pmp cross-cutting skills have been updated in the pmp exam · pdf file ·...

38
IILCERT5 Project Stakeholder Management The Project Management Cer;ficate Program 1 ©2014 Interna;onal Ins;tute for Learning, Inc. PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam is changing in 2016. Download the new Exam Content Outline to study cross-cutting skills here: http://www.brainshark.com/pmiorg/2015PMPExamChange

Upload: docong

Post on 25-Mar-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

1  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab).

Learn about why the PMP exam is changing in 2016.

Download the new Exam Content Outline to study cross-cutting skills here:http://www.brainshark.com/pmiorg/2015PMPExamChange

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

2  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

3  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Review  these  learning  objec;ves  carefully.      

The  learning  content  contained  within  this  module  is  based  on  these  learning  objec;ves.  

At  the  end  of  this  module  or  the  end  of  the  course,  you  should  be  able  to  answer  quiz  or  test  ques;ons  related  to  these  learning  objec;ves.    

If  you  are  par;cipa;ng  in  this  course  for  cer;fica;on,  you  will  be  beQer  prepared  to  pass  a  cer;fica;on  exam  by  recalling  these  learning  objec;ves.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

4  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Project  Stakeholder  Management  includes  the  processes  required  to  iden;fy  all  people  or  organiza;ons  impacted  by  the  project,  analyzing  stakeholder  expecta;ons  and  impact  on  the  project  and  developing  appropriate  management  strategies  for  effec;vely  engaging  stakeholders  in  project  decisions  and  execu;on.  

PMBOK®  Guide  –  FiWh  Edi;on,  Glossary  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

5  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  describes  the  key  benefit  of  this  process  as  “enabling  iden;fica;on  of  the  appropriate  focus  for  stakeholders.”  

PMBOK  Guide®  -­‐  FiWh  Edi;on,  p.  393  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

6  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  defines  the  following  for  this  first    Project  Stakeholder    Management  process:  

•  Inputs  

―  Project  charter  ―  Procurement  documents  

―  Enterprise  environmental  factors  

―  Organiza;onal  process  assets  •  Tools  &  Techniques  

―  Stakeholder  analysis  ―  Expert  judgment  ―  Mee;ngs  

•  Outputs  

―  Stakeholder  register    

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

7  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: While  the  project  charter’s  primary  objec;ve  is  to  authorize  the  project,  authorize  the  project  manager,  and  to  authorize  the  project  manager  to  expend  resources  on  behalf  of  the  project,  it  may  also  include  some  of  the  key  stakeholders  involved  in  the  project  such  as:  

•  Execu;ves  •  Clients  •  Team  members  

Procuring  services,  personnel  and  materials  from  outside  the  organiza;on  adds  a  number  of  new  stakeholders  to  the  project.  These  can  include  a  general  contractor,  foreman,  workers,  tradesmen,  lawyers,  etc.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

8  

Iden;fying  stakeholders  begins  with  collec;ng  informa;on  about  who  the  project  stakeholders  might  be  and  then  collec;ng  informa;on  that  will  assist  with  analyzing  how  stakeholders  might  impact  the    project.  These  stakeholders  include  decision  makers,  anyone  affected  by  the  project,  and  others  that  may  have  a  role  to  play  on  your  project.  Next,  it  is  important  to  iden;fy  the  impact  or  support  that  could  be  given  by  each  stakeholder.  You  will  begin  to  understand  how  each  stakeholder  might  respond  to  various  s;muli  within  the  project  environment.  

We  will  explore  a  couple  classifica;on  models  that  can  be  used  for  stakeholder  analysis.  These  modes  are  the  Power/Interest  grid  and  the  Salience  model.  Your  instructor  may  wish  to  describe  other  models…;me  permihng.  

It  is  important  to  iden;fy  all  your  stakeholders.  Missing  a  stakeholder  means  missing  poten;al  requirements.  Therefore  you  should  talk  to  as  many  people  as  possible  to  insure  you  iden;fy  all  the  stakeholders.  

