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 11Positioning the rollers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 13Moving the magnet into the RF-room . . . . . . . . . . . . . . . . . . . . . . . 3 - 14

    PageSiemens AG Register 8 M2-050.031.01 Page 3 of 6 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 0 - 4 ContentsPositioning the magnet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 15Positioning the magnet within the markings . . . . . . . . . . . . . . . . . . . .3 - 15Levelling the magnet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 16Adding the aluminium shim plates . . . . . . . . . . . . . . . . . . . . . . . . .3 - 18Setting the center height of the magnet . . . . . . . . . . . . . . . . . . . . . .3 - 19

    Checking the galvanic separation of the magnet . . . . . . . . . . . . . . . . . . . .3 - 19Removing the shipping brackets . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 20

    At the gradient coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 20Between magnet and gradient coil . . . . . . . . . . . . . . . . . . . . . . . . .3 - 21

    Sea Ship Kit Removal Instructions . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 22Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 22Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 23

    Air Ship Kit Removal instructions. . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 24Instruction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 24Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 25

    Determining the temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 26General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 26Position of the carbon temperature sensors . . . . . . . . . . . . . . . . . . . .3 - 26Flowchart for magnet installation . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 27Measuring the cryogenic linear temperature sensors . . . . . . . . . . . . . . .3 - 28

    Connecting the quench tube . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 - 30

    4 ______ Component installation in the RF-room ____________________________4 - 1

    Read this first . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 1Example of room layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 2Remote control for Magnet Stop . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 3Installing the table guide support . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 4

    Connecting the ground cables for the AS 25 coil . . . . . . . . . . . . . . . . . . 4 - 6Installing the magnet covers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 6

    Installing the adaption plate for the cable duct of the patient table . . . . . . . . . 4 - 7Installing the front and back panel . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 8

    Magnet side panels. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 13Side panels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 13DCU adjustments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 14

    Lighting in the patient tunnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 15Video camera. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 16Installation of the filter plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 17Installing the RFCC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 18Installation of patient table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 19

    Preparing the patient table . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 19Opening of the patient table . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 20Removing the transport brackets . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 21Installing the cable duct and the patient table . . . . . . . . . . . . . . . . . . .4 - 22

    Intercom . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 - 24

    PageMAGNETOM Register 8 M2-050.031.01 Page 4 of 6 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Contents 0 - 55 _______Computer Room _______________________________________________ 5 - 1

    General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 1Read this first . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 1Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 1Prerequisites. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 2Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 2Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 2

    Areas prone to earthquakes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 3Bolting the MR cabinets to the floor . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 3Bolting the magnet to the floor . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 4Unloaoding and setting up the three-in-one cabinet . . . . . . . . . . . . . . . . 5 - 4Unloading and setting up the ACCU and RFPA cabinet. . . . . . . . . . . . . . . 5 - 6

    Installation of ACCU (Air Compressor Chiller Unit) . . . . . . . . . . . . . . . . . . . 5 - 7General Description/Subsystems . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 7Connecting the on-site water supply. . . . . . . . . . . . . . . . . . . . . . . . . 5 - 8Connecting the hoses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 10Checking the synthetic hoses for leaks . . . . . . . . . . . . . . . . . . . . . . 5 - 11

    Connecting the cold head with the refrigerator . . . . . . . . . . . . . . . . . . . . 5 - 12General / Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 12Connecting the semirigid pressure lines via the filter plate . . . . . . . . . . . . 5 - 13Attaching the half-shells to the filter plate . . . . . . . . . . . . . . . . . . . . . 5 - 15Connecting the cold head power cable via the filter plate . . . . . . . . . . . . . 5 - 17Connecting the water hoses for the gradient coil . . . . . . . . . . . . . . . . . 5 - 18Connecting the ramping cables to the filter plate . . . . . . . . . . . . . . . . . 5 - 23Connecting the monitoring cables to the filter plate . . . . . . . . . . . . . . . . 5 - 24Connecting the gradient cable plate . . . . . . . . . . . . . . . . . . . . . . . . 5 - 25

    Control and Supervision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 25Room thermostat . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 26

    6 _______Control room __________________________________________________ 6 - 1

    Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 1MR-console . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 2

    Key caps to be replaced . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 4Alarm box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 5

    PageSiemens AG Register 8 M2-050.031.01 Page 5 of 6 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 0 - 6 Contents7 ______ Component cabling _____________________________________________7 - 1

    Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 1Additional information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 1

    Circuit diagrams . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 1Bending radius for cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 1Type numbers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 2

    Ready, set, go . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 3We recommend the following cable installation to avoid spikes . . . . . . . . . . . . 7 - 3

    Cabling in the computer room . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 3Cabling in the magnet room . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 3Cabling in the control room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 3

    Line voltage connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 4Line voltage cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 4Protective conductor cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 6

    Detailed views of component connections . . . . . . . . . . . . . . . . . . . . . . . 7 - 8Gradient cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 8Overview of connectors on top of the PCA cabinet. . . . . . . . . . . . . . . . .7 - 11Overview of connectors on top of the CCA cabinet. . . . . . . . . . . . . . . . .7 - 12Overview of the connectors on top of the RFPA cabinet . . . . . . . . . . . . . .7 - 13Overview of the table connectors . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 14Overview of the RFAS connectors . . . . . . . . . . . . . . . . . . . . . . . . .7 - 15Preasurized air connections between Resonator and RFAS . . . . . . . . . . . .7 - 16Overview of the RFCC connectors . . . . . . . . . . . . . . . . . . . . . . . . .7 - 17Top view of ACCU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 18

    Cable routing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 19Cable numbers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 19

    Installing the shim filter assembly . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 20Protective Conductor Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 21Installing the magnet covers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 21Examples of cable installations. . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 22

    Computer room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 22Magnet room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 - 24

    8 ______ Changes to previous version _____________________________________8 - 1

    PageMAGNETOM Register 8 M2-050.031.01 Page 6 of 6 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • 1 - 1

    MAGNETOMning & Installation

    General 1Siemens AG Register 8 M2-050.031.01 Page 1 of 12Medical Engineering Rev. 09 04/99 TD SD 23 Plan

    Read this first 1The separate installation guide provided previously with the system documentation has been elimi-nated. Register 8 of the Planning Guide is the reference guide for the MR installation. The individual installation steps are described in detail in the respective chapters of this manual.Information regarding site-planning is contained in the Planning Guide.The flowchart below provides you with an overview of the complete installation.

    Fig. 1 Installation flowchart

    Install2

    Preliminary stepschapter 1 (this chapter)

    MagnetOR35refer to chapter 3

    Rem.systemcomp.refer to chapter 4

    Control roomrefer to chapter 6

    Computer roomrefer to chapter 5

    CablingMagnetcovers

    refer to chapter 7

    Start-up (register 1 of Start-up manual)

    InstallationStart

    RF-roomrefer to chapter 2

  • 1 - 2 GeneralSafety Note 1The superconducting magnet described in this document is designed for use with whole body Magnetic Resonance Imaging (MRI) systems. The magnet is designed for stationary use.

    Wear the following protective clothing:

    safety shoes face mask gloves (cryogenics) leather gloves (RF-room)

    Always

    wear protective clothing (leather gloves, safety shoes, hard hats) inspect all equipment and tools for defects prior to use ensure that tools and auxiliary materials are in satisfactory condition and conform to manufacturers

    specifications (comply with legal regulations) use only the transport devices specified inform temporary personnel assigned to Siemens employees of the potential hazards and of the

    safety measures to be taken when handling heavy loads secure the transport device and load before moving the load report defects to supervisors immediately

    Superconducting magnets are highly sensitive pieces of medical equipment. Use utmost caution during transport and delivery to avoid hazardous condi-tions to the equipment as well as the personnel. Only specially trained per-sonnel may install/service the magnet. Review the safety instructions before working on the magnet.

