pleasant valley school district...part 1, t24 ccr. 3.a dsa certified inspector wtih class 3 shall be...

4
1. ALL WORK SHALL CONFORM TO 2019 EDITION TITLE 24 CALIFORNIA CODE OF REGULATIONS (CCR). 2. CHANGES TO APPROVED DRAWINGS AND SPECIFICATIONS SHALL BE MADE BY AN ADDENDUM OR A CONSTRUCTION CHANGE DOCUMENT (CCD) APPROVED BY THE DIVISION OF THE STATE ARCHITECT AS REQUIRED BY SECTION 4-338, PART 1, T24 CCR. 3. A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS INSPECTION OF THE WORK. THE DUTIES OF THE INSPECTION ARE DEFINED IN SECTION 4-342, PART 1, T24, CCR. THE PROJECT INSPECTOR SHALL BE CERTIFIED BY DSA TO INSPECT. 4. APPARENT DISCREPANCIES ON DRAWINGS AND/OR SPECIFICATIONS SHALL BE REPORTED TO THE ARCHITECT BEFORE PROCEEDING WITH THE WORK. 5. ANY DIFFERENCE BETWEEN THE EXISTING CONSTRUCTION AS OBSERVED IN THE FIELD AND AS SHOWN ON THE DRAWING SHALL BE REPORTED TO THE ARCHITECT BEFORE PROCEEDING WITH THE WORK. 6. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS PRIOR TO STARTING WORK. THE ARCHITECT SHALL BE NOTIFIED OF ANY DISCREPANCIES OR INCONSISTENCIES. THE CONTRACTOR IS RESPONSIBLE FOR CHECKING AND COORDINATING DIMENSIONS. 7. IT SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR TO ENSURE THAT ALL APPLICABLE SAFETY LAWS ARE STRICTLY ENFORCED AND TO MAINTAIN A SAFE CONSTRUCTION PROJECT. 8. IT SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR TO PROVIDE SUPERVISION OF THE CONSTRUCTION WORK TO ENSURE THAT IT IS BUILT IN CONFORMANCE WITH THE APPROVED PLANS AND SPECIFICATIONS. THE ARCHITECT WILL PROVIDE ONLY PERIODIC OBSERVATION OF THE WORK. SEE NOTE 3 FOR DSA INSPECTION REQUIREMENTS. 9. ANY DAMAGE DONE TO THE EXISTING CONSTRUCTION DURING THE COURSE OF THIS WORK SHALL BE REPLACED BY THE CONTRACTOR AT THE CONTRACTOR'S EXPENSE WITH NO ADDITIONAL COST TO THE OWNER. 10. GRADING PLANS, DRAINAGE IMPROVEMENTS, ROAD & ACCESS REQUIREMENTS AND ENVIRONMENTAL HEALTH CONSIDERATIONS SHALL COMPLY WITH ALL LOCAL ORDINANCES. 11. CUTTING, BORING, SAWCUTTING OR DRILLING THROUGH THE NEW OR EXISTING STRUCTURAL ELEMENTS TO BE DONE ONLY WHEN SO DETAILED IN THE DRAWINGS OR ACCEPTED BY THE ARCHITECT AND THE STRUCTURAL ENGINEER WITH THE APPROVAL OF DSA REPRESENTATIVE. ALL WELDING SHALL BE SPECIALLY INSPECTED BY AN AWS-CWI QUALIFIED INSPECTOR APPROVED BY DSA. ALL BRACING OF DUCTS AND PIPING SHALL BE INSTALLED IN ACCORDANCE WITH SMACNA GUIDELINES AS APPROVED BY DSA. WHERE BRACING DETAILS ARE NOT SHOWN ON THE DRAWINGS OR IN THE GUIDELINES, THE FIELD INSTALLATION SHALL BE SUBJECT TO THE APPROVAL OF THE ARCHITECT, MECHANICAL ENGINEER AND FIELD ENGINEER. A COPY OF THE GUIDELINES PUBLISHED BY SMACNA AND APPROVED BY DSA SHALL BE PROVIDED BY THE CONTRACTOR AND KEPT ON THE JOB AT ALL TIMES. 12. SHOULD ANY EXISTING CONDITIONS SUCH AS DETERIORATION OR NON COMPLYING CONSTRUCTION BE DISCOVERED WHICH IS NOT COVERED BY THE DSA APPROVED DOCUMENTS WHEREIN THE FINISHED WORK WILL NOT COMPLY WITH TITLE 24, C.C.R., OR SEPARATE SET OF PLANS AND SPECIFICATIONS, DETAILING AND SPECIFYING THE REQUIRED REPAIR WORK SHALL BE SUBMITTED TO AND APPROVED BY DSA BEFORE PROCEEDING WITH THE REPAIR WORK.. 13. A DSA ACCEPTED TESTING LABORATORY DIRECTLY EMPLOYED BY THE SCHOOL DISTRICT SHALL CONDUCT ALL THE REQUIRED TESTS AND INSPECTIONS FOR THE PROJECT. 14. ALL WORK (AS APPLICABLE) MUST MEET THE MANDATORY MEASURES OF THE 2019 CALIFORNIA GREEN BUILDING STANDARDS (CAL GREEN) CODE (TITLE 24, PART II). EXISTING BUILDING ROOF AREA TO BE REPLACED AT GYMNASIUM BUILDING ROOF AREA: 7,700 S.F. 15 Z & AND ANGLE @ AT C CENTERLINE DIAMETER OR ROUND # POUND OR NUMBER ACT ACOUSTICAL ACD AMENDED CONSTRUCTION DOCUMENT ACO AREA COMPLIANCE OFFICER AD AREA DRAIN ADA AMERICANS WITH DISABILITIES ACT ADJ ADJUSTABLE AFF ABOVE FINISH FLOOR AGGR AGGREGATE ALUM ALUMINUM ANNLD ANNEALED AOR ARCH OF REC APP APPROXIMATE ARCH ARCHITECT/URAL ASPH ASPHALT ASS'Y ASSEMBLY BD BOARD BLDG BUILDING BLK BLOCK BLK'G BLOCKING BM BEAM BOT BOTTOM CAB CABINET CB CATCH BASIN CEM CEMENT CER CERAMIC CI CAST IRON CG CORNER GUARD CLG CEILING CAUK'G CAULKING/CHALKING CLO CLOSET CLR CLEAR CO CASED OPENING COR CONTR OF REC COL COLUMN CONC CONCRETE CONN CONNECTION CONSTR CONSTRUCTION CONT CONTINUOUS CONTR CONTRACTOR CORR CORRIDOR CTSK COUNTERSUNK CNTR COUNTER CTR CENTER DBL DOUBLE DEPT DEPARTMENT DF DRINKING FOUNTAIN DET DETAIL DIA DIAMETER DIM DIMENSION DISP DISPENSER DN DOWN DO DOOR OPENING DR DOOR DWR DRAWER DS DOWNSPOUT DSP DRY STANDPIPE DWG DRAWING (E) EXISTING E EAST EA EACH EEOR ELEC ENG OF REC EJ EXPANSION JOINT EL ELEVATION ELEC ELECTRICAL ELEV ELEVATOR EMER EMERGENCY ENCL ENCLOSURE ENG ENGINEER EP ELECTRICAL PANEL EQ EQUAL EQP EQUIPMENT ES EDGE STRIP EVS ENVIRONMENTAL SERVICES EWP END WALL PROTECTOR EXPO EXPOSED EXP EXPANSION EXTR EXTERIOR FA FIRE ALARM FB FLAT BAR FLR DRN FLOOR DRAIN FD FIRE DAMPER FDN FOUNDATION FE FIRE EXTINGUISHER FEC FIRE EXTINGUISHER CAB FH FULL HEIGHT FHC FIRE HOSE CABINET FIN FINISH FLR FLOOR FLS FIRE & LIFE SAFETY FLSO FIRE LIFE SAFETY OFFICER FLASH FLASHING FLUOR FLUORESCENT FOC FACE OF CONCRETE FOF FACE OF FINISH FOS FACE OF STUD FP FIREPROOF(ING) FR FIRE RATED or FIRE RATING FRP FIBERGLASS REINFORCED PLASTIC FSD FIRE-SMOKE DAMPER FT FOOT or FEET FTG FOOTING FURR FURRED or FURRING FUT FUTURE GA GAUGE GALV GALVANIZED GB GRAB BAR GL GLASS GLZ GLAZING GRD GROUND GR GRADE GYP GYPSUM HB HOSE BIBB HDWD HARDWOOD HDWR HARDWARE HORZ HORIZONTAL HR HOUR HSKP HOUSEKEEPING HT HEIGHT HW HEAD OF WALL ID INSIDE DIAMETER IN INCH(ES) ISO ISOLATION INSUL INSULATION INT INTERIOR IOR INSPECTOR OF RECORD JAN JANITOR JT JOINT KIT KITCHEN LAB LABORATORY LAM LAMINATE LAV LAVATORY LKR LOCKER LT LIGHT LTG LIGHTING MAT'L MATERIAL MAX MAXIMUM MB MACHINE BOLT M.C. MEDICINE CABINET MECH MECHANICAL MEOR MECH ENG OF REC MEMB MEMBRANE MTL METAL MFG MANUFACTURER MH MANHOLE MIN MINIMUM MIR MIRROR MISC MISCELLANEOUS M.O. MASONRY OPENING MTD MOUNTED MTR MONITOR MULL MULLION (N) NEW N NORTH NEG PRES NEGATIVE PRESSURE NIC NOT IN CONTRACT NR NON RATED NO. NUMBER NOM NOMINAL NTS NOT TO SCALE OA OVERALL O/ OVER OC ON CENTER OD OUTSIDE DIAMETER OFF OFFICE OPN'G OPENING OPP OPPOSITE OSHPD OFFICE OF STATE HEALTH PLANNING & DEVELOPMENT PRCST PRECAST PL PROPERTY LINE PLAM PLASTIC LAMINATE PLSTR PLASTER PLYWD PLYWOOD PR PAIR PT POINT PTD PAPER TOWEL DISPENSER PTD/R COMBINATION PAPER TOWEL DISPENSER & RECEPTACLE PTN PARTITION PTR PAPER TOWEL RECEPTACLE QT QUARRY TILE R RADIUS RD ROOF DRAIN REC RECORD REFR REFERENCE REF REFRIGERATOR RGTR REGISTER REINF REINFORCED REQ'D REQUIRED RB RESILIENT BASE RM ROOM RO ROUGH OPENING RWD REDWOOD RWL RAIN WATER LEADER S SOUTH SC SOLID CORE SCD SEAT COVER DISPENSER SCH SCHEDULE SD SMOKE DETECTOR SECT SECTION SEOR STRCT ENG OF REC SFD SMOKE / FIRE DAMPER SFM STATE FIRE MARSHALL SHF SHELF SHWR SHOWER SHT SHEET SHTHG SHEATHING SIM'L SIMILAR SND SANITARY NAPKIN DISPENSER SNR SANITARY NAPKIN RECEPTACLE S.D. SOAP DISPENSER SPEC SPECIFICATION/S SQ SQUARE S.S. STAINLESS STEEL SSK SERVICE SINK STA STATION STD STANDARD STL STEEL STO STORAGE STRCT STRUCTURAL SUSP SUSPENDED SYM SYMMETRICAL T TREAD TB TOWEL BAR TOC TOP OF CURB TEL TELEPHONE TEMP TEMPORARY TEZZ TERRAZZO T&G TONGUE & GROOVE THK THICK TLT TOILET TOP TOP OF PAVEMENT OR PARAPET TOS TOP OF SLAB TPD TOILET PAPER DISPENSER TRT TREATMENT TS TUBE STEEL TOW TOP OF WALL TV TELEVISION TYP TYPICAL UG UNDERGROUND UL UNDERWRITERS LABORATORIES UNF UNFINISHED UON UNLESS OTHERWISE NOTED UTIL UTILITY UR URINAL VCT VINYL COMPOSITION TILE VERT VERTICAL VEST VESTIBULE VTR VENT THRU ROOF W WEST W/ WITH WC WATER CLOSET WD WOOD WF WIDE FLANGE WH WATER HEATER W/O WITHOUT WP WATERPROOF WSCT WAINSCOT WSP WET STANDPIPE WT WEIGHT STUD SIZE STUD GAUGE COLUMN GRID REFERENCE DIMENSION TO FINISH MATERIAL DIMENSION TO CENTERLINE DIMENSION TO GRIDLINE 15 (NOT ALL MAY APPLY) ABBREVIATIONS PLEASANT VALLEY SCHOOL DISTRICT LOS ALTOS MIDDLE SCHOOL GYMNASIUM ROOF REPLACEMENT 0146* NONE SECTION SHEET WHERE DRAWN DETAIL SHEET WHERE DRAWN SHEET WHERE DRAWN ENLARGED DETAIL NEW SPOT GRADE DIRECTION OF DRAINAGE FLOW LEVEL LINE, BENCH MARK, WORK POINT OR CONTROL POINT DIMENSION LINE AND POINT CENTER LINE OR FLOOR LINE PROPERTY, BOUNDARY OR CUTLINE MATCH LINE, SHADED SIDE IS BEING CONSIDERED OUTLINE OF HIDDEN OBJECT, NIC ITEMS, REMOVED MATERIAL FENCE LINE BREAK LINE NOTE SYMBOL, SEE NUMBERED NOTES COLUMN REVISION NUMBER REVISION CLOUD, OPTIONAL COLUMN GRID REFERENCE, POINT OF HEXAGON TOWARDS COLUMN LINE ELEVATION NUMBERS SHEET WHERE DRAWN ELEVATION SYMBOL, ROOM NUMBER ROOM MATERIAL CODE * CEILING HEIGHT ROOM NAME * SEE ROOM MATERIAL CODE SHEET EQUIPMENT SCHEDULE EQUIPMENT MARK WINDOW MARK & TYPE DOOR MARK 22 1 A 125 LOBBY 2B5 10'-0" A 101A 52 A422 ELEVATION DIRECTION 3 A601 EXISTING SPOT GRADE NEW CONTOURS EXISTING CONTOURS PARTIAL LIST OF APPLICABLE CODES AS OF January 1, 2020 2019 California Building Standards Administrative Code, Title 24 C.C.R. 2019 California Building Code (CBC), Title 24 C.C.R. (2018 International Building Code of the International Code Council, with California Amendments) 2019 California Electrical Code (CEC), Title 24 C.C.R. (2017 National Electrical Code of the National Fire Protection Association, NFPA) 2019 California Mechanical Code (CMC), Title 24 C.C.R. (2018 Uniform Mechanical Code of the International Association of Plumbing and Mechanical Officials, IAPMO) 2019 California Plumbing Code (CPC), Title 24 C.C.R. (2018 Uniform Plumbing Code of the International Association of Plumbing and Mechanical Officials, IAPMO) 2019 California Energy Code (CEC), Part 6, Title 24 C.C.R. 2019 California Fire Code, Title 24 C.C.R. (2018 International Fire Code of the International Code Council) 2019 California Green Building Standards Code (CALGreen Code), Title 24 C.C.R. 2019 California Referenced Standards Code, Title 24 C.C.R. Title 19 C.C.R., Public Safety, State Fire Marshal Regulations. PARTIAL LIST OF APPLICABLE STANDARDS NFPA 13 Automatic Sprinkler Systems 2019 Edition NFPA 14 Standpipe Systems (CA Amended) 2013 Edition NFPA 17A Wet Chemical Extinguishing Systems 2013 Edition NFPA 20 Stationary Pumps 2019 Edition NFPA 24 Private Fire Service Mains (CA Amended) 2019 Edition NFPA 72 National Fire Alarm and Signaling Code (CA Amended) 2019 Edition NFPA 80 Fire Door and Other Opening Protectives 2019 Edition NFPA 253 Critical Radiant Flux of Floor Covering 2019 Edition NFPA 2001 Clean Agent Fire Extinguishing Systems 2018 Edition Reference code section for NFPA standards - 2019 CBC (SFM) Chapter 35. See Chapter 35 for State of California amendments to NFPA standards. PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, TRANSPORTATION, INSURANCE, AND SERVICES TO REPLACE EXISTING ROOF SYSTEM WITH NEW ROOF SYSTEM AT UPPER PORTION OF THE GYMNASIUM BUILDING. GENERAL G-001 TITLE SHEET/ GENERAL INFORMATION/ VICINITY MAP/ SITE PLAN G-002 SPECIFICATIONS ARCHITECTURAL A-221 ROOF PLAN & DEMOLITION PLAN A-701 ROOF DETAILS 0146* TEMPLE AVE. BLDG B BLDG A BLDG C BLDG D BLDG E BLDG F MULTI-PURPOSE/ GYMNASIUM BUILDING EXISTING PARKING LOT AREA OF WORK G-001 TITLE SHEET / GENERAL INFORMATION 802 EAST COTA STREET. SUITE A SANTA BARBARA, CA 93103 TEL (805) 963-1955 CONSULTANT STAMP ARCHITECT STAMP PROJECT OWNER & TITLE SHEET TITLE DRAWN BY: SHEET NO. DATE: REVISIONS THE ARCHITECT DOES NOT REPRESENT THAT THESE PLANS OR THE SPECIFICATIONS ARE SUITABLE FOR ANY SITE OTHER THAN THE ONE FOR WHICH THEY WERE SPECIFICALLY PREPARED. THE ARCHITECT DISCLAIMS RESPONSIBILITY FOR THESE PLANS AND SPECIFICATIONS IF THEY ARE USED IN WHOLE OR IN PART AT ANY OTHER SITE NO. DATE DESCRIPTION # AGENCY APPROVAL FM No. xxxxxxxx PLEASANT VALLEY SCHOOL DISTRICT LOS ALTOS MIDDLE SCHOOL GYMNASIUM ROOF REPLACEMENT CAMARILLO, CA, 93010 JOB NUMBER: 20027.01 APRIL 28, 2020

