poland effi - world banksiteresources.worldbank.org/globalenvironmentfacilitygefoperations… ·...
TRANSCRIPT
A WORLD BANK GROUP GLOBAL ENV IRONMENT FAC I L I TY PROGRAM PUBL ICAT ION
WORLD BANK GEFPost- Imp lementat ion Impact Assessment
Poland Effi cient Lighting Project
WORLD BANK GEFPost-Implementation Impact Assessment
POLAND EFFICIENT LIGHTING PROJECT
GLOBAL ENVIRONMENT FACILITY PROGRAM
THE WORLD BANK
©2006
The International Bank for Reconstruction and Development/
THE WORLD BANK
1818 H Street, N.W.
Washington, D.C. 20433, U.S.A.
Manufactured in the United States of America
This report was prepared by le Groupe-conseil baastel ltée. Special thanks to all stakeholders met either
in Poland or in other countries, to Russell Sturm (IFC) and Siv Tokle of the GEF Evaluation Office for
their insightful comments, and to Esther Monier-Illouz, World Bank, for editorial assistance. The World
Bank’s Task Manager was Samuel Wedderburn.
Cover and book design: The Word Express, Inc. and Esther Monier-Illouz; book design based on work
by Jim Cantrell.
Cover image: Stuart Gregory/Getty Images
Images in text: Josh Westrich/zefa/Corbis
All rights reserved
The World Bank has used its best efforts to ensure that the information contained within this report is
accurate, however, it cannot guarantee its accuracy. The representations, interpretations, and conclusions
expressed herein do not necessarily reflect the views of the Executive Directors of the World Bank or the
government that they represent.
Rights and Permissions
The material in this publication is copyrighted. Copying and/or transmitting portions or all of this work
without permission may be a violation of applicable law. The International Bank for Reconstruction and
Development / The World Bank encourages dissemination of its work and will normally grant permis-
sion to reproduce portions of the work promptly. For permission to photocopy or reprint any part of
this work, please send a request with complete information to the Copyright Clearance Center Inc., 222
Rosewood Drive, Danvers MA 01923, USA; telephone: 978-750-8400; fax: 978-750-4470; Internet:
www.copyright.com.
iii
CONTENTS
ABBREVIATIONS AND ACRONYMS VII
EXECUTIVE SUMMARY 1
1. INTRODUCTION 91.1 Manufacturers’ Subsidy Component 111.2 Luminaire Subsidy Component 111.3 Consumer Education Component 121.4 Pilot Demand-side Management Component 121.5 M&E Component 13
2. METHODOLOGY I5
3. PELP PROJECT IMPLEMENTATION I93.1 Project Context 193.2 Achieved Project Outcomes 20 3.2.1 Energy Savings and Reduction in GHG Emissions 20 3.2.2 Project Benefits to the Polish Economy 21 3.2.3 Level of Awareness to Potential Benefits of DSM Programs and DSM Capacity Building 22
4. IMPACT ASSESSMENT 234.1 Post-project Context 234.2 Findings and Analysis 25 4.2.1 Global Environmental Impacts 25 4.2.2 Impacts on Institutional Development 32
iv
Post Implementation Impact Assessment: Poland Efficient Lighting Project
4.2.3 Impacts on the Market and on Beneficiaries 42 4.2.4 Mainstreaming Global Environmental Concerns 59 4.2.5 Impacts on Local Environment and Health 624.3 Replicability 64
5. LESSONS LEARNED 695.1 Lessons for Energy Efficiency Sector Projects 695.2 Lessons in Project Management and Implementation of EE Initiatives 71
6. RECOMMENDATIONS 73
APPENDIXES
Appendix A: Project Organizational Chart 75Annex B: Interviewees 77Appendix C: Bibliography 79
TABLES
Table 4.1 Total Estimated Energy Saving 27 Table 4.2 Total Estimated GHG Reduction 28 Table 4.3 Forecasts of CFL Sales Increases 28 Table 4.4 CFL Sales, Energy Savings, and GHG Emission Reductions with and without PELP 30 Table 4.5 GHG Emission Reductions in Programs That Replicated PELP 31
FIGURES
Figure 4.1 Energy Consumption, Intensity and GDP in Poland 1997—2002 (FEWE) 31 Figure 4.2 Level of Satisfaction with CFLs Purchased 44 Figure 4.3 45 Figure 4.4 47 Figure 4.5 What will your next light bulb be? 48
v
ABBREVIATIONS AND ACRONYMS
AGH University of Mining and Metallurgy in Krakow
BEE Business Energy Ecology
CFL compact fluorescent lamp
CO2 carbon dioxide
DSM demand-side management
EE energy efficiency
ELI Efficient Lighting Initiative
ENGO environmental nongovernmental organization
ENVGC Environment Department Global Environment Coordination
ESCO energy services company
ES Systems Energy Savings Systems
EU European Union
FEWE Polish Foundation for Energy Efficiency
GDP gross domestic product
GEF Global Environment Facility
GHG greenhouse gas
GLS general lighting services
GWh gigawatt-hour
IAEEL International Agency for Energy-Efficient Lighting
IFC International Finance Corporation
IIEC International Institute for Energy Conservation
kWh kilowatt-hour
M&E monitoring and evaluation
NGO nongovernmental organization
vi
Post Implementation Impact Assessment: Poland Efficient Lighting Project
NOx nitrogen oxide
PELP Polish Efficient Lighting Project
PEMP Polish Efficient Motor Project
PLN zloty [Polish currency]
PNEC Polish Network “Energie Cities”
PSE Polish power grid company
RE renewable energy
SOx sulfur oxide
Note: All dollar amounts are U.S. dollars unless otherwise indicated.
1
EXECUTIVE SUMMARY
The World Bank’s Global Environment Facil-
ity (GEF) Coordination Team has embarked
on a series of post-implementation project im-
pact assessments in order to better understand
the extent of impacts of GEF project interven-
tions, the sustainability of these impacts, and
lessons learned and to determine how the
GEF operational programs’ long-term goals
are being addressed. These reviews focus on
lessons learned at the project and thematic
level that are relevant to the World Bank and
GEF policies and strategies.
Four climate change projects in the energy
efficiency (EE) thematic area were selected for
study in 2004—5: the Poland Efficient Lighting
Project (PELP), Mexico High Efficiency Light-
ing Project, Jamaica Demand-Side Manage-
ment Demonstration Project, and Thailand
Promotion of Electricity Energy Efficiency.
This report deals with the Poland project. This
review of PELP also served as a pilot for the
other three impact assessments. Its purpose
was to contribute to the identification of fac-
tors that determine the sustainability and rep-
lication of project outcomes and to identify
lessons that will help to improve the design
and implementation of World Bank-GEF
projects. The pilot phase was also intended
to provide lessons on conducting assessments
of this type, long after projects have been
completed. (The challenges encountered
and lessons learned from conducting im-
pact assessments are presented in a separate
document prepared for the World Bank by
le Groupe-conseil baastel ltée.)
The review was conducted by le Groupe-
conseil baastel ltée between April and July
2004. The report is based on a thorough
desk review, preliminary interviews, and a
two-week mission to Poland during which
the Study Team met with key informants
and reviewed further documentation. The
interviewees included representatives from
the executing agency, relevant ministries,
electric utilities, municipal representatives,
environmental nongovernmental organiza-
2
Post Implementation Impact Assessment: Poland Efficient Lighting Project
tions, energy consultants, the private sector,
consumers, retailers, compact fluorescent
lamp (CFL) and luminaire manufacturers, and
other relevant stakeholder groups. The Study
Team also conducted a basic retail survey in
major cities in Poland. This involved visit-
ing the major large, medium-size, and small
stores that sell CFLs and luminaries, as well as
electric and lighting specialty shops, in order
to assess availability, EE lighting promotion,
and shelf space, prices, types, brands, and
other relevant data.