Other  tools  you  can  use  to  iden;fy  stakeholders  include  brainstorming  and  networking.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

9  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: •  Step  1:  Iden/fy  poten/al  stakeholders  and  associated  informa;on  (e.g.,  role,  department,  interests,  knowledge  level,  expecta;ons,  influence.  

•  Step  2:  Iden/fy  poten/al  impact  or  support  stakeholders  could  generate,  and  classify  them  to  help  define  an  approach  strategy.  

•  Step  3:  Assess  poten;al  stakeholder  reac;ons  to  use  in  developing  a  plan  for  influencing  them  and  elici;ng  their  support.  

The  informa;on  needs  of  the  various  stakeholders  should  be  analyzed  to  develop  a  methodical  and  logical  view  of  their  informa;on  needs  and  sources  to  meet  those  needs.  The  analysis  should  consider  methods  and  technologies  suited  to  the  project  that  will  provide  the  informa;on  needed.  Care  should  be  taken  to  avoid  was;ng  resources  on  unnecessary  informa;on.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

10  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Iden;fying  stakeholders  begins  with  iden;fying  individual  and  groups  of  stakeholders.  Wri;ng  stakeholder  names  or  groups  on  Post-­‐It  notes  is  a  convenient  way  to  place  them  on  the  Power/Interest  Grid.  You  may  want  to  also  include  the  classifica;on  from  the  Stakeholder  Engagement    Assessment  Matrix  men;oned  in  the  next  sec;on.    This  kind  of  analysis  facilitates  traceability  with  requirements  and  deliverables.  Understanding  who  provided  a  requirement  and  where  they  sit  on  this  grid,  can  help  you  when  a  change  in  scope  or  a  priori;za;on  of  requirements  is  ini;ated.  It  also  is  useful  when  planning  how  to  manage  stakeholder  ahtudes.  For  instance,  if  you  have  a  stakeholder  in  the  high  power,  high  concern  area  who  is    resistant,  you  may  need  to  begin  building  a  rela;onship.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

11  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  intent  of  the  model  is  to  allow  the  “project  manager”  to  decide  upon  the  rela;ve  salience  of  a  stakeholder,  which  is  “the  degree  to  which  managers  give  priority  to  compe;ng  stakeholder’s  claims”  or  expecta;ons.  

Salience  Model,  by  Puneet  Kuthiala,  PMP,  published  in  JustPM  Blog,  October  8,  2009  

Each  circle  has  a  unique  label:  “Power,”  “Urgency,”  or  “Legi;macy.”  Power  is  the  ability  to  impose  one’s  will,  i.e.  the  ability  of  the  stakeholder  to  influence  the  organiza;on;  Urgency  is  the  ability  to  command  aQen;on,  because  of  the  cri;cality  and  ;me-­‐sensi;vity  of  the  requirements  being  set  for  by  the  stakeholder  for  the  organiza;on;  Legi;macy  is  the  “right”  one  has  to  be  involved  –  the  legi;macy  of  the  rela;onship  and  ac;ons  of  the  stakeholder  with  the  organiza;on  in  terms  of  desirability,  properness  or  appropriateness.    

Adapted  from  hQp://www.12manage.com/methods_stakeholder_mapping.html  

Each  circle  includes  four  numeric  values  that  represent  different  salient  (the  degree  to  which  managers  give  priority  to  compe;ng  stakeholder’s  claims)  classifica;ons,  and  of  the  four,  one  is  unique  to  each  circle.    