Upload: others

Post on 20-Jan-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PLEASANT VALLEY SCHOOL DISTRICT...PART 1, T24 CCR. 3.A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS INSPECTION OF THE WORK. THE

1. ALL WORK SHALL CONFORM TO 2019 EDITION TITLE 24 CALIFORNIA CODE OF REGULATIONS (CCR).

2. CHANGES TO APPROVED DRAWINGS AND SPECIFICATIONS SHALL BE MADE BY AN ADDENDUM OR A CONSTRUCTION

CHANGE DOCUMENT (CCD) APPROVED BY THE DIVISION OF THE STATE ARCHITECT AS REQUIRED BY SECTION 4-338,

PART 1, T24 CCR.

3. A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS

INSPECTION OF THE WORK. THE DUTIES OF THE INSPECTION ARE DEFINED IN SECTION 4-342, PART 1, T24, CCR. THE

PROJECT INSPECTOR SHALL BE CERTIFIED BY DSA TO INSPECT.

4. APPARENT DISCREPANCIES ON DRAWINGS AND/OR SPECIFICATIONS SHALL BE REPORTED TO THE ARCHITECT BEFORE

PROCEEDING WITH THE WORK.

5. ANY DIFFERENCE BETWEEN THE EXISTING CONSTRUCTION AS OBSERVED IN THE FIELD AND AS SHOWN ON THE

DRAWING SHALL BE REPORTED TO THE ARCHITECT BEFORE PROCEEDING WITH THE WORK.

6. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS PRIOR TO STARTING WORK. THE ARCHITECT SHALL BE NOTIFIED OF

ANY DISCREPANCIES OR INCONSISTENCIES. THE CONTRACTOR IS RESPONSIBLE FOR CHECKING AND COORDINATING

DIMENSIONS.

7. IT SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR TO ENSURE THAT ALL APPLICABLE SAFETY LAWS

ARE STRICTLY ENFORCED AND TO MAINTAIN A SAFE CONSTRUCTION PROJECT.