In addition, the Study Team held a focus
group of consumers – some of the primary
beneficiaries of the project – in order to
collect detailed quantitative and qualitative
data to be measured against the outcomes of
the project and to assess the current state of
affairs. The Team contracted with the most
nationally recognized social science research
firm (PINTOR) to assist with the organization
and independent administration of a survey to
cover these project beneficiaries. This focus
group allowed for a verification and triangula-
tion of findings from other sources.
Findings
The review demonstrated that PELP has had
significant long-term impacts in Poland in
terms of the environment, the market for
CFLs, and various beneficiaries. The assess-
ment also brought to light various challenges
in terms of the long-term impact of PELP.
Although the issue of attribution is difficult
in the impact assessment context, this report
attempts to highlight direct and indirect con-
tributions observable from PELP in the long
term and does not significantly deviate from
findings and data substantiated from numer-
ous current sources.
Global Environmental Impacts
The Study Team concludes, using available
information on the current CFL market, that
total greenhouse gas (GHG) emissions re-
duction attributable to PELP approximates
3.62 million tons of carbon dioxide (CO2)
equivalent – substantially more than the
2.79 million tons of CO2 estimated by Navi-
gant Consulting in 1999. This difference is
due essentially to more households with
CFLs than originally estimated and market
saturation for CFLs in Poland. In addition,
the global environmental benefits in terms
of GHG emission reduction induced by
subsequent projects that were inspired by
the PELP experience (or that replicated PELP
to some degree) could also be significant.
Total anticipated impacts of three key PELP
follow-up or replicated projects are in the
range of 18.4 million tons of CO2.
Institutional Development
The capacity for information management
and awareness raising exists at certain levels
within the country, and some of it was fur-
thered through PELP. For example, institu-
tions such as the University of Mining and
Metallurgy in Krakow (AGH), the Polish Net-
work “Energie Cities” (PNEC), and the Polish
Foundation for Energy Efficiency (FEWE) all
Executive Summary
3
have the capacity to undertake awareness
raising initiatives throughout the country
and are currently doing so. However, groups
such as FEWE and PNEC rely on project-
related funding and have little core funding
available to ensure continuity and a strong
logical framework for their actions on EE. The
national government does not appear to be
currently committed to EE and demand-side
management (DSM) in any forceful manner,
and municipalities are constrained in terms of
both human and financial capacity for aware-
ness rising. As many stakeholders have made
clear, PELP focused primarily on shifting the
market for CFLs and not necessarily on raising
EE awareness or developing the capacity to
do so for the long term. It should be noted that
this was a contextually appropriate choice
for the project’s emphasis, but it impeded
some degree of contributions being made
to long-term raised awareness and related
capacities for EE.
Although there may generally be capacity for
policy making, planning, and decision mak-
ing for EE and DSM, since several national
laws and policies address EE issues, the laws
are not well enforced or implemented due to
various contextual factors. At the municipal
level, the capacity for planning and deci-
sion making on EE is almost nonexistent and
therefore needs to be addressed. At national
and municipal levels, the government’s ca-
pacity to implement the decisions on EE and
DSM does not seem to be present, but this
capacity does exist within nongovernmental
institutions or organizations. It is evident that
utilities, too, have this capacity, but they are
generally not as interested in pursuing these
initiatives, given current market realities in
Poland. PELP had limited success in bringing
change to that overall situation, although it
did support pilot initiatives in certain munici-
palities that helped further the implementa-
tion capacity of some groups in partnership
with municipalities. The need to broaden
the experience and reach of that capacity
remains significant, given the EE situation in
the country.
The incomplete enabling environment for
pursuing EE in Poland is not conducive to
use of the capacity to enforce legislation,
which does not seem to be present at any
level. If EE is to be pursued in the future, this
capacity will need to be built. The capacity
to pool human, technological, and ecological
resources does lie with institutions like FEWE
and energy consultants. However, as indi-
cated earlier, what is missing is the capacity
to pool financial resources required to move
EE and DSM ahead in Poland.
Energy service companies (ECSOs), which
normally would be a key player in pool-
ing resources by marketing, implementing,
and structuring financing for EE measures at
various levels (and were envisioned as such
by PELP), are not important in Poland. The
efforts of PELP to build an ESCO legacy as a
key institutional driver of broader and sus-
tainable market transformation for efficient
4
Post Implementation Impact Assessment: Poland Efficient Lighting Project
lighting in Poland in the longer run have
not proved fruitful. This appears to be due,
in particular, to the absence of an adequate
market-enabling environment to allow the
companies to flourish.
Impacts on the Market and Beneficiaries
For consumers, there have been many di-
rect and indirect benefits from PELP in the
long term. As the market for CFLs has been
transformed, the availability and selection of
CFLs has increased dramatically. The price of
CFLs remains at similar levels since the end
of PELP (which means a lower price in real
terms). Consumers are still enjoying energy
savings by using CFLs, even though it is dif-
ficult to calculate such savings in the current
Polish context of rising electricity prices and
a rapidly evolving electricity sector. Gener-
ally, consumers are aware of the benefits of
CFLs and are purchasing them, but consum-
ers need to be further informed about the
differences between high- and low-quality
bulbs. Cheaper, lower-quality CFLs imported
from Asia are less energy-efficient, but many
consumers are attracted to the lower price. As
many lower-quality bulbs on the market burn
out early or do not work properly, indications
suggest that consumers’ level of satisfaction
has decreased since PELP.
Some manufacturers have benefited greatly
from this market transformation, while oth-
ers have experienced significant challenges.
Sales overall are very high, as is the pen-
etration rate. Philips and Osram continue
to dominate the CFL market, as they did at
the time of the project. Philips has certainly
benefited directly from PELP (as did Energy
Saving Systems in the luminaire market),
while Osram and other manufacturers have
benefited indirectly through a transformed
market and increased sales overall. How-
ever, local manufacturers have not been
able to compete with cheaper Asian imports
or with the big established players. There
are more “local players” in the market now,
but they are mostly distributors of imported
goods, and they do not see their business as
sustainable. In addition, the sustainability
of the CFL market is further in question, as
consumer confidence is apparently erod-
ing, due to lower-quality products and the
absence of adequate mechanisms to control
this aspect.
Some electric utilities have benefited from
PELP over time and have adopted DSM and
EE to avoid large investments. However,
this is usually only for peak shaving and is
certainly not widespread. Through PELP and
initiatives that grew from it, municipalities
continue to reap the benefits of EE, as the
awareness of CFLs has spread to municipali-
ties beyond those targeted by PELP.
Mainstreaming into National and Sectoral
Policies, Laws, and Plans
Although some stakeholders believe that
PELP may have indirectly contributed to
bringing some EE-related issues to the surface
and to the attention of the central govern-
Executive Summary
5
ment, they also recall that the government,
while it was officially supportive of EE and
PELP, was not involved in the project, and
no active relationship or mechanism was in
place to ensure feedback of PELP experience
at the policy level. Poland’s current acces-
sion to the EU is the main impetus behind
laws and policies in Poland, which are more
focused on renewable energy than on energy
efficiency. EE has therefore not been main-
streamed into Poland’s laws and policies to
the extent that could be expected. Where
it has, enforcement of legislation has been
lacking and requires attention. In addition,
PELP did not have an observable impact on
legislation development.
Nevertheless, it seems that PELP did have a
significant impact on the development of EE-
related curricula at various levels of schooling
in the country, although this is not reflected
in education laws or policies per se. PELP
catalyzed an educational and intellectual
focus on EE-related issues in Poland, and its
impacts can be observed in the wide array
of courses and curricula, especially at the
university level, dealing with this topic and
in the greatly expanded number of graduates
and experts who have emerged.
Impacts on the Local Environment
and Health
There are some direct and indirect benefits for
the local health and environment as a result of
PELP, due to the avoidance of expanded coal
power generation, which reduced pollutants
in the air, including nitrogen oxide and sulfur
oxide. Direct attribution to or contributions
from PELP are difficult to assess in the context
of this evaluation, however. Less difficult to
assess is the impact PELP has had in the long
run for the preserved or improved eyesight of
children in schools where EE lighting systems
have replaced non-EE lighting systems.
