pm, managing projects course slides

186
© ESI International PMC:CPM:EN:000 ver. 2.0 Introduction 1 Welcome Emergency phone number Local emergency exit procedures Floor and facility layout Start and end expectations Breaks Attendance Agenda Passing this course Ground rules

Upload: rdailey20999060962

Post on 24-Nov-2015

62 views

Category:

Documents


0 download

DESCRIPTION

Slides from a Project Management course that helps entry level project managers learn how to effectively manage projects.

TRANSCRIPT

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    1

    WelcomeEmergency phone numberLocal emergency exit proceduresFloor and facility layoutStart and end expectationsBreaksAttendanceAgendaPassing this courseGround rules

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    2

    Course OverviewModule 1: Introduction to Project ManagementModule 2: Project InitiationModule 3: Project PlanningModule 4: Project ImplementationModule 5: Project Closeout

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    3

    Course ScopeThis course does

    Teach the fundamentals, tools,and concepts of projectmanagementDiscuss the role of the projectmanager and the teammembers in managing a projectPractice the fundamentals ofproject management

    This course does notTeach everything there is toknow about projectmanagementCover all topics of projectmanagement in great depthTeach everything you need toknow for the credentialing

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 416.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    4

    Standards and Best PracticesA standard is a basis for uniformly measuring or specifyingperformance.1A best practice is a generally accepted process or technique thatconsistently outperforms and delivers greater value and benefitswithin a discipline.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    5

    Global Best Practices in Project ManagementGlobal best practices in project management are promoted throughthe following:

    Various project management standards organizations, includingProject Management Institute (PMI)International Project Management Association (IPMA)Association for Project Management (APM)International Organization for Standardization (ISO)

    Practicing experts within the fieldYour organization

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    6

    Course ObjectivesBy the end of this course, you will be able to

    Describe the roles and responsibilities of project managers acrossthe project life cycleDefine and develop the foundations of a project plan, including therequirements document, work breakdown structure (WBS), budget,schedule, and other resourcesManage and control the project against the baselineClose out a project effectively

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Introduction

    7

    Participant IntroductionsNameLocationYears in current organizationProject experienceExpectations of this courseMost challenging project you haveworked on

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-1

    Introduction to Project Management

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-2

    ObjectivesBy the end of this module, you will be able to

    Identify the fundamental concepts of project managementDescribe project processes that make up every projectIdentify the roles and responsibilities of the project manager

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-3

    What Is a Project?Projects are

    TemporaryUniqueTime-based

    Project ManagementIs using the resources you have to get the job done successfully

    Good project management discipline helps to ensure projectsuccess.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-4

    How Does a Project Fit into the Bigger Picture?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-5

    DiscussionWhy Does a Project Fail or Succeed?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-6

    Project Constraints

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-7

    Managing Projects Using Project ConstraintsBalancing the constraints to completethe projectCombining art and scienceDefining and refining the project on anongoing basis

    Managing project constraints involves aconstantly changing balance.

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 416.2 PMBOK is a registered mark of the Project Management Institute, Inc.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-8

    Some Global Standards Governing ProjectManagement

    A standard is a "basis for uniformly measuring or specifyingperformance."1

    A Guide to the Project Management Body of Knowledge(PMBOK Guide2)

    Project Management Institute (PMI)Identifies the subset from overall project managementknowledge that is generally recognized as good practiceProvides and promotes common language and vocabulary

    The APM Body of KnowledgeAssociation for Project Management (APM), a UK-basedmember of the International Project Management Association(IPMA)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-9

    Some Global Standards Governing ProjectManagement (continued)

    PRojects IN Controlled Environments (PRINCE2)Template-based approach to project management thatoriginated in the UK

    ISO 21500:2012, Guidance on Project ManagementJoint venture between

    International Project Management Association (IPMA)International Organization for Standardization (ISO)Project Management Institute (PMI)

    Guidance on project management for any organization andany type of project regardless of complexity or size

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-10

    Project Management Best PracticesProject management has many areas to focus on and pay attention:

    Integration Human resourcesScope CommunicationsTime Stakeholder expectationsCost RiskQuality Procurement/contractingValue GovernanceBenefits CompetencyHealth safety and environment

    For more information, See the PMBOK Guide and the APMBoK.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-11

    Project Life Cycle

    Projects are usually divided into phases to provideExtra control to manage the completion of deliverablesA common understanding or frame of reference whendiscussing project statusA quick guide to the work being done on a project; the start,middle, and end

    Collectively, these phases make up the project life cycle.

    Project life cycles depend on the organization and the product orservice being built.

    Appendix A: Typical Project Life Cycles

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-12

    Project Management is an Iterative Set ofProcesses

    The five basic project process groups in the image below areInitiating Activities to start up/begin a project or phasePlanning Activities to organize and prepare for a project or phaseExecuting Activities to coordinate and accomplish work of aproject or phaseMonitoring and Controlling Activities to manage and direct theimplementation of a project or phaseClosing Activities to close down and end a project or phase

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-13

    Project Life Cycle Key Documentation

    Appendix B: Generic View of Project Documentation

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-14

    Project Manager 's Roles and ResponsibilitiesA project manager is the one responsible and accountable for thesuccessful coordination and execution of a project to meet the needs andrequirements of project stakeholders on time and on budget.Roles and Responsibilities

    Define the project scope and clarify requirements.Select, build, and lead a project team.Identify/assess stakeholders.Develop the project plan, including the budget and schedule.Manage and control project risks.Manage all project changes.Manage the project constraints.Manage stakeholder needs and expectations.Monitor and report the project progress and status.Monitor the quality metrics.Manage expectations and watch for and react to future trends.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-15

    DiscussionWhat makes a great project manager great?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-16

    Skills Needed by Project Managers

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 342.2 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 348.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-17