8. IT SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR TO PROVIDE SUPERVISION OF THE CONSTRUCTION

WORK TO ENSURE THAT IT IS BUILT IN CONFORMANCE WITH THE APPROVED PLANS AND SPECIFICATIONS. THE

ARCHITECT WILL PROVIDE ONLY PERIODIC OBSERVATION OF THE WORK. SEE NOTE 3 FOR DSA INSPECTION

REQUIREMENTS.

9. ANY DAMAGE DONE TO THE EXISTING CONSTRUCTION DURING THE COURSE OF THIS WORK SHALL BE REPLACED BY

THE CONTRACTOR AT THE CONTRACTOR'S EXPENSE WITH NO ADDITIONAL COST TO THE OWNER.

10. GRADING PLANS, DRAINAGE IMPROVEMENTS, ROAD & ACCESS REQUIREMENTS AND ENVIRONMENTAL HEALTH

CONSIDERATIONS SHALL COMPLY WITH ALL LOCAL ORDINANCES.

11. CUTTING, BORING, SAWCUTTING OR DRILLING THROUGH THE NEW OR EXISTING STRUCTURAL ELEMENTS TO BE DONE

ONLY WHEN SO DETAILED IN THE DRAWINGS OR ACCEPTED BY THE ARCHITECT AND THE STRUCTURAL ENGINEER WITH

THE APPROVAL OF DSA REPRESENTATIVE. ALL WELDING SHALL BE SPECIALLY INSPECTED BY AN AWS-CWI QUALIFIED

INSPECTOR APPROVED BY DSA. ALL BRACING OF DUCTS AND PIPING SHALL BE INSTALLED IN ACCORDANCE WITH

SMACNA GUIDELINES AS APPROVED BY DSA. WHERE BRACING DETAILS ARE NOT SHOWN ON THE DRAWINGS OR IN THE

GUIDELINES, THE FIELD INSTALLATION SHALL BE SUBJECT TO THE APPROVAL OF THE ARCHITECT, MECHANICAL

ENGINEER AND FIELD ENGINEER. A COPY OF THE GUIDELINES PUBLISHED BY SMACNA AND APPROVED BY DSA SHALL

BE PROVIDED BY THE CONTRACTOR AND KEPT ON THE JOB AT ALL TIMES.

12. SHOULD ANY EXISTING CONDITIONS SUCH AS DETERIORATION OR NON COMPLYING CONSTRUCTION BE DISCOVERED

WHICH IS NOT COVERED BY THE DSA APPROVED DOCUMENTS WHEREIN THE FINISHED WORK WILL NOT COMPLY WITH

TITLE 24, C.C.R., OR SEPARATE SET OF PLANS AND SPECIFICATIONS, DETAILING AND SPECIFYING THE REQUIRED

REPAIR WORK SHALL BE SUBMITTED TO AND APPROVED BY DSA BEFORE PROCEEDING WITH THE REPAIR WORK..

13. A DSA ACCEPTED TESTING LABORATORY DIRECTLY EMPLOYED BY THE SCHOOL DISTRICT SHALL CONDUCT ALL THE

REQUIRED TESTS AND INSPECTIONS FOR THE PROJECT.

14. ALL WORK (AS APPLICABLE) MUST MEET THE MANDATORY MEASURES OF THE 2019 CALIFORNIA GREEN BUILDING

STANDARDS (CAL GREEN) CODE (TITLE 24, PART II).

EXISTING BUILDING ROOF AREA TO BE REPLACED

AT GYMNASIUM BUILDING ROOF AREA: 7,700 S.F.

15

Z

& AND

ANGLE

@ AT

C CENTERLINE

Ø DIAMETER OR

ROUND

# POUND OR NUMBER

ACT ACOUSTICAL

ACD AMENDED

CONSTRUCTION

DOCUMENT

ACO AREA COMPLIANCE

OFFICER

AD AREA DRAIN

ADA AMERICANS WITH

DISABILITIES ACT

ADJ ADJUSTABLE

AFF ABOVE FINISH FLOOR

AGGR AGGREGATE

ALUM ALUMINUM

ANNLD ANNEALED

AOR ARCH OF REC

APP APPROXIMATE

ARCH ARCHITECT/URAL

ASPH ASPHALT

ASS'Y ASSEMBLY

BD BOARD

BLDG BUILDING

BLK BLOCK

BLK'G BLOCKING

BM BEAM

BOT BOTTOM

CAB CABINET

CB CATCH BASIN

CEM CEMENT

CER CERAMIC

CI CAST IRON

CG CORNER GUARD

CLG CEILING

CAUK'G CAULKING/CHALKING

CLO CLOSET

CLR CLEAR

CO CASED OPENING

COR CONTR OF REC

COL COLUMN

CONC CONCRETE

CONN CONNECTION

CONSTR CONSTRUCTION

CONT CONTINUOUS

CONTR CONTRACTOR

CORR CORRIDOR

CTSK COUNTERSUNK

CNTR COUNTER

CTR CENTER

DBL DOUBLE

DEPT DEPARTMENT

DF DRINKING FOUNTAIN

DET DETAIL

DIA DIAMETER

DIM DIMENSION

DISP DISPENSER

DN DOWN

DO DOOR OPENING

DR DOOR

DWR DRAWER

DS DOWNSPOUT

DSP DRY STANDPIPE

DWG DRAWING

(E) EXISTING

E EAST

EA EACH

EEOR ELEC ENG OF REC

EJ EXPANSION JOINT

EL ELEVATION

ELEC ELECTRICAL

ELEV ELEVATOR

EMER EMERGENCY

ENCL ENCLOSURE

ENG ENGINEER

EP ELECTRICAL PANEL

EQ EQUAL

EQP EQUIPMENT

ES EDGE STRIP

EVS ENVIRONMENTAL

SERVICES

EWP END WALL PROTECTOR

EXPO EXPOSED

EXP EXPANSION

EXTR EXTERIOR

FA FIRE ALARM

FB FLAT BAR

FLR DRN FLOOR DRAIN

FD FIRE DAMPER

FDN FOUNDATION

FE FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER CAB

FH FULL HEIGHT

FHC FIRE HOSE CABINET

FIN FINISH

FLR FLOOR

FLS FIRE & LIFE SAFETY

FLSO FIRE LIFE SAFETY

OFFICER

FLASH FLASHING

FLUOR FLUORESCENT

FOC FACE OF CONCRETE

FOF FACE OF FINISH

FOS FACE OF STUD

FP FIREPROOF(ING)

FR FIRE RATED or FIRE

RATING

FRP FIBERGLASS

REINFORCED PLASTIC

FSD FIRE-SMOKE DAMPER

FT FOOT or FEET

FTG FOOTING

FURR FURRED or FURRING

FUT FUTURE

GA GAUGE

GALV GALVANIZED

GB GRAB BAR

GL GLASS

GLZ GLAZING

GRD GROUND

GR GRADE

GYP GYPSUM

HB HOSE BIBB

HDWD HARDWOOD

HDWR HARDWARE

HORZ HORIZONTAL

HR HOUR

HSKP HOUSEKEEPING

HT HEIGHT

HW HEAD OF WALL

ID INSIDE DIAMETER

IN INCH(ES)

ISO ISOLATION

INSUL INSULATION

INT INTERIOR

IOR INSPECTOR OF RECORD

JAN JANITOR

JT JOINT

KIT KITCHEN

LAB LABORATORY

LAM LAMINATE

LAV LAVATORY

LKR LOCKER

LT LIGHT

LTG LIGHTING

MAT'L MATERIAL

MAX MAXIMUM

MB MACHINE BOLT

M.C. MEDICINE CABINET

MECH MECHANICAL

MEOR MECH ENG OF REC

MEMB MEMBRANE

MTL METAL

MFG MANUFACTURER

MH MANHOLE

MIN MINIMUM

MIR MIRROR

MISC MISCELLANEOUS

M.O. MASONRY

OPENING

MTD MOUNTED

MTR MONITOR

MULL MULLION

(N) NEW

N NORTH

NEG PRES NEGATIVE

PRESSURE

NIC NOT IN CONTRACT

NR NON RATED

NO. NUMBER

NOM NOMINAL

NTS NOT TO SCALE

OA OVERALL

O/ OVER

OC ON CENTER

OD OUTSIDE DIAMETER

OFF OFFICE

OPN'G OPENING

OPP OPPOSITE

OSHPD OFFICE OF STATE HEALTH

PLANNING & DEVELOPMENT

PRCST PRECAST

PL PROPERTY LINE

PLAM PLASTIC LAMINATE

PLSTR PLASTER

PLYWD PLYWOOD

PR PAIR

PT POINT

PTD PAPER TOWEL DISPENSER

PTD/R COMBINATION PAPER

TOWEL DISPENSER &

RECEPTACLE

PTN PARTITION

PTR PAPER TOWEL

RECEPTACLE

QT QUARRY TILE

R RADIUS

RD ROOF DRAIN

REC RECORD

REFR REFERENCE

REF REFRIGERATOR

RGTR REGISTER

REINF REINFORCED

REQ'D REQUIRED

RB RESILIENT BASE

RM ROOM

RO ROUGH OPENING

RWD REDWOOD

RWL RAIN WATER LEADER

S SOUTH

SC SOLID CORE

SCD SEAT COVER DISPENSER

SCH SCHEDULE

SD SMOKE DETECTOR

SECT SECTION

SEOR STRCT ENG OF REC

SFD SMOKE / FIRE DAMPER

SFM STATE FIRE MARSHALL

SHF SHELF

SHWR SHOWER

SHT SHEET

SHTHG SHEATHING

SIM'L SIMILAR

SND SANITARY NAPKIN DISPENSER

SNR SANITARY NAPKIN

RECEPTACLE

S.D. SOAP DISPENSER

SPEC SPECIFICATION/S

SQ SQUARE

S.S. STAINLESS STEEL

SSK SERVICE SINK

STA STATION

STD STANDARD

STL STEEL

STO STORAGE

STRCT STRUCTURAL

SUSP SUSPENDED

SYM SYMMETRICAL

T TREAD

TB TOWEL BAR

TOC TOP OF CURB

TEL TELEPHONE

TEMP TEMPORARY

TEZZ TERRAZZO

T&G TONGUE & GROOVE

THK THICK

TLT TOILET

TOP TOP OF PAVEMENT OR

PARAPET

TOS TOP OF SLAB

TPD TOILET PAPER

DISPENSER

TRT TREATMENT

TS TUBE STEEL

TOW TOP OF WALL

TV TELEVISION

TYP TYPICAL

UG UNDERGROUND

UL UNDERWRITERS LABORATORIES

UNF UNFINISHED

UON UNLESS OTHERWISE NOTED

UTIL UTILITY

UR URINAL

VCT VINYL COMPOSITION TILE

VERT VERTICAL

VEST VESTIBULE

VTR VENT THRU ROOF

W WEST

W/ WITH

WC WATER CLOSET

WD WOOD

WF WIDE FLANGE

WH WATER HEATER

W/O WITHOUT

WP WATERPROOF

WSCT WAINSCOT

WSP WET STANDPIPE

WT WEIGHT

STUD SIZE

STUD GAUGE

COLUMN GRID

REFERENCE

DIMENSION TO

FINISH MATERIAL

DIMENSION TO

CENTERLINE

DIMENSION TO

GRIDLINE

15

(NOT ALL MAY APPLY)