Replicability
One strong impact of PELP is found in the
number, type, and quality of replication that
has taken place. Lessons, approaches, and
experiences from PELP have been replicated
widely, both in Poland at various levels and
at the international level. PELP lessons and
approaches were replicated by PNEC, FEWE,
AGH University stakeholders, and energy
consultants at municipal and national levels
in Poland and are currently seen in initiatives
such as the Polish Efficient Motor Project.
At the international level, the International
Finance Corporation’s Efficient Lighting Initia-
tive stands as a good example of a replication
activity of PELP, although its approach is
appropriately adjusted to the context of the
country in which it takes place.
Lessons Learned
Lessons for Energy Efficiency
Sector Projects
An overarching lesson from this impact as-
sessment of PELP is that there are key chal-
lenges that must be considered and addressed
in market transformation toward energy
efficiency in developing economies:
6
Post Implementation Impact Assessment: Poland Efficient Lighting Project
• The development of an appropriate en-
abling environment for energy efficiency
actions is very important.
• Building the capacity of local-level gover-
nance institutions to plan, implement, and
enforce legislation and to pool adequate hu-
man and financial resources is paramount.
• Special attention must be paid to build-
ing and sustaining the capacity to raise
awareness on EE/DSM issues and benefits
at various levels.
• The promotion of global environmental
benefits can contribute to bringing a more
sustainable longer-term attitudinal change
toward energy-efficient practices.
• Sustaining raised awareness to have a long-
term impact on changing attitudes and
behaviors requires that adequate emphasis
be placed on information dissemination
and education in an ongoing manner and
at all levels.
• To achieve total and sustainable market
transformation, capacities must be built
within central government, municipalities,
the private sector, and nongovernmental
actors active in the sector.
• Where the macroeconomic and social
context is not conducive to EE, it is difficult
to get government commitment to steer the
process and ensure an adequate enabling
environment.
• In a rapidly changing and opened (or
“opening”) economy, adequate atten-
tion must also be paid to the capacity to
compete with imported products and the
effects this might have.
In addition, the impact assessment of PELP
also generated these other lessons from EE
projects:
• Direct incentives to manufacturers can
be an efficient way to bring about mar-
ket transformation in favor of a given EE
product.
• For sustained impact in EE or DSM, ap-
propriate champions must be identified
and integrated into the initiatives.
• In the context of EE initiatives, it can be
beneficial to work more with end users
and final consumers, who have the most
to gain from electricity savings.
• The argument about health (namely, the
relation of children’s eyesight to proper
lighting) can be a convincing factor in
bringing public support for EE lighting
initiatives.
Lessons in Project Management and
Implementation of EE Initiatives
Assessing PELP in the long term helped
to identify some lessons for learning from
and improving on the experiences of the
project:
• Having an “objective” promoter of the
product to the public, someone who is
seen as independent, is an effective pro-
motional tool.
• Contextually appropriate project executors
and partners are key factors in the short-
term and long-term success of EE initia-
tives.
Executive Summary
7
• The involvement of appropriate local
resources in the design of the project
helps ensure that the intricacies of the lo-
cal context and the changing contextual
environment are taken into account during
the project.
• Project implementation approaches must
be contextually appropriate.
• In order to address emerging constraints
and to build on successes, consideration
should be given to planning for additional
follow-up activities.
Recommendations
The Study Team formulated the following
recommendations related to addressing a
sustained market transformation for energy
efficiency:
• Further use of existing networks in Poland
that raise consumer awareness should be
built on as part of a larger effort in aware-
ness raising on EE at local and municipal
levels.
• A phased strategy in terms of consumer
awareness is recommended, focusing
perhaps initially on economic aspects to
induce a shift, but then focusing on global
environmental aspects in order to address
sustainability.
• Municipalities in Poland should be made
more aware of available funds for EE ini-
tiatives, and related capacities should be
built to facilitate access to those funds.
• The enabling environment, including the
legal structure and enforcement, must
be considered as part of a larger effort
to address capacity development for EE-
related policy making, implementation,
and enforcement.
• Future EE initiatives should look at the
development of mechanisms to ensure
CFL quality and heightened EE savings in
the long run.
• Awareness raising initiatives must move
beyond urban areas to rural ones and must
begin to target municipalities and areas
where CFLs and EE generally have yet to
emerge.
9
The World Bank’s Monitoring and Evalu-
ation (M&E) policy (OD 10.70) recom-
mends that, in addition to mid-term and
final evaluation, major impact evaluations
should be conducted on a selective basis
several years after a project is completed to
measure long-term changes brought about
by the project. The Operations Evaluation
Department conducts Project Performance
Assessments on 25 percent of the Bank’s
portfolio. These provide accountability as
well as serving a learning function, but
to date they have included relatively few
Global Environment Facility (GEF) projects,
given the small number of completed GEF
projects each year.
In addition, paragraph 44 of the GEF Monitor-
ing and Evaluation Policies and Procedures
of January 2002 encourages GEF Partner
Agencies to conduct impact evaluation of
projects after completion. However, these
studies have not been a part of project M&E
activities.
The World Bank’s GEF Coordination Team
hence identified the need to assess post-
implementation results, especially in terms
of longer-term impacts, sustainability, rep-
licability, and lessons learned. In particular,
there is a need to focus on lessons in order to
better understand the extent of impacts, and
sustainability of these impacts, and thus help
determine how GEF operational programs’
long-term goals are being addressed.
In light of this, a set of post-implementation
impact assessments were conducted. These
reviews adopted a long-term perspective
and were based on the study of a cluster of
projects in a specific GEF thematic area. They
focused on lessons learned at the project
and thematic level that are relevant to the
World Bank and the GEF policies and strate-
gies. More specifically, the issues evaluated
included the following:
• Contribution of outcomes to the achieve-
ment of expected impacts
1 INTRODUCTION
10
Post Implementation Impact Assessment: Poland Efficient Lighting Project
• The project’s impacts on the global envi-
ronment
• The project’s impacts on institutional de-
velopment
• The project’s impacts on beneficiaries
(such as livelihoods)
• Lessons learned regarding the sustainabil-
ity of project impacts
• Replicability of project outcomes achieved
and catalytic effect of the project
• The project’s impacts on mainstream-
ing global environment concerns in the
country’s national development and sector
policies
• Lessons learned for improving the design
and management of future activities, an-
swering the question, How can we do it
better?
Four climate change projects in the energy
efficiency (EE) thematic area were selected for
study in 2004—5: the Poland Efficient Lighting
Project (PELP), Mexico High Efficiency Light-
ing Project, Jamaica Demand-Side Manage-
ment Demonstration Project, and Thailand
Promotion of Electricity Energy Efficiency
Project. This report deals with the Poland
project. This review of PELP also served as a
pilot for the other three impact assessments.
In addition to the issues just mentioned, the re-
view of the projects selected in the EE/climate
change cluster included assessments of:
• Private sector impact and market develop-
ment, including issues related to market
growth such as product sales, investment,
and industry structure
• Capacity building achieved in the EE/de-
mand-side management (DSM) area and
its transferability in the context of the
power sector reforms taking place in some
countries
• The impact of GEF on the lighting industry
in the selected country, given the theme of
efficient lighting products in the selected
projects
The post-implementation impact assess-
ment of PELP was conducted by le Groupe-
conseil baastel ltée between April and June
2004, approximately six years after the
project was completed. PELP was a $5-
million greenhouse gas (GHG) reduction
initiative funded by GEF. The International
Finance Corporation (IFC) implemented
PELP in Poland from 1995 through 1998.
The Netherlands Energy Company was
chosen on a competitive basis by IFC as
the local executing agency to adminis-
ter PELP through its daughter company,
Netherlands Energy Efficient Lighting.
