pmp_inputs and outputs of all processes
TRANSCRIPT
-
8/3/2019 PMP_Inputs and Outputs of All Processes
1/24
Process Group & Knowled
Knowledg Area S.N Process
Initiating Integration
1 Develop Project Charter
Initiating Integration
Initiating Integration
Initiating Integration
Initiating Integration
Initiating Communication
2 Identify StakeholdersInitiating Communication
Initiating Communication
Initiating Communication
Planning Integration
3 Develop Project Management PlaPlanning Integration
Planning Integration
Planning Integration
Planning Scope
4 Collect Requirements
Planning Scope
Planning Scope
Planning Scope
Planning Scope
Planning Scope
Planning Scope
Planning Scope
Planning Scope
5 Define ScopePlanning Scope
Planning Scope
Planning Scope
Planning Scope
6 Create WBSPlanning Scope
Planning Scope
Planning Scope
Planning Time
Planning Time
ProjectProcessGroups
-
8/3/2019 PMP_Inputs and Outputs of All Processes
2/24
Planning Time
Planning Time
Planning Time
8 Sequence Activities
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
9 Estimate Activity Resources
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
10 Estimate Activity Duration
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
11 Develop Schedule
Planning TimePlanning Time
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
Planning Time
Planning Cost
12 Estimate Costs
Planning Cost
Planning Cost
Planning Cost
Planning Cost
Planning Cost
Planning Cost
-
8/3/2019 PMP_Inputs and Outputs of All Processes
3/24
Planning Cost
Planning Cost
Planning Cost
13 Determine Budget
Planning Cost
Planning Cost
Planning Cost
Planning Cost
Planning Cost
Planning Cost
Planning Quality
14 Plan Quality
Planning Quality
Planning Quality
Planning Quality
Planning Quality
Planning Quality
Planning Quality
Planning Quality
Planning Quality
Planning
15 Develop Human Resource PlanPlanning
Planning
Planning Communication
16 Plan CommunicationsPlanning Communication
Planning Communication
Planning Communication
Planning Risk
17 Plan Risk Management
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
HumanResourceHumanResource
HumanResource
-
8/3/2019 PMP_Inputs and Outputs of All Processes
4/24
Planning Risk
18 Identify Risks
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
19 Perform Qualitative Risk Analysis
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
20 Perform Quantitative Risk Analysi
Planning Risk
Planning Risk
Planning Risk
Planning Risk
Planning Risk
21 Plan Risk ResponsePlanning RiskPlanning Risk
Planning Risk
Planning Procurements
22 Plan Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Planning Procurements
Executing Integration
-
8/3/2019 PMP_Inputs and Outputs of All Processes
5/24
Executing Integration
23 Direct and Manage Project ExecutExecuting Integration
Executing Integration
Executing Integration
Executing Quality
24 Perform Quality AssuranceExecuting Quality
Executing Quality
Executing Quality
Executing
25 Acquire Project TeamExecuting
Executing
Executing
Executing
26 Develop Project Team
Executing
Executing
Executing
Executing
Executing
Executing
27 Manage Project Team
Executing
ExecutingExecuting
Executing
Executing Communication
28 Distribute InformationExecuting Communication
Executing Communication
Executing Communication
29 Manage Stakeholders Expectation
Executing Communication
Executing Communication
Executing Communication
Executing Communication
Executing Communication
Executing Procurements
Executing Procurements
Executing Procurements
HumanResource
umanResourceHumanResource
umanResourceHumanResource
umanResourceHumanResource
umanResourceHumanResource
umanResourceHumanResource
umanResourceHuman
ResourceumanResourceHumanResource
-
8/3/2019 PMP_Inputs and Outputs of All Processes
6/24
Executing Procurements
30 Conduct ProcurementExecuting Procurements
Executing Procurements
Executing Procurements
Executing Procurements
Executing Procurements
Integration
31 Monitor and Control Project WorkIntegration
Integration
Integration
Integration
32 Perform Integrated Change Contr
Integration
Integration
Integration
Integration
Scope
33 Verify ScopeScope
Scope
Scope
Scope
34 Control ScopeScopeScope
Scope
Scope
Time
35 Control Schedule
Time
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&&
&
&
&
&
&
&
&
&
&
&
&
&
&
-
8/3/2019 PMP_Inputs and Outputs of All Processes
7/24
Cost36 Control Cost
Cost
Cost
Quality
37 Perform Quality Control
QualityQuality
Quality
Quality
Quality
Quality
Quality
Quality
Quality
Communication
38 Report Performance