    Adhere to the safety information in Register 2 of this manual when performing the work described in this chapter.

    CAUTION

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 2 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • General 1 - 3Never

    stand under heavy loads use defective or damaged equipment allow personnel to stay close to a moving load exceed the load capacity of devices route or stretch ropes, chains and straps over sharp edges knot rope or chains twist rope block emergency exits

    Refer to Register 2 of this manual for a detailed description of the various safety recommendations for electrical or mechanical activities.

    NOTICESiemens AG Register 8 M2-050.031.01 Page 3 of 12 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 1 - 4 GeneralMagnet Overview 1

    Transport dimensions 1 Maximum height (current probe inserted) 2508 mm Minimum height 2411 mm Width 2150 mm Length 2264 mm Magnet weight (with gradient coil and cryogens) 8000 kg Gradient coil weight 1500 kg

    Fig. 2

    You have to add the diamensions of the transport tools which will be used.

    For detailed smallest possible transport dimensions refer to register 5, chap-ter 1 of this manual.

    M-or35

    NOTICE

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • General 1 - 5Floor Loading 1Request assistance from a civil or constructional engineer. This applies for: Installation on ground level with a solid base Installation on one of the other floors or a suspended floor Installation on a sectionally constructed floor such as timber or pre-cast concrete slabs

    Magnet environment 1

    Availability of LHe when the magnet is shipped cold 1

    Ferromagnetic objects in close proximity to the magnet adverselyaffect the field homogeneity of the magnet.

    Just like the Impact magnet, the OR 35 magnet is usually shipped cold. No time will be lost to precooling the magnet. Instead it can be filled with helium immediately after it has been moved into the building. For that purpose you should have at least 450 liters of liquid helium on-site.

    Refer to chapter 3 in this register for checking the temperature and/or the liq-uid helium level of the magnet.

    In case the magnet is shipped warm, refer to chapter 3 in Register 1 of the Start-up manual.

    NOTICE

    NOTICE

    NOTICE

    NOTICESiemens AG Register 8 M2-050.031.01 Page 5 of 12 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 1 - 6 GeneralIssuing orders and transport procedures 1 All transport activities, including delivery into the RF room, should be performed by a licensed carrier

    only. Transport of the magnet or any other heavy components by SIEMENS employees is prohibited.

    Transport routes 1 Before issuing orders to the carrier, the project manager and the architect/construction engineer must

    determine the weight capacity of the floor along the transport route and in the temporary storage areas. The architect/construction engineer must certify in writing that the route can withstand the expected load.

    It is the responsibility of the carrier to obtain information concerning the various transport routes before the actual transport. Copies of the transport plans and certification must be provided by the carrier upon receipt of the order.

    Issuing the order 1 The order for transport by a licensed carrier must be issued in writing. In addition to general

    information (e.g., a list of parts, etc.), the order must contain the following data and documen-tation:

    Copies of plans for the transport route/temporary storage areas. Copy of the certification regarding the weight capacity of the floor. Final destination of transport.

    (It is recommended that the carrier obtain information concerning the transport route before the actual transport).

    Weight of components to be transported (refer to Register 1 of this folder). Dimensions of components to be transported (refer to Register 1 of this folder). Use of transport devices. MAGNETOM Register 8 M2-050.031.01 Page 6 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • General 1 - 7Inspecting the magnet shock indicators 1The shock indicators are located at the back of the magnet (right side, middle section) as seen from the patient table. One is configured for 2 g, the other one is for 6 g.

    Inspect the shock recorders immediately on the truck when the magnet arrives at the installation site (refer to the figure on the next page).

    Check the condition of the shock indicators again after final positioning of the magnet in the magnet room.

    Fig. 3

    Report the shock indicator status to OMT, Oxford, using the form and enve-lope enclosed with the shipment.

    Shock_3

    NOTICESiemens AG Register 8 M2-050.031.01 Page 7 of 12 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 1 - 8 GeneralChecking the shock indicators 1

    Damage during system transport 1Inform the carrier immediately if you detect damage to the packing or the product.After you have informed the carrier, send a FAX to the Oxford Shipping Department and to TD MR in Erlangen. Indicate the nature or extent of damage in the fax. If at all possible, includephotographs of the damaged items.

    Fig. 4 Undamaged shock indicators

    Do not forget to complete the Magnet Acceptance Protocol (included inRegister 9 of the System Manual)

    Check all items against the packing list supplied with each magnet and notify the Oxford Quality Department and TD MR in Erlangen by FAX of any short-age or damage.

    Shocki_1

    The shock indicators are o.k if the balls are stillin the holders.

    NOTICE

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 8 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • General 1 - 9Important notes for the operation of the magnet 1

    Fig. 5

    1 It is essential that the installation/operators manual be read and understood before commenc-ing any operation on the system.

    2 Always wear protective clothing when handling cryogens and heed all warnings and safety notices associated with cryogens and magnetic fields.

    3 Never allow recommended pressure levels to be exceeded in cryogen dewars or vessels inside the magnet.

    4 Before energizing the magnet, ensure that the ERDU is connected to the magnet and in full working order.

    5 Always ensure that the helium vessel is fully depressurized before removing any blanking plug buffle set or fitting from the turret.

    6 Always check that the current probe is connected for the correct magnet polarity before run-ning current into or out of the magnet and ensure that gas is venting through the probe with adequate flow.

    7 Never leave a running magnet power supply unattended while it is in operation. Before remov-ing the current probe, ensure the power supply is in standby and no fault lights are illuminated.

    8 Always keep a log of any operation performed and record cryogen levels on a daily basis.

    9 Never allow the helium level to fall below the recommended minimum.

    10 Always keep a stock of essential spares on-site.

    ImportantNotes

    The Important Notes are located on the right side ofthe magnet as seen from the patient table (fig. 1-5 on the left).These notes are very important for the installation engineer and operator.

    Installation engineer/operatorPlease read this first.(Text is also listed below).Siemens AG Register 8 M2-050.031.01 Page 9 of 12 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 1 - 10 GeneralComponent Overview 1

    System components 1

    Refer to the next page for a listing of the system components.

    Fig. 6 System overview VISION

    compon_1

    RFfilterplate&RFCC

    ACCU RF-Power MR-ElectronicsCabinet

    CCA PCA GPS

    Alarmbox

    MagnetOR35

    Patienttable

    19" 15"

    MRCMAGNETOM Register 8 M2-050.031.01 Page 10 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • General 1 - 11The system consists of the following components: Magnet 1.5 Tesla / Type OR35 ACCU Cabinet (Air Compressor Chiller Unit), RF Power Cabinet MR Electronics Cabinet (consisting of CCA/PCA/GPS) RF Filter Plate and RFCC, Patient Table, Alarm Box, MRC

    Explanation of the abbreviations used 1

    The installation instructions contain certain abbreviations which are explained below: CCA Control Cabinet PCA Power Cabinet GPS Gradient Power Supply RFPA Radio Frequency Power Cabinet ACCU Air Compressor Chiller Unit RFCC Radio Frequency Control Cabinet RFAS Radio Frequency Amplifier System MRC MR Console MRSC MR Satellite Console SMI Siemens Medical Imager CCU Communication Control Unit RFSU Radio Frequency Small UnitSiemens AG Register 8 M2-050.031.01 Page 11 of 12 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 1 - 12 GeneralThis page intentionally left blank.MAGNETOM Register 8 M2-050.031.01 Page 12 of 12 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • 2 - 1

    MAGNETOMning & Installation

    Installation of the RF-room 2Siemens AG Register 8 M2-050.031.01 Page 1 of 2Medical Engineering Rev. 09 04/99 TD SD 23 Plan

    Read this first 2Most of the modular RF-rooms used in Germany and Europe are manufactured by Siemens Matsush-ita GmbH & Co. KG in Heidenheim and installed by a team of Simon Hegele employees. In view of Sie-mens Med minimal involvement in these areas and the separate, detailed documentation available on the subject, we are only providing General Notes for the RF-room installation.