The initiative was designed to foster the
replacement of conventional incandes-
cent bulbs with energy-efficient compact
fluorescent lamps (CFLs) in households
in Poland, thereby avoiding electricity
consumption and the emission of GHGs
associated with electricity generation and
distribution.
The main objectives of the initiative were:
Introduction
11
• To reduce GHG emissions from the Polish
electricity sector
• To maximize benefits to the Polish econ-
omy from domestic CFL manufacturing
resources
• To develop the capacity of entities within
Poland to deliver DSM resources
• To demonstrate the value of DSM pro-
grams to the Polish electric power sector,
the government, and Polish nongovern-
mental organizations (NGOs)
1.1 Manufacturers’ Subsidy Component
The CFL subsidy program was the largest
component of PELP. Over $2.6 million of
GEF funds were made available to five Polish
lighting manufacturing companies to reduce
the cost of more than 1.2 million screw-base
CFLs to consumers and to stimulate demand
for the product. PELP provided subsidies on
a competitive basis to Polish CFL manufactur-
ers, using a “manufacturer subsidy” approach.
The project relied on private sector involve-
ment and competitive market principles to
encourage manufacturers, wholesalers, and
retailers to increase the availability of CFLs
and lower their price.
Rather than selling CFLs, PELP aimed to pro-
vide subsidies directly to CFL manufacturers
via a competitive bidding process. Success-
ful bidders agreed to pass on at least the
full value of the subsidies to CFL customers
in the form of lower wholesale prices. CFL
manufacturers interested in participating in
PELP had to submit proposals in order to get
subsidies. Manufacturers who were able to
provide the greatest energy savings in terms
of projected avoided electricity use for the
smallest application of subsidies were allocat-
ed larger shares of subsidies. If manufacturers
were unable to meet the sale goals stated in
their proposals, their entitlement to the sub-
sidies could be reallocated to more-efficient
manufacturers. This competitive system was
designed to provide incentives to manufac-
turers to achieve higher efficiency and lower
CFL market prices. By providing subsidies
to manufacturers and encouraging them to
sell the CFLs, PELP could take advantage of
the CFL manufacturers’ existing distribution
channels and networks.
1.2 Luminaire Subsidy Component
To realize the full potential of energy-ef-
ficient lighting technology in Poland, it was
necessary to also promote the luminaire
market. This subsidy funded a technology
transfer and education program to intro-
duce technically sound prototype compact
fluorescent technologies to Polish luminaire
manufacturers, who were generally not fa-
miliar with them.
PELP promoted energy-efficient residential
luminaires through a program that used a
similar design to the CFL subsidy. More than
57,000 CFL luminaires were sold, receiving
PELP subsidies totaling over $82,000. In
addition, the use of energy-efficient commer-
cial/institutional luminaires was promoted
through retrofits of three Polish schools.
12
Post Implementation Impact Assessment: Poland Efficient Lighting Project
After completing the retrofits, the economic
results were thoroughly analyzed and the
findings published and distributed. PELP also
sponsored design seminars and a luminaire
design competition to help raise awareness
in the Polish academic, engineering, and
industrial design communities about CFL
luminaire design.
1.3 Consumer Education Component
In order for the PELP CFL subsidy to have a
sustained impact on the market for energy-
efficient lighting products in Poland, it was
essential to develop consumer awareness of
CFLs and of the PELP promotion. The public
education component promoted the CFL
subsidy program (and CFLs generally) to
the public by providing general consumer
information on the benefits of energy-ef-
ficient lighting from a trusted nonindustry
source. Specifically, PELP fostered public
awareness of energy efficiency and CFL use
through a combination of traditional advertis-
ing vehicles and cooperation with the NGO
community and public schools. The public
education component included:
• A logo for the program designed to help
consumers identify the energy-efficient,
high-quality lighting products promoted
under the program
• Television and print advertising
• Press conferences and interviews
• A school education program
• An energy efficiency awareness program
in the Krakow area developed by the Pol-
ish Ecological Club and funded by PELP
targeted professional lighting designers
1.4 Pilot Demand-side Management
Component
The pilot DSM component was designed
to provide an important opportunity to test
the effectiveness of promoting CFLs through
Polish municipalities with the help of elec-
tric utilities. The program included targeted
installation of CFLs, a city-wide promotion
campaign, and capacity building of indig-
enous Polish expertise.
The DSM pilot was initially designed to be led
and implemented by selected electric power
distribution companies in Poland, but their
reluctance to engage in such a role forced the
pilot to be redesigned. (Among other things,
their reluctance was based on the belief
that a project that would result in reduced
electricity sales could not be good for their
business.) The new pilot design depended on
the involvement and leadership of municipal
governments, with power distribution com-
panies providing a supporting role. The DSM
pilot was implemented with the help of many
organizations, most notably the Polish Net-
work “Energie Cities” (PNEC), the University
of Mining and Metallurgy in Krakow (AGH
University), three municipal governments,
and the power distribution companies of
Torun, Bialystok, and Bielsko Biala.
Three cities – and their regional electric
utilities – were selected to participate in the
Introduction
13
DSM pilot: Chelmno, a city of about 22,000
inhabitants in north-central Poland; Elk, a
city of about 54,000 inhabitants in northeast
Poland; and Zywiec, a city of about 35,000
inhabitants in south-central Poland. They
were selected because they were willing
and able to participate and they had areas
with grid capacity problems that the DSM
pilot was designed to address. While the
entire areas of all three cities participated
in the DSM pilot, several target areas within
the cities were established for intensive CFL
promotion and electric load analysis.
1.5 M&E Component
Another important component of the project
was the monitoring and evaluation system.
This was designed to measure the effective-
ness of the project activities, as well as to
determine the environmental, economic, and
market transformation effects of the overall
program. The techniques used were a mix
of manufacturers’ and consumers’ surveys,
direct internal information produced by
the subsidy system, and third parties’ sta-
tistical and contextual analyses. The M&E
component was contracted out to Synergic
Resources Corporation and then to Navigant
Consulting.
Other stakeholders in the project included
the Polish Foundation for Energy Efficiency
(FEWE), CFL manufacturers such as Philips,
luminaries manufacturers such as Energy Sav-
ings (ES) Systems, and an advisory committee
with representatives of these organizations as
well as the Institute for Environment Protec-
tion, the Institute for Sustainable Develop-
ment, and the Polish Energy Conservation
Agency. (See Appendix A for an organiza-
tional chart of the project.)
15
2 METHODOLOGY
The following methodology was used by
the Study Team to conduct this impact as-
sessment:
Preliminary documentation review: The
Study Team initiated the mandate with a pre-
liminary review of documentation identified
in conjunction with the World Bank. This
contributed to the preparation of the detailed
proposed evaluation methodology and spe-
cific data collection tools. The Study Team
briefly reviewed documents, Web sites, and
other sources relevant to the project and to
the long-term impact assessment of DSM/EE
projects. (For a list of documents reviewed,
please see Appendix B.)
Development of a detailed evaluation meth-
odology: Based on the preliminary documen-
tation review, preliminary discussions with
World Bank staff, and experience and lessons
learned from other impact assessments, the
Study Team developed a detailed proposed
evaluation methodology for impact assess-
ment covering all aspects to be reviewed.
The draft methodology was sent to the World
Bank in Washington for review.
Development of the impact evaluation matri-
ces and data collection tools: The Study Team
developed evaluation matrices, which were
at the core of the data gathering and analysis
process. Specific matrices were developed for
each aspect of the project. Matrices addressed
the overarching objectives through detailed
sub-questions, development of appropriate
indicators of performance (using results-based
management methodology), identification of
relevant data sources, methods of data collec-
tion, and sampling approaches as required.