ABBREVIATIONS

PLEASANT VALLEY SCHOOL DISTRICT

LOS ALTOS MIDDLE SCHOOL

GYMNASIUM ROOF REPLACEMENT

NONE

SECTION

SHEET WHERE DRAWN

DETAIL

SHEET WHERE DRAWN

SHEET WHERE DRAWN

ENLARGED DETAIL

NEW SPOT GRADE

DIRECTION OF

DRAINAGE FLOW

LEVEL LINE, BENCH MARK,

WORK POINT OR CONTROL

POINT

DIMENSION LINE AND POINT

CENTER LINE OR FLOOR LINE

PROPERTY, BOUNDARY OR

CUTLINE

MATCH LINE, SHADED

SIDE IS BEING CONSIDERED

OUTLINE OF HIDDEN OBJECT,

NIC ITEMS, REMOVED MATERIAL

FENCE LINE

BREAK LINE

NOTE SYMBOL,

SEE NUMBERED

NOTES COLUMN

REVISION NUMBER

REVISION CLOUD, OPTIONAL

COLUMN GRID REFERENCE,

POINT OF HEXAGON

TOWARDS COLUMN LINE

ELEVATION NUMBERS

SHEET WHERE DRAWN

ELEVATION SYMBOL,

ROOM NUMBER

ROOM MATERIAL CODE *

CEILING HEIGHT

ROOM NAME

* SEE ROOM MATERIAL

CODE SHEET

EQUIPMENT SCHEDULE

EQUIPMENT MARK

WINDOW MARK & TYPE

DOOR MARK

22

1

A

125

LOBBY

2B5

10'-0"

A

101A

52

A422

ELEVATION DIRECTION

3

A601

EXISTING SPOT GRADE

NEW CONTOURS

EXISTING CONTOURS

PARTIAL LIST OF APPLICABLE CODES AS OF January 1, 2020

2019 California Building Standards Administrative Code, Title 24 C.C.R.

2019 California Building Code (CBC), Title 24 C.C.R.

(2018 International Building Code of the International Code Council, with California Amendments)

2019 California Electrical Code (CEC), Title 24 C.C.R.

(2017 National Electrical Code of the National Fire Protection Association, NFPA)

2019 California Mechanical Code (CMC), Title 24 C.C.R.

(2018 Uniform Mechanical Code of the International Association of Plumbing and Mechanical Officials, IAPMO)

2019 California Plumbing Code (CPC), Title 24 C.C.R.

(2018 Uniform Plumbing Code of the International Association of Plumbing and Mechanical Officials, IAPMO)

2019 California Energy Code (CEC), Part 6, Title 24 C.C.R.

2019 California Fire Code, Title 24 C.C.R.

(2018 International Fire Code of the International Code Council)

2019 California Green Building Standards Code (CALGreen Code), Title 24 C.C.R.

2019 California Referenced Standards Code, Title 24 C.C.R.

Title 19 C.C.R., Public Safety, State Fire Marshal Regulations.

PARTIAL LIST OF APPLICABLE STANDARDS

NFPA 13 Automatic Sprinkler Systems 2019 Edition

NFPA 14 Standpipe Systems (CA Amended) 2013 Edition

NFPA 17A Wet Chemical Extinguishing Systems 2013 Edition

NFPA 20 Stationary Pumps 2019 Edition

NFPA 24 Private Fire Service Mains (CA Amended) 2019 Edition

NFPA 72 National Fire Alarm and Signaling Code (CA Amended) 2019 Edition

NFPA 80 Fire Door and Other Opening Protectives 2019 Edition

NFPA 253 Critical Radiant Flux of Floor Covering 2019 Edition

NFPA 2001 Clean Agent Fire Extinguishing Systems 2018 Edition

Reference code section for NFPA standards - 2019 CBC (SFM) Chapter 35.

See Chapter 35 for State of California amendments to NFPA standards.

PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, TRANSPORTATION, INSURANCE, AND SERVICES TO REPLACE EXISTING

ROOF SYSTEM WITH NEW ROOF SYSTEM AT UPPER PORTION OF THE GYMNASIUM BUILDING.

GENERAL

G-001 TITLE SHEET/ GENERAL INFORMATION/ VICINITY MAP/ SITE PLAN

G-002 SPECIFICATIONS

ARCHITECTURAL

A-221 ROOF PLAN & DEMOLITION PLAN

A-701 ROOF DETAILS

TEMPLE AVE.

BLDG B BLDG A

BLDG C BLDG D

BLDG E

BLDG F

MULTI-PURPOSE/

GYMNASIUM BUILDING

EXISTING PARKING LOT

AREA OF

WORK

G-001

TITLE SHEET /

GENERAL

INFORMATION

802 EAST COTA STREET. SUITE A

SANTA BARBARA, CA 93103

TEL (805) 963-1955

CONSULTANT STAMPARCHITECT STAMP

PROJECT OWNER & TITLE

SHEET TITLE

DRAWN BY:

SHEET NO.

DATE:

REVISIONS

THE ARCHITECT DOES NOT REPRESENT THAT

THESE PLANS OR THE SPECIFICATIONS ARE

SUITABLE FOR ANY SITE OTHER THAN THE ONE

FOR WHICH THEY WERE SPECIFICALLY

PREPARED. THE ARCHITECT DISCLAIMS

RESPONSIBILITY FOR THESE PLANS AND

SPECIFICATIONS IF THEY ARE USED IN WHOLE OR

IN PART AT ANY OTHER SITE

NO. DATE DESCRIPTION

#

AGENCY APPROVAL

FM No. xxxxxxxx

PLEASANT VALLEY SCHOOL

DISTRICT

LOS ALTOS MIDDLE

SCHOOL GYMNASIUM

ROOF REPLACEMENT

CAMARILLO, CA, 93010

JOB NUMBER: 20027.01

APRIL 28, 2020

Page 2: PLEASANT VALLEY SCHOOL DISTRICT...PART 1, T24 CCR. 3.A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS INSPECTION OF THE WORK. THE

PART 1 - GENERAL

1.00 SUMMARY

The work includes but is not necessarily limited to the tear off then installation of an Self Adhered Roofing System including membrane,

flashings and other components.

A. Section Includes

1. Tear off existing roof system

2. Tapered Insulation to Drains

3. ¼ Cover-board

4. Low Rise Foam for Coverboard and Insulation attachment

5. Self Adhered Roof Membrane

6. Fasteners and termination accessories

7. Roof Membrane Flashings

8. Adhesive for Flashings

9. Other Metal Flashings

10. Sealants

1.01 SUBMITTALS

A. At the time of award the Applicator will submit to the Owner (or Representative) the following (submittals of equals are to be submitted

prior to the time of bid by the applicator only):

1. Copies of Specification.

2. Samples of each primary component to be used in the roof system and the manufacturer's current literature for each component.

3. Sample copy of the warranty.

4. Sample copy of Applicator's warranty.

5. EPD's for the roofing membrane

6. Safety Data Sheets (SDS)

1.02 QUALITY ASSURANCE

A. Track Record - Install only PVC Roofing systems from manufacturers able to demonstrate the product on 5 existing functional roofs

=>20 year old roofs within 200 miles of the proposed project.

B. Use only a Manufacturer who has initiated a post consumer recycling program and can demonstrate a minimum of five projects where

the existing PVC roof has been removed and recycled into new roofing membrane or PVC components.

C. Use only a Manufacturer certified ISO 14001.

D. Use only a Roofing Contractor who has a minimum of 5 years experience installing the specified roofing system prior to bid date.

E. Unreinforced or polyester reinforced membrane flashings are prohibited.

F. No “Private Label” or third party membrane manufacturers.

G. No deviation from the Project Specification or the approved shop drawings is permitted without prior written approval by the Owner, the

Owner's Representative and Manufacturer.

H. Only Applicator personnel trained and authorized by manufacturer are permitted to complete work pertaining to the installation of

membrane and flashings.

I. Verify the roof deck and roof construction is structurally sound to provide support for the new roof system.

J. The Manufacturer must provide interim and final roof inspection from a directly employed dedicated team of experienced inspectors.

Sales personnel may not be used for on site inspection of installations.

1.03 REGULATORY REQUIREMENTS

These requirements are minimum standards and no roofing work will start without written documentation of the system's compliance, as

required in the "Submittals" section of this specification.

