    PNEUMATIC SEALANT MACHINE

    4/20/2015PEB Steel Buildings Co., Ltd.

    Prepared by: Tran Nhat Duc

  • 7/24/2019 Pneumatic Sealant Machine

    2/14

    1

    TABLE OF CONTENTS

    PNEUMATIC SEALANT MACHINE

    I. PARTS OF PNEUMATIC SEALANT MACHINE

    II. STEP BY STEP OPERATING PROCEDURE

    1. Clean sealant nozzle before and after operation

    2. Control valve

    3. Electric connection

    4. Sealant barrel positioning

    5. Sealant nozzle adjustment

    6. Pneumatic sealant machine operation

    7. Operation complete

  • 7/24/2019 Pneumatic Sealant Machine

    3/14

  • 7/24/2019 Pneumatic Sealant Machine

    4/14

  • 7/24/2019 Pneumatic Sealant Machine

    5/14

    4

    1. Sealant pump

    2. Air compressor

    3. Butyl Sealant barrel

    4. Sealant hose

    5. Air hose No. 1

    6. Rubber seal

    7. Electric wire of air

    compressor

    8. Electric wire of power source9. Circle breaker

    10. Air valve No. 1

    11. Air valve No. 2

    12. Air valve No. 3

    13. Air valve No. 4

    14. Air hose No. 2

    15. Air hose No. 3

    16. Air control lever

    17. Sealant nozzle

    18. Sealant needle valve19. Air valve No. 5

  • 7/24/2019 Pneumatic Sealant Machine

    6/14

    5

    III. STEP BY STEP OPERATING PROCEDURE

    We have 7 steps.

    1. Clean sealant nozzle and needle valve before and after operation

    Uninstall sealant nozzle and needle valve.

    Clean all of them by thinner.

  • 7/24/2019 Pneumatic Sealant Machine

    7/14

    6

    Assemble them again.

    Finish.

    2. Control valve

    Connect air compressor and sealant needle valve by air hose No.3. Air

    hose No.3 must have air valve No.4.

  • 7/24/2019 Pneumatic Sealant Machine

    8/14

    7

    Connect sealant pump and sealant nozzle by sealant hose.

    Overview

  • 7/24/2019 Pneumatic Sealant Machine

    9/14

  • 7/24/2019 Pneumatic Sealant Machine

    10/14

    9

    Turn on air valves No.2 and No.3.

    Insert sealant barrel.

    Use air control lever to control level of sealant pump.

    Turn LEFT air control lever to push sealant pump UP.

    Turn MIDDLE air control lever to keep sealant pump STOP.

    Turn RIGHT air control lever to pull sealant pump DOWN.

  • 7/24/2019 Pneumatic Sealant Machine

    11/14

    10

    Finish when level of sealant pump is lowest.

    5. Sealant nozzle adjustment

    Tighten all bolts of sealant nozzle and needle valve.

    Control steel bar to adjust gap between of nozzle and panel to be about

    1mm.

  • 7/24/2019 Pneumatic Sealant Machine

    12/14

    11

    Adjust needle valve for the suitable flow of sealant size (about 3mm)

    6. Sealant machine operation

    Turn off air valve No.3. Turn on air valve No.4.

    Turn on air valve No.5 when panel touch sealant nozzle.

    Turn off air valve No.5 before cutting panel.

  • 7/24/2019 Pneumatic Sealant Machine

    13/14

  • 7/24/2019 Pneumatic Sealant Machine

    14/14

    Connect air compressor and air hose No.1.

    Turn off air valve No.2, turn on air valve No.1.

    Turn left air control lever to move up sealant pump. Then get sealant

    barrel out.