The evaluation matrices and associated tools
built on the final evaluations of the project,
from whence data informed a baseline from
which to measure sustained outcome achieve-
ment and larger impacts in the sector and the
country. The development of the matrices was
completed following an iterative approach
with the World Bank and other relevant proj-
16
Post Implementation Impact Assessment: Poland Efficient Lighting Project
ect stakeholders, prior to the missions in the
field. As results-based management methodol-
ogy dictates, these evaluation tools were de-
veloped in an iterative fashion and remained
flexible to be adjusted based on contextual
and current realities in the field.
Inception mission to Washington: Before the
field missions, a member of the Study Team
met with key World Bank and IFC staff in
Washington. The purpose of the inception
mission was to collect more information
and documents related to each project to be
reviewed and to get more details on potential
key informants to meet in the field. The mis-
sion also allowed the Study Team and the
client to finalize the discussion related to the
detailed proposed methodology and project
context and to begin the process of data col-
lection with key project-related staff.
Logistical arrangements for field missions:
Given the time elapsed since project closure,
the field mission was preceded by an exten-
sive logistical effort to identify and contact
the relevant stakeholders. Where possible,
original project stakeholders were targeted,
including both project implementers and ben-
eficiaries. In the field, logistical arrangements
continued to be difficult, as making contact
with key stakeholders was a challenge for a
project completed years ago. A local resource
was hired to assist with this aspect.
In-depth desk review: The further in-depth
review of all available project-related and
country or sectorally related documents al-
lowed the Study Team to acquire a thorough
understanding of the project reviewed and
of the context of both the country and sector
and to identify and develop strategies to cope
with any unforeseen barriers and challenges
to the evaluation mission. The review also
allowed further identification of persons to be
met, as well as a more in-depth understanding
of both the successes and challenges experi-
enced by the project. The desk review also
included exploratory phone interviews with
key informants.
Field mission: Two members of the Study
Team undertook a two-week mission to
Poland. They conducted interviews that
constituted the primary tool for qualitative
research. The team interviewed all key infor-
mants from various stakeholder groups. The
interviewees included representatives from
the executing agency, relevant ministries,
electric utilities, municipal representatives,
environmental nongovernmental organi-
zations (ENGOs), energy consultants, the
private sector, consumers, retailers, CFL and
luminaire manufacturers, and other relevant
stakeholder groups. (A list of stakeholders
interviewed is found in Appendix C.)
In addition, the Study Team conducted a
basic retail survey in major cities in Poland.
This involved visiting the major large, me-
dium-size, and small stores that sell CFLs and
luminaries, as well as electric and lighting
specialty shops, in order to assess availability,
Methodology
17
EE lighting promotion, and shelf space, prices,
types, brands, and other relevant data.
To learn more about some primary beneficia-
ries of the project, the Study Team held a fo-
cus group of consumers in Warsaw, in order
to collect detailed quantitative and qualitative
data to be measured against the outcomes of
the project and to assess the current state of
affairs. The team contracted with the most
nationally recognized social science research
firm (PINTOR) to assist with the organization
and independent administration of a survey
to cover these project beneficiaries. The focus
group allowed for a verification and triangula-
tion of findings from other sources.
While in the field, the team also collected
further documentation, including relevant
reports, statistical analyses, sectoral docu-
ments, policies, and laws, in an attempt to
collect documents that could not be easily
retrieved from a distance.
Data analysis: At this stage, the Study Team
compiled and analyzed all collected data.
This stage included the comprehensive and
statistical analysis of all relevant quantitative
and qualitative data. Contextual elements
were presented along with statistical results,
in order to facilitate their interpretation and
the subsequent conclusions, lessons, and
recommendations. Data triangulation was
achieved through multiple data collecting
sources, procedures, and strategies, allowing
for verification and support of the findings
presented.
Reporting: This report represents the final
version of the impact assessment report. It
integrates comments made by the World
Bank during the review process.
19
3.1 Project Context
Starting in 1992, Poland’s economy began
to grow as it recovered from the loss of
traditional markets and the shock of the
country’s initial transition away from central
planning. This renewed industrial production
was accompanied by a more rational use of
energy, which meant that Poland’s energy
consumption remained relatively stable, at
levels approximately 30 percent lower than
in 1989.1 Despite these marked improve-
ment in terms of energy efficiency at the
beginning of the 1990s, Poland’s economy
could still be characterized by inefficient
energy use.
In 1993, the United States Agency for In-
ternational Development funded a study
of DSM potential in Poland that identified
significant energy consumption associated
with lighting in the residential, commercial,
and industrial sectors. In the residential sector
in 1993, lighting use accounted for 14,550
gigawatt-hours (GWh), or 55 percent of total
electricity consumption for the sector, repre-
senting a total installed end-use capacity of
13,250 megawatts. This was consistent with
an almost exclusive reliance on inefficient in-
candescent lighting technology in homes and
the low incidence of other major electric ap-
pliances, such as heating or air-conditioning
equipment. In 1994, there were an estimated
209.5 million incandescent general lighting
services (GLS) lamps in use in Poland. The
residential sector used the most, 191 million
(91 percent); the commercial sector used 18
million GLS lamps (9 percent); and the indus-
trial sector used 500,000 GLS lamps.
The Polish CFL market was established in
1992, when Philips Lighting Poland began,
at very low levels, selling CFLs domestically.
Prior to this, sales in Poland of imported CFLs
had been negligible, and Philips was export-
ing most of the CFLs it was producing there.
Prior to the PELP program, CFLs cost at least
PLN (or zloty) 38 ($15.14) at retail, compared
with PLN 1 (40¢) for an incandescent lamp.
3 PELP PROJECT IMPLEMENTATION
20
Post Implementation Impact Assessment: Poland Efficient Lighting Project
Although CFLs were already a cost-effective
investment for Polish consumers at prevailing
electricity rates, this price difference posed
a significant “first cost” barrier. Therefore,
some types of product subsidy to lower the
retail price was seen as the most effective
way to stimulate the market. In addition,
benefits of CFL use needed to be spread and
raised at various levels to further stimulate
consumer interest. The potential market was
significant, with Poland’s population nearing
35 million.
3.2 Achieved Project Outcomes
Project outcomes can be defined as observ-
able results that can be measured at the end
of a project. Based on the review of existing
reports and evaluations, this chapter summa-
rizes the project outcomes achieved in terms
of the objectives described in Chapter 1 – re-
ducing GHG emissions in Poland, maximiz-
ing benefits from domestic CFL manufacturing
resources, developing the capacity of Polish
entities to deliver DSM resources, and dem-
onstrating the value of DSM programs.
3.2.1 Energy Savings and Reduction
in GHG Emissions
Within the context of the M&E component
of the PELP project, a final evaluation of
project outcomes in terms GHG reduction
was realized.
The direct impacts were estimated using stan-
dard evaluation methods for residential light-
ing programs. PELP’s energy impacts were
quantified through impact parameters, such
as the number of CFLs installed in each type
of room (kitchen, living room, or bathroom,
for example), the average number of hours
each room’s CFL was on over the course of
one year, and so on. Once the program’s
annual impact in terms of energy savings (in
kilowatt-hours, kWh) was estimated for the
life of the lamps, these values were then con-
verted to the total amount of carbon dioxide
(CO2) reduced using annual estimates of the
emission rates of plants generating marginal
power.
According to the final evaluation, the CFL
subsidy component of PELP produced direct
and verifiable electricity savings of at least
435 GWh and GHG reductions totaling at
least 529,000 tons of CO2. These direct im-
pacts refer to the effect of the purchase and
installation of subsidized CFLs only during
the two-year CFL subsidy program, exclusive
of any spillover or market transformation ef-
fects (that is, installations resulting indirectly
from the program).
This evaluation also provided the estimated
total program impacts, which account for
the overall market transformation impacts of
the program (all aspects of the project) and
therefore are larger than the direct impacts of
the CFL subsidy project component. Accord-
ing to the evaluation, the entire PELP project
produced a total electricity savings of at least
2,320 GWh and GHG reductions of at least
2.79 million tons of CO2. Total estimated
PELP Project Implementation
21
program savings included those resulting
from the transformation of the Polish CFL
market attributable to PELP. Data indicate
that PELP accelerated the maturation of the
Polish CFL market toward saturation within
approximately three years. The methodol-
ogy used to calculate total program impact
is discussed further in Chapter 4.
