pm685 - kwon
TRANSCRIPT
A Study on Calculating the Optimal Contingency and Management Reserves for Project Budget
( 프로젝트 예산 편성을 위한 적정 예비비 산정에 관한 연구 )
Kwon, HyukChun CPA / PMP
November 27th,2009
The Project’s Success leads to Business Success.
2
Problem Background
Experiences Theory
KnowledgeSkills
TechniquesTools
Application
Business
The Application of Knowledge, Skills, Tools and Techniques to Project Activities to meet Requirement.
UAA MSPM
Background
Personal
Project Management?
3
Project Management
Project Triple Constraints
Scope, Time, Cost
Background
Project Cost Management
Plan Do Check Act
Budget Expense Variance Cost
Estimate,Predict Spend fund Budget – Actual
Expense Sum of Expense
Project
Temporary, Unique
4
BudgetBackground
Why Accurate Budget ?
• Budget > Cost
Surplus Fund
Loss Business Opportunities
• Budget < Cost
Lack of Fund
• Stop Project • Add more
Fund
Impact Financing Plan
Estimate, Predict the Budget What a Project will Cost.
5
Budget / Cost
Project
Scope
Work Package
Activity
Specification(Quality)
ResourcesQuantities/
Time
˟ Unit Price = Budget
Budget : The Sum of Resources Monetary Value
• Budget : Plan, Estimate, Predict• Cost : Sum of Expenses, Result
∑
Background
WBS
6
The Factors to Change the Budget
ItemsRisk/
Opportu-nity
CausesTo change Risk Type Type of
Budget
Scope(WBS)
Work Pack-age
(Activities)
Increase/Decrease
Uncertainty(Risk)
NotIdentified
Manage-ment Re-
serve
IdentifiedContin-
gency Re-serve
Resource
Specifica-tion
(Quality)Low/High Error/
Mistake Known
Point Esti-mate
(Allowance)Quantities Lack/Surplus Error/Mistake Known
Unit Price High/Low Inflation/Deflation Known
Background
7
The Study Approach
Theory Literature Review Survey Study
Net Cost ○ ○ ○ ●
Point Esti-mate
(Allowance)○ ○ ○ ●
Contingency Reserve ○
○ ○
●
Management Reserve ○ ●
MSPM,PMBOK Case Study
NASA Cost Hand-bookDr. Stephen BookOthers
59 Respondents in Korea
Apply the theory thru Case Study
Background
8
Theory
UAA, MSPM
PMBOK Guide, Text Book, Case Study
Theory
9
The Factors to affect Project Risk
Stakeholders
Team Members
* InternalProject Boundary
* ExternalUncertainty (Known, Unknown, Identified, Not Identified)
Project
Environment
Human Resources
Theory
10
Internal Factors – Human Resource
* Stakeholder’s Risk Tolerance
* Team Member’s
• Experience Level
• Required Skill (Tech, Leadership, Communication …)
• Knowledge, Competency, Ability
→ Refer to NASA Cost Estimating Hand Book Volume 4
High
Median
Low
Low Median High
Probability
Impact
Risk Tolerance Line
Theory
11
Resources
Time
Budget with Risk
Time Management
Scope(WBS)
Resource Management
Cost Management
Budget without Risk
Scope without Risk(Scope Management)
Risk Management
Scope with Risk
TheoryCost /Time / Scope / Risk
12
Risk / Budget
Outcomes ($)
Knowns Unknowns
Process
(%)
KnownKnown Knowns(Experience, Education)
Known UnknownsProject Risk Management
Unknown
Unknown Knowns(Laziness, Mistakes, Errors, No Project Management)
Unknown UnknownsProject Novelty Management
PMI Global Congress North America 2007
Theory
(Net Cost) (Contingency Reserve)
(Allowance) (Management Reserve)
(Point Estimate)
13
TheoryBudget
Resources
Time