A. Factory Mutual Research Corporation (FM) - Norwood, MA

1. Class 1-90

B. Underwriters Laboratories, Inc. - Northbrook, IL

1. Class A assembly

1.04 PRE-INSTALLATION MEETINGS

A. A pre-construction conference to be attended by the Applicator, Owner's Representative and Manufacturer(s).

B. Discuss all aspects of the project including but not limited to:

1. Safety

2. Set up

3. Construction schedule

4. Contract conditions

5. Coordination of the work

1.05 DELIVERY, STORAGE AND HANDLING

A. Deliver all products to the job site in the original unopened containers or wrappings bearing all seals and approvals.

B. Handle all materials to prevent damage. Place all materials on pallets and fully protect from moisture.

C. Store membrane rolls lying down on pallets and fully protected from the weather with clean canvas tarpaulins. Un-vented polyethylene

tarpaulins are not accepted due to the accumulation of moisture beneath the tarpaulin in certain weather conditions that may affect the

ease of membrane weldability.

D. Store all adhesives at temperatures between 40º F and 80º F. Read instructions contained on adhesive canister for specific storage

instructions.

E. Store all flammable materials in a cool, dry area away from sparks and open flames. Follow precautions outlined on containers or

supplied by material manufacturer/supplier.

F. All materials which are determined to be damaged by the Owner's Representative or manufacturer are to be removed from the job site

and replaced at no cost to the Owner.

1.06 PROJECT CONDITIONS

A. Check the underside of deck for possible hazards that might be in the way of fasteners.

B. Materials may be installed under certain adverse weather conditions but only after consultation with manufacturer, as installation time

and system integrity may be affected.

C. Install only as much of the new roofing as can be made weathertight each day. Heat weld all seams before leaving the job site that day.

D. Schedule and execute all work without exposing the interior building areas to the effects of inclement weather.

E. All surfaces to be dry before installing insulation, Cover board, membrane or flashings. Dry the surface prior to application as required.

F. Secure all new and temporary construction, including equipment and accessories, to preclude wind blow-off and roof or equipment

damage.

G. Install uninterrupted waterstops at the end of each day's work. Completely remove before proceeding. Waterstops must not emit

dangerous or unsafe fumes and shall not remain in contact with the finished roof as the installation progresses.

H. Prior to and during application, remove all dirt, debris and dust.

I. Follow all safety regulations as required by OSHA and any other applicable authority having jurisdiction.

J. Immediately take all roofing, insulation, flashings and metal work removed during construction to a legal dumping area authorized to

receive such materials. Hazardous materials, such as materials are to be removed and disposed of in strict accordance with applicable

City, State and Federal requirements.

K. Immediately remove all new roofing waste material (i.e., scrap roof membrane, empty cans of adhesive) and properly transport to a

legal dumping area authorized to receive such material.

L. Take precautions that storage and/or application of materials and/or equipment does not overload the roof deck or building structure.

M. Stop work if any unusual or concealed condition is discovered and immediately notify Owner of such condition in writing.

M. The Roofing Contractor is cautioned that certain PVC membranes are incompatible with asphalt, coal tar, heavy oils, roofing

cements, creosote and some preservative materials. No contact with such materials and standard single-ply membranes. Consult

Manufacturer regarding compatibility, precautions and recommendations.

1.07 SEQUENCING

A. Arrange work sequence to avoid use of newly constructed roofing as a walking surface or for equipment movement and storage.

Where such access is absolutely required, provide all necessary protection and barriers to segregate the work area and to prevent

damage to adjacent areas. Provide a substantial protection layer consisting of plywood over Sarnafelt or plywood over insulation board

for all roof areas that receive rooftop traffic during construction.

SECTION 07 54 19

PVC ADHERED

THERMOPLASTIC MEMBRANE ROOFING

1.08 WARRANTY

Upon successful completion of work the following warranties must be provided:

1. 20 Year System Warranty

2. Year Roofing Contractor Warranty

A. System Warranty (only products purchased from single manufacturer are covered under System Warranty)

Upon successful completion of the work to manufacturer's satisfaction and receipt of final payment, manufacturer will issue a System

Warranty which includes all fasteners, cover board, accessories and covers wind speeds up 60 mph.

B. Applicator/Roofing Contractor Warranty

Supply the Owner with a separate 2 Year workmanship warranty. In the event any work related to roofing, flashing, or metal is found to

be within the Applicator warranty term, defective or otherwise not in accordance with the Contract Documents, at no cost to the Owner

the Applicator will repair the defect. The warranty obligation of the Applicator is directly to the Owner, and a copy is to be sent to

membrane manufacturer.

PART 2 - PRODUCTS

2.01 MANUFACTURERS

A. The components of the Adhered roof system are based on products of Sika Sarnafil (Sika Roofing Systems) G410 80 mill SA

B. Tremco TPA

C. Fiber Tite Extreme

2.02 MATERIALS

A. Sarnafil G410 fiberglass reinforced membrane with a lacquer coating.

B. Conform membrane to ASTM D4434 (latest version), "Standard for Polyvinyl Chloride Sheet Roofing". Classification: Type II, Grade I.

1. Main Field Sheet - Sarnafil G410-20 SA, 80 mil minimum thermoplastic membrane with fiberglass reinforcement.

C. Color of Membrane - Main Field and Flashings - White

2.03 FLASHING MATERIALS

A. Wall/Curb Flashing

1. G459 60 mill Membrane

A fiberglass reinforced membrane with a lacquer coating.

2. Clad

A PVC-coated, heat-weldable sheet metal capable of being formed into a variety of shapes and profiles. Clad is a 25 gauge, G90

galvanized metal sheet with a 20 mil unsupported PVC membrane laminated on one side.

2.04 COMPONENTS

A. Tapered Insulation

A Glass Faced 20 psi Poly Iso Insulation. Available in 4 ft x 4 ft or 4 ft x 8 ft flat and

tapered sizes in various thicknesses.

.

B. Coverboard

Dens Deck Prime is provided in a 4 ft x 8 ft board size and in thickness of ¼ inch

2.05 ATTACHMENT COMPONENTS & ACCESSORIES

A. Flashing Adhesive

Stabond Adhesive

A low VOC reactivating-type adhesive used to attach membrane to flashing substrate.

B. Coverboard Attachment

A two-component foamable polyurethane board adhesive that is applied in one step and sets up in

minutes

.

C. Circles

A 60 mil thick prefabricated 4 1/2 in. round circle patch injection molded.

D. Stop

An extruded aluminum, low profile bar used with certain fasteners to attach to the roof deck or to

walls/curbs at terminations, penetrations and at incline changes of the substrate. Stop is a 1 inch

wide, flat aluminum bar 1/8 inch thick that has predrilled holes every 6 inches on center.

E. Stack Universal

A prefabricated stack/pipe flashing made from 0.060 inch thick membrane. Accommodates

stack/pipe penetration from ¾” to 8”.

F. Corners

Prefabricated outside and inside flashing corners made of 0.060 inch thick membrane that are heat-

welded to membrane.

2.06 ACCESSORIES

A. Drains

OMG OlyFlow Hercules Scupper Retro-drain with Clad Metal which are designed for existing through/wall scupper drainage pipe

B. Aluminum Tape

A 2 inch wide pressure-sensitive aluminum tape used as a separation layer between small areas of asphalt contamination and the

membrane and as a bond-breaker under the coverstrip at clad joints.

C. Multi-Purpose Tape

A high performance sealant tape used with metal flashings as a preventive measure against air and wind blown moisture entry.

D. Membrane Cleaner

A high quality VOC compliant solvent cleaner used for the general cleaning of residual asphalt, scuff marks, etc., from the membrane

surface. Membrane Cleaner is also used daily to clean seam areas prior to hot-air welding in tear off or dirty conditions or if the

membrane is not welded the same day it is unrolled.

2.07 SEALANTS

A. Multi-Purpose Sealant (for termination details).

B. Sika1 A (single component sealant) or equal

C. Depending on substrates, the following sealants are options for temporary overnight tie-ins:

1. Low Rise Foam Adhesive.

2. Multiple layers of roofing cement and felt.

3. Spray-applied, water-resistant urethane foam.

4. Mechanical attachment with rigid bars and compressed sealant.

2.08 MISCELLANEOUS FASTENERS AND ANCHORS

A. Post-galvanized steel, aluminum or stainless steel is mandatory for all fasteners, anchors, nails, straps, bars, etc. Avoid galvanic

corrosion by not mixing metal types and methods of assembly. Use expansion type fasteners with stainless steel pins for attachment of

metal to masonry. A minimum embedment of 1¼ inch for all concrete fasteners and anchors and the fastener's are to be approved by

the manufacturer to be used in that manner. A minimum embedment of 1 inch for all miscellaneous wood fasteners and anchors used

for flashings and the fastener's are to be approved by the manufacturer to be used in that manner.

PART 3 - EXECUTION

3.01 SUBSTRATE CONDITION

A. Tear off existing Hypalon and BUR roof. All fasteners are to be backed out or cut and not pulled out of the Tectum deck.

B. The Tectum Deck is to be replaced in all four corners and anywhere the Tectum Deck is damaged.

C. Acceptance or provision of proper substrate to receive new roofing materials will be by the Applicator.

D. Verify that the work done under related sections meets the following conditions:

1. Roof drains and/or scuppers have been installed properly.

2. Roof curbs, nailers, equipment supports, vents and other roof penetrations are properly secured and prepared to receive new

roofing materials.

3. All surfaces are smooth and free of dirt, debris and incompatible materials.

4. No water, ice and snow on the roof surface.

3.02 SUBSTRATE PREPARATION

The roof deck and existing roof construction must be structurally sound to provide support for the new roof system. Load materials on

the rooftop in such a manner as to eliminate risk of deck overload due to concentrated weight. The Owner's Representative is to verify

that the roof deck is secured to the structural framing according to local building code and in such a manner as to resist all anticipated

wind loads in that location.

3.03 SUBSTRATE INSPECTION

A. Prepare a dry, clean and smooth substrate to receive the Adhered roof system.

B. Inspect the substrate for defects such as excessive surface roughness, contamination, structural inadequacy, or any other condition

that will adversely affect the quality of work.