    Key MessagesA project is a temporary undertaking to create a unique product orservice. 1Project management is the application of knowledge, skills, tools,and techniques to project activities to meet or exceed stakeholderneeds and expectations from a project. 2Project managers must balance the project constraintscost,scope, time, risk, quality, and resourceover the life of the project.The phases of a project (which often vary by type of project) makeup the projects life cycle.An example of a project life cycle is initiation, planning,implementation, and closing.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-18

    Key Messages (continued)Five interacting process groups work together to make up a project:initiating, planning, executing, monitoring and controlling, andclosing.Activities and processes within the five process groups arecategorized within the nine knowledge areas.To be effective, project managers need to have hard skills, suchas planning and budgeting, as well as soft, people-related skillslike communicating and conflict resolution.The project managers primary role is to manage the project, butalso important are the related roles of planning, leading,communicating, negotiating, and problem solving.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-19

    Next Steps: Action PlanHow can you apply what you learned in this module to your workenvironment?

    Turn to the Action Plan tab and find the worksheet for this module.Develop a list of actions to complete when you return to work.For each action (what), identify

    Who needs to be involvedWhen you anticipate completing the action

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 1

    1-20

    Next Steps: Action Plan (continued)Take a few minutes to think about what you have learned duringclass and review the questions below.

    What are the project life-cycle phases called in your organization? Ifyou don't use a life-cycle framework, how might you go aboutintroducing it?Recall a recent project in which one of the project constraintschanged. What happened to the other constraints?Given the same situation and what you have just learned, howwould you now handle the change?How does your project fit within your organizations setup?Why are people skills so important for a project manager?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-1

    Project Initiation

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-2

    ObjectivesBy the end of this module, you will be able to

    Identify stakeholders and organizational influences on a project overits life cycleDescribe quantitative and qualitative methods for project selectionCreate SMART (specific, measurable, agreed-upon, realistic, time-constrained) objectivesDocument project requirements from identified needs

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-3

    The Project Life Cycle

    Initiation PhaseConduct a high-level stakeholder assessment.Assess business needs and opportunities.Evaluate financial benefits and costs.Determine objectives and requirements.Identify the purpose/components of a project charter.Prepare requirements documentation.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-4

    Influences on a ProjectProjects are influenced by

    Key stakeholdersProject sponsorProject managerCustomerVendors andsuppliersOther stakeholders

    Internal factorsSystemOrganizationalstructureCultureBusiness/organizationalneed

    External factorsSocialEconomicEnvironmentalMarket demandRegulations

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-5

    Identifying Key StakeholdersWho are the stakeholders? Consider

    Who gets the output from the project?Who provides the input?Who has oversight?Who has other related responsibilities?Who reaps the rewards?Who suffers the penalties?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-6

    Stakeholder Identification and AssessmentTo determine the best approach to managing stakeholderexpectations throughout the whole project

    Identify the key stakeholdersAnalyze them on

    Interest in the projectPower to impact the projectEngagement to the project

    Identify their needs and expectations

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-7

    Types of Stakeholders

    Tool: Stakeholder Register (Simple)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-8

    Understanding the Roles of GovernanceSenior management includes your leaders/managers:

    Program managersDivision headsVice presidentsManaging partnersSponsorPortfolio manager

    Usually, they use governance policies to select and initiate projects.As a project manager, think

    What do they need from me?What do I need from them?How do they want my project governed?How do I escalate and resolve issues?How does my project align with and support my organizationstrategy?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-9

    Case Study 2-1Good Answers Is Growing: Introducing YourNext Project

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-10

    Assess Business Needs and OpportunitiesProject concepts originate in response to

    Product obsolescenceCompetitive forcesCustomer/client requirementsEmployee suggestionsProcess improvementBusiness transformationOrganizational changeRegulatory changes

    Projects should support the organization's major business andstrategic goals.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-11

    Project SelectionSelection practices are unique to each organization.Best practices encourage objectivity.Project selection is rarely purely quantitative.Selection should align with an organization's strategic intent.Selection is an integral part of an organization's balanced portfolio.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-12

    Selection ToolsQualitative Factors Quantitative Factors

    Stakeholder biasOrganizational fitRisk analysisScoring models

    Benefit-cost ratio (BCR)Present value (PV)Net present value (NPV)Payback period

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-13

    Benefit-Cost Ratio (BCR)A comparative analysis of benefits to costs:

    Example:Project A will charge $100,000 (cost) and generate $150,000 invalue (benefit).Project B will charge $100,000 (cost) and generate $160,000 invalue (benefit).

    Which has a higher BCR?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-14

    Present Value (PV)What is the value today of future cash flow?

    RememberPV = present value of moneyFV = future valuei = interest rate (also known as internal discount rate or cost ofcapital)n = number of time periods from today

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-15

    Present Value (PV) (continued)Someone wants to repay your invoice of $1,000 by waiting until theend of next year (today is Jan. 1) and will pay you $1,250 at the endof next December.Lets assume your organizations cost of capital is 15%.

    Is this a good deal?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-16

    Net Present Value (NPV)To determine the value of an investment over timeAdd the PV from each year to determine the Total Benefit:

    Use the following formula to determine NPV:

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-17

    Net Present Value (NPV) (continued)Which project is financially smarter?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-18

    Payback PeriodHow long it will take to balance the cost of the project before turninga profit

    Which has the shorter payback period?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-19

    Exercise 2-1Net Present Value

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-20

    Project CharterA document issued by the project approver that authorizes theexistence of a project

    Acts as the written agreement between senior management, theproject manager, and functional managersDelineates preliminary roles, responsibilities, authority, andaccountabilityDescribes project scope, including high-level requirements and risksDocuments business needs and a current understanding of theproduct service or resultDocuments a high-level milestone schedule and budgetSummarizes, as a minimum, the preliminary boundaries of a project

    Tool: Project Charter

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-21

    The Right StartNeeds are formalized into

    ObjectivesRequirements

    BusinessUserFunctionalTechnical

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-22

    Needs AssessmentCollect requirements to define and document the needs of theproject.