 

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

12  

Classifica;on  1  indicates  a  Dormant  Stakeholder  who  has  the  ability  to  impose  their  will,  but  they  have  neither  the  ability  to  command  aQen;on  nor  “right”  to  be  involved  

Classifica;on  2  for  a  Discre;onary  Stakeholder  has  neither  the  ability  to  impose  their  will  nor  the  ability  to  command  aQen;on,  but  they  do  have  “right”  to  be  involved  

Classifica;on  3  that  is  for  a  Demanding  Stakeholder  does  not  have  ability  to  impose  their  will  nor  the  “right”  to  be  involved,  but  they  have  ability  to  command  aQen;on  

Classifica;on  4  is  a  Dominant  Stakeholder  has  the  ability  to  impose  their  will  and  the  “right”  to  be  involved,  but  the  inability  to  command  aQen;on  

Classifica;on  5  is  for  a  Dangerous  Stakeholder  has  the  ability  to  impose  their  will  and  the  ability  to  command  aQen;on,  but  they  have  no  “right”  to  be  involved.  

Classifica;on  6  is  a  Dependent  Stakeholder  has  the  ability  to  command  aQen;on  and  the  “right”  to  be  involved,  but  an  inability  to  impose  their  will.    

Classifica;on  7  indicates  a  Defini;ve  Stakeholder  has  all  three:  the  ability  to  impose  their  will,  the  “right”  to  be  involved,  and  the  ability  to  command  aQen;on.    

You  can  have  number  8  outside  the  Venn  diagram  to  indicate  a  Non‑stakeholder,  if  needed.  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

13  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Stakeholder  Register-­‐A  project  document  including  the  iden;fica;on,  assessment,  and  classifica;on  of  project  stakeholders  The  stakeholder  register  is  a  living  document  that  lists  various  pieces  of  informa;on  about  stakeholders  that  will  be  used  during  the  life  of  the  project  to  manage  the  team’s  interac;ons  with  stakeholders.  This  informa;on  includes,  but  is  not  limited  to:  

•  Stakeholder  names  

•  Posi;on  •  Titles  and  roles  •  Expecta;ons  •  Influence  •  Drivers  •  How  they  are  classified  The  register  is  a  tool  to  aid  in  gaining  support  and  minimize  nega;ve  impacts  of  stakeholders  during  the  life  of  the  project.  

The  idea  behind  the  stakeholder  register  is  to  capture:  

•  Iden;fica;on  informa;on  

•  Assessment  informa;on  

•  Stakeholder  classifica;on  

Other  fields  that  you  may  want  to  have  in  a  stakeholder  register  include:  

•  Stakeholder  interest(s)  in  the  project  

•  Assessment  of  impact  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

14  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  describes  the  key  benefit  of  this  process  as  providing  “a  plan  to  engage  stakeholders  to  support  the  project’s  interests.”  

PMBOK  Guide®  –  FiWh  Edi;on,  p.  399  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

15  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  defines  the  following  for  this  second  Project  Stakeholder  Management  process:  

•  Inputs  

―  Project  management  plan  ―  Stakeholder  register  ―  Enterprise  environmental  factors  

―  Organiza;onal  process  assets  •  Tools  &  Techniques  

―  Expert  judgment  

―  Mee;ngs  ―  Analy;cal  techniques  

•  Outputs  

―  Stakeholder  management  plan  ―  Project  document  updates  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

16  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  project  management  plan  provides  much  of  the  informa;on  to  put  the  management  of  stakeholders  in  context.  The  project  management  plan  will  describe  the  lifecycle  used  and  this  can  point  to  stakeholders  that  need  to  be  involved.  The  project  management  plan  will  also  describe  the  work  to  be  done  and  how  it  will  be  done.  If  changes  are  requested,  the  project  management  plan  will  describe  how  they  are  to  be  processed.    Finally,  the  it  defines  how  communica;ons  between  stakeholders  will  be  handled.  

The  stakeholder  register  was  described  in  the  previous  process.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

17  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: A  stakeholder  engagement  matrix  is  used  to  map  stakeholder’s  current  level  of  engagement  and  their  desired  level  of  engagement.  Informa;on  from  this  matrix  is  used  when  planning  how  to  manage  stakeholder  engagement  throughout  the  project.    