Net Cost (Known Knowns)
Budget Base Line
Total Project Budget
Point Estimate
Allowance (Unknown Knowns) Contingency Reserve (Known Unknowns)
Management Reserve(Unknown Unknowns)
Uncertainty(Risk)
14
From PMBOK Guide, page 170
Management Reserve
TheoryContingency & Management Reserve
ContingencyReserve included
15
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Monitor & Control Risks
Risk Management Plan
Risk List / Description
Risk Description / Probability / Impact Matrix
Risk Description / Probability / Impact / Amount
Risk Resister(Updates)• Budget & Schedule activity for Responses• Contingency Reserve
Planning Process
Estimate Costs
Contingency Reserve ProcessTheory
• PMBOK Guide, Risk Management Process
16
Management Reserve Process
Estimate Costs
Determine Budget
Control Costs
Risk Resister• Budget & Schedule
activity for Responses• Contingency Reserve
EVM(Earned Value Management)
Basis of Estimates
Cost Performance BaselineProject Funding Requirement• Management Reserve
Planning Process
Scope Baseline
Project Schedule
Human Resource Plan
Theory
• PMBOK Guide, Cost Management Process
17
Literature Review
• NASA Cost Handbook 2008
• Dr. Stephen Book
- Allocating “Risk Dollars” back to Individual Cost Elements
• Paul Garvey
- Cost Risk Analysis without Statistics
• Michael W. Newell, Marina N. Grashina
- The Project Management Question and Answer Book
• Dr. Prasanta Kumar Dey
- A Combined Analytic Hierarchy Process and Decision Tree Approach
• Others
LiteratureReview
18
Decision Making Tools
Solution Approach/Methods/Techniques LiteratureReview
■ Three Points Estimate
AHP(Analytic Hierarchy Process) / Ph. D Thomas L. Saaty HDP (Hierarchical Decision Process) Ph. D Jang W. Ra
■ Normal Distribution @risk, Crystal Ball
■ Decision Tree Analysis
■ Confident Level
19
Three Points Estimate
Base Estimate or Point Estimate Cost.*
The total cost of a project, where Cost (BE) is the sum of the cost element costs summed across the system’s Work Breakdown Structure(WBS) without any adjustment for Risk/Uncertainty ;
Probability
Cost
Three Point Estimate
Cost Account(Work-package)
Point Estimate(Most likely)
Low High
Budget
* Cost Risk Analysis Without Statistics. - Paul R. Garvey
LiteratureReview
Reserves ?
20
AHP(Analytic Hierarchy Process) / HDP (Hierarchical Decision Process)
Three basic principles of the AHP/HDP
• Hierarchical Representation and Decomposition
• Priority Discrimination and Synthesis
(Pair-wise comparison)
• Logical Consistency
LiteratureReview
21
AHP/HDP
ExampleHigh-Volume Coil Winding ma-
chine
Net present worth
Safety Future ca-pability
Manage-ment Re-quirement
Upgrade existingMachine
New semiauto-matic
Machine
Fully automaticMachine
Goal
Criterion/ Factors
Alternatives
LiteratureReview
22
Net : Safety = 3:1Net : future = 6:1Net : Mgmt = 7:1Safety: Fut = 5:1Safety:Mgmt = 2:1Fut : Mgmt = 1:3
Coil Winding machine
Net Safety Future Mgmt
Upgrade New Fully automatic
AHP/HDP LiteratureReview
23
Normal Distribution @risk, Crystal Ball
Monte Carlo Simulation
LiteratureReview
24
• Incorporate the cost of each choice, the probabilities of each
possible scenario , and rewards of each alternative logical path.