    Needs exist on various levels.Needs should be separated from wants.Projects are often built on conflicting needs.Customers often do not know, or understand, their needs.

    Review the organizations methodologies and internalprocesses.

    Needs are assessed passively through document review,questionnaires, surveys, analyses, and audits.A participative needs assessment can be done using interviews,focus groups, facilitative workshops, and prototypes.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-23

    Formulating Good ObjectivesObjective

    An understanding between someone who needs something andsomeone who can provide itExists at all levels (corporate, project, work team, specific task)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-24

    Requirements and Specifications

    Functional/NonfunctionalRequirements Technical SpecificationsWritten in business language Written in technical languageSolution agnostic Particular technology solutionPerformance characteristics Design specificationsCustomer/client view Build team viewProduct features & capabilities Sometimes called "specifications"

    Key problems:Customers dictating the technical solutionTeam members rewriting customer requirements (outside of thechange process)

    Tool: Requirements Checklist (Basic)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-25

    Case Study 2-2Working with Customers to Develop GoodRequirements

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-26

    Requirements DocumentationProject requirements document (PRD)

    Lists what the project is to doLinks the project requirements to business objectives

    Business requirements document (BRD)Lists the TO-BE solutionMaps business goals and needs to solution scope andrequirements

    Requirements work planDocuments how requirements are to be collectedIncorporated into the project management plan

    Traceability matrixMaps each requirement through the life of the project

    Tool: Traceability Matrix (Basic)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-27

    Project Requirements DocumentA formal document used to communicate requirements for projectstakeholders

    Documents the project objectives and identifies and prioritizesrequirementsSupports the business caseDrafted by the project team and approved by senior management/key stakeholdersProvides a basis for planning and designing the product/solution,including cost and time estimatesReduces the amount of rework on the project

    Tool: Project Requirements

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-28

    Case Study 2-3Off to a Strong Start: Creating a ProjectRequirements Document

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-29

    From Initiation to PlanningCharter/PRD

    Tools used (*key project management documents):Tool: Project Charter*Tool: Project Requirements*Tool: Requirements Checklist (Basic)Tool: Stakeholder Register (Simple)*Tool: Traceability Matrix

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-30

    Key MessagesInternal and external factors influence every project.Senior management usually selects and initiates a project.Qualitative methods and quantitative considerations enter intoproject selection.Projects originate for many reasons, from product obsolescence toclient requirements to individual innovation.Needs must be assessed, objectives set, and requirements definedso that specifications can be set.Customers define the requirements.The project team develops the technical specifications.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-31

    Key Messages (continued)A project charter spells out the roles and responsibilities of theproject manager, key members of the project team, and input fromother organizational agencies.The requirements documentation comes in many forms: projectrequirements documents and business requirements documents.The PRD is the official document that describes the identifiedproject requirements.The requirements traceability maps the evolution of therequirements from the beginning to the end of the project.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-32

    Next Steps: Action PlanHow can you apply what you learned in this module to your workenvironment?

    Turn to the Action Plan tab and find the worksheet for this module.Develop a list of actions to complete when you return to work.For each action (what), identify

    Who needs to be involvedWhen you anticipate completing the action

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 2

    2-33

    Next Steps: Action Plan (continued)Take a few minutes to think about what you have learned duringclass and review the questions below.

    In the past, what steps have you taken to ensure you have identifiedall of the stakeholders in your projects? What can you do to ensureyou do so in the future?In the past, have you been successful in identifying who seniormanagement is and what they need? Remember to ask yourself,What do they need from me and what do I need from them?Historically, how has your organization identified needs, writtengood objectives, and created both functional and technicalrequirements? What can be done in the future to improve how thisis done on your project?What uses can you see in your organization for a project charterand a PRD?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-1

    Project Planning

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-2

    ObjectivesBy the end of this module, you will be able to

    Assemble the core project team to plan a projectDocument the project scope in a scope statementDocument the project work in a WBSComplete and interpret work estimatesIdentify the appropriate resources necessary for a projectBuild a project scheduleEstimate and interpret project costsIdentify strategies for dealing with positive and negative risksExplain the basics for procuring external goods and servicesExplain the relevance of communications and quality planningComplete and interpret a project management planDefine and interpret baselines

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-3

    The Project Life Cycle

    Planning PhaseBuild the core project team.Build a WBS.Estimate durations, costs, and resources.Develop the project schedule.Conduct risk management and risk response planning.Develop subsidiary management plans, including communicationand quality plans.Develop the project management plan.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-4

    Core Project TeamA core group of key people should

    Include a representative from the major business functionalareasNot be the whole teamNot be senior management

    The core team should be self-directed and interactive.Project management tip: Get the right people with the right skillsand knowledge on the core team!

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-5

    The Project Management PlanBook of Plans: How best to manage this project; a place to documentkey project decisions

    What life cycle is best to be used? Why?What level of detail is required on activities? Why?What tools/techniques are being used? Why?How will the selected processes

    Be used?Actually work?Integrate with other processes?

    How will the integrity on the baseline be maintained?What are the key management reviews to be accomplished? Whenand with what information?

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 397.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-6

    Scope ManagementScope: "The sum of the productsand services to be provided by theproject."1Scope statement: Describes indetail the projects deliverables andthe work necessary to complete thedeliverables

    Scope was outlined in the projectsInitiation phase; now it is time to focus onwhat is specifically in scope and what isnot in scope.