    However, you can always contact Siemens Med, TD MR 7, in Erlangen, if you have questions regard-ing the installation of the RF-room. The telephone numbers to call are ..-9131-84-3791 or 6201.

    Safety 2The following should be worn during the installation of the RF-room: Protective gloves (made from leather) Safety shoes Safety helmet Safety glasses

    When using other RF-rooms (e.g. copper or aluminium-clad RF-rooms, etc.) outside of Germany or Europe, manufacturers specifications and installation instructions should be used.

    Refer also to Register 2 of this manual.

    NOTICE

    NOTICE

  • 2 - 2 Installation of the RF-roomGeneral Notes 2 The RF-room and floor have to be completed before the magnet arrives at the site. Ensure that the

    opening in the RF-room wall allows for easy transportation of the magnet into the room. The floor has to be level (including the grouting, etc.) It is recommended to start the installation of the first side panel at the corner located opposite the RF-

    room door. The contact surfaces of the RF-gaskets (used with particular designs) should be free of grease. The nuts should be tightened with the torque specified by the manufacturer. The RF-integrity of the RF-room must be measured (attenuation 90 dB). The door contacts cannot be damaged. The protocols must be filled out and filed with the other protocols (register 9 of the system manual).

    The spectroscopy retrofit requires a second filter plate which includes the RF wave guides for the gradient cables.Depending on the location of the second filter plate, the gradient cables may not be long enough. For this reason install the second filter plate in a way, which allows you to reuse the gradient cables.

    Dont forget the RF-gaskets while installing the filter plate for the copper-clad or steel-clad RF-room.

    NOTICE

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 2 of 2 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • 3 - 1

    MAGNETOMning & Installation

    Unloading and positioning the magnet 3Siemens AG Register 8 M2-050.031.01 Page 1 of 30Medical Engineering Rev. 09 04/99 TD SD 23 Plan

    Additional information 3

    Moving the magnet into the room (through the front) 3 If there is very little room between the sides of the magnet and the wall, move in the rear magnet

    covers before positioning the magnet on its location.

    Depending on the space available and the layout of the facilities, the cabinets may have to be moved into the computer room before transporting the patient table, magnet cover, and magnet into the MR suite.Refer to the examples on the next two pages for further details.The order of bringing in the system components depends on the location of the opening for magnet transport plus the space available for magnet posi-tioning.

    Fig. 1 Handling of the rear magnet covers when the installation is from the front

    NOTICE

    Raump_1

    Installing the magnet through the front

    Final position of the rear magnet coverframe

    It is not possible to install the rear coversbecause there is not enough spacebetween the magnet and the RF wall!

  • 3 - 2 Unloading and positioning the magnetMoving the magnet into the room (through the back) 3 Move in the patient table and the front magnet cover before positioning the magnet on its location.

    Fig. 2 Handling of the front magnet covers and the patient table when the installation is from the back

    Raump_2

    Installing the magnet through the back

    Front magnetcover frame

    Patie

    nt ta

    bleMAGNETOM Register 8 M2-050.031.01 Page 2 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 3Checklist 3 This checklist ranges from the preliminary steps to moving/installing the magnet

    Fig. 3 Checklist for the magnet installation

    Required L-Heliumon site or ordered

    Rooms completed

    checkl

    RF-room installed

    Waterinstallation forACCU prepared

    Final location ofmagnet marked

    Magnet moved inACCU positioned

    Finalized transportroute

    Roped off unloadingzone

    Coldhead connected

    Licensed carrierinformed/crane

    Yes No

    ACCU

    MagnetSiemens AG Register 8 M2-050.031.01 Page 3 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 4 Unloading and positioning the magnetSafety instructions 3 Always wear safety shoes and protective clothing Never stand under heavy loads Rope off the unloading zone (take into consideration detours or other traffic regulations) Use only tools which are in good working condition

    Installation Prerequisites 3

    Transport Requirements 3 Ensure that the magnet room is ready and the RF-shielding is installed. Ensure that the opening to the RF-room is large enough (refer to the Planning Guide). Verify dimensions of the RF-room opening (height, width; refer to the Planning Guide). Provide temporary storage for the magnet with sufficient floor load capacity

    (refer to the Planning Guide). Ensure sufficient space for magnet installation (refer to the Planning Guide). Take into account obstructions due to dropped ceilings, support beams, and columns. Determine the final magnet location in the RF-room (refer to the Planning Guide). Verify that the water for the ACCU has been routed to the final location of the ACCU. In this way you

    will be able to quickly connect the compressor. This is an important advantage when the magnet has been shipped cold, and the cold head has to be connected immediately to reduce the boil-off rate.

    Rope off the unloading zone to prevent injury to onlookers. Avoid blocking emergency or other vital access routes to the hospital. Stay within traffic regulations. If necessary, get in touch with the hospital administration. Only a licensed carrier should transport the magnet to the site and into the magnet room.

    To ensure maximum safety for the personnel and the system, the chains, straps, or other lifting devices, as well as the hydraulic lifts and the steel roll-ers must be in good working condition.

    Read through this chapter carefully. It lists all the items/steps that should have been completed or prepared before the magnet arrives at the site.

    The distance of the truck to the unloading zone determines the size and capacity of the crane.

    CAUTION

    NOTICE

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 5Completion of the MR suite 3 The rooms have been completed. This means that the RF-room has been installed including

    the opening for moving in the magnet. In addition, the room should have sufficient light and the floor should be level and clean for easy transportation of the system.

    The four corners of the magnet have been drawn on the floor of the RF-room (refer to Fig. 3-28 on page 22 of this register).

    The floor from the unloading zone to the final location of the magnet in the examination room has been covered with steel plates (min. 5 mm thick).

    The tools and auxiliary tools must be on-site (steel rollers, hydraulic lifts, etc.) For detailed information refer to chapter 1 of this register (transport requirements). Review the checklist one more time (page 4 of this chapter).

    Tools 3

    Fig. 4 Transport rollers for moving heavy loads

    Manruverable in every direction Four sets of steel rollers with a weight capacity of3 tons each.

    The four sets of the steel rollers should be fully maneuverable in every direction. Siemens AG Register 8 M2-050.031.01 Page 5 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 6 Unloading and positioning the magnetTools required 3 Four hydraulic lifts Sufficient number of steel plates (5mm thick for covering the floor). Several crowbars for positioning and moving the magnet. Standard tool set 4 insulation plates (included in the magnet shipment) Aluminium shim plates for levelling out the magnet (included in the magnet shipment) Water level Yardstick Fluke meter Protective ground meter Special tools for magnet installation Water hose level 4 shackles (load capacity 3000 kg each) 4 chains/ropes (each approximately 4m in length, load capacity 3000 kg each)

    Unloading 3

    Unloading of a crated magnet 3

    Ensure that the measurement devices and tools are in good working condi-tion.

    Fig. 5 Magnet shipped in overseas container

    NOTICE

    For deliveries outside Europe, the magnet is shippedin an overseas container. MAGNETOM Register 8 M2-050.031.01 Page 6 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 7Fig. 6 Marks indicating the openings for lifting the magnet

    Fig. 7 Opening for the chains

    Fig. 8 Feeding the chains through the opening using a bar

    There are two openings in the floor of the container. Use only these openings in combination with the lift-ing device (rope or chain).

    Feed the chains through these openings.