C. The substrate will be clean, smooth, dry, free of flaws, sharp edges, loose and foreign material, oil and grease. Correct all defects

before roofing starts.

D. No water, ice and snow on the roof surface prior to starting.

E. Apply membrane over compatible and accepted substrates only.

3.04 TAPERED INSULATIONCOVERBOARD INSTALLATION

A. Install Taper Insulation on the East and West Perimeter wall to move water to the drains and Cover board according to manufacturer's

instructions and shop drawings.

1. Neatly cut to fit around penetrations and projections.

2. Cover all Insulation, Cover board with membrane by the end of the day or the onset of inclement

weather.

3. Low Rise Foam Attachment

All surfaces must be clean, dry, and free of dirt, grease, oil, or other contaminants or particulates. All concrete surfaces must be cured

prior to applying Board Adhesive.

Apply the Sarnacol AD Board Adhesive directly to the substrate, using a ribbon pattern. Space the 1/2 in. wide wet beads at a

maximum of 12 in. o.c. to achieve proper coverage rate. Allow the adhesive to rise (approx. 4 - 8 minutes) before placing the

insulation or cover board into the adhesive. Walk boards in, ballast if necessary, to achieve proper contact with substrate. Adhesive

open time varies depending on weather conditions.

Notes:

a) Do not apply in wet weather or to a wet surface.

b) The minimum product temperature before application should be 72°F.

c) The minimum ambient and surface temperatures should be 40°F and rising.

d) Not recommended for use with insulations boards larger than 4' x 4'

e) All boards must lay flat upon roof surface.

f) Unused adhesive can be applied at a later date by simply replacing the mixing tip.

g) Do not allow the adhesive to skin over.

3.05 INSTALLATION OF MEMBRANE

Inspect the surface of the insulation or substrate prior to installation of the roof membrane. The substrate will be clean, dry, free from

debris and smooth with no surface roughness or contamination. Remove and replace delaminated, wet or damaged insulation boards.

1. Sarnafil G 410 SA Membrane:

1. The surface of the insulation or substrate shall be inspected prior to installation of the Sarnafil membrane. The substrate shall

be clean, dry, free from debris and smooth with no surface roughness or contamination. Broken, delaminated, wet or damaged

insulation boards shall be removed and replaced.

2. The membrane is installed after proper preparation of substrate. Peel back release liner and press onto substrate. Roll

membrane immediately afterwards with a steel membrane roller.

3. Refer to individual Product Data Sheets (PDS) and Adhered Systems: Self Adhered Membrane section of Sika Sarnafil Roofing

Applicator Handbook for detailed installation instructions.

3.06 HOT-AIR WELDING OF SEAM OVERLAPS

A. General

1. Hot-air weld all seams. Seam overlaps should be 3 inches wide when automatic machine-welding and 4 inches wide when

hand-welding, except for certain details.

2. Manufacturer will provide or approve the welding equipment. Successful completion of a training course provided by a

Manufacturer Technical Representative prior to welding by all mechanics intending to use the equipment is mandatory.

3. All membrane is to be clean and dry before welding.

B. Hand-Welding

Complete hand-welded seams in two stages. Allow hot-air welding equipment to warm up for at least one minute prior to welding.

1. Weld the back edge of the seam with a narrow but continuous weld to prevent loss of hot air during the final welding.

2. Insert the nozzle into the seam at a 45degree angle to the edge of the membrane. Once the proper welding temperature has

been reached and the membrane begins to "flow," the hand roller is positioned perpendicular to the nozzle and rolled lightly. For

straight seams, the 1-1/2 inch wide nozzle is recommended for use. For corners and compound connections, use the 3/4 inch wide

nozzle.

C. Machine Welding

1. Machine welded seams are achieved by the use of Sika Sarnafil's automatic welding equipment. When using this equipment,

follow Sika Sarnafil's instructions and local codes for electric supply, grounding and over current protection observed. Dedicated

circuit house power or a dedicated portable generator is recommended. Use no other equipment simultaneously off the generator.

2. Metal tracks may be used over the deck membrane and under the machine welder to minimize or eliminate wrinkles.

D. Quality Control of Welded Seams

1. Check all welded seams for continuity using a rounded screwdriver. Visible evidence that welding is proceeding correctly is

smoke during the welding operation, shiny membrane surfaces, and an uninterrupted flow of dark grey material from the underside of

the top membrane. On-site evaluation of welded seams shall be made daily by the Applicator at locations as directed by the Owner's

Representative or Manufacturer's representative. Take one inch wide cross-section samples of welded seams at least three times a

day. Correct welds display failure from shearing of the membrane prior to separation of the weld. Patch each test cut by the

Applicator at no extra cost to the Owner.

3.07 MEMBRANE FLASHINGS

Install all flashings concurrently with the roof membrane as the job progresses. No allowance for temporary flashings without the prior

written approval of the Owner's Representative and Manufacturer. Only specific locations on specific dates will be approved. If any

water is allowed to enter under the newly completed roofing, remove and replace the affected area at the Applicator's expense. Adhere

flashing to compatible, dry, smooth, and solvent-resistant surfaces. Use caution to ensure adhesive fumes are not drawn into the

building.

A. Adhesive for Membrane Flashings

1. Over the properly installed and prepared flashing substrate, apply adhesive according to instructions found on the Product Data

Sheet. Apply the adhesive in smooth, even coats with no gaps, globs or similar inconsistencies. Flash only an area which can be

completely covered in the same day's operations. Firmly press the bonded sheet in place with a hand roller.

2. Apply no adhesive in seam areas that are to be welded. Apply all panels of membrane in the same manner, overlapping the

edges of the panels as required by welding techniques.

B. Install stop according to the Detail Drawings with approved fasteners into the structural deck at the base of parapets, walls and curbs.

C. Follow Manufacturer's requirements, recommendations and the specifications. Accept all material submittals prior to installation.

D. Extend all flashings a minimum of 8 inches above roofing level unless otherwise accepted by the Owner's Representative and

Manufacturer's Technical Department.

E. Consistently adhere all flashing membranes to substrates. Cut and hot-air weld into place all interior and exterior corners and miters.

No contact with bitumen and the membrane.

F. Mechanically fasten all flashing membranes along the counter-flashed top edge with stop at 6-8 inches on center.

G. Terminate flashings according to Manufacturer's recommended details.

H. Add additional securement to all flashings that exceed 30 inches in height. Consult Manufacturer's Technical Department for

securement method

3.08 TEMPORARY CUT-OFF

Install all flashings concurrently with the roof membrane in order to maintain a watertight condition as the work progresses. Construct all

temporary waterstops to provide a 100% watertight seal. The stagger of the insulation joints will be made even by installing partial

panels of insulation. Carry the new membrane into the waterstop. Seal the waterstop to the deck and/or substrate so that water will not

be allowed to travel under the new or existing roofing. Seal the edge of the membrane in a continuous heavy application of sealant.

When work resumes, cut out the contaminated membrane. Remove all sealant, contaminated membrane, insulation fillers, etc. from the

work area and properly disposed of off site. Use none of these materials in the new work.

Provide the labor necessary to monitor and maintain a watertight condition, if inclement weather occurs while a temporary waterstop is

in place.

If any water is allowed to enter under the newly-completed roofing, remove and replace the affected area at the Applicator's expense.

3.09 COMPLETION

Prior to demobilization from the site, the work shall be reviewed by the Owner's Representative and the Applicator. All defects noted

and non-compliances with the Specifications or the recommendations of the manufacturer shall be itemized in a punch list. These

items must be corrected immediately by the Applicator to the satisfaction of the Owner's Representative and Manufacturer prior to

demobilization.

3.10 FIELD QUALITY CONTROL

Upon completion of the installation and the delivery to Manufacturer by the Applicator of a certification that all work has been done in

strict accordance with the contract specifications and Manufacturer's requirements, a Technical Representative will inspect and review

the installed roof system.

3.13 MANUFACTURER DEMONSTRATION

Provide maintenance documents and personal instruction for the facilities staff and other interested parties at a single

pre-determined mutually convenient time.

The instruction shall include the following topics:

1. Access restriction and precautions

2. Avoiding Mechanical Damage

3. Potential Contaminants and rectification

4. Cleaning

5. Emergency repairs

I. Procedures for permanent repairs and alterations

G-002

SPECIFICATIONS

802 EAST COTA STREET. SUITE A

SANTA BARBARA, CA 93103

TEL (805) 963-1955

CONSULTANT STAMPARCHITECT STAMP

PROJECT OWNER & TITLE

SHEET TITLE

DRAWN BY:

SHEET NO.

DATE:

REVISIONS

THE ARCHITECT DOES NOT REPRESENT THAT

THESE PLANS OR THE SPECIFICATIONS ARE

SUITABLE FOR ANY SITE OTHER THAN THE ONE

FOR WHICH THEY WERE SPECIFICALLY

PREPARED. THE ARCHITECT DISCLAIMS

RESPONSIBILITY FOR THESE PLANS AND

SPECIFICATIONS IF THEY ARE USED IN WHOLE OR

IN PART AT ANY OTHER SITE

NO. DATE DESCRIPTION

#

AGENCY APPROVAL

FM No. xxxxxxxx

PLEASANT VALLEY SCHOOL

DISTRICT

LOS ALTOS MIDDLE

SCHOOL GYMNASIUM

ROOF REPLACEMENT

CAMARILLO, CA, 93010

JOB NUMBER: 20027.01

APRIL 28, 2020

Page 3: PLEASANT VALLEY SCHOOL DISTRICT...PART 1, T24 CCR. 3.A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS INSPECTION OF THE WORK. THE

(E) RIDGE

1/2":12"

1/2":12"

2

A-701

1

A-701

1

1 1

1

2 2

2 2

4

3

44

6

A-701

TYP. OF 4

4

TYP. OF 5

5

4

6

80'-7"

96'-0"

7777

NUMBERED NOTES

LEGEND

NEW SARNAFIL ROOFING SYSTEM O/ (E) TECTUM ROOF

DECKING O/ (E) ROOF FRAMING

NEW SARNAFIL ROOFING SYSTEM O/ (E) TECTUM ROOF DECKING O/ (E) ROOF FRAMING

4 (E) MECHANICAL EXHAUST VENT TO BE REINSTALLED. IF NECESSARY, RAISE CURB

TO MEET PROPER FLASHING REQUIREMENTS

5

(E) STANDING SEAM METAL ROOFING, TO REMAIN

DEMOLITION NOTES

1

2

3

4

5

GENERAL NOTES

1. THE PLANS AND SPECIFICATIONS INDICATE THE GENERAL EXTENT OF WORK BASED

ON OWNER PROVIDED `EXISTING' DRAWINGS AND LIMITED FIELD VERIFICATION. THE

CONTRACTOR SHALL VERIFY THE EXISTING CONDITIONS AND WILL BE RESPONSIBLE

FOR DISCONNECTING AND RECONNECTING PLUMBING, MECHANICAL AND

ELECTRICAL SYSTEMS NECESSARY TO ACCOMPLISH REMODEL WORK WHETHER

SPECIFICALLY INDICATED OR NOT.