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 470.2 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 470.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-7

    Work Breakdown Structure (WBS)The WBS is

    A hierarchical structured grouping of project elements thatorganizes and defines the total scope of the project 1Each descending level is an increasingly detailed definition of aproject component for each descending level of the WBS.2

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-8

    Key WBS TermsControl Account Work Package Planning Package

    Is typically abovethe work packagelevelIs the level formanagementreportingIs the level wherecosts are accruedand monitored

    Is the level wherework is assignedand monitoredIs the basic levelfor addressingschedules, cost,and resourcesneededIs the lowest levelof the WBS

    Is primarily usedwith rolling waveplanningIs below thecontrol accountIs a work packagewith known workcontent that hasnot been detailedor scheduled

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-9

    WBS Models (Graphical)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-10

    WBS Models (Outline/Indented)1.0 Management Information Software System

    1.1 Assess needs1.1.1 Measure state of current system

    1.1.1.1 Identify components of current system1.1.1.2 Analyze components of current system

    1.1.2 Determine future capability requirements1.1.2.1 Perform gap assessment1.1.2.2 Identify required changes

    1.1.3 Develop alternative approaches1.1.3.1 Identify alternative approaches1.1.3.2 Analyze alternative approaches

    1.2 Develop specification1.2.1 Develop preliminary software and hardwarespecifications1.2.2 Develop detailed software specifications

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-11

    DiscussionWhat Are Some Important Benefits and Usesof a WBS?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-12

    Building a Work Breakdown Structure (WBS)As a team1. Understand the purpose of your project2. Review existing templates, WBSs from past projects, and historical

    records such as lessons learned3. Establish the major breakout segments of the work4. Break down these large pieces into the next level of components5. Break down each component into subcomponents6. Continue down to the level where you will assign and monitor

    project work7. Hold a review session with the core project team, client, and other

    key stakeholders to gain buy-in and identify missing items8. Prepare the WBS dictionary

    Tool: WBS Checklist

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-13

    WBS DictionaryIs not a book of terms and definitionsProvides detailed information on those work packages that needfurther clarificationCaptures critical information about the activity such as, but notlimited to

    WBS task name and numberTask description including deliverables to be produced anddeliverables scheduleResource requirements and assignmentsPreceding/subsequent activitiesCost estimatesQuality requirements

    Contains varying content, depending on the need for information

    Tool: WBS Dictionary

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-14

    Case Study 3-1Creating the Project's WBS

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-15

    Translating the WBS into the ScheduleThe WBS identifies the work to be donein work packages.Work packages are further broken into activities that specify thework necessary to complete the work packages.Activities are used as a basis to quantify estimates of

    DurationCostResourcesSchedule dependencies

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 151.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-16

    EstimatingForecasting the cost, schedule, and resource requirements neededto produce a specific deliverable1

    Estimating is a deliberate process:The quality of the estimate leads is directly proportional to thequality of the project schedule and budget.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-17

    Good Estimating PracticesAcknowledge the level of accuracy:

    Estimates can and should be done at varied levels ofaccuracy.Communicate the level of accuracy with the estimate.

    Get input from many sources:In-house sourcesOutside sourcesProfessional organizations

    Document your assumptions.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-18

    Estimating TechniquesSTETParametricHistoricalThree-pointPERT (Program Evaluation and ReviewTechnique)Wideband Delphi

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-19

    Three-Point Estimating Formulas

    Where:O = optimistic P = pessimistic ML = most likely E = expected

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-20

    Creating the ScheduleEstimates the time duration to complete the projectEstablishes relationships between various work packagesBenefits from the use of tools only when accurate information isused

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 142.2 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 470.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-21

    Considerations for Estimating Activity DurationEffort: "Number of labor units required to complete an activity"1Work period: Unit of time when resources are generally availableto perform work (8 hours = 1 day)Working time: "Period of time in which actual work on a project canbe, and should be, completed"2 (24 hours effort = 3 workdays)Elapsed time: Accounts for all calendar time (weekends, holidays,and breaks) and not just time spent on a project (24 hours = 1elapsed day)Availability: The time that a resource is present, ready for, andcapable of performing the workProductivity: Measure of efficiency of a resource in performingworkInterruptible duration: Work time that is not contiguous

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-22

    Common Scheduling ToolsNetwork diagram

    Schematic display of the logic relationships of projectactivitiesBest for analysis

    Gantt chartEasiest to make and understandAppropriate for smaller projects

    Project calendarHigh-level detailsQuick public way to show project responsibilities

    MilestonesSummary-level scheduling showing significant events thatinclude completion of major deliverablesConsume no resources or time

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-23

    Network DiagramsThe chronological relationship between scheduled activities isshown.Activities are represented by boxes.Dependencies are represented by arrows.Multiple arrows (dependencies) are possible.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-24

    Transforming a WBS into a Network DiagramWork package: Install new building fire alarm system

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-25

    Uses of the Network Diagram

    Step Action ResultForward Pass By path, start at the beginning, add

    all durations togetherDuration of theproject

    Backward Pass By path, start at the end, subtractall durations

    Float

    Path Analysis By path, review each path for theleast amount of float

    Critical path

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-26

    Forward Pass

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-27

    Backward Pass

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 175.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-28

    FloatAmount of time that an activity may be delayed from its early start withoutdelaying the project end date. Derived by subtracting the early start fromthe late start or early finish from the late finish; it may change as theproject progresses and as changes are made to the project plan.1

    Calculated from thenetwork diagram aftercompleting a backwardpassIndicates the amount offlexibility the projectmanager has to adjustthe timing of a particularactivityAlso called slack andtotal float

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-29

    Determining Float

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-30

    Completed Network Diagram Showing CriticalPath

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-31

    Network AnalysisAnalysis of the network reveals the

    Duration of the projectFloatCritical path

    Longest of all paths through the projectShortest time to complete the projectPath with the least float/slack time

