Page 1: Point Place Meeting 9-14-05

Point PlaceSewer

Improvements

Neighborhood Advisory Committee

September 14, 2005

Page 2: Point Place Meeting 9-14-05

Today’s Meeting

• Water department – service interruption notification policy

• Program construction update

• Update/review Phase 2C of sewer improvement project

• Gather input on:• Boring vs. Open Cut• Construction issues• Traffic issues

Page 3: Point Place Meeting 9-14-05

Point Place – Edgewater Pump Station

Page 4: Point Place Meeting 9-14-05

Point Place – Edgewater Drive

Page 5: Point Place Meeting 9-14-05

Point Place –Pump Station Demolition

Page 6: Point Place Meeting 9-14-05

Point Place –290th Street Pump Station

Page 7: Point Place Meeting 9-14-05

River Road Area –River Road

Page 8: Point Place Meeting 9-14-05

River Road Area –River Road Park

Page 9: Point Place Meeting 9-14-05

Program Update

• Bay View Expansion• Discussions continue with Port Authority on land for

senior golf course

Page 10: Point Place Meeting 9-14-05

Bay View Wastewater Treatment Plant

Page 11: Point Place Meeting 9-14-05

Bay View Wastewater Treatment Plant

Page 12: Point Place Meeting 9-14-05

Bay View Wastewater Treatment Plant

Page 13: Point Place Meeting 9-14-05

Bay View Wastewater Treatment Plant

Page 14: Point Place Meeting 9-14-05

Phase 2C – Schedule

• Bids are in:

• Gleason Construction is apparent low bidder

• $2.14 million for boring

• $1.9 million for open trench

• Construction Begins – November 2005

• Street Restoration – Spring 2006

Page 15: Point Place Meeting 9-14-05

Phase 2C – Overview

• 24-inch gravity relief sewer from 135th north on Edgewater to 149th

• Bid two ways• Open trench• Boring

Page 16: Point Place Meeting 9-14-05

Boring or Open Trench

• Difficult, disruptive project either way

• Detour still needed under either option

Page 17: Point Place Meeting 9-14-05

Boring - Pros & Cons

• Boring Pros• Requires several large pits but no long trenches• Less truck traffic hauling dirt in and out

• Boring Cons• More expensive• Only areas disturbed will be re-paved – not the

whole street

Page 18: Point Place Meeting 9-14-05

Options - Pros & Cons

• Open Trench Pros• Less Expensive

• Open Trench Cons• Difficult, messy

Page 19: Point Place Meeting 9-14-05

Boring vs. Open Trench

• Discussion

Page 20: Point Place Meeting 9-14-05

Detour Option #1 – One-Way Bypass

• Northbound traffic routed on three-phase detour

• Southbound traffic routed on Edgewater – one lane maintained• Flaggers needed on some sections

• No on-street parking on detour route

Page 21: Point Place Meeting 9-14-05

Option #1 – One-Way Bypass• Phase 1

• 136th east to Lakeside northeast to 317th north to 141st west

• 138th bypass - 136th east to 313th north to 138th west

• Phase 2• One-lane maintained with flaggers between 141st

and 145th

• Phase 3• 145th east to 321st north to 146th east to 324th north to

149th west to Edgewater south

Page 22: Point Place Meeting 9-14-05

Detour Route

Page 23: Point Place Meeting 9-14-05

Option #2 – One Lane With Flaggers• No detour• Like last phase of Edgewater work• One lane maintained around construction with

flaggers

Page 24: Point Place Meeting 9-14-05

Recommendations

• City recommends one-way bypass detour• Approved by TARTA and Fire Department

• Bus route re-confirmed with Tarta after last meeting – tested and approved.

Page 25: Point Place Meeting 9-14-05

Access for Safety Services

• Police and Fire will have direct communication with construction crews

Page 26: Point Place Meeting 9-14-05

Public Notification/Communications• Meetings with businesses and Police/Fire• Point Shoreland Journal – advertising with map

showing construction schedule and detours• Run 2 times before start of construction

• Signage placed on Edgewater warning of coming detours (2 weeks prior)

Page 27: Point Place Meeting 9-14-05

Public Notification/Communications• Notification of residents

• Point Place by mail• Literature drop in Lost Peninsula

• Other recommendations from Committee• Another public meeting prior to start of

construction

Page 28: Point Place Meeting 9-14-05

Next Meeting

• Date