pmp exam preparation course: 11 project procurement management

24

Click here to load reader

Upload: b-m-shahrier-majumder-pmp

Post on 16-Apr-2017

2.188 views

Category:

Education


2 download

TRANSCRIPT

Page 1: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

B. M. Shahrier Majumder, PMPPMP® Exam Preparation

Page 2: PMP Exam Preparation Course: 11 Project Procurement Management

Project Procurement Management

Page 3: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Learning Objectives

Upon completion of this topic you will learn about

– The processes, activities and documentation items for Project Procurement Management

– Elements (and deliverables) for Project Procurement Management

– Tools and techniques of the key activities of the Project Procurement Management

3

Page 4: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Procurement Management

Includes the processes necessary to purchase or acquire products,

services or results needed from outside the project team.

4

Page 5: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Key Activities of Procurement Management

Plan Procurements: The process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers.

Conduct Procurements: The process of obtaining seller responses, selecting a seller, and awarding a contract.

Administer Procurements: The process of managing procurement relationship, monitoring contract performance, and making changes, and corrections as needed.

Close Procurements: The process of completing each project procurement.

5

Page 6: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements | Data Flow Diagram

Page 7: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements

Inputs Tools & Techniques Outputs

Scope baselineRequirement documentationTeaming agreementRisk registerRisk related contract decisionsActivity resource requirementsProject scheduleActivity cost estimatesCost performance baselineEnterprise environmental factorsOrganizational process assets

Make-or-buy analysisExpert judgmentContract types

Procurement management planProcurement statement of workMake-or-buy decisionsProcurement documentsSource selection criteriaChange requests

Page 8: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

• Make-or-buy Analysis

• Is a general management technique used to determine

whether particular work can be best be accomplished by the

project team or must be purchased from outside sources.

• Budget constrains may influence make-or-buy decisions.

• Example: You are trying to decide whether to lease or buy an item

for your project. The daily leas cost is $100. To purchase the item,

the investment cost is $1000 and daily cost is $20. How long will it

take for the leas cost to be the same as the purchase cost?

8

Page 9: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

• Answer

Let D equal the number of days when the purchase and leas cost are equal.$100D = $1000 + 20D$100D – 20D = $1000$80D = $1000D = 12.5This calculation helps a project manager decide whether it is better to lease or buy. The calculation says that the costs are the same after 12.5 days. Therefore, if you are planning to use the item for fewer than 12.5 days, you should lease. If you are planning to use it for more than 12.5 days, it would be cheaper to buy the item.

9

Page 10: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

• Contract Types

Mainly 3 categories of contract types:

• Fixed priced contract (FP)

• Cost reimbursable contract (CR)

• Time and material contract (T&M)

10

Page 11: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

Fixed Price Contract– Fixed Price Contract is inappropriate, if

• Seller may not have the details accounting records of past project activities required to accurately estimate future projects.

• Buyers may not have the expertise to prepare a complete procurement statement of work.

– If Statement of work is incomplete in FP• The seller is forced to accept a high level of risks• The seller would need to add a huge amount of services to

their price to cover their risks and the buyer, therefore, pays more than they might otherwise have

• The seller can more easily try to increase profits by cutting scope or claiming that work the buyer wants is outside the contract and thus requires a change.

11

Page 12: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

Fixed Price Contract– Fixed Price Incentive Fee (FPIF)

• Example: Contract is $1,000,000. For every month the early the project is finished, an additional $5,000 will be paid to the seller.

– Fixed Price Award Fee (FPAF)• Example: Contract is $1,000,000. For every month

performance exceeds the planned level by more than 15% an additional $5,000 will be awarded to the seller, with a maximum award of $50,000.

– Fixed Price Economic Price Adjustment (FPEPA)• Example: Contract price is $1,000,000 but a price increase will

be allowed in year two to account for increase in specific material cost.

12

Page 13: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

Cost Reimbursable Contract– Cost Price (CP)

• Contract = Cost. There is no profit.• Appropriate for non-profit organization

– Cost Plus Fee (CPF)• Contract = Cost plus 10% of cost as fee

– Cost Plus Fixed Fee (CPFF)• Contract = Cost plus a fee of $10,000

– Cost Plus Award Fee (CPAF)• Contract = Cost plus $5,000 for every month production

exceeds 10,000 units with maximum award of $50,000.

13

Page 14: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Tools and Techniques

Time and Material Price Contract

• The buyer pays per item or per hour basis

• Example: Contract is $100 per hour plus expenses or

materials at cost.

14

Page 15: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Risk and Contract Type

15

Page 16: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Plan Procurements > Outputs

• Procurement management Plan• Types of contracts to be used• Risk management issues• Evaluation criteria• Standardize procurement document• Any constrain and assumption• Identifying prequalified sellers

• Procurement Documents• Request for Information (RFI)• Invitation for Bid (IFD)• Request for Proposal (RFP)• Request for Quotation (RFQ)

16

Page 17: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Conduct Procurements | Data Flow Diagram

Page 18: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Conduct Procurements

Inputs Tools & Techniques Outputs

Project management planProcurement documentsSource selection criteriaQualified seller listSeller proposalsProject documentsMake-or-buy decisionsTeaming agreementOrganizational process assets

Bidder conference Proposal evaluation techniquesIndependent estimatesExpert judgmentAdvertisingInternet searchProcurement negotiations

Selected sellersProcurement contract awardResource calendarsChange requestsProject management plan updatesProject document updates

Page 19: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Contract Procurements > Outputs

• Procurement Contract Award• Statement of work or

deliverables• Schedule baseline• Performance reporting• Roles and

responsibilities• Pricing• Payment terms• Place of delivery• Acceptance criteria• Warranty• Product support

• Insurance and performance bond

• Penalties• Change request

handling• Termination and

alternative dispute resolution mechanism

19

Page 20: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Administer Procurement | Data Flow Diagram

Page 21: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Administer Procurement

Inputs Tools & Techniques Outputs

Procurement documentsProject management planContractPerformance reportsApproved change requestsWork performance information

Contract change control system Procurement performance reviewInspections and auditsPerformance reportingPayment systemClaims administrationRecord management system

Procurement documentationOrganizational process assets updatesChange requestsProject management plan updates

Page 22: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Close Procurements | Data Flow Diagram

Page 23: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Close Procurements

Inputs Tools & Techniques Outputs

Project management planProcurement documents

Procurement auditNegotiated settlementsRecord management system

Closed procurementsOrganizational process assets updates

Page 24: PMP Exam Preparation Course: 11 Project Procurement Management

www.wizardea.com | [email protected]

Questions

24

• [[email protected]]

• http://bd.linkedin.com/in/shahrier