    Use the bar for this purpose. Siemens AG Register 8 M2-050.031.01 Page 7 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 8 Unloading and positioning the magnetFig. 9 Overseas container lifted by the crane

    Fig. 10 Lifting the container from the truck

    Fig. 11 Removing the screws on each side

    The chains can be extended as required.

    The tension of the chains must be distributed uniformly for lifting the container.

    The overseas container should be lifted carefully from the truck.

    Location of screwss Remove the screws which connect the upper

    section with the lower section of the container. Each side has 4 screws. MAGNETOM Register 8 M2-050.031.01 Page 8 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 9Fig. 12 Attaching the ring nut

    Fig. 13 Running the chain through the lifting eye

    Fig. 14 Removing the upper section of the container

    Attach a ring nut to each side of the container.

    Each corner has a hole for the ring nut. The hole is located at a height of approximately 2 m.

    Attach a lifting eye to each of the 4 ring nuts and run the chain through the lifting eye.

    Remove the upper section of the container. Siemens AG Register 8 M2-050.031.01 Page 9 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 10 Unloading and positioning the magnetProceed with the transportation of the magnet into the building as described on the next pages.

    The magnet is attached to the four corners of the container floor.Remove the four nuts before you lift the magnet from the container. The same four holes can be used to bolt the magnet to the floor in areas prone to earthquakes.

    Fig. 15 Attachment points of the chains

    Attach the chains to the magnet as described under Domestic transport with-out crate (page 12 and up).

    Lift up the magnet carefully out of the lower container and position it on the four transport rollers.

    NOTICE

    Mag_1

    Attach the lifting eyes with the chains atthis points only!

    NOTICE

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 10 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 11Unloading a magnet without crate 3 Use four ropes or chains with a capacity of at least 3000 kg per rope/chain (length of rope/

    chain is approx. 4 m).

    Fig. 16

    Fig. 17 Attaching the lifting eyes

    Remove the remaining crates carefully from the truck.

    When opening the crates, do not damage any system components.

    30mm

    Lifting eye

    Diameter25 mm

    Attach the four lifting eyes to the magnet.

    The bolts should have a diameter of 25 mm. The inside diameter of the lifting eye at the magnet is 29 mm. The width of the lifting eyes must be 30 mmSiemens AG Register 8 M2-050.031.01 Page 11 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 12 Unloading and positioning the magnetFig. 18 Hooking the shakle into the lifting eye

    Fig. 19 Magnet lifted by the crane

    Do not damage or tear off the connections on the turret or other pipes at the magnet. The transport rollers should be positioned on the steel plates by now (refer to Fig. 20 on page 13).

    Proceed slowly while unloading the magnet from the truck.Never stand under the magnet during the unloading process.

    Shackle Hook the four shackles into the lifting eyes. The

    opening of the shackle has to be secured by a safety slide.

    To prevent the shackle from getting twisted, it should have enough space in the lifting eye.

    Raise the magnet slowly.

    Before you lift the magnet from the truck, ensure once more that the shackles and lifting eyes are fitted correctly.

    NOTICE

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 12 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 13Positioning the rollers 3

    Position the four maneuverable steel rollers under the magnet.

    Lower the magnet carefully onto the rollers.

    Identify the front and the back of the magnet. Position the magnet correctly on the steel rollers so that you do not have to turn it around in the RF-room.

    Fig. 20 Configuration of the four sets of transport rollers

    Verify that the magnet and the steel rollers are balanced.

    The steel rollers must not shift when you move the magnet. If they do, the magnet may be damaged when it slides off the rollers.

    NOTICE

    ANORD_1

    Maneuverablesteelrollers

    Aluminiumbeams Magnet

    NOTICE

    CAUTIONSiemens AG Register 8 M2-050.031.01 Page 13 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 14 Unloading and positioning the magnetMoving the magnet into the RF-room 3

    To facilitate moving the magnet, a manual or electrical cable winch can be used.

    Fig. 21 Steering the magnet with the front rollers

    Move the magnet slowly and carefully!

    Fig. 22 Moving the magnet with a cable winch

    Ensure that the ropes attached to the magnet do not damage the magnet or the gradient coil.When using the cable winch, ensure that the magnet does not pick up speed (especially when the floor runs slightly downhill).

    Steer the magnet into the desired direction with the four rollers.

    NOTICE

    Mag_3

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 14 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 15Positioning the magnet 3

    Positioning the magnet within the markings 3

    Position the magnet exactly above the markings on the floor (refer to the Register 3, chapter 1-6 of this manual). It is not necessary to draw the markings for the insulation and shim plates. However, just before positioning the magnet, verify that insulation and shim plates are handy.

    Fig. 23 Slowing down the magnet

    Adhere to the distances required for the side panels. They may vary accord-ing to the size and layout of the room.

    Fig. 24 Removing the transport rollers

    Magnet transport can be slowed down by using wooden blocks.

    NOTICE

    Insert the four swan necks into the magnet supportbeams

    Move the four hydraulic lifts underneath the swan necks.

    Raise the magnet uniformly and remove the rollersSiemens AG Register 8 M2-050.031.01 Page 15 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 16 Unloading and positioning the magnet Lower the magnet carefully and uniformly onto the floor.

    Levelling the magnet 3

    The objective is to align the magnet in the horizontal and to set the center height of the magnet.For that purpose, you need the following tools:

    Water hose level Insulation plates Aluminium shim plates Hydraulic lifts

    Fig. 25 Markings for the magnet

    Leave the hydraulic lifts at the magnet. You will need them again.

    Mark_2

    Patie

    nt E

    nd

    Serv

    ice

    End

    Markings for thecornerpoints ofthe magnet

    Magnetsupportbeams

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 16 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 17Procedure Use the water level hose to level A with B and C with D (in the x direction). Raise the magnet with the hydraulic lifts and slide the insulation plate and the aluminium shim plates

    between the magnet support beam and the floor (refer to Fig. 27 as well). Lower the magnet and verify that A,B and C,D are aligned with one another. If they are not , add more

    shim plates until the markings match the water level. Subsequently, check whether A is level with C (on the left side of the magnet) and B is level with D (on

    the right side of the magnet). Align the magnet referring to the markings on the flor in the z direction(as described in Fig. 25).

    Finally, check the alignment of all four points, A,B,C, and D, to one another. The markings must be on the same level according to the water hose level. Acceptable tolerance is 3 mm.

    Fig. 26 Leveling the magnet with a waterhose level

    Verify that the magnet rests squarely on the floor.

    Centrpu1

    PatientEnd

    leveling hose

    X

    Z

    Y A

    B

    C

    D

    CAUTIONSiemens AG Register 8 M2-050.031.01 Page 17 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 18 Unloading and positioning the magnetAdding the aluminium shim plates 3 Slide the insulation plates and the aluminium shim plates underneath the magnet support beam

    (the number and the thickness of the aluminium shim plates depend on how much the magnet alignment deviates from the values of the water hose level).

    For each corner of the magnet you are provided with the following amount of plates: 5 x 1mm aluminium shim plates 1 x 3mm aluminium shim plates 1 x 5mm insulation plateThe size of the plates is 300mm x 200mm.

    Fig. 27

    51

    23 Shimpl_1

    Magnet support beam

    Shimplates

    Insulation plateMAGNETOM Register 8 M2-050.031.01 Page 18 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 19Setting the center height of the magnet 3 Measure the center height of the magnet.

    It should be 1100 mm (max. 1105 mm, min. 1095 mm). Either add or take away the same number of aluminium plates at each corner of the magnet until the

    center height of the magnet is 1100 mm.

    When the magnet is aligned correctly, remove the hydraulic lifts. Store the remaining aluminium shim plates in a safe place.

    The procedure for positioning the magnet is now completed.