• EMV(Expected Monetary Value)
Decision Tree Analysis LiteratureReview
25
Confidence Level
• Appropriate level of Confidence
• Cover Unidentified Risk, Residual Risks, and Secondary Risks
• Consider Risk Dollar amount beyond Budget Baseline
• Executable within the Level of Confidence
• Lessons learned : Historical Data, Performance
LiteratureReview
26
2008 NASA Cost Estimating Handbook LiteratureReview
Table of Contents
Volume 1 Cost Estimating Volume 2 Cost Risk
Volume 3 Economic and Supporting Analysis Volume 4 NASA Cost Estimator Career Development Guide
Volume 5 Knowledge Management
Volume 6 Reference
27
Cost Risk Approaches
Step 1. Generate / Obtain Point Estimate
Step 2. Quantify Cost Estimating Uncertainty
Step 3. Quantify Technical Risk
Step 4. Quantify Correlation
Step 5. Run Simulation
Step 6. Assess Risk Dollars/ Unallocated Future Expense
Step 7. Allocate Risk Dollars to the WBS
• Analytic Approach
• Simulation Approach
• Hybrid Scenario Based Approach
• Integrated Risk Management
LiteratureReview
28
Unallocated Future Expense(UFE)
• Held by the Project to be allocated to WBS
• Held by the Program(Mission Directorate):
Probability
CostPoint Estimate or Sum of Most likely WBS Element Costs
Confident level 70%
Unallocated Future Expense(UFE)
Unallocated Future Expense (UFE):
The Difference between the Confidence Level Amount and the Funded Amount.
LiteratureReview
Contingency Reserve
Management Reserve
Budget Baseline Estimated total Budget
29
Allocating “Risk Dollars” Back to Individual Cost Elements – Stephen A. Book
Merge WBS-Element Cost DistributionWBS-Element Triangular
Cost Distribution
+
+
+
Most likely
Most Likely Total CostProbability
CostPoint Estimate or Sum of Most likely WBS Element Costs
Confident Level (70%)
UFE
A.
B.
C.
To be allocated in proportion to their Riskiness.
LiteratureReview
30
Summary of Literature ReviewLiteratureReview
WBS Elements
Tree Point Estimate
Define Point Estimate
Calculate Needs
Define Confident Level
Allocate Risk Dollars
• More Cost Risk, More Risk Dollar
• More Uncertainty, Wider Range of Cost
Distribution
• Allocation method
- Confident level
- Standard Deviation
- Risk Response Plan
To be allocated in proportion to their Riskiness.
31
ContingencyReserve
ManagementReserve
Risks Identified Not Identified
Budget Base line Included Not Included
Approval to use From Project Manager From Program Man-ager
When used No Change the Budget Baseline
Change the Budget Baseline
LiteratureReview
Summary of Literature Review
32
NASA Cost Estimator Career Development Guide.
Responsible : The NASA Office of Human Capital Management
Table of Contents
Cost Estimator Career Development Philosophy Leadership Development Philosophy Minimum Actions to Ensure Effective Career Development Career Directions and General Career paths General and Technical Competencies Attitude Training and Development Experiences Certification and Continuing Professional Education Individual Development Planning
LiteratureReview
33
Survey Result
10 Questionnaires
• What Reserves they use?
- Contingency Reserve or Management Reserve or both
• How to Calculate the Reserves Amount ? Open Survey (Thru PMPCafe)
59 Respondents
Survey
34
건설 , 중공업 , Plant (19)
IT, SI 등 Software 구축(29)
연구 개발 , 신제품 개발 (5)
업무 개선 (BPR, 조직개편 ,
업무 개선 )(6)
Total 59
Survey Result
Q1. Which Project Category do you handle ?
32%
49%
9%
10%
Survey
35
Survey Result Survey
Q 2. Do you estimate the Contingency Reserve and Management Reserve in your project budget?
별도로 각각 존재함 (0)
Contingency, Management Reserve 구분 없이 예비비 (Reserve) 있음 (40)
예비비 (Reserve) 없음 (19)
Total 59
68 %
32 %
36
Q 3. How to calculate the reserve amount in project budget?