3.2.2 Project Benefits to the
Polish Economy
The final evaluation of PELP highlighted the
several transformations that occurred in the
CFL market in Poland between the beginning
and the end of the project. The major transfor-
mations occurred at the following levels:
• Price: By the end of the PELP initiative, the
retail price of CFLs had decreased by 34
percent in real terms relative to 1995.
• Penetration rate: PELP significantly in-
creased the number of Polish household
using CFLs. CFL penetration in Poland
increased from 11.5 percent of households
prior to PELP to 33.2 percent one year af-
ter the PELP initiative. The penetration of
CFLs was then higher than in many other
countries, even some of the higher-income
countries such as the United Kingdom and
the United States.
• Sales: CFL sales increased in Poland at
more than double the rate in the rest of
Central and Eastern Europe.
• Stock of CFLs: CFLs are more widely
stocked. This wider retail availability was
being sustained.
• Consumer intention: The percentage of
consumers intending to purchase CFLs in-
creased from 29.2 percent to 37.8 percent,
and they intended to purchase significantly
more CFLs (2.41 in the first program year
to 3.45 post-program).
• Distribution system: Prior to PELP, distri-
bution of CFLs was primarily from manu-
facturers to wholesalers to small retail
shops selling a limited range of electrical
products. During the program, CFLs also
began to appear in the new hypermarkets
and supermarkets that were becoming
popular, and also in home centers.
• Consumers’ allegiance: 97 percent of
purchasers of CFLs intend to replace their
CFLs with another one when the current
bulb burned out.
• Media coverage: Print media coverage in-
creased and shifted from explaining CFLs
to describing where and how to best use
them, indicative that CFLs are becoming
more common rather than something that
needed to be introduced to consumers.
• Number of manufacturers: New manufac-
turers entered the Polish market.
In terms of the impact on manufacturers,
restricting participation to Polish manufac-
turers did not prove to be an effective way
to strengthen them.2 The “Polish content”
requirement did not appear to benefit any
parties. Rather, this requirement excluded the
second largest manufacturer of CFLs serving
Poland (Osram). Although every effort was
made to encourage small and medium-size
22
Post Implementation Impact Assessment: Poland Efficient Lighting Project
enterprises to participate through widespread
outreach and targeted negotiations, market
conditions worked against their full involve-
ment. The ones that initially participated in
PELP were either consolidated into larger part-
ners or chose to leave the market. However, it
is important to recognize that it may be overop-
timistic for market transformation programs to
expect to accomplish “mixed agendas” (such
as supporting local manufacturers) in addition
to the primary objective of accelerating the
penetration of a certain technology.
3.2.3 Level of Awareness to Potential Ben-
efits of DSM Programs and DSM Capacity
Building
A primary goal of the DSM pilot was to de-
termine the impact of the CFL installation on
critical locations with capacity problems in
the distribution system, including the peak
demand, load shape, and energy impacts.
The IFC/GEF Poland Efficient Lighting Proj-
ect: Demand-Side Management Pilot Report 3 demonstrated that:
• Reduction in peak demand can be signifi-
cant: Monitored results indicated that a 15
percent drop in residential peak electricity
demand was achieved in targeted neigh-
borhoods of selected distribution utilities
facing near-term capacity constraints.
Moreover, some households exhibited up
to a 40 percent reduction in peak power
usage.
• CFL sales achieved during a short amount
of time can be high: In the pilot project,
more than 33,000 CFLs were sold in six
weeks.
• Saturation levels can top five CFLs per
households: In the targeted districts,
saturation levels reached 5.36 units per
household.
• High-density installation of CFLs does
not have an impact on power quality: No
adverse power quality effects could be
ascribed to the installation of non-power-
quality-corrected CFLs.
• DSM could be a cost-effective option for
electric distribution utilities: Researchers
concluded that given the avoidance of the
need to build new transformer capacity
as a result of the savings generated by the
high concentration of CFLs installed, the
program would have been cost-effective
for the local electric distribution utility to
implement itself.
As expected, the project helped build capac-
ity within the utility sector to successfully
implement future DSM efforts. It demon-
strated the direct and indirect economic and
environmental benefits to be derived from
DSM efforts. The project built awareness and
developed the capacity necessary for broader
DSM initiatives, which are critical for the
long-term success of integrated resource plan-
ning in Poland. The cost of reducing GHG
emissions could in certain cases be negative
because the DSM programs potentially cost
less than building or upgrading power plants
and the power grid.4
23
4.1 Post-project Context
Before discussing impacts as such, it is useful to
look at the overall macro policy and economic
context surrounding the post-implementation
of PELP. In 1997, the Polish Energy Law (1997)
was enacted. It provided official policy sup-
port for EE-related measures. For instance, it
espoused the need for municipalities to plan
for EE at the local level by developing energy
plans. It states, “local government is respon-
sible for elaboration of heat supply plans… and
utilisation of surplus local energy sources.”
The law further states that each municipality
should have someone responsible for EE in a
municipal government position.
Recently, however, the focus of government
support and policies with regards to energy
and the environment has been on renewable
energy (RE) rather than EE. The implementa-
tion and enforcement of the energy law with
respect to EE has therefore lagged somewhat
behind.
Indeed, in recent years accession to the
European Union (EU) has been the highest
political priority for Poland. The negotiation
process toward full EU membership started
in 1998. In January and February 1999,
the first technical phase of the negotiations
on the environment chapter of the acquis
communautaire began with a review of the
environmental legislation system. The trans-
position of more than 170 EU legislative
acts, some of which directly or indirectly
affected the national GHG emission profile,
was completed in December 2002. Poland
was the biggest new country to join the EU
on May 1, 2004.
In line with the focus on EU accession, in
September 2000 the Polish Council of Minis-
ters endorsed the Renewable Energy Strategy,
and in August 2001 the was accepted by the
Parliament. The strategy, put forward by the
Ministry of Environment, calls for 7.5 percent
of primary energy to come from renewable
sources by 2010. EU accession, the primary
4 IMPACT ASSESSMENT
24
Post Implementation Impact Assessment: Poland Efficient Lighting Project
motivation for change in government policies
in recent years, places much more emphasis
on RE than EE. It is quite clear that “the Polish
policy regarding renewable energy is guided
by the accession to the EU.”5
An important contextual factor is that Poland
currently has overcapacity in the electricity
generation sector; DSM/EE is therefore not
the prime priority of utilities either. Gener-
ally, DSM/EE is marginally being promoted
by utilities in the following cases:
• When it allows for avoidance of large in-
frastructure investments: Therefore, given
the overcapacity in Poland, utilities are
most often interested in “peak shaving”
only, which refers to reducing the amount
of electricity consumption during peak
times of the day or year (in the winter, for
example, or weeknights after work).
• When there is competition with alternate
sources of energy and distribution compa-
nies (such as gas distribution companies):
EE becomes a way for a utility to secure a
market through long-term service contracts
attached to the EE measures for the end us-
ers, which usually means for the end user a
better service or lower monthly electricity
bills.
• When end users, such as municipalities,
are pushing for EE themselves: This is
the exception rather than the rule how-
ever,, as municipalities normally require
a “partner” with the necessary financial
resources and capacity to undertake EE
initiatives. They rarely have the funds to
finance the EE measures themselves, given
their precarious financial situation in the
new government decentralization now in
taking place in Poland.