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-32

    Gantt ChartsA Gantt chart

    Is a graphical representation of the project schedule that shows howthe work flows over timeShows activity start and end dates and durations

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-33

    Project Calendar (Month 4)The project calendar

    Is a visual representation of what work needs to happen on acertain dayShows days, work hours, and weekends/holidays

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-34

    Milestone ChartsMilestones

    Activities of zero durationTake no timeConsume no resources

    Record significant events or deliverablesMajor project happenings (component X complete)Funding points (30% of budget expended)Key dates (Start of Sochi Winter OlympicsFebruary 7,2014)

    Serve as reminders to check on overall project status at key points

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-35

    Case Study 3-2Network Diagramming

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-36

    Estimating Costs to Determining BudgetHow much will the project cost?Inputs:

    Scope baselineWBSWBS dictionary

    Project scheduleRoles and ResponsibilitiesRisk register

    Outputs:Cost estimatesDuration (time) estimatesBasis of estimates

    Documentation on how estimates were determinedDocumented assumptions and constraintsThe precision range of estimates and confidence level

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-37

    Three Levels of Estimates

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-38

    Cost ComponentsDirect Costs

    LaborInternalContract

    Materials and equipmentOther direct costs

    FeesTravelIncidentals

    Indirect Costs (Overhead)General administrativeHeadquarter (HQ) expenses

    Fringe benefitsDepreciation

    Marketing and salesResearch and development

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-39

    Cumulative Cost Curve

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-40

    Resource PlanningPlan for the resources you need to do the project:

    PeopleSkillsEquipmentFacilitiesMaterials

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-41

    Human Resource PlanningHow will I get the best resources and use who I have as best I can?

    Planning for the project resourcesAcquiring project resourcesDeveloping, maintaining, and managing project resourcesReplenishing project resources as needed

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-42

    Resource Planning Tools and TechniquesRoles and responsibilitiesResource Gantt chartResource loading tableResource loading histogram

    Resource leveling

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-43

    Roles and Responsibilities MatrixThe roles and responsibilities matrix identifies the appropriateskill/person for each task and his or her role on that specific task.

    Tool: Roles and Responsibilities Matrix

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-44

    Resource Gantt ChartHorizontal bar chart showing duration of assignments for eachresource and activity

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-45

    Resource Loading TableStructure that shows the resource allocation by time period

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-46

    Resource Loading HistogramHow available resources can be allocated over the life of the project

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-47

    Resource LevelingUsed to smooth the peaks and valleys of planned resources over aperiod of time

    Limit of no more than seven people involved

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 386.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-48

    RiskRisk event

    "Discrete occurrence that may affect a project, positively ornegatively."1Probability of the risk event occurringImpact (consequence) of that risk events occurrence

    Based on the assessment of probability and impact, you shouldprioritize the risk by

    Best utilizing the available resourcesAddressing the highest-impacting events first, then addressthe remaining lower-impacting events as time and resourcesallow

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 387.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-49

    Risk Management Planning"The procedures to be used to manage risk during the life of aproject."1

    Risks are threats or opportunities.Risk planning is an integral part of project planning.Individuals are assigned responsibility for managing certain areas ofrisk

    Risk management consists of eight processes:Plan risk managementplanningIdentify risksAnalyze risks quantitativelyand qualitativelyPrioritize risks

    Plan risk responsesExecute risk responses asappropriateEvaluate and reidentifyDocument options andoutcomes

    Tool: Risk Register

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-50

    ESIs Risk Management ModelThe circle below illustrates the 8 steps of ESIs risk managementmodel.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-51

    Response Strategies for ThreatsThreats

    Accept: Prepare for and deal with a risk's consequences, eitheractively (create a contingency fund) or passively (do nothing).Mitigate: Reduce the probability and/or impact of a threat to anacceptable threshold.Transfer: Shift a threat's consequences to a third party.Avoid: Eliminate the threat, usually by eliminating its potentialcause.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-52

    Response Strategies for OpportunitiesOpportunities

    Accept: Prepare for and deal with a risk's consequences, eitheractively (create a contingency fund) or passively (do nothing).Enhance: Modify the potential of an opportunity by increasingprobability and/or positive impact and by identifying and maximizingkey drivers.Exploit: Ensure that the opportunity is realized; eliminate theuncertainty associated with a particular risk by making theopportunity definitely happen.Share: Allocate ownership to a third party best able to capture theopportunity.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-53

    Procurement PlanningGoing outside the team to purchase or acquire

    MaterialsServicesPeople

    The project manager becomes the customerSelecting the contract typePreparing procurement documentsSelecting the contractor (vendor)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-54

    Selecting a Contract Type

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-55

    Preparing Procurement DocumentsProcurement documents are used to solicit proposals from sellers. Someof the most common ones are

    Request for information (RFI)Request for proposal (RFP)Request for quotation (RFQ)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-56

    Selecting a Contractor*Evaluate and choose the best proposal or bid:

    TechnicalBusiness fitCost

    Negotiate and award the contract.*Also may be referred to as seller or contractor.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-57

    Communication PlanningHow will information flow during your project?

    Who needs to know what?How will you tell them?How urgently and how often?What do you make part of a permanentrecord and how?What technology will be used?Who authorizes the release of classifiedinformation?What are the escalation processes?What are the constraints oncommunications?

    Tool: Communication PlanDetailed

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 363.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-58

    Planning for Project QualityThe process of identifying quality requirements and/or standards for theproject and product, and documenting how the project will demonstratecompliance.1The project manager and team must

    Plan for quality, perform quality assurance, and perform qualitycontrolClarify quality policy duration

    Link to customer's policyLink to organization's strategy

    Determine project standards and metrics for tasks within standardsDocument how and when metrics will be measuredDocument how project quality will integrate with product/servicescore

    Tool: Quality Plan

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-59

    Project Management PlanThe project management plan provides the road map to theImplementation phase of a project.