2. ITEMS TO BE REMOVED WITHIN THE EXTENT OF DEMOLITION ON THIS PLAN ARE TO

BE VERIFIED WITH THE OWNER'S DESIGNATED REPRESENTATIVE AS TO WHICH

ITEMS ARE TO BE RETURNED TO THE OWNER.

3. ALL EXISTING MATERIAL NOT TO BE REUSED OR NOT INDICATED TO BE RETAINED BY

THE OWNER SHALL BE REMOVED FROM THE SITE AND BE COME THE PROPERTY OF

THE CONTRACTOR FOR SALVAGE.

4. THE CONTRACTOR IS RESPONSIBLE FOR PERIODICALLY REMOVING DEBRIS AND

CLEANING THE AREA WHERE THEY ARE WORKING. THE CONTRACTOR MUST

PROVIDE THEIR OWN MEANS OF DEBRIS AND WASTE REMOVAL AND MAY NOT USE

THE OWNER'S WASTE RECEPTACLES.

5. THE CONTRACTOR SHALL MAKE EVERY EFFORT TO KEEP EXISTING FACILITY

UTILITIES IN OPERATION. THE CONTRACTOR SHALL NOTIFY THE OWNER A MINIMUM

OF 48 HOURS IN ADVANCE FOR ALLOWANCE OF DISRUPTION IN SERVICES.

DISRUPTION IN SERVICES SHALL BE ONLY AT THE OWNER'S DISCRETION.

6. IT IS THE INTENT OF THE PLANS THAT THE CONTRACTOR SHALL TURN OVER TO THE

OWNER A CLEAN AND COMPLETE JOB. ANY WORK NOT SPECIFICALLY CALLED FOR

OR SPECIFIED, BUT NECESSARY TO COMPLY WITH THE INTENT OF QUALITY AND

COMPLETENESS SHALL BE PERFORMED AS PART OF THIS CONTRACT.

7. ANY ADJACENT ITEMS OR SURFACES TO THE DEMOLITION WORK THAT IS DAMAGED

DURING THE CONSTRUCTION SHALL BE RESTORED TO ITS ORIGINAL CONDITION OR

FINISHED TO MATCH ADJACENT SURFACES AT NO ADDITIONAL COST TO THE OWNER.

8. ANY WORK REQUIRED TO BE REMOVED, BUT NOT SPECIFICALLY CALLED FOR, SHALL

BE REMOVED AND REINSTALLED, OR THE VACATED AREAS PATCHED AND FINISHED

TO MATCH ADJACENT SURFACES, WHICHEVER BEST MEETS THE INTENT OF THE

PLANS, AT NO ADDITIONAL COST TO THE OWNER.

9. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING THE BUILDING IN A

SECURED CONDITION IN THE AREA THAT IS INVOLVED IN THIS WORK AT ALL TIMES

DURING CONSTRUCTION.

10. FINISHES NOT SPECIFICALLY CALLED OUT SHALL BE FINISHED TO MATCH ADJACENT

SURFACES.

11. FOR CONDITIONS WHERE NO DETAILS ARE SHOWN, CONSTRUCTION SHALL BE AS

SHOWN FOR SIMILAR WORK.

12. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING ALL CONDUITS, PIPES, OR

OTHER OBSTRUCTIONS AS NEEDED FOR THIS WORK. CONTRACTOR SHALL PROVIDE

A COMPLETE SYSTEM

13. THE CONTRACT DRAWINGS AND SPECIFICATIONS REPRESENT THE FINISHED

PRODUCT AND DO NOT INDICATE METHODS. PROCEDURES, OR SEQUENCES OF

CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE TO FIELD VERIFY ALL

POTENTIAL INTERFERENCES ANDS OBSTRUCTIONS ASSOCIATED WITH THE WORK

AND TO MAKE THE APPROPRIATE PROVISIONS TO WORK AROUND THESE

CONDITIONS AND OR TO TEMPORARY RELOCATE OR REMOVE AND REPLACE

EXISTING CONSTRUCTION, M/E//P UTILITIES AND FIRE AND LIFE SAFETY SERVICES AS

REQUIRED TO PERFORM THE WORK. THE CONTRACTOR SHALL TAKE ALL

NECESSARY PRECAUTIONS AND PROVIDE ADEQUATE SHORING, BRACING, ETC.

WHETHER OR NOT CALLED OUT ON THE PLANS TO MAINTAIN AND ENSURE THE

INTEGRITY OF THE STRUCTURE AND M/E/P UTILITIES DURING CONSTRUCTION.REFER

TO ARCHITECTURAL, M/E/P DRAWINGS AND SPECIFICATIONS, FOR ADDITIONAL

INFORMATION.

14. SEE DETAIL 12/A-701 FOR INSULATION TAPER PLAN

3

2

1

6

DEMOLITION NOTES

1. REMOVE EXISTING RETROFITTED MECHANICALLY ATTACHED CSPE SINGLE-PLY

ROOF MEMBRANE SYSTEM TO EXPOSE AND ALLOW ACCESS TO THE ORIGINAL

BUILT-UP ROOF SYSTEM FOR DEMOLITION AND REMOVAL. IT IS INCUMBENT UPON

THE CONTRACTOR TO UTILIZE APPROPRIATE TECHNIQUES AND CARE DURING

DEMOLITION WORK TO PROTECT THE INTERIOR GYM FLOOR FROM DAMAGE. IT IS

EQUALLY IMPORTANT THAT THE EXISTING STRUCTURAL TECTUM ROOF DECK BE

PROTECTED FROM ANY DAMAGE AS A RESULT OF THE REQUIRED WORK. THIS

MAY REQUIRE THAT ALL FASTENERS; (SCREWS OR BARB TYPE), BE REMOVED BY

CAREFULLY BACKING OUT OF THE TECTUM STRUCTURAL ROOF DECK. THIS

WORK MAY INVOLVE THE CUTTING OFF OF ALL FASTENER HEADS FLUSH TO THE

TOP OF THE TECTUM STRUCTURAL ROOF DECK. IT IS IMPERATIVE THAT THE

TECTUM ROOF DECK INTEGRITY IS NOT DAMAGED OR COMPROMISED. IT IS THE

CONTRACTORS RESPONSIBILITY TO REMOVE AND REPLACE ANY CONTRACTOR

DAMAGED TECTUM ROOF DECKING AT CONTRACTOR COST. ALL FASTENERS

USED ON THE TECTUM STRUCTURAL ROOF DECK MUST BE APPROPRIATE AND

APPROVED FOR USE.

7

(E) RIDGE

1/2":12"

1/2":12"

1 3

1

3

1

3

1 3

2

2

444 4

5

80'-7"

96'-0"

4

A-221

ROOF PLAN &

DEMOLITION PLAN

2PROPOSED ROOF PLAN

3/32" = 1'-0"

802 EAST COTA STREET. SUITE A

SANTA BARBARA, CA 93103

TEL (805) 963-1955

CONSULTANT STAMPARCHITECT STAMP

PROJECT OWNER & TITLE

SHEET TITLE

DRAWN BY:

SHEET NO.

DATE:

REVISIONS

THE ARCHITECT DOES NOT REPRESENT THAT

THESE PLANS OR THE SPECIFICATIONS ARE

SUITABLE FOR ANY SITE OTHER THAN THE ONE

FOR WHICH THEY WERE SPECIFICALLY

PREPARED. THE ARCHITECT DISCLAIMS

RESPONSIBILITY FOR THESE PLANS AND

SPECIFICATIONS IF THEY ARE USED IN WHOLE OR

IN PART AT ANY OTHER SITE

NO. DATE DESCRIPTION

#

AGENCY APPROVAL

FM No. xxxxxxxx

PLEASANT VALLEY SCHOOL

DISTRICT

LOS ALTOS MIDDLE

SCHOOL GYMNASIUM

ROOF REPLACEMENT

CAMARILLO, CA, 93010

JOB NUMBER: 20027.01

APRIL 28, 2020

1DEMOLITION ROOF PLAN

3/32" = 1'-0"

Page 4: PLEASANT VALLEY SCHOOL DISTRICT...PART 1, T24 CCR. 3.A DSA CERTIFIED INSPECTOR WTIH CLASS 3 SHALL BE EMPLOYED BY THE DISTRICT AND SHALL PROVIDE CONTINUOUS INSPECTION OF THE WORK. THE

NOTE:

1) METAL EXTENDER PIECE IS REQUIRED IF EXISTING COUNTERFLASHING

IS CONTAMINATED AND OR COUNTERFLASHING FASCIA IS LESS THAN

4 INCHES WIDE. FASTENED 12 INCHES O.C. WITH GROMMETTED FASTENER.

2) VAPOR RETARDER SHALL BE SEALED AT EDGES.