The context for coal production and use in
Poland is also significant for this assessment
of PELP, in order to better understand the
enabling and economic environment in
the country. It is important to note that the
coal sector is a central part of the country’s
economy and society, providing 80 percent
of energy generation. The sector provides
many jobs. The larger context for transferring
to other forms of power generation remains a
complex issue in Poland, in both economic
and social terms. With unemployment cur-
rently at 18 percent and with more job loss to
be expected by reducing coal production, it is
a sensitive social and political issue. In addi-
tion, the historically influential “coal lobby”
remains active in Poland. This is why, some
stakeholders noted, government support
was not perceived as being strong for PELP
and similar EE initiatives, which encourage a
decrease in energy consumption and there-
fore in coal electricity generation. From the
government’s perspective, the political and
social costs of creating new jobs in the RE
sector, in biomass energy production, for ex-
ample, are much lower than the political and
social costs of reducing energy production
through DSM or EE, which involves laying
off coal miners without creating alternative
jobs in the energy sector.
Impact Assessment
25
In December 2002, Poland ratified the
Kyoto Protocol, thus making a commitment
to reduce its aggregate emissions of GHGs so
that average annual emissions in the period
2008—12 do not exceed its assigned amounts
(6 percent below 1988 total GHG emissions).
However, given the challenges of both the
economic transformation process and the EU
accession process, at the beginning of the
twenty-first century climate change is not seen
as a political priority in Poland. Correspond-
ingly, the Study Team of the Third National
Report of Poland on the climate change treaty
noted a low financial budget and very limited
administrative capacity in this field.6 Still, Po-
land expressed its intention to make use of the
flexible mechanisms of the Kyoto Protocol.
Poland has undertaken several activities to
mitigate emissions of GHGs; these were
actions implemented jointly or joint imple-
mentation projects with Norway (such as
coal-to-gas conversion in 30 nonindustrial
boiler houses and energy efficiency improve-
ments in new residential buildings), with the
Netherlands (heating system modernizations,
district heating systems, biomass boiler instal-
lations), and with Canada (small hydropower
plants). In addition, Poland intended to join
the EU emissions trading market in 2005.
In terms of government commitment to EE
for reducing GHG emissions, it is important
to note that total GHG emissions in Poland
fell by 32 percent between 1988 and 2000,
largely reflecting the restructuring of its
economy and energy sector. The greatest
emission reductions were achieved in en-
ergy supply (—32 percent) and energy use in
the residential and commercial sector (—59
percent). This drastic reduction in GHGs is
an important part of the context of current
priorities in Poland. In 2000, Poland’s GHG
reductions were already well beyond the
Kyoto target of a 6 percent drop from 1988’s
level. Nonetheless, the Study Team of the
Third National Report of Poland felt that
major domestic GHG reduction potential
had not been fully exploited, as Poland’s
GHG emission intensity (the per unit gross
domestic product (GDP) per capita, for ex-
ample) was high compared with that of West
European countries.
It is in this context – accession to the EU,
overcapacity for electricity generation,
achieved GHG emission reduction, and the
social implications for switching away from
coal production – that EE was found quite
far down the list of government priorities in
Poland in 2004. Therefore, although some-
times in the official discourse the government
supports EE, it is much more inclined toward
the transition to RE sources when it comes
to action. This has had a significant impact
on the evolution of EE in Poland and on the
assessment of the impacts of PELP.
4.2 Findings and Analysis
4.2.1 Global Environmental Impacts
This area of assessment focuses on analyz-
ing how much the project has affected the
26
Post Implementation Impact Assessment: Poland Efficient Lighting Project
global environment. This section begins by
reassessing the results obtained from the
final evaluation conducted by Navigant at
the end of the project (see section 3.2.1).
Although data and statistics were difficult to
obtain for assessing energy savings from EE
lighting, which complicated extrapolations
for estimating GHG emission reduction, the
Study Team attempted to assess this to the
extent possible and also to assess whether
Navigant’s projections were still accurate,
given what we knew about the Polish CFL
market in 2004.
At any given year X after a project start-up, the
impact of a project in terms of the global stock
of GHG can be defined as the estimated dif-
ference between TX-real, the estimated global
stock of GHG in year X, and TX-hypothetical, the
hypothetical global stock of GHG in year X
had the project not occurred.
have been realized. Under this assumption
the impact on PELP in that year and in every
subsequent year would be nil and PELP
would not have had an impact on the CFL
market saturation level. This assumption im-
plied that with PELP, market saturation would
have been achieved earlier than it would
have been in the absence of the program,
but that ultimately the maximum market size
would remain unchanged.
Estimation of Energy Saving
The amount of energy saved from the project
was calculated by using the estimate of GWh
savings per CFL derived from the direct im-
pact analysis7 and by defining a projection of
CFL sales from the start of the program until
several years in the future. This projection
was then compared with a baseline projec-
tion for Polish CFL sales if there had been
no PELP project. The baseline used was
based on the average sales growth rate that
the International Agency for Energy-Efficient
Lighting (IAEEL) estimated for all of Eastern
Europe, including Poland. Total estimates for
GWh saved were calculated based on the
following formula:
Project Intervention TX
Yes Stock of GHG X-real
No Stock of GHG X-hypothetical
To evaluate the total project impacts in terms
of GHG reduction, Navigant determined year
X as the year in which the Polish CFL market
would have reach saturation in the absence of
the PELP project. In that year, they assumed
that the stock of CFLs installed in Poland
would be the same in the two scenarios and
that all global environmental benefits would
ES GWh CFLSprog CFLnoprog ESfactoi
i
n
i( ) ( )*= −
=∑
1
rri
ES(GWh) = Total program estimated energy
saving in GWh in year i
i = Year 1 of the project ( 1995)
n = Number of years between the first year
of the project and the year in which the
Impact Assessment
27
counter-factual scenario for the CFL market
would have reached saturation (2005)
CFLSprogi: Stock of CFL installed in the year
i with PELP
CFLSnoprogi: Estimated stock of CFL in-
stalled in the year i in the counter-factual
scenario (no PELP)
ESfactori: Energy saving factor per CFL in-
stalled in GWh in the year i
Estimation of GHG Emission Reduction
Reductions in GHGs (or CO2 specifically)
resulting from the net direct electricity savings
were determined by FEWE using an hourly
production cost model to determine which
power plants would be operated less due to
the electricity savings:
ACO2: Total program estimated CO2
avoided
i = Year 1 of the project ( 1995)
n = Number of years between the first year
of the project and the year in which the
counter-factual scenario the CFL market
would have reached saturation
ESi: Estimated energy saving in year i in
KWh
CO2RIi: CO2 Reduction Index (kg CO2/ kWh)
= Average tons of CO2 saved per kWh not
produced in year i
The Study Team reassessed the hypotheses
used by Navigant to calculate total program
impact.
Market saturation level and timing
During project implementation, the potential
Table 4.1 Total Estimated Energy Saving
Thousands of Bulbs
Estimated Stock of CFLs Stock of CFLs Added CFLs Energy saving Energy Saving Installed Installed from PELP factor per (GWh) with PELP with no PELP CFLSprogi- CFL installed in kWh/bulb CFLSprogi CFLSnoprogi CFLSnoprogi ESfactori ES(GWh)
1996 6216 4701 1515 56,7 86
1997 9681 6809 2873 56,7 163
1998 13645 9219 4426 53,3 236
1999 18188 11982 6206 53,3 331
2000 22152 14062 8090 53,3 432
2001 25515 16318 9198 53,3 491
2002 25515 18771 6745 53,3 360
2003 25515 21694 3821 53,3 204
2004 25515 25172 343 53,3 18
2005 25515 25515 0 53,3 0
Total 2320
ACO ES CO RIi
i
n
i21
2=
=∑ *
28
Post Implementation Impact Assessment: Poland Efficient Lighting Project
size of the Polish market for CFLs was esti-
mated by the International Institute for Energy
Conservation (IIEC) to be 21—26 million units,
with annual sales reaching saturation at 4
million units.8 When Navigant conducted
the evaluation at the end of the PELP proj-
ect, the three leading Polish manufacturers
were asked to forecast annual sales for 1998
through 2002 and the year they believed the
market would reach saturation. The responses
were weighted by each manufacturer’s 1997
sales in Poland. The forecast of CFL sales
increases between 1998 and 2002 were as
follows:
At the same time, manufacturers predicted
that market saturation would be attained
when the average number of CFLs per
household reached 2.43 (that is, 25.5 million
CFLs based on a constant 10.5 million house-
holds). This implied that market saturation
was to occur in 2001 with the PELP Project
and in 2005 without the project.9 Navigant
took the assumption of a constant number
of households in Poland for conservative
purposes; however, it should be noted that
this was inconsistent with a 17.1 sales growth
rate predicted for 2002.