Communication
Communication
Communication
Communication
Risk
39 Monitor and Control Risks
Risk
Risk
Risk
Risk
Risk
Procurements
40 Administer Procurements
Procurements
Procurements
ProcurementsProcurements
Procurements
Procurements
Closing Integration
41 Close Project Or PhaseClosing Integration
Closing Integration
Monitoring&Controlin &
&
&
&&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&
&&
&
&
-
8/3/2019 PMP_Inputs and Outputs of All Processes
8/24
Closing Procurements
42 Close ProcurementClosing Procurements
Closing Procurements
-
8/3/2019 PMP_Inputs and Outputs of All Processes
9/24
g Area Maping ITTO ----- Created by: www.MonzerOsama.com
INPUTS Tools and Techniques
Project statement of work
Expert Judgment
Business case
Contract
Enterprise Environmental Factors
Organization Process assets
Project CharterStakeholder Analysis
Procurement Documents
Enterprise Environmental FactorsExpert Judgment
Organization Process assets
Project Charter
Expert JudgmentOutputs From Planning Process
Enterprise Environmental Factors
Organization Process assets
Project Charter Interviews
Stakeholder Register Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making Technique
Questionnaires and Surveys
Observations
Prototypes
Project Charter Expert Judgment
Requirement Documentation Product analysis
Organization Process assets Alternatives Identification
Facilitated Workshops
Project Scope Statement
DecompositionRequirement Documentation
Organization Process assets
Scope Baseline Decomposition
Enterprise Environmental Factors Rolling Wave Planning
-
8/3/2019 PMP_Inputs and Outputs of All Processes
10/24
Organization Process assets Templates
Expert Judgment
Activity List Precedence Diagramming Method (
Activity Attributes Dependency Determination
Milestone List Applying Leads and Lags
Project Scope Statement Schedule Network Templates
Organization Process assets
Activity List Expert Judgment
Activity Attributes Alternatives Analysis
Resource Calendars Published Estimating Data
Enterprise Environmental Factors Bottom-Up Estimating
Organization Process assets Project Management Software
Activity List Expert Judgment
Activity Attributes Analogous Estimating
Activity Resource Requirements Parametric Estimating
Resource Calendars Three-Point Estimates
Project Scope Statement Reserve Analysis
Enterprise Environmental Factors
Organization Process assets
Activity List Schedule Network Analysis
Activity Attributes Critical Path MethodProject Schedule Network Diagra Critical Chain Method
Activity Resource Requirements Resource Leveling
Resource Calendars What-if Scenario Analysis
Activity Duration Estimate Applying Leads and Lags
Project Scope Statement Schedule Compression
Enterprise Environmental Factors Scheduling Tool
Organization Process assets
Scope Baseline Expert Judgment
Project Schedule Analogous Estimating
Human Resource Plan Parametric Estimating
Risk Register Bottom-Up Estimating
Enterprise Environmental Factors Three-Point Estimates
Organization Process assets Reserve Analysis
Cost of Quality
-
8/3/2019 PMP_Inputs and Outputs of All Processes
11/24
Project Management Estimating So
Vendor Bid Analysis
Activity Cost Estimate Cost Aggregation
Basis Of Estimate Reserve Analysis
Scope Baseline Expert Judgment
Project Schedule Historical Relationships
Resource Calendars Funding Limit Reconciliation
Contract
Organization Process assets
Scope Baseline Cost-Benefit Analysis
Stakeholder Register Cost of Quality
Cost Performance Baseline Control Charts
Schedule Baseline Benchmarking
Risk Register Design of Experiments
Enterprise Environmental Factors Statical Sampling
Organization Process assets Flowcharting
Proprietary quality Management M
Additional Quality Planning Tools
Activity Resource Requirements Organization Chart and Position De
Enterprise Environmental Factors Networking
Organization Process assets Organization Theory
Stakeholder Register Communication Requirements Anal
Stakeholder Management Strateg Communication Technology
Enterprise Environmental Factors Communication Models
Organization Process assets Communication Methods
Project Scope Statement
Planning Meetings and Analysis
Cost Management Plan
Schedule Management Plan
Communication Management Plan
Enterprise Environmental Factors
Organization Process assets
Risk Management Plan Documentation Reviews
Activity Cost Estimate Information Gathering Techniques
Activity Duration Estimate Checklist Analysis
-
8/3/2019 PMP_Inputs and Outputs of All Processes
12/24