Stakeholder  Engagement  Levels:  

Unaware:  Unaware  of  project  and  poten;al  impacts  

Resistant:  Resistant  to  the  project  

Neutral:  Not  Suppor;ve  or  Resistant  

Suppor2ve:  Suppor;ve  to  the  project  

Leading:  Takes  a  leadership  role  to    ensure  the  success  of  the  project  

Your  organiza;on  may  have  its  own  classifica;on  scheme  that  you  may  wish  to  use.  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

18  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Communica;on  with  stakeholders  begins  with  understanding  the  nature  of  the  stakeholder.  There  are  many  tools  for  characterizing  the  nature  of  individuals.  Myers  Briggs  Test,  DiSC  IV,  Personalysis,  and  Social  Styles  are  a  few  of  the  more  common  tools..  Analysis  of  a  stakeholder  and  his  communica;on  style  can  help  you  deliver  informa;on  in  a  way  that  the  stakeholder  can  best  process  and  accept  the  informa;on.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

19  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  Stakeholder  Management  Plan  is  part  of  the  progressively  elaborated  Project  Management  Plan.  The  stakeholder  management  plan  provides  the  necessary  background  to  intelligently  engage  the  project  stakeholders.  A  by-­‐product  of  the  process  of  building  the  Stakeholder  Management  Plan  may  lead  to  a  need  to  update  requirements  and  the  stakeholder  register,  schedule,  budget,  etc.  

   

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

20  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  describes  the  key  benefit  of  this  process  is  allowing  the  project  manager  “to  increase  support  and  minimize  resistance  from  stakeholders.”  

PMBOK  Guide®  -­‐  FiWh  Edi;on,  p.  404    Ac;vely  managing  stakeholder  expecta;ons  increases  the  likelihood  that  the  project  will  stay  on  track.    

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

21  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  defines  the  following  for  this  third  Project  Stakeholder  Management  process:  

•  Inputs  

―  Stakeholder  management  plan  ―  Communica;ons  management  plan  ―  Change  log  ―  Organiza;onal  process  assets  

•  Tools  &  Techniques  

―  Communica;on  methods  ―  Interpersonal  skills  ―  Management  skills  

•  Outputs  

―  Issue  log  ―  Change  requests  ―  Project  management  plan  updates  ―  Project  documents  updates  ―  Organiza;onal  process  assets  updates  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

22  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  communica;on  management  plan  is  an  excellent  example  of  where  parts  of  the  Project  Management  Plan  become  inputs  to  other  subsidiary  plans  to  the  plan.  The  communica;on  management  plan  directs  how  stakeholders  should  be  communicated  with,  the  informa;on  they  should  be  given,  the  proper  level  of  informa;on,  which  individuals  should  receive  the  informa;on,  and  how  escala;on  over  issues  should  take  place.  

Remember  that  any  changes  to  the  project  scope  should  be  communicated  to  the  appropriate  stakeholders.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

23  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  communica;on  plan  provides  informa;on  on  how  stakeholders  need  to  be  communicated  to.  This  may  include  mee;ngs,  conference  calls,  wriQen  means,  email,  collabora;on  tools,  etc.  We  will  discuss  the  communica;ons  management  plan  in  more  detail  in  a  later  lesson.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

24  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Trust,  as  described  in  the  American  Heritage  Dic/onary  is  “confidence  in  the  integrity,  ability,  character,  and  truth  of  a  person  or  thing.”  

Trust  is  the  genesis  of  leadership  and  is  built  by  every  ac;on,  every  ini;a;ve  and  every  word  of  the  project  manager.  Albert  Schweitzer,  the  humanitarian,  theologian,  missionary,  organist,  and  medical  doctor,  said,    “Example  is  not  the  main  thing  in  influencing  others,  it’s  the  only  thing.”    

Trust  works  both  ways.  If  you  are  in  a  leadership  posi;on,  trust  will  keep  you  there,  or  the  lack  of  trust  in  you  will  diminish  your  capabili;es  as  a  leader.      