PIPE PENETRATION

SIKAFLEX-1A

STAINLESS STEEL

HOSE CLAMP

SARNASTACK UNIVERSAL

HOT-AIR WELDED

SARNAFIL MEMBRANE O/

(N) DENSDECK O/(E)

TECTUM ROOF DECK

O/ (E) ROOF FRAMING

NOTE:

1) SEALANT IS A MAINTENANCE ITEM. MAINTENANCE IS NOT COVERED UNDER SARNAFIL WARRANTY.

2) VAPOR RETARDER SHALL BE SEALED AT EDGES.

3) PIPE SEAL MUST HAVE INTACT RIB AT TOP EDGE, REGARDLESS OF PIPE DIAMETER.

4) DECK FLANGES OF THE PRE-MOLDED PIPE SEAL SHALL NOT BE OVERLAPPED, CUT OR APPLIED OVER

ANY ANGLE CHANGE.

5) THE EMPTY SPACE MAY BE FILLED WITH AN EXPANDING URETHANE FOAM. THIS WILL MINIMIZE

CONDENSATION FORMATION

AS WELL AS PROVIDING SOME RESILIENCY TO THE FINISHED DETAIL.

8" M

IN

.

1" M

IN

.

SUITABLE FASTENER

NOTE:

1) WEIGHT OF UNIT TO BE EVENLY DISTRIBUTED OVER CROSS-SECTIONAL AREA OF

EXPOSED WOOD NAILER.

2) IF WEIGHT OF UNIT EXCEEDS MAXIMUM ALLOWED BY INSULATION MANUFACTURER,

A TREATED WOOD NAILER BELOW THE SARNAFIL MEMBRANE IS REQUIRED.

SARNAFIL MEMBRANE O/

(E) TECTUM ROOF DECK O/

(E) ROOF MEMBRANE

SARNAFIL MEMBRANE

'PROTECTION LAYER'

HOT-AIR WELDED

IN-PLACE

DURA-BLOCK ROOF SUPPORT

TREATED WOOD NAILER

TO MATCH HEIGHT OF

INSULATION (AS NEEDED)

ALTERNATE OPTION

USE SIKAFLEX 1A

BETWEEN PROTECTION

SHEET OF MEMBRANE

AND DURA-BLOK AND

PIN MEMBRANE ON

THE SIDES

SARNAFIL MEMBRANE

PROTECTION LAYER

SIKAFLEX 1A SEALANT

SLEEVE

SEAL ALL AROUND

5" DIA STD. PIPE

OVERFLOW PER PLAN

8

'

-

0

"

(E) SOFFIT

NOTE:

1) REFER TO SARNAFIL DETAIL 1.3 FOR FLASHING

DETAIL AT BUTT-ENDS OF SARNACLAD METAL

EDGE PIECE.

EDGE OF SARNACLAD METAL

8" WIDE G410 FLASHING STRIP,

HOT AIR WELDED IN PLACE

SARNAFIL FLASHING STRIP, HOT AIR WELDED

SARNACLAD METAL FASCIA

PLATE OVER FLASHING STRIP

AT THE END JOINTS OF THE

SARNACLAD METAL (SEE NOTE)

8

"

M

IN

.

ANTENNA WIRE. AFFIX TO

(N) DURABLOCK PLACED

4'-0" O.C.

ANTENNA

SARNAFIL FLASHING TO

ACCEPTABLE SUBSTRATE

7

A-701

ADDITIONAL 4" WIDE SARNAFIL

MEMBRANE

REINSTALL (E) BRACKETS TO

PARAPET WALL

8 M

IN

."

(E) SLOPED METAL

ROOFING TO REMAIN

(E) SLOPED METAL

MANSARD ROOF

4

A-701

SARNAFIL MEMBRANE O/

(E) TECTUM ROOF DECK

O/ (E) ROOF MEMBRANE

(E) SOFFIT

(E) OVERFLOW OUTLET

SARNAFIL MEMBRANE O/

(E) TECTUM ROOF DECK

O/ (E) ROOF MEMBRANE

CONCRETE

PARAPET WALL

4

A-701

CONCRETE

PARAPET WALL

HOT AIR WELD

ATTACH WITH MANUF.

APPROVED FASTENER

SARNAFIL FLASHING TO

ACCEPTABLE SUBSTRATE

TREATED WOOD NAILER

SECURELY ANCHORED

SARNAFIL FLASHING STRIP,

SECURELY ANCHORED

CONTINUOUS METAL HOOK STRIP

MULTI PURPOSE TAPE

SARNAFIL MEMBRANE O/

(N) DENSDECK O/(E)

TECTUM ROOF DECK

O/ (E) ROOF FRAMING

SARNACLAD METAL FASTENED

4" IN. O.C., STAGGERED METAL

FASTENED GALVANIZED

ANNULAR RING NAILS OR

OTHER ACCEPTABLE

FASTENER

HOT-AIR WELD

SARNAFIL MEMBRANE

SARNAFIL FLASHING TO ACCEPTABLE SUBSTRATE

METAL EXTENDER PIECE IF REQUIRED (SEE NOTE)

GROMMETTED FASTENER 12 INCHES O.C.

ADDITIONAL WOOD BLOCKING, IF REQUIRED

(TO ACHIEVE AN 8 IN. MIN. FLASHING HEIGHT)

SELF-FLASHING UNIT

DENSDECK O/ TECTUM ROOF DECKING

6REMOVABLE CURB FLASHINGSCALE: N.T.S.

1SECTION THRU MANSARD ROOF @ OVERFLOWN.T.S

2SECTION THRU MANSARD ROOF N.T.S

7DURA BLOCK DETAILN.T.S

5SARNACLAD FASCIA PLATE AT METAL JOINTSN.T.S

9(E) ANTENNA AT WALLN.T.S

4SECTION THRU MANSARD ROOF TYP.N.T.S

8SARNASTACK UNIVERSALN.T.S

3(E) OVERFLOW PIPE PENETRATION AT WALLN.T.S

SIM.

10PIPE PENETRATION FLASHINGN.T.S

SARNAFIL FLASHING MEMBRANE

SARNAFIL BASE FLASHING

STAINLESS STEEL HOSE CLAMP

PIPE PENETRATION

12TAPER PLANN.T.S

SARNAFLASHING AND SARNADISC

SARNAFIL MEMBRANE O/

(N) DENSDECK O/(E)

TECTUM ROOF DECK

O/ (E) ROOF FRAMING

ALUMINUM TAPE (SEE NOTE)

PIPE PENETRATION

OVERFLOW

SARNAFIL SEALANT (SEE NOTE)

STAINLESS STEEL HOSE CLAMP

SARNAFIL MEMBRANE O/

(N) DENSDECK O/(E)

TECTUM ROOF DECK

O/ (E) ROOF FRAMING

HOT-AIR WELD

HOT-AIR WELD

G459 PVC FLASHING MEMBRANE

G459 PVC FLASHING MEMBRANE

NOTE:

1) ALUMINUM TAPE IS REQUIRED IF EXISTING PENETRATION IS CONTAMINATED.

2) SEALANT IS A MAINTENANCE ITEM, MAINTENANCE IS NOT COVERED UNDER THE

SARNAFIL WARRANTY.

3) VAPOR BARRIER SHALL BE SEALED AT EDGES.

ALUMINUM TAPE

ALUMINUM TAPE

SARNAFIL FLASHING TO

ACCEPTABLE SUBSTRATE

TREATED WOOD NAILER

SECURELY ANCHORED

SARNAFIL FLASHING STRIP,

SECURELY ANCHORED

CONTINUOUS METAL HOOK STRIP

MULTI PURPOSE TAPE

SARNAFIL MEMBRANE O/

(N) DENSDECK O/(E)

TECTUM ROOF DECK

O/ (E) ROOF FRAMING

SARNACLAD METAL FASTENED

4" IN. O.C., STAGGERED METAL

FASTENED GALVANIZED

ANNULAR RING NAILS OR

OTHER ACCEPTABLE

FASTENER

11SECTION THRU MANSARD ROOF @ ROOF DRAINN.T.S

NOTE: SEE DETAIL 3/- FOR ROOF MEMBRANE INSTALLATION AT OVERFLOW

ATTACH WITH MANUF. APPROVED FASTENER

3

A-701

LOW RISE FOAM ALL

AROUND OPENING

PVC CLAD OMG 4"

SCUPPER THRU-WALL

RETRODRAIN

(E) 4" DIA. ROOF DRAIN

(E) SLOPED METAL

MANSARD ROOF

(E) SLOPED METAL

MANSARD ROOF

SARNAFIL SEALANT (SEE NOTE)

NOTE:

1) ALUMINUM TAPE IS REQUIRED IF EXISTING PENETRATION IS CONTAMINATED.

2) SEALANT IS A MAINTENANCE ITEM, MAINTENANCE IS NOT COVERED UNDER THE

SARNAFIL WARRANTY.

3) VAPOR BARRIER SHALL BE SEALED AT EDGES.

A-701

ROOFING DETAILS

802 EAST COTA STREET. SUITE A

SANTA BARBARA, CA 93103

TEL (805) 963-1955

CONSULTANT STAMPARCHITECT STAMP

PROJECT OWNER & TITLE

SHEET TITLE

DRAWN BY:

SHEET NO.

DATE:

REVISIONS

THE ARCHITECT DOES NOT REPRESENT THAT

THESE PLANS OR THE SPECIFICATIONS ARE

SUITABLE FOR ANY SITE OTHER THAN THE ONE

FOR WHICH THEY WERE SPECIFICALLY

PREPARED. THE ARCHITECT DISCLAIMS

RESPONSIBILITY FOR THESE PLANS AND

SPECIFICATIONS IF THEY ARE USED IN WHOLE OR

IN PART AT ANY OTHER SITE

NO. DATE DESCRIPTION

#

AGENCY APPROVAL

FM No. xxxxxxxx

PLEASANT VALLEY SCHOOL

DISTRICT

LOS ALTOS MIDDLE

SCHOOL GYMNASIUM

ROOF REPLACEMENT

CAMARILLO, CA, 93010

JOB NUMBER: 20027.01

APRIL 28, 2020