    Tool: Project Plan OutlineTypical

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-60

    Case Study 3-3Planning for Success: Building the ProjectManagement Plan

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 32.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-61

    Project BaselinesWhat: "Project management frame of reference established basedon the detailed project plan and incorporating the project's cost,schedule, and quality objectives to provide a basis for measuringprogress, comparing planned and actual events and expenditure,and identifying and executing changes to the project's scope ofwork."1

    ScopeCostScheduleQuality

    Why: To define a standard against which project success can bejudgedWhen: Upon approval and endorsement of all baseline components

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-62

    Who Uses Baselines?CustomerProject managerManagementAccountingProject team

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-63

    From Planning to Implementation: The ProjectPlan

    Tools used (*key project management documents):WBS ChecklistWBS DictionaryRoles and Responsibilities MatrixRisk Register*Communication PlanDetailedQuality PlanProject Plan OutlineTypical*

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-64

    Key MessagesThe core project team is involved in project planning.Understanding the scope is key to project planning.A WBS is a hierarchical breakdown of the scope in order to betterplan for its completion.Although a WBS has different formats, levels of detail, and ways ofbeing created, the work package is always the bottommost level.Work packages break down into activities. It is these activities thatare used to build the network diagram that leads to the projectschedule.A WBS dictionary provides important working-level informationabout each work package.Schedule planning involves determining the timing of the project,including critical path and float, and may be presented in manyformats.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-65

    Key Messages (continued)Cost planning involves determining the direct costs that the workpackages required as well as indirect costs (overhead) allocated tothe project.Resource planning covers people, materials, facilities, and otherresources.Risks (both opportunities and threats) must be identified, analyzed,prioritized, and planned for through the appropriate responsestrategy.Procurement planning involves deciding whether to procure outsideservices and how to choose which outside entity to use.Communication and quality round out the project managersplanning processes.Baselines are used by stakeholders to measure how the project isdoing in reference to cost, scope, and schedule baseline.All these processes come together in the project management plan.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-66

    Next Steps: Action PlanHow can you apply what you learned in this module to your workenvironment?

    Turn to the Action Plan tab and find the worksheet for this module.Develop a list of actions to complete when you return to work.For each action (what), identify

    Who needs to be involvedWhen you anticipate completing the action

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 3

    3-67

    Next Steps: Action Plan (continued)Take a few minutes to think about what you have learned duringclass and review the questions below.

    What form of WBS does your organization use?Why is having a WBS for a project important?Why is determining the critical path and float so important to yourproject?How can your organization benefit by having each project produce aresource/responsibility matrix?What is your organizations risk planning process? Is it effective?What can you do to strengthen or enhance it?What is your organizations procurement planning process? Is iteffective?What can you do to strengthen or enhance it?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-1

    Project Implementation

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-2

    ObjectivesBy the end of this module, you will be able to

    Assess and monitor project performance based on cost, schedule,scope, and quality baselines as well as stakeholder expectationsand team performanceDescribe methods for managing and controlling change for a projectAddress risks as they occurDescribe characteristics of an effective team, their roles andresponsibilities, and possible organizational team structuresAlign project team performance with stakeholder expectationsComplete a performance report

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-3

    The Project Life Cycle

    Implementation PhaseExecute

    Develop the product or serviceMonitor

    Assess, monitor, and report project performanceDevelop, monitor, and support the project team

    ControlManage changeManage riskManage stakeholder expectations

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-4

    Assessing Project PerformanceMonitoring

    Continuous, ongoingUsed by project team to adjust the project

    EvaluatingPeriodicUsed by senior management and customers to adjust the projectThrough status reports

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 462.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-5

    Monitoring Project PerformanceCompare against baselines:

    ScopeCost performanceSchedule

    Identify variance:Is the difference between aplan and actual time, cost, orperformance1

    Responds as appropriateAvailable techniques

    Trend analysisCritical path methodCritical chain methodEarned value management (EVM)

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-6

    Earned Value Management (EVM)An objective look at project statusSchedule and cost variancesAssessing schedule, cost, and work statusSingle system to integrate multiple assessments into a singlereporting structure

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-7

    How Is the Project Doing?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-8

    EVM Terminology

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-9

    Variances

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-10

    Variances (continued)

    Key EVM Tools and TechniquesCost Variance Cost Performance IndexCV = EV AC CPI = EV / ACSchedule Variance Schedule Performance IndexSV = EV PV SPI = EV / PVBudget at Completion Estimate at CompletionBAC = Sum of all PVs EAC = BAC / CPI or BAC-EV

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-11

    Interpreting Earned Value Management (EVM)Calculations

    Generally good variance:Ahead of scheduleCosts under budgetPositive values for costvariance (CV) and schedulevariance (SV)Ratios greater than 1 for costperformance index (CPI) andschedule performance index(SPI)

    Generally bad variance:Behind scheduleCosts over budgetNegative values for CV and SVRatios less than 1 for CPI andSPI

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-12

    Exercise 4-1Earned Value Management Calculations

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-13

    Assessing Project StatusTimeCostScopeResourcesQuality

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-14

    Indicators That Corrective Action Is NeededSchedule slippage for a specific task on the critical path or for theproject as a wholeOver budget on a specific task on the critical path or for the projectas a wholeInability to resolve problems promptlyInsufficient or high turnover in resourcesUnmanaged changes in scopeQuality problems resulting in excessive reworkChanges in customer or user requirements

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-15

    Corrective ActionsChange the task relationships (fast-tracking).Increase the resources (crashing).Redistribute the resources.Change the project solution design.Use improved technology.Change the contract scope.Change suppliers.Renegotiate the terms.Use subcontractors.Update the estimates.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-16

    Ways to Speed Up SchedulesCrashing Fast-Tracking

    Accelerates projectcompletion (to fightschedule slippage) byadding resources to criticalpath activitiesAnticipates increasedproject costsSelects activities that willcost the least to crash

    Carries out activities inparallel on the critical pathto accelerate the scheduleIncreases project riskRequires greater level ofcontrol and coordination

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-17

    DiscussionBased on the Network Diagram You Createdin Case Study 3-2, How Would You ApplyCrashing and Fast-Tracking Techniques?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-18

    Performance ReportingNo matter the form, no matter the frequency, include these threecomponents:

    What/how you have done since the last report (status)What you anticipate in the near future (forecast)Other key information the reader needs to know

    The performance report needs to be constructed, updated, and distributedin accordance with the communication plan.