    Checking the galvanic separation of the magnet 3 Ensure that the magnet is galvanically separated from the RF-room.

    Fig. 28 Measuring the center height of 1100 mm

    Check once more the horizontal alignment of the magnet, the distance to the walls on either side, as well as the center height.

    The magnet must rest squarely on the floor!

    The magnet must be galvanically separated from the RF-room.

    Centrpu3Patient

    End

    1100

    +/-5

    m

    m

    NOTICE

    CAUTION

    CAUTIONSiemens AG Register 8 M2-050.031.01 Page 19 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 20 Unloading and positioning the magnetRemoving the shipping brackets 3

    At the gradient coil 3

    To ensure safe transport, the gradient coil is secured on each side by two brackets and four screws.

    Each end of the magnet support beams includes a hole for bolting the magnet to the floor in areas prone to earthquakes.

    Fig. 29 Position of the brackets

    NOTICE

    Brackets Remove the two brackets in front and in back of

    the magnet.MAGNETOM Register 8 M2-050.031.01 Page 20 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 21Between magnet and gradient coil 3

    Fig. 30 Location of the screws at the upper coil suspension

    Fig. 31 Location of the screws at the lower coil suspension

    Screw

    Lock nut

    Apply Loctite 221 to the upper screws (two each in front and back) and back up the screws to the endstop.

    Secure the screw with the lock nut.

    Screw

    Lock nut

    Apply Loctite 221 to the lower screws (two each in front and back) and back up the screws to the endstop.

    Secure the screw with the lock nut.Siemens AG Register 8 M2-050.031.01 Page 21 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 22 Unloading and positioning the magnetSea Ship Kit Removal Instructions 3

    Introduction 3If the magnet system has been sea freighted with liquid helium contained in the helium vessels, the venting system will be equipped with a relief valve and bursting disk, regulating the pressure in the sys-tem to 2 bar absolute (see figure below.)The magnet system can be left safely venting through the relief valve, until depressurizing is required. When depressurization is required, carefully follow the procedure described below.

    Fig. 32 Sea ship kit

    Ensure that the system includes the DCL Baffle and 1/3 psi pressure gauge before you perform this procedure.

    SEASHIP1

    Blank

    30 psia relief valve

    Helium syphonventline

    Quench valve with integral10 psi bursting disc

    Pressure gauge

    AutofillHelium syphon Depressurisation

    valve (shown closed)

    2 Bar bursting disc

    1/3 PSI non return valve

    Shut off valve(shown on anelbow for clarity)

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 22 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 23Procedure 3

    Check that the shut-off valve at the quench valve is in the closed position (handle is at right angles to the valve axis.)

    Remove the VW25KF blank from the end of the shut-off valve and connect the valve to the site venting.

    Ensure that the pipes used are supported and not left to hang on the connections alone. If the site venting is not installed, run the pipes to atmosphere outside the MR suite.

    To minimize the amount of helium lost, open the shut-off valve slowly to approximately 15 degrees from the closed position and monitor the pressure gauge.

    Helium gas should now be heard escaping. The vent line will cool in a few minutes until it becomes very cold.

    When the pressure indicated on the gauge has dropped to 5 psi, the valve opening should be gradually increased until fully open.

    Open the depressurization valve.

    Allow the system to depressurize until the vent line has thawed, indicating the system is now at atmospheric pressure.

    Remove the bursting disk assembly from the end of the quench valve and connect the site venting to the quench valve.

    Remove the 30 psia valve assembly and replace it with the stopper rod (baffle assembly) which is packed in the accessories case.

    Replace the 2 bar pressure gauge with the 1/3 psi gauge which is packed in the accessories case.

    This procedure should be performed only by trained personnel, wearing pro-tective clothing.

    Helium gas should not be allowed to vent into the MR suite or any other closed room.

    Do not come in contact with cold components. Do not smoke or use open flames.

    The following operations should be performed quickly to prevent air from entering the system.

    NOTICE

    NOTICE

    NOTICE

    NOTICESiemens AG Register 8 M2-050.031.01 Page 23 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 24 Unloading and positioning the magnet Remove the shut-off valve from the quench valve and blank the outlet with an NW25KF blank and check the depressurization valve. The system will now pressurize to its normal operating pressure, 1/3 psi (approx. 20 mbar).

    Pack the removed parts and return them to the Oxford Service Department for reuse.

    Adress:

    Oxford Magnet Technology Ltd.Wharf Road, EynshamWitney, Oxon OX8 1BP, EnglandTelephone: 0044 (1865) 880 880Fax: 0044 (1865) 880 872

    Air Ship Kit Removal instructions 3

    Instruction 3If the magnet system has been air freighted with liquid helium contained in the helium vessel, the vent-ing system will be fitted with relief valve which ensure that the pressure within the helium vessel is kept above atmospheric pressure.The magnet system can be left safely venting through the relief valves until depressurisation is required.

    Fig. 33 Air ship kit

    AIRSHIP2.AI

    Blank

    13 psig relief valveHelium syphonventile

    Quench valve with integral10 psi bursting disc

    Blank 16 psia reliefvalve

    Pressure gauge

    SmartHelium Syphon

    Depressurisationvalve (shown closed)

    Blank A

    F

    D

    B

    E

    C

    depressurisationlineMAGNETOM Register 8 M2-050.031.01 Page 24 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 25Procedure 3

    Remove the blanking plug (A) from the end of the depressurisation line. There may be a small release of gas, but there should not be a continuous flow. If there is, cap off the tube and call the Oxford Service Department, since there may be a fault with the quench valve. Do not proceed further since this might allow air to enter the system.

    Assuming there is no flow refit blank (A) and remove the large blanking flange (B) from the end of the quench valve and connect the site venting to the quench valve.

    Open the depressurisation valve (C).

    Allow the system to depressurise until the depressurisation line has thawed, indicating that the system is now at atmospheric pressure.

    Remove the 13 psig valve (F) assembly and and replace it with the current lead baffle assembly which is packed in the accessories case.

    Remove the 16 psia valve (D) from the 1/3 psig valve (E), remove blank (A) from the Tee, connect the Tee to the 1/3 psig valve and close the depressurisation valve (C). The system will now pressurise to its normal operating pressure, 1/3 psi.

    Pack the remove parts and return them to the Oxford Service Department for re-use.(Address for the return parts on page 24)

    Proceed with care during the depressurization procedure described on this page.

    This procedure should only be carried out by trained personnel, wearing pro-tective clothing.Ensure DCL Baffle is on hand prior to carrying out this procedure.

    Helium gas should not be allowed to vent into the imaging suite or any closed room.

    Do not touch the cold parts. Smoking and naked lights are forbidden.

    The following operation should be done quickly to prevent air entering the system.

    CAUTION

    NOTICE

    NOTICE

    NOTICE

    NOTICESiemens AG Register 8 M2-050.031.01 Page 25 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 26 Unloading and positioning the magnetDetermining the temperature 3

    General 3The magnet is usually shipped cold. However, the magnet may warm when it is shipped to certain countries or when it is in transport or storage for an extended period of time.For that reason, the temperature of the helium vessel should be determined as quickly as possible after the magnet arrives at the customer site. The temperature of the helium vessel is measured via the three carbon temperature sensors in the helium vessel.If the magnet is still cold, that is, the vessel contains liquid helium, the temperature can be maintained if you refill the magnet immediately with liquid helium. You will not only save time, you will also save a great deal of money.However, should the magnet have warmed, you have to pump down the vacuum and fill it with helium again.Refer to the next page for instructions on how to measure the temperature as well as on how to deter-mine the threshold between a warm and a cold magnet.