전체 예산의 일정 비율 (%) (19)
Risk Response Plan( 리스크 대응 계획 ) 에 의한 방법 (14)
예비비 없음 (18)
상기 이외의 방법 (3)
무응답 (5)
5 %
Total 59
32 %
24 %
31 %
8 % • Under 5% : 7• 10 ~15% : 9• 16~30% : 3
Survey Result Survey
37
Survey Result
Q 4. Have you done your project within the budget including reserves?
항상 전체 예산 ( 예비비포함 ) 초과 함 (14)
예비비를 사용하나 전체 예산 범위내에서 완료 함(26)
예비비를 사용하지 않고 완료함 (19)
Total 59
24 %
44 %
32 %
Survey
38
Survey Summary
No Cases to use both Contingency and Management Reserve.
Use Management Reserve only
Use Three Point Estimate ? - Never Use 63% (37/59) - Occasionally use 37% (22/59)
Use Monte Carlos Simulation (Crystal Ball or @Risk) ? - Never use 86% (51/59) - Occasionally use 14% (8/59)
Survey
39
Case Study
“ Construction Project for Production Base in Vietnam”
Case Study
Developed by D Construction Co. Ltd.
40
WBS
Project
PM
Civil Works
Architecture Works
Mechanical Works
ElectricalWorks
# 1. On-Shore
Works
# 2. Off-Shore
Works
# 3.Power Plant
# 4.Utilities
House
# 5. Main Office
# 6. Facilities
# 7. Machines
# 8. Electric
Equipments
# 9 Cabling
Omit PM for easy calculation of the budget
Case Study
PM
41
Work Package L M H MEAN Weighted avg
#1 191 380 1151 574 477
#2 96 192 582 290 241
#3 33 76 143 84 80
#4 9 18 27 18 18
#5 77 154 465 232 193
#6 30 58 86 58 58
#7 11 22 66 33 27.5
#8 58 120 182 120 120
#9 120 230 691 347 288.5
Sum 1,250 1,756 1,503
• Assumption : Base Estimate Cost 1,250 does not include contingency (but include technical/commercial allowances)• MEAN = (L+M+H)/3, Weighted avg= (L+4*M+H)/6
Example : “Case Study” Project
Case Study - Select Base Estimated Cost Case Study
42
@RiskStatistics
Output value
Trial 1,000
MEAN 1,756(52.5%)
Median 1,741(50.0%)
Base Esti-mate
1,250(2.22%)
Weight avg 1,503(19.0%)
Minimum 1,089
Maximum 2,694
Select Base Estimated Cost Case Study
43
Risk Register Case Study
44
Risk category
Pri-or-ity
(Weight
)
RisksLo-cal%
Global
%
Techni-cal
47
Scope change
36 17
Materi-als
12 6
. . .
Fi-nance& eco-nomic
23
Inflation 38 9
Fund 15 3
. . .
Organi-zation
15
Capa. 44 7
Vendor capabil-ity
23 3
. . .
Market 6Market share
57 3
. . . .
Total 100 100
Pro. %
Cri-terion
Al-ter-na-
tives
Cost/Im-pact
EMV
25
a A450
-
b B380
-
c C320
80
37
a
D220
-b
E190
70c
9
a H670
60
b I740
c J690
100% 1,352
% WP
Con-tin-
gencyre-
serve
# 1
28.0
# 2
32.4
# 3
16.8
# 4
12.0
# 5
59.8
# 6
26.6
# 7
14.7
# 8
15.0
# 9
54.7
29
a
F250
b
G172
50c
260 260.0
#1
#2
#3
#4
19.2%
Allocation of the Contingency Reserve Case Study
45
Calculate total amount of identified Risk dollars required.