    Tool: Project Status Summary Report

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-19

    Case Study 4-1How Are We Doing? Reporting ProjectPerformance

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-20

    Project EvaluationPeriodic project evaluations

    Encourage timely adjustmentFacilitate midcourse corrections instead of waiting until theendHelp with stakeholder communication

    Outcomes of evaluation includeContinue as plannedPerform minor redirectionPerform major redirectionTerminate earlyShelve or put project on temporary hold

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-21

    Sunk CostsHave already gone into the project andcannot be recoveredShould not affect decisions about thecontinuation of the project

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-22

    Managing ChangeChange happens for many reasons and in many forms:

    CustomerTeamOrganizational managementEnvironmentProduct obsolescenceFunding changesTechnology

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-23

    Change Control Board (CCB) An organized systematic approach is helpful in managing change:

    Tool: Change Request

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 80.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-24

    Configuration ManagementA configuration management system is a process used to apply technicaland administrative direction to

    Document the functional and physical characteristics of an item orsystemControl any changes to such characteristicsRecord and report each change and its implementation statusSupport the audit of the products, results, or components to verifyconformance to requirements1

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-25

    Managing RiskBe proactive.Monitor earlier assumptions.Monitor changes in organizational risk tolerance over the course ofthe project.Watch for risk triggers and risk symptoms.Implement responses, as needed, from your risk management plan.Evaluate the effectiveness of the response and modify as needed.Document what you do.Reidentify and reassess risks again.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-26

    QualityQuality assurance (QA) includes all the activities and proceduresundertaken to ensure that quality is achieved.

    What are the steps to performing a QA?What characteristics should each QA activity include?What are the most common QA tools?

    Quality control (QC) includes all the activities and proceduresneeded to analyze performance and identify and recommendchanges.

    What are the steps to QC?What are the most common QC tools?

    Quality is planned into a project, not inspected in.

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 355.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-27

    Developing the Project Team"A project team is a group with complementary skills, a common purpose,shared goals, and mutual accountability who share responsibility foraccomplishing project goals and who report to the project manager."1

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-28

    Characteristics of an Effective TeamRight sizeCommon purposeCommon approachComplementary skillsClear set of objectivesMutually accountable

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-29

    Acquiring Project Team MembersPreassignment by senior managementSelected by project manager via negotiation

    Experience and skillsInterestPersonal traitsAvailabilityProductivityWork styleAbility to work with others in a team environment

    Buy/outsource

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-30

    Project Team StructuresMirror imageSpecialtyDirectiveSelf-managed

    With todays technology, virtual teams can easily incorporate theseteam structures.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-31

    Virtual Teams

    In virtual teams, communication is critical. Set aside the time toestablish

    Clear expectationsProtocols for resolving conflictDecision-making proceduresClear communication links and channels

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-32

    Types of Teams

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-33

    How to Form a Successful TeamDefine roles and responsibilities for the project manager and theteam members.Delegate and share project management responsibilities.Anticipate and constructively channel conflict.Communicate the project scope and its alignment with businessobjectives.Allow and encourage diversity.Work toward satisfying closure on project tasks.Motivate the team and support team identity.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-34

    Managing the Project TeamDuring development of the product/system, the project managermust monitor and support the team.

    Hold regular meetings with the team to identify and resolve anydevelopment problems.Ensure that the team is developing the product/system according tothe client's business requirements and the design specifications.Provide the team with supplemental resources, if necessary, tokeep the project on track.Manage conflicts.Reward team members.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-35

    Managing Stakeholder Expectations andEngagements

    Building and maintaining a relationship with stakeholders to satisfy theirneeds and to be prepared to address project issues as they occur.Managing expectations

    Is anticipating the stakeholders reaction to any component of theprojectIncreases the probability of project successDecreases the risk that the project will fail to meet goals andobjectivesIs the responsibility of the project manager

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-36

    Techniques for Managing ExpectationsInterpersonal Skills Management Skills

    Active listeningCommunication skillsEmpathyConflict resolutionTrust buildingCoaching others throughchangeCritical thinking

    Negotiation skillsPresentation skillsFacilitation skillsProblem solvingDecision makingWriting skillsPublic speaking

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 460.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-37

    Transition to Customer Acceptance"Determining the correctness of the final product, system, or systemcomponent with respect to the users requirements."1

    This means askingDid you do what you said you were going to do?Did you gain agreement on the scope activities anddeliverables having been completed?

    Two stepsDialogue with your team and check the WBS.Dialogue with the customer.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-38

    From Implementation to Closeout

    Tools used (*key project management documents):Project Status Summary Report*Change Request*

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-39

    Key MessagesMonitoring and controlling is ongoing and used by the team;evaluating is periodic and used by senior management.EVM and trend variance analysis shows the project manager thedifference between what was planned and what has occurred at acertain point in time.Performance reports should be prepared differently for differentaudiences.Risk response plans can be used to manage risks once they occur.Change can be managed with a well-designed change managementsystem.The project manager must develop, manage, and support theproject team for it to perform well.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-40

    Key Messages (continued)Conflict is inevitable and must be managed.Validate scope against agreed-upon requirements.The probability of project success increases when activelymanaging stakeholders expectations.Open lines of communication and good interpersonal skills arebeneficial in managing stakeholders expectations.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-41

    Next Steps: Action PlanHow can you apply what you learned in this module to your workenvironment?