    Position of the carbon temperature sensors 3

    Fig. 34

    Sensor

    R-Top

    R-Middle

    R-Bottom

    Heliumvessel

    The helium vessel contains three carbon temperature sensors. MAGNETOM Register 8 M2-050.031.01 Page 26 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 27Flowchart for magnet installation 3The course of the magnet installation is illustrated in the flowchart shown below.The diagram on the next page helps you in determining whether the magnet is warm or cold.

    Fig. 35 Flowchart for determing the temperature

    Flolw_2

    Determining the magnet temperature by measuring viathe carbonsensors or the helium service levelmeter

    and by comparing these values with the values from theOMT factory acceptance protocol

    Quench tube installation(or tempory exhaust to theoutside)LHe refilling up to100% (98%)

    Magnet cold =Temperature is between

    helium and nitrogentemperature

    Refilling liquid heliumrefer to register 8,

    chapter 1"Preventive Maintanance"

    Magnet warm =Temperature is between

    nitrogen and roomtemperature

    Precooling and filling ofthe magnet OR 35refer to Start up manualregister 1"System Start-up"

    Continue with start upMagnet / ACCUon the next pages Siemens AG Register 8 M2-050.031.01 Page 27 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 28 Unloading and positioning the magnetMeasuring the cryogenic linear temperature sensors 3 Use a digital voltmeter and measure the resistance (in ohm) of every CTLS at plug C on the magnet

    service turret.

    Fig. 36 Location of plug C

    A

    B

    Ca

    b

    c

    d

    eCommon

    R-Bottom

    R-Top

    R-Middle

    C-plug

    Plug C MAGNETOM Register 8 M2-050.031.01 Page 28 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Unloading and positioning the magnet 3 - 29 Enter the actual values measured at the sensors into the tabl.

    Enter the values from the Oxford Magnet Acceptance Protokol into Table 1 (for room-,nitrogen-,and helium temperature).

    Compare the actual values with the resistance values from the OMT Magnet Acceptance Protocol.

    If the temperature ranges between a room temperature of 293 K and a nitrogen temperature of 77 K, precool and fill the magnet as described in chapter 15 of Register 1 in the Start-up Manual.

    If the temperature ranges between 77 K (liquid nitrogen) and 4.2 K (liquid helium), refill the cry-ostat with LHE only as described in chapter 1 of register 8 in the System Manual.

    Fig. 37 Pin configuration of plug C

    Points Room temp. (293K) Nitrogen temp. (77K) Helium temp. (4.2K)A - E (top)

    B - E (middle)

    C - E (bottom)

    If C-E (bottom) is 77 K, refill the cryostat immediately to prevent additional warming of the magnet.

    C_plug_2

    a

    b

    c

    d

    eCommon

    R-Bottom

    R-Top

    R-Middle

    Fig. 37 shows the pin configuration of plug C.

    A - E (top)

    B - E (middle)

    C - E (bottom)

    CAUTIONSiemens AG Register 8 M2-050.031.01 Page 29 of 30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 3 - 30 Unloading and positioning the magnetConnecting the quench tube 3

    For more detailed information refer to chapter 6 in Register 4 of this manual.

    Prior to refilling liquid helium, install the quench tube or an equivalent so that escaping gas can be exhausted to the outside.

    Fig. 38

    Verify that the magnet is galvanically separated from the quench tube.

    CAUTION

    adaption flangeThe quench tube comes supplied with a Teflon seal. The flange for connecting the quench tube has to be configured on-site.

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 30 of 30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • 4 - 1

    MAGNETOMning & Installation

    Component installation in the RF-room 4Siemens AG Register 8 M2-050.031.01 Page 1 of 24Medical Engineering Rev. 09 04/99 TD SD 23 Plan

    Read this first 4 The chart provides you with an overview of the components to be installed in the RF-room.

    Fig. 1 System components inside the examination room

    The RF-shielding of the RF-room must not be damaged when installing the magnet stop or the cable ducts.

    hfroom

    RF-room

    Filterplate RFCC

    Intercom

    Remote control for magnet stop

    Magnet covers

    Videocamera, microphone

    Patient table

    Tunnel lighting

    Cablingrefer to chapter 7

    NOTICE

  • 4 - 2 Component installation in the RF-roomExample of room layout 4For other room layouts, please refer to Register 3 of this manual

    Fig. 2 The example is showing the installation of the filterplate and the RFCC

    raumplan

    ACCURFCCFilterplate

    RFASRFPA

    PCA

    CCA

    GPSMAGNETOM Register 8 M2-050.031.01 Page 2 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 3Remote control for Magnet Stop 4

    Install the remote control for the Magnet Stop at an easily accessable location in the examination room (see Fig. 3)

    Do not locate the Magnet Stop in the vicinity of the dewars.Use non magnetic srews only.

    Fig. 3

    Fig. 4 Magnet stop button open

    CAUTION

    magstop

    80

    80

    120

    200

    1600

    ~~

    Emergencyshut-downbutton

    Cable inletMagnet stop

    Use non magnetic screwsSiemens AG Register 8 M2-050.031.01 Page 3 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 4 Component installation in the RF-roomInstalling the table guide support 4The table guide is aligned via four adjustable bolts to the table guide supports.The following drawing is valid for the front and rear support of the table guide.

    Mount the front and back support to the magnet flange using the allen screws M10x16.Use the allen screws M10x50 and lock nuts to stabilize the supports in the vertical direction (refer to Fig. 6 on the next page). Do not forget the washers.

    Fig. 5

    Do not forget to connect the grounding cable from the AS 25 coil to the magnet (page 6, Fig.7)

    support1

    frontview

    M10x16locknut

    M10x50 allen screws and locknuts

    adjustment bolts

    M10X20 allen screwand brass washer

    front support

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 5 Attach the adjustment bolts to the table guide. Do not forget the lock nuts. Attach the table guide with the four adjustment bolts to the table supports. Since you need the funnel to set the vertical distance of the table guide, this procedure will be

    described later on pages 10-14 (Installing the front and back panel) in this chapter.

    Fig. 6 Support for the table slideway

    Front

    locknut

    Adjustment screw

    Screw M10x16

    Front support

    support2

    Magnet flange

    90 degreesSiemens AG Register 8 M2-050.031.01 Page 5 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 6 Component installation in the RF-roomConnecting the ground cables for the AS 25 coil 4The two grounding cables are locatet at the rear side of the magnet nearby the tuning boxes.

    Installing the magnet covers 4The magnet covers consist of one front panel, one back panel, as well as three right and three left side panels. The following panel components are already integrated and adjusted in the factory: Front panel:

    Light localizer, the DCU with touchscreen, and the coil connector at the right side. Back panel:

    Patient air, light box for tunnel lighting.

    Fig. 7 Connecting the ground cables

    The two bolts which are holding the front-funnel to the front-panel are locked with nuts. These nuts have to be removed. They are just for transportation!

    The front panel is top heavy. Ensure that it does not tip over when you remove it from the pallet.

    Connection point forthe grounding cable

    Attach the two grounding cables together with thetable guide support to the rear magnet flange.

    NOTICE

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 6 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 7View of the front panel

    Installing the adaption plate for the cable duct of the patient table 4 Attach the distance plate to the front panel frame using screws M16X30 as shown in Fig.9.

    Fig. 8 Attaching the front panel to the magnet

    Fig. 9 Adaption plate for the patient table duct

    frontv_1

    Bracket

    Levelling feet Levelling feetPlate for patient table

    Bracket

    Bracket

    tischfla

    bolts

    bolts

    M12

    frontpanel

    M16x30

    distance plate

    levelling feet

    magnet

    frontpanel frameSiemens AG Register 8 M2-050.031.01 Page 7 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 8 Component installation in the RF-roomInstalling the front and back panel 4

    Insert the twelve bolts M16 into the holes (detail "X") at the patient and service end of the magnet. Tighten the bolts with lock nuts. Attach a second nut and a washer onto the bolt. Attach the front panel onto the support bolts and fix it with washers and nuts.