A  good  moQo  is:  Trust  un;l  you  have  a  compelling  reason  to  mistrust.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

25  

One  of  the  best  ways  to  think  of  this  model  is  from  the  core    (inner  ring)  and  a  set  of  rela;onship-­‐based  skill  families  (central  core).    But  since  it  will  take  the  whole  module  to  get  there,  we  wanted  to  provide  a  brief  preview  of  it  here.  Let’s  keep  the  four  families  of  rela;onship  skills  “anchored”  while  we  look  out  through  the  project  lifecycle  (PLC)  layer,  which  can  be  “spun”  to  align  with  the  current  PLC  phase.  In  turn,  the  outer  circle  can  also  be  “spun”  so  that  each  family  of  skills  in  some  way  supports  every  combina;on  of  Stakeholder  category/PLC  phase.      However,  if  we  tried  to  cover  all  that  territory,  we  would  need  a  two-­‐week  workshop.  So,  in  our  model,  we  have  posi;oned  each  family  of  rela;onship  skills  opposite  the  major  categories  for  which  that  family  provides  the  most  effec;ve  solu;ons.  In  some  cases,  there  is  also  a  primary  PLC  phase,  e.g.,  we  see  the  Advocacy  family  of  skills  having  the  most  impact  with  Governing  Bodies,  especially  in  the  early  stages  or  Concept  phase.  That  does  not  mean  that  the  skills  that  we  describe  as  being  in  the  Advocacy  family  will  not  be  needed  for  other  combina;ons  of  stakeholder  category/PLC  phase,  but  that  the  par;cular  combina;on  we  have  iden;fied  will  be  used  to  demonstrate  the  skill,  in  what  we  think  is  the  most  effec;ve  scenario  for  prac;ce  and  successful  knowledge  transfer.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

26  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Dealing  with  stakeholders  takes  good  management  skills  to  bring  harmony,  agreement  and  coordina;on  to  bring  about  the  project’s  objec;ves.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

27  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  issue  log  (or  register)  can  minimize  the  impact  of  schedule,  cost  and  resource  issues  by  documen;ng  the  issue,  assessing  the  impact,  and  assigning  a  responsible  party  to  take  correc;ve  ac;ons.  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

28  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  describes  the  key  benefit  of  this  process    as  “efficiently  and  effec;vely  engaging  stakeholders  as  the  project  evolves.”  

PMBOK  Guide®  -­‐  FiWh  Edi;on,  p.  409  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

29  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: The  PMBOK®  Guide  –  FiWh  Edi;on  defines  the  following  for  this  fourth  Project  Stakeholder  Management  process:  

•  Inputs  

―  Project  management  plan  ―  Issue  log  ―  Work  performance  data  

―  Project  documents  •  Tools  &  Techniques  

―  Informa;on  management  ―  Expert  judgment  ―  Mee;ngs  

•  Outputs  

―  Work  performance  informa;on  ―  Change  requests  ―  Project  management  plan  updates  ―  Project  document  updates  ―  Organiza;onal  process  assets  updates  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

30  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

31  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

32  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

33  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Expert  judgment  extends  not  only  to  industry  and  project  knowledge,  but  how  to  accomplish  things  in  your  environment.  When  most  people  hear  the  word  “Poli;cs”  and  par;cularly  “Office  Poli;cs,”  they  conjure  up  nega;ve  thoughts  of  self-­‐interest  and  betrayals.  Instead,  try  to  think  of  organiza;onal  poli;cs  as  using  the  interpersonal  skills  you’ve  obtained  to  help  achieve  the  strategic  objec;ves  of  the  organiza;on.  This  is  a  worthwhile  and  noble  pursuit  and  will  keep  you  on  the  right  path.  

For  more  informa;on  on  the  topic,  see  Jeffrey  K.  Pinto’s  book  en;tled  POWER  &  POLITICS  in  Project  Management.  