    Turn to the Action Plan tab and find the worksheet for this module.Develop a list of actions to complete when you return to work.For each action (what), identify

    Who needs to be involvedWhen you anticipate completing the action

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 4

    4-42

    Next Steps: Action Plan (continued)Take a few minutes to think about what you have learned duringclass and review the questions below.

    Recall a recent project in which conflict was not dealt with efficiently.What were the ramifications to the project?Given the same situation and what you have just learned, howwould you handle the conflict?What type of team structure does your organization generally use?Is it effective?What can you do to strengthen or enhance it?How would a customers experience be changed if stakeholderexpectations were managed from the beginning of a project?What type of performance reporting do you currently do? Whatmight you do differently in the future?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-1

    Project Closeout

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-2

    ObjectivesBy the end of this module, you will be able to

    Identify key tasks required for proper project or phase closeoutExplain the importance of documenting and communicating lessonslearned for the project

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-3

    The Project Life Cycle

    Closeout PhaseObtain final customer acceptance.Provide the customer with relevant project information.Recognize, reward, and reassign project team members.Terminate outstanding purchase orders from subcontractors.Prepare the final payment.Dispose materials and supplies.Prepare final cost and schedule reports.Document lessons learned.Celebrate project successes.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-4

    Closing Out a Project or PhaseThe process of finalizing all activities across all phases of the projectmanagement process groups to formally complete the project or phase

    Tool: Project Closeout ChecklistTool: Closeout Procedures

  • 1 Ward, J. LeRoy. Dictionary of Project Management Terms. 3rd ed. Arlington, Va.: ESI International, 2008, p. 113.

    ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-5

    Getting Customer AcceptanceDocumented sign-off by the customer that all project deliverables satisfyrequirements.1

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-6

    Guidelines for Project CloseoutEnsure that the project Closeout phase is formally acknowledged onthe project schedule.Review the closeout steps listed in the WBS for previous projects.Prepare a detailed closeout plan (plan for closeout in the WBS).Continue to preserve the team's identity by stressing the importanceof its efforts.Continue to conduct periodic status meetings until all projectactivities have been completed.Visit remote sites if the project team is physically dispersed.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-7

    Guidelines for Project Closeout (continued)Provide performance feedback to functional managers for all teammembers.Schedule a formal closeout review or project audit.Review and document lessons learned to help improve performanceon future projects.Prepare a final project report and communicate it to stakeholders.Use a project closeout checklist.Celebrate success.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-8

    Project Closeout IssuesProject TeamLoss of interest in remaining tasksFear of no future workDissatisfaction with next assignmentLoss of project-derived motivationLoss of team identityDiversion of effortReassignment of personnel

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-9

    Project Closeout IssuesClient/CustomerChange in attitudeLoss of interest in projectChanges in personnel assigned to projectUnavailability of key personnelUp-to-date documentationResistance to solution ownershipResistance to changeScope creepKnowledge transfer

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-10

    Procurement and Project or Phase CloseoutProcurement Closeout

    Make sure all contracts have beensatisfied and vendors have beenpaid.Collect, and have available forreview, product/systemdocumentation, contractdocumentation, and other projectrecords.Archive contract documentation.

    Project or Phase CloseoutPrepare project andcontract closeoutdocumentation:

    Lessons learnedFinal project reportProcurement audit

    Archive projectdocumentation.

    Tool: Final Project Report Outline

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-11

    Lessons LearnedWhat did we learn on this project so that the next project will runmore smoothly?

    TimelyRelevantIn contextDetailedFiled and accessible

    Tool: Lessons Learned

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-12

    People-Oriented Closeout ActivitiesSite/equipment/materials closeoutPersonal closeoutPublic relations closeoutProject team closeoutCelebration

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-13

    Closeout

    Tools used (*key project management documents):Project Closeout ChecklistCloseout Procedures*Lessons Learned*Final Project Report Outline

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-14

    Key MessagesPlan for closeout of the WBS and schedule.Procurement and project or phase closeout ensure that all projectrequirements are met.Lessons learned impart valuable knowledge to your organization foruse in future work.Close out with the team, stakeholders, and yourself, including theappropriate recognition and celebration of your efforts.

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-15

    Next Steps: Action PlanHow can you apply what you learned in this module to your workenvironment?

    Turn to the Action Plan tab and find the worksheet for this module.Develop a list of actions to complete when you return to work.For each action (what), identify

    Who needs to be involvedWhen you anticipate completing the action

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-16

    Next Steps: Action Plan (continued)Take a few minutes to think about what you have learned duringclass and review the questions below.

    Does your organization typically plan closeout into projects?Why is it important to plan for closeout?How can you improve your scope verification and customeracceptance?How well does your organization document and share lessonslearned?Is it effective?What can you do to strengthen or enhance it?

  • ESI International PMC:CPM:EN:000 ver. 2.0

    Module 5

    5-17

    MyESI and the learning ModelMyESI is the ESI online training portal.

    https://esi-intl.com/myesiView your course history, print a transcript, andregister for new courses.

    Through MyESI you can accessPrecourse activities (available upon registration), which include thebest practices survey, knowledge assessment, and focus questionsPostcourse resources and activities, which include

    Course-specific action and development plans and coursetools and templates, which are available the day classconcludesThe best practices survey, knowledge assessment, andtargeted online review content, which are generally available45 days after the class concludes