Analysis the Risk Probability and Impact
Risk Risk Response EMVAssigned
WP
Risk #1, 4,,5
Response #1 80
# 1
# 4
# 5
Risk #2,6,7 Response #2 70
# 2
# 3
# 6
# 7
Risk #3,8 Response # 3 50# 2
# 9
Risk #9,10 Response #4 60
# 5
# 8
# 9
Total 260
WP : Work Package
Calculate Cost by Decision tree and HDP method
Case Study
46
Risk Response CostAssigned
WPWeight
Allocated AmountOf Cost
Response #1 80
# 1 35% 28
# 4 15% 12
# 5 50% 40
Response #2 70
# 2 17% 11.9
# 3 24% 16.8
# 6 38% 26.6
# 7 21% 14.7
Response # 3 50# 2 41% 20.5
# 9 59% 29.5
Response #4 60
# 5 33% 19.8
# 8 25% 15
# 9 42% 25.2
Total 260 260
Define a WBS-elements “Need”
Calculate allocated amount by Decision tree and HDP method
Case Study
47
Allocate Risk dollars to WBS-Elements
WP #1
WP#2
WP #3
WP #4
WP #5
WP #6
WP #7
WP #8
WP #9 Total
28 32.4 16.8 12 59.8 26.6 14.7 15 54.7 260
Allocated Risk dollars amount to Work-Packages
Budget Base Line
Base Estimate 1,250 (2.22%)
Contingence Reserve + 260
Budget Base Line 1,510 ( 19.6%)
Case Study
48
WPBase Esti-mate
Contin-gency Re-
serveTotal
# 1 380 28 408
# 2 192 32.4 224.4
# 3 76 16.8 92.8
# 4 18 12 30
# 5 154 59.8 213.8
# 6 58 26.6 84.6
# 7 22 14.7 36.7
# 8 120 15 135
# 9 230 54.7 284.7
sums 1,250 260 1,51
0
Percentile(Confidence
level)
Cost Value
5% 1,362
10% 1,405
20% 1,512
30% 1,600
40% 1,672
50% 1,741
60% 1,817
70% 1,899
80% 1,979
90% 2,114
Contingency Reserve of WBS-Element
(19.6%)
Allocate Risk dollars to WBS-Elements
WP : Work Package
Case Study
49
Define Management Reserve At Confidence level.
Percentile(Confidence level)
Cost Value
5% 1,362
10% 1,405
20% 1,512
30% 1,600
40% 1,672
50% 1,741
60% 1,817
70% 1,899
80% 1,979
90% 2,114
50% is the Confidence level of this project.
Case Study
50
Management Reserve
Risk dollar amount at Confidence level – (Base Estimate + Contingence Reserve)
Determine Management Reserve
50% is the Confidence level : $ 1,741
$ 1,741 - $ 1,510 = $ 231 (15.3 % of the Budget Base line)
Case Study
51
@RiskStatistics
Output value
Trial 1,000
MEAN 1,756(52.5%)
Median 1,741(50.0%)
Base Estimate 1,250(2.22%)
Budget Baseline(incl. Contin-
gency reserve)1,510(19.6%)
Total budget(incl. Manage-ment reserve)
1,741(50.0%)
Weight avg 1,503(19.0%)
Minimum 1,089
Maximum 2,694Base Estimate Budget Baseline Total budget
Contingency Reserve
Management Reserve
Summary Case Study
52
C/A Base Estimate Contingency Reserve Total
# 1 380 28 408
# 2 192 32.4 224.4
# 3 76 16.8 92.8
# 4 18 12 30
# 5 154 59.8 213.8
# 6 58 26.6 84.6
# 7 22 14.7 36.7
# 8 120 15 135
# 9 230 54.7 284.7
Budget Base-line
1,250 260 1,510
Management Reserve (15.3%)
231
Total Esti-mated Budget
1,741
Case Study Summary
53
Conclusions / Recommendations
Move from Deterministic Point Estimates to Probabilistic Estimates.
Generate a Point Estimate
Budget based upon a Quantification of all the Risks.
Define Confidence Level
Allocate Risk Dollars as Reserves
Develop Human Resource Management
Conclusion
54
Thank You!
Q & A
UAA MSPM Hyukchun Kwon, CPA/PMP