Scope Baseline Assumption Analysis
Stakeholder Register Diagramming Techniques
Cost Management Plan SWOT Analysis
Schedule Management Plan Expert Judgment
Quality Management Plan
Project Documents
Enterprise Environmental Factors
Organization Process assets
Risk Register Risk Probability and Impact Assess
Risk Management Plan Probability and Impact Matrix
Project Scope Statement Risk Data Quality Assessment
Organization Process assets Risk Categorization
Risk Urgency Assessment
Expert Judgment
Risk Register Data Gathering and Representation
Risk Management Plan Quantitative Risk Analysis and Mod
Cost Management Plan Expert Judgment
Schedule Management Plan
Organization Process assets
Risk Register Strategies For Negative Risk or Thr
Risk Management Plan Strategies For Positive Risk or OppContingent Response Strategies
Expert Judgment
Scope Baseline Make-or-Buy Analysis
Requirement Documentation Expert Judgment
Teaming Agreements Contract Types
Risk Register
Risk-Related Contract Decision
Activity Resource Requirements
Project Schedule
Activity Cost Estimate
Cost Performance Baseline
Enterprise Environmental Factors
Organization Process assets
Project Management Plan Expert Judgment
-
8/3/2019 PMP_Inputs and Outputs of All Processes
13/24
Approved Change Request Project Management Information S
Enterprise Environmental Factors
Organization Process assets
Project Management Plan
Quality Metrics
Work Performance Information Quality Audits
Quality Control Measurements Process Analysis
Project Management Plan Pre-assignment
Enterprise Environmental Factors Negotiation
Organization Process assets Acquisition
Virtual Teams
Project Staff assignment Interpersonal Skills
Project Management Plan Training
Resource Calendars Team-Building Activities
Ground Rules
Co-Location
Recognition and Reward
Project Staff assignment Observation and Conversation
Project Management Plan Project Performance Appraisals
Team Performance Assessment Conflict ManagementPerformance Reports Issue Log
Organization Process assets Interpersonal Skills
Project Management Plan Communication Methods
Performance Reports Information Distribution Tools
Organization Process assets
Stakeholder Register Communication Methods
Stakeholders Management strategInterpersonal Skills
Project Management Plan Management Skills
Issue Log
Change Log
Organization Process assets
Project Management Plan Bidder Conferences
Procurement Documents Proposal Evaluation Techniques
Source Selection Criteria Independent Estimates
Plan Quality and Perform Quality
Control Tools and Techniques
-
8/3/2019 PMP_Inputs and Outputs of All Processes
14/24
Qualified Seller List Expert Judgment
Sellers Proposals Advertising
Project Documents Internet search
Make-Or-Buy Decision Procurement Negotiation
Teaming Agreements
Organization Process assets
Project Management Plan Expert Judgment
Performance Reports Project Management Information S
Enterprise Environmental Factors
Organization Process assets
Project Management Plan Expert Judgment
Work Performance Information Change Control Meeting
Change Request
Enterprise Environmental Factors
Organization Process assets
Project Management Plan
InspectionRequirement Documentation
Requirement Traceability Matrix
Validated Deliverables
Project Management Plan
Variance AnalysisWork Performance InformationRequirement Documentation
Requirement Traceability Matrix
Organization Process assets
Project Management Plan Performance Review
Project Schedule Variance Analysis
Work Performance Information Project Management Software
Organization Process assets Resource Leveling
What-if Scenario Analysis
Adjusting Leads and Lags
Schedule Compression
Scheduling Tool
Project Management Plan Earned Value Management
Project Funding Requirements Forecasting
Work Performance Information To-Complete Performance Index
-
8/3/2019 PMP_Inputs and Outputs of All Processes
15/24
Organization Process assets Performance Review
Variance Analysis
Project Management Software
Project Management Plan Cause and Effect Diagram
Quality Metrics Control ChartsQuality Checklists Flowcharting
Work Performance Measurement Histograms
Approved Change Request Pareto Charts
Deliverables Run chart
Organization Process assets Scatter Diagram
Statical Sampling
Inspection
Approved Change Request Review
Project Management Plan Variance Analysis
Work Performance Information Forecasting Methods
Work Performance Measurement Communication Methods
Budget Forecast Reporting System
Organization Process assets