    Use nut A and B (Fig. 10, detail "X") to set the distance .

    Fig. 10 Installing the front and rear panel

    Front

    Not used at the back and the frontbolts

    lock nuts

    bracket

    back viev

    X X

    XRear

    XX

    A

    B

    Detail "X"

    magnet_3MAGNETOM Register 8 M2-050.031.01 Page 8 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 9 Adjust the distance of 245 mm +/-5mm between the outside surface of the front panel and the front flange of the magnet refer to Fig.11.

    Click the front funnel into the holders of the front panel. Adjust the front panel. Use for the adjustment the levelling feet and the nuts shown in Fig. 8 and Fig. 9

    The adjustment has to be done with the front funnel installed! The front panel with the front funnel must be in align with the guide rails of the gradient coil (Fig.13).

    Attach the rear panel onto the support bolts. Mount the front and rear panel with the guide rails together (Fig. 12).Check wheather the guide rails

    are levelled horizontal. Mount the two cross bars to the points A and B . Refer to Fig. 12

    Fig. 11 Measuring the distance between cover and magnet

    Fig. 12 Magnet with front and back panel and guide rails

    flange Measure the distance between the outside surface of the front panel to the magnet flange.

    front

    guide rails

    A B

    cover_1Siemens AG Register 8 M2-050.031.01 Page 9 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 10 Component installation in the RF-room If the guide rails are not levelled horizontal readjust the front or/and the rear panel in the height.

    Ensure that the guide rails (Fig.12) are levelled out horizontal.This is important for the adjustment of the side cover panels.

    Check the adjustment of the front funnel the rear funnel and the table guide during readjustment of the panels.

    Fig. 13 Adjustment of the front panel

    Affix the Laser Warning Labels on the front panel (refer to Register 2,chapter 1, page 7).

    NOTICE

    CAUTION

    Front panel

    coveradj

    Guide rails

    Funnel

    Guide rails

    FunnelPosition of the funnelmust be centered withthe guide rails

    approx.3mm

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 10 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 11 Place the table guide (with the adjustment bolts already installed) onto the front and reartable support. Use the M10X20mm allen screws with the large brass washers to fix the table guide to the supports. Align the table guide as shown in Fig.14 .

    In the vertical, the upper platform of the table guide has to be completely flush with the triangular surface of the funnel. In the x-direction, the table guide has to be positioned symmetrically to the gradient coil (guide rails). In the z-direction, the front of the table guide has to lie against the front panel.

    Adjust the back panel. The guide rails define the upper distance from the front panel to the back panel. The exact

    position of the back panel is determined by the back funnel. Ensure that the funnel is symmet-ric with the gradient coil in the x-direction.

    Fig. 14 Adjustment for the tableguide

    Levelling feet Levelling feet

    Front panel

    Plate for patient table duct

    Funnel

    Guide rail

    Funnel

    Guide rail

    guideadj

    Table guideup

    down

    Position of funnelmust be centered withthe guide railsSiemens AG Register 8 M2-050.031.01 Page 11 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 12 Component installation in the RF-roomDon t forget to attach the connector ( Wire W26, see also wiring diagrams in the Planing Guide, Reg.10 ) of the Display-box (part number: 31 04 077) in the opening 1 (see Fig.15) of the back funnel.

    Fig. 15 Location of the connector

    CAUTION

    connector Attach the connector to the rear funnel befor yuo

    attach the funnel to the rear cover.MAGNETOM Register 8 M2-050.031.01 Page 12 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 13Magnet side panels 4

    Side panels 4 Attach the side panels on both sides and adjust them as required.

    We recommend to mount the side panels when the cabling (described in chapter 7 of this register) has been completed.

    Fig. 16 Side panels of the magnet cover

    NOTICE

    frontfine adjustment

    sidecovSiemens AG Register 8 M2-050.031.01 Page 13 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 14 Component installation in the RF-roomDCU adjustments 4 The DCU is factory adjusted. In case additional adjustments are required, refer to the functions

    of the screws described in Fig. 17.

    Fig. 17 DCU adjustmaent hardware

    The mounting hardware shown in Fig.17 is the same for both sides of the DCU.

    2

    3 1 4

    Adjustment and mounting screws

    - 1 - Mounting screws- 2 - Height adjustment- 3 - Distance to funnel- 4 - Height adjustment including tilt angle

    NOTICEMAGNETOM Register 8 M2-050.031.01 Page 14 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 15Lighting in the patient tunnel 4The tunnel lighting consists of a light bar which is part of the inside covering for the AS 25 coil. The light generated in the light box by the Halogen lamp (at the back panel of the magnet) is distributed via a large number of individual fiber optic cables.

    Handle the black corrugated hose with care during the installation process. The hose contains the highly fragile fiber optic cables.

    Fig. 18 Light box

    CAUTION

    A

    Connect the fiber optic cable connector at the end of the corrugated hose to the housing of the light box.

    Secure the end of the corrugated hose with the headless screw A. Siemens AG Register 8 M2-050.031.01 Page 15 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 16 Component installation in the RF-roomVideo camera 4The video camera and the microphone for patient monitoring are contained in the same housing.

    Take off the back cover of the camera housing by removing the two screws. Route the video and audio cable through the opening in the back panel, up through the swivel arm

    into the camera housing which also contains the sockets. Connect the cables to the sockets. Attach the swivel arm to the back panel using the four supplied screws. Attach the back cover of the camera housing. Attach the support arm using the five supplied Allen screws.

    Handle the camera and the microphone with care. Like any other electronic device, they are highly sensitive to shock or other impacts.

    Fig. 19 Video camera and microphone

    CAUTION

    Location and configuration of the video cameraand the microphone.MAGNETOM Register 8 M2-050.031.01 Page 16 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 17Installation of the filter plate 4To provide the service engineer with enough room, the RF filter plate together with the RFCC should not be installed in the immediate vicinity of the magnet. In addition, a more cost-effective cover can be selected for the RFCC.In a modular RF-room, the filter plate can be installed directly in the recess provided for that purpose. In a conventional RF-room the filter plate can be installed directly as well, as long as the RF integrity is maintained. However, we recommend the use of a filter frame (refer to chapter 3 Components in Reg-ister 1 and to chapter 1 'RF-shielding' in Register 4 of this manual). Install the RF filter plate (56 screws M10).

    Fig. 20 Installation of the filter plate

    The RF integrity can now be measured if the transport opening of the RF-room has been closed.

    Interior ofRF-room

    RF filter frameRF filter plate

    filterpl

    NOTICESiemens AG Register 8 M2-050.031.01 Page 17 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 18 Component installation in the RF-roomInstalling the RFCC 4 Attach the two mounting brackets for the RFCC (8 washers, lock washers, nuts M6 each)

    Lift up the RFCC, guide the support bolts through the elonguated holes in the mounting brackets. Secure the RFCC to the brackets using 10 washers, lock washers, and nuts M6.

    Shift the RFCC in the elonguated holes until it is flush with the RF-room wall. Tighten the nuts.

    Fig. 21 Installation of the RFCC mounting brackets

    The RFCC is very heavy. You either need a lifting device or three people for the installation.

    Fig. 22 Installation of the RFCC

    interior ofRF-room

    mountingbracketattach mounting brackets

    brackets

    CAUTION

    rfccin

    RFCC

    InteriorofRF-room

    RFCCMAGNETOM Register 8 M2-050.031.01 Page 18 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 19Installation of patient table 4

    Preparing the patient table 4 Protect the tabletop against damage by covering it with corrugated paper or packing material.