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

34  

Stakeholder  mee;ngs  are  used  for:  •  Informa;on  sharing  

•  Planning/coordina;ng  

•  Problem  solving  

•  Decision  making  

•  Team  building  

Prior  to  a  stakeholder  mee;ng,  an  agenda  should  be  provided  to  all  aQendees,  especially  for  virtual  mee;ngs.    Be  sure  to  include:  

•  Name  of  mee;ng  

•  Loca;on  (if  virtual…provide  all  connec;on  informa;on)  

•  Time  (zone  if  necessary),  dura;on  and  date  

•  Objec;ve  to  be  reached  during  mee;ng  

•  Who  is  aQending  

•  Content  

If  the  mee;ng  is  offsite,  be  sure  to  provide  direc;ons  to  the  mee;ng  loca;on.  Send  and  collateral  material  that  is  needed,  including  suppor;ng  material  for  discussion.  

If  the  mee;ng  is  virtual,  have  aQendees  arrive  early  to  solve  connec;on  problems  and  avoid  interrup;ons  during  the  mee;ng.    

 

 

 

 

 

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

35  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes: Work  performance  informa;on  is  derived  from  the  data  that  is  collected  throughout  the  project.  While  data  is  just  the  raw  material  of  informa;on,  informa;on,  when  craWed  properly,  prevents  stakeholders  from  misinterpre;ng  the  data.  Informa;on  about  performance  is  focused  on  ensuring  that  stakeholders  correctly  understand  the  context  and  status  of  the  project  and  can  make  proper  decisions  concerning  the  project.  

Frequently,  in  the  execu;on  of  a  project,  it  is  learned  that  there  might  have  been  a  beQer  procedure  for  execu;ng  a  task  or  dealing  with  a  risk.  Feedback  from  stakeholders  and  the  outcome  of  lessons  learned  mee;ngs  should  be  recorded    by  upda;ng  any  of  the  project  documents  that  are  impacted.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

36  

RESPECT  STANDARDS  

We  inform  ourselves  about  the  norms  and  customs  of  others  and  avoid  engaging  in  behaviors  they  might  consider  disrespecNul.    

This  ethics  standard  goes  beyond  cultural  diversity.  It  requires  that  we  proac;vely  understand  the  customs  of  our  stakeholders  and  demonstrate  respecwul  behavior.    

We  approach  directly  those  persons  with  whom  we  have  a  conflict  or  disagreement.    

It  can  be  difficult  to  confront  colleagues  that  we  disagree  with.  Many  ;mes  people  gossip  behind  coworker’s  backs  rather  than  confront  a  disagreement  head  on.  However,  it  is  more  respecwul  to  work  with  the  person  we  have  a  disagreement  with  to  try  and  resolve  the  situa;on.    

We  conduct  ourselves  in  a  professional  manner,  even  when  it  is  not  reciprocated.    

One  of  the  most  challenging  situa;ons  we  find  ourselves  in  is  when  someone  is  behaving  poorly  or  being  cri;cal  of  our  work  or  our  decisions.  None  the  less,  we  should  hold  ourselves  to  a  higher  standard  and  demonstrate  professional  conduct  even  when  others  aren’t.  

We  do  not  act  in  an  abusive  manner  toward  others.    

Related  to  conduc;ng  our  selves  professionally,  we  must  never  behave  abusively  towards  others.  This  includes  not  being  disrespecwul,  openly  cri;cal  in  front  of  others,  or  rude.  

We  do  not  exercise  the  power  of  our  exper2se  or  posi2on  to  influence  the  decisions  or  ac2ons  of  others  in  order  to  benefit  personally  at  their  expense.    

Slide  54  discusses  the  various  types  of  power.  As  project  managers  we  oWen  have  expert  power  and  to  an  extent,  posi;on  power.  It  is  important  to  exercise  that  power  with  integrity  rather  than  to  benefit  personally.  

IIL-­‐CERT5  

Project  Stakeholder  Management  The  Project  Management  Cer;ficate  Program  

38  ©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

©2014  Interna;onal  Ins;tute  for  Learning,  Inc.  

Participant’s Notes:

IIL-­‐CERT5  

Project  Stakeholder  Management  

39  

The  Project  Management  Cer;ficate  Program