Risk Register Risk Reassessment
Project Management Plan Risk Audits
Work Performance Information Variance and Trend Analysis
Performance Reports Technical Performance Measurem
Reserve Analysis
Status Meetings
Procurement Documents Contract Change Control System
Project Management Plan Procurement Performance Reviews
Contract Inspections and Audits
Performance Reports Performance ReportingApproved Change Request Payment Systems
Work Performance Information Claims administration
Record Management System
Project Management Plan
Expert JudgmentAccepted Deliverables
Organization Process assets
-
8/3/2019 PMP_Inputs and Outputs of All Processes
16/24
Project Management Plan Procurement Audits
Procurement Documents Negotiation Settlement
Record Management System
-
8/3/2019 PMP_Inputs and Outputs of All Processes
17/24
OUTPUTS
Project Charter
Stakeholder Register
Stakeholder Management Strategy
Project Management Plan
Requirement Documentation
Requirement Management Plan
Requirements Traceability Matrix
s
Project Scope Statement
Project Document Updates
WBS
WBS Dictionary
Scope Baseline
Project Document Updates
Activity List
Activity Attributes
-
8/3/2019 PMP_Inputs and Outputs of All Processes
18/24
Milestone List
Project Schedule Network Diagram
Project Document Updates
Activity Resource Requirements
Resource Breakdown Structure
Project Document Updates
Activity Duration Estimate
Project Document Updates
Project Schedule
Schedule BaselineSchedule Data
Project Document Updates
Activity Cost Estimate
Basis Of Estimate
Project Document Updates
-
8/3/2019 PMP_Inputs and Outputs of All Processes
19/24
ftware
Cost Performance Baseline
Project Funding Requirements
Project Document Updates
Quality Management Plan
Quality Metrics
Quality Checklists
Process Improvement Plan
Project Document Updates
thodology
Human Resource Plan
Communication Management Plan
Project Document Updates
Risk Management Plan
-
8/3/2019 PMP_Inputs and Outputs of All Processes
20/24
Risk Register
Risk Register Update
Risk Register Update
Risk Register Update
Risk-Related Contract DecisionProject Management Plan Update
Project Document Updates
Procurement Management Plan
Procurement Statement Of Work
Make-Or-Buy Decision
Procurement Documents
Source Selection Criteria
Change Request
Deliverables
-
8/3/2019 PMP_Inputs and Outputs of All Processes
21/24
Work Performance Information
Change Request
Project Management Plan Update
Project Document Updates
Organization Process assets Update
Change Request
Project Management Plan Update
Project Document Updates
Project Staff assignment
Resource Calendars
Project Management Plan Update
Team Performance Assessment
Enterprise Environmental Factors Updates
Enterprise Environmental Factors Updates
Organization Process assets Update
Change RequestProject Management Plan Update
Organization Process assets Update
Organization Process assets Update
Change Request
Project Management Plan Update
Project Document Updates
Selected Sellers
Procurement Contract Award
Resource Calendars
-
8/3/2019 PMP_Inputs and Outputs of All Processes
22/24
Change Request
Project Management Plan Update
Project Document Updates
Change Request
Project Management Plan Update
Project Document Updates
Change Request Status Update
Project Management Plan Update
Project Document Updates
Accepted Deliverables
Change Request
Project Document Updates
Work Performance Measurement
Organization Process assets UpdateChange Request
Project Management Plan Update
Project Document Updates
Work Performance Measurement
Organization Process assets Update
Change Request
Project Management Plan Update
Project Document Updates
Work Performance Measurement
Budget Forecast
Organization Process assets Update
-
8/3/2019 PMP_Inputs and Outputs of All Processes
23/24
Change Request
Project Management Plan Update
Project Document Updates
Quality Control Measurements
Validated ChangesValidated Deliverables
Organization Process assets Update
Change Request
Project Management Plan Update
Project Document Updates
Performance Reports
Organization Process assets Update
Change Request
Risk Register Update
Organization Process assets Update
Change Request
Project Management Plan Update
Project Document Updates
Procurement Documentation
Organization Process assets Update
Change Request
Project Management Plan Update
Final Product, Service or Result Transition
Organization Process assets Update
-
8/3/2019 PMP_Inputs and Outputs of All Processes
24/24
Closed Procurements
Organization Process assets Update