    Fig. 23 Patient table

    Fig. 24 Detailed view of the patient table

    liege1

    connectorplates

    vertical motor

    table front coverscrews holding the side panel

    screws

    liegedet

    S2transport

    levelling

    limit switch S4

    mechanical endstop

    feets

    roller

    gear bolt 1 of 4Siemens AG Register 8 M2-050.031.01 Page 19 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 20 Component installation in the RF-roomOpening of the patient table 4

    Fig. 25 Table front cover removed

    Fig. 26 Screws for removing the side sections

    Fig. 27 Unlock and remove the table stop button

    front cover removed

    Remove the front cover of the table (4 Allen screws). Refer to Fig.25.

    S

    Take off the side sections by removing the screws "S" shown in Fig.26.

    Be careful when you take off the side sections. You have to unlock and remove the table STOP button before removing the side sections.

    Unlock the button by turning the lever (see arrow in Fig.27). MAGNETOM Register 8 M2-050.031.01 Page 20 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 21Removing the transport brackets 4

    Fig. 28 Rails for bellow shaped cover

    Fig. 29 Transport brackets inside the patient table

    Fig. 30

    S

    Remove the rails which hold the bellow-shaped cover of the patient table. on both sides.

    Remove screws "S" shown in Fig.28.

    The bellow-shaped cover comes off easily.

    transich

    transport brackets

    mounting screws

    Position the ratchet at the gear bolt and crank the table upward by approx. 3 cm. Refer to Fig. 30and 31.

    Remove the mounting screws of the transport brackets see Fig.29.

    Remove the transport brackets.Siemens AG Register 8 M2-050.031.01 Page 21 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 22 Component installation in the RF-roomInstalling the cable duct and the patient table 4 Attach the cable duct to the two bolts sitting on the mounting plate refer to Fig.32 (tighten by hand

    only). Move the patien table in position behind the cable duct. Lower the transport rollers of the patient table until the table is sitting on the floor. Mount the cable duct and the patient table with the delivered screws together and tighten them.

    Fig. 31 Gear bolt

    Fig. 32 Installation of the cable duct

    View of the gear bolt for cranking up the patient tableby hand.

    Cable duct

    ductmon

    85mm

    Front panelInstallation frame

    M16

    mounting plate

    BoltsM12MAGNETOM Register 8 M2-050.031.01 Page 22 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Component installation in the RF-room 4 - 23 Align the patient table with the cable duct to the magnet, table guide and front funnel refer to Fig. 33.

    To prevent potential injuries, the distance between the table guide and the patient table cover at the head end must not exceed 5 mm (see Fig. 33)

    Fig. 33 Align the patient table with the cable duct to magnet, table guide and front funnel

    The patient table will be aligned and bolted to the floor during system start-up (Start up manual, register 1, chapter 9).

    CAUTION

    allign

    max.5 mm distance

    magnet cover

    cable ductmagnet

    patient table

    NOTICESiemens AG Register 8 M2-050.031.01 Page 23 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 4 - 24 Component installation in the RF-roomIntercom 4The intercom system is integrated into the CCA cabinet K2120. A loudspeaker has to be installed inside the RF-room. A second loudspeaker (piezo) is already installed the rear table guid support.

    The RF-shielding of the RF-room must not be damaged when installing the loudspeaker.

    Fig. 34 Loudspeeker

    CAUTION

    lautspr

    Attach the loudspeaker bracket to the wall. Attach the loudspeaker to the bracket.MAGNETOM Register 8 M2-050.031.01 Page 24 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • 5 - 1

    MAGNETOMning & Installation

    Computer Room 5Siemens AG Register 8 M2-050.031.01 Page 1 of 26Medical Engineering Rev. 09 04/99 TD SD 23 Plan

    General 5

    Read this first 5To keep the helium boil-off to a minimum, install the ACCU cabinet (ACCU = Air Compressor Chiller Unit) first so that the cold head can be connected as quickly as possible.Install the three-in-one cabinet (CCA, PCA, gradient) and the RFPA in parallel or immediately after completion of the ACCU cabinet. Route the cables after you finished installing the cabinets.After the ACCU has been connected to the PCA, switch on the refrigerator immediately (naturally only if the helium vessel contains liquid helium).

    Flowchart 5The flowchart provides you with an overview of the components to be installed in the computer room.

    Fig. 1 Installation flowchart for the computer room

    equippm

    Installation ofACCU to

    reduce boil off

    Installation ofthe othercabinets

    Cabling / referto chapter 7

    Start-uprefrigerator

    Installation incomputer room

    Magnet unloading,transport,set-up

    Installation inRF-room

    Set up thecabinet

    Connect the waterhoses

    Connect the semi-rigid lines

    Connect the powercable between cold head and

    refrigerator

  • 5 - 2 Computer RoomPrerequisites 5

    The interior of the rooms has been completed The location of the cabinets has been drawn on the floor The chilled water hoses for the ACCU have been installed The magnet has been aligned

    Tools 5

    Standard tool kit Drill, etc. Forklift for transporting the cabinets 4 hydraulic jacks

    Safety 5

    Refer to Register 2 of this manual.NOTICEMAGNETOM Register 8 M2-050.031.01 Page 2 of 26 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Computer Room 5 - 3Areas prone to earthquakes 5

    Bolting the MR cabinets to the floor 5

    In areas prone to earthquakes, the cabinets have to be bolted to the floor according to local regulations.

    Fig. 2 Holes for ACCU and RFPA

    Fig. 3 Holes for the electronics cabinet

    CAUTION

    holes450

    710

    Mark the holes to be drilled into the floor. Use a piece of tape or a felt pen.

    Drill the holes (17 mm in diameter) Insert the anchors Position the cabinets Secure with nuts and washers Ensure that the cabinets are secure. They must

    not tip over when you remove one of the assemblies.

    1650

    710

    holes_3Siemens AG Register 8 M2-050.031.01 Page 3 of 26 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 5 - 4 Computer RoomBolting the magnet to the floor 5

    Unloaoding and setting up the three-in-one cabinet 5Move cabinet unit on the transport pallet in the immediate vicinity of its final location.Remove the screw connections between the cabinet unit and the pallet.

    Fig. 4 Position of the holes

    Fig. 5 Remove transport pallet

    Do not wrap the cabinet.

    holemagPatient End

    Service End

    magnet

    magnet support beams

    Mark the holes. There is a hole in each of the four corner joints of the magnet support beams.

    Remove the magnet. Drill the holes, and insert the respective anchors (parts like the screws and the anchors have to be obtained locally).

    Position the magnet again. Align the magnet vertically and horizontally. Refer

    to chapter 8 of this register for additional details. Bolt the magnet to the floor.

    1

    34

    2

    2

    3

    1

    1

    Remove the red lifting brackets attached to the cabinet (1/Fig. 5), turn them by 180, and reattach them.

    Connect the 4 hydraulic jacks so that they can be raised and lowered in common (2/Fig. 5).

    Uniformly lift the cabinet unit with the 4 hydraulic jacks (3/Fig. 5).

    Remove the transport pallet (4/Fig. 5).

    CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 4 of 26 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical Engineering

  • Computer Room 5 - 5Fig. 6 Position the rollers

    Fig. 7 Positioning of the cabinets

    5

    6

    5

    6

    Position four rollers (5/Fig.6) under the first and last cabinet section next to the cabinet interconnections.

    Lower the cabinet unit onto the rollers (6/Fig.6).

    7 9

    8

    9

    8

    Position the cabinet (7/Fig.7). Uniformly lift the cabinet with the

    4 hydraulic jacks (8/Fig.7). Remove the rollers (9/Fig.7).Siemens AG Register 8 M2-050.031.01 Page 5 of 26 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning & Installation

  • 5 - 6 Co