In 2004, the projected number of households
in Poland was estimated at 13.7 million.10
Keeping the 2.43 CFLs per household as the
saturation level, this would imply that 33.29
million of CFLs were installed by 2004. This
alone is consistent with the significantly
higher annual sales than predicted by the
IIEC and Navigant (about 4 million CFLs per
year). However, as the number of annual
Table 4.2 Total Estimated GHG Reduction
Estimated Energy Saving CO2 reduction CO2 reduction (GWh) index (000 tons)
1996 85.9 1.27 109.1
1997 162.8 1.24 201.9
1998 236.1 1.23 290.4
1999 331.1 1.21 400.6
2000 431.6 1.20 517.9
2001 490.7 1.19 583.9
2002 359.8 1.18 424.6
2003 203.8 1.18 240.5
2004 18.3 1.17 21.4
2320.1 2790.4
Table 4.3 Forecasts of CFL Sales Increases
Year Sales Increase Over the Previous Year
1998 14.4%
1999 14.6%
2000 15.9%
2001 16.0%
2002 17.1%
Impact Assessment
29
CFL sales is currently estimated by major CFL
manufacturers at about 9 million, using the
17.1 percent growth rate for 2002 and a con-
stant annual sales growth rate of 12.2 percent
per year in 2003 and 2004 to arrive at the
estimated 9 million units sold in 2004 would
mean that the total stock of CFLs installed
would have already reached more than 39
million units. This indicates that the satura-
tion level of CFLs per household in Poland is
probably over 2.43 per household.
Everything else being equal, a higher number
of households and a saturation level higher
than 2.43 CFLs per household would imply a
greater impact of PELP in terms of reduction
in total energy consumption. This would be
true even if we assume that this higher satura-
tion level has not been induced by PELP and
is in fact the baseline saturation level. Based
on the assumption of an annual sales growth
rate of 17.1 percent in 2002 and 12.2 percent
in 2003 and 2004, total GHG emission reduc-
tion could be more that 35 percent greater
than estimated by Navigant.
Energy saving factor per
CFL installed in GWh
Energy saving factors per CFL installed in
GWh were calculated by Navigant using the
following formula:
Esfactor i= Energy saving factor per CFL
installed in GWh in year i
∆W i = Wattage of bulb replace minus watt-
age of CFL installed per location
HrsOP i = Hours of operation of the CFL
installed per location
ADJfactor i = Adjustment factor in year
i=free ridership factor in year i *persistence
factor in year i *snapback factor in year i
*usage adjustment in year i *T&D losses
factor in year i
An in-depth reassessment of the energy sav-
ing factor per CFL installed was beyond the
scope of this impact assessment. However, it
should be mentioned here that growing num-
bers of new, cheaper, less-efficient CFLs on
the Polish market might have had a negative
impact on the energy saving factor per CFL
installed. Low-cost CFLs can be up to 50 per-
cent less efficient than other brands. It is not
clear what fraction of the market share is held
by the cheaper and less-efficient CFLs, but
according to the major CFL manufacturers,
the market share of low-cost CFLs has been
growing steadily over the last few years.
Everything else being equal, a growing mar-
ket share of low-cost CFLs would imply a
lower energy savings factor per CFL installed,
inducing a lower impact of PELP in terms of
a reduction in total energy consumption. For
example, if half the stock of CFLs installed
was 50 percent less efficient than assumed
by Navigant between 2000 and 2004, this
would imply that the total GHG emission re-
ductions resulting from PELP would be about
15 percent less than Navigant estimated. It
ESfactor GWh W HrsOP ADJfactori i i i( ) * *= ∆
30
Post Implementation Impact Assessment: Poland Efficient Lighting Project
should be noted here that it is extremely un-
likely that as much as 50 percent of the stock
installed between 2000 and 2004 was 50
percent less efficient than in previous years,
and these numbers are used for conservative
estimation purposes.
Based on this analysis, the Study Team con-
cluded that the total impact of the PELP proj-
ect in terms of reduction in GHG emissions
as estimated by Navigant in 1999 had already
been achieved. Using available information
on the current CFL market, the Study Team
approximated the total GHG impact attribut-
able to PELP at 3.62 million tons of reduced
CO2, a substantially higher figure than the
2.79 million tons estimated by Navigant in
1999. This difference was due essentially
to a larger than originally estimated market
saturation level for CFLs in Poland. Details
and assumptions are shown in Table 4.4.
It should be noted that this result is obtained
holding the very conservative assumption
made by Navigant concerning the adjustment
factors, in particular the arguable free rider-
ship factor of 15 percent.11 A free ridership
factor could be included in an adjustment
factor to take into account that a portion of
the households would have purchased and
installed the same number of CFL bulbs with
or without PELP. However, in this particular
case it could be argued that the free riders
included in the numbers for the PELP case
Table 4.4 CFL Sales, Energy Savings, and GHG Emission Reductions with and without PELP
With PELP Counter-factual Scenario
Energy Total Saving CO2 Total Annual Stock Added Factor Reduc- CO2 Annual Annual Stock Sales Annual of CFLs per CFL Estimated tion Reduc- Sales Sales of CFLs of Sales CFLs from Installed Energy Index tion of CFLs Growth Installed CFLs Growth Installed PELP in kWh/ Saving (kg CO2/ (000 (000) Rate (000) (000) Rate (000) (000) bulb (GWh) KWh) tons)
1996 2938 103.3% 6 216 1621 30.0% 4701 1515 56.7 86 1.27 109.1
1997 3465 17.9% 9 681 2107 30.0% 6809 2872 56.7 163 1.24 201.9
1998 3964 14.4% 13 645 2411 14.4% 9219 4426 53.3 236 1.23 290.4
1999 4543 14.6% 18 188 2763 14.6% 11982 6205 53.3 331 1.21 400.6
2000 5208 15.9% 22 152 3202 15.9% 14062 8090 40.0 324 1.20 388.4
2001 5971 16.0% 25 615 3715 16.0% 16318 9298 40.0 372 1.19 442.7
2002 6846 17.1% 29 649 4350 17.1% 18771 10878 40.0 435 1.18 513.6
2003 7849 12.2% 34 104 4880 12.2% 21481 12623 40.0 505 1.18 596.0
2004 9000 12.2% 39 015 5474 12.2% 24468 14548 40.0 582 1.17 681.0
Total 3034.0 3623.7a Growth rate for 2003 and 2004 were set at 12.2 percent so that the annual sales for 2004 would be of 9 million units, as estimated
by the major national CFL manufacturers.b Total stock of CFL = previous year stock + the annual sales – 90 percent of the CFLs installed five years earlier.c The energy saving factor used for 2000 onward assume that 50 percent of the CFL stock installed is 50 percent less efficient than
the average stock installed in 1999.
Impact Assessment
31
are also included in the counter-factual
scenario.
In addition, it is worth noting that the global
environmental benefits in terms of GHG
emission reductions induced by the projects
that were inspired by the PELP experience (or
that replicated PELP to some degree) could
be significant. Anticipated impacts of three
key PELP follow-up or replicated projects
are in the range of 18.4 million tons. (See
Table 4.5.)
Energy Consumption in Poland
Furthermore, Figure 4.1, with statistics col-
lected by FEWE, demonstrates that although
there was an increase in GDP in Poland over
the last few years, energy consumption has
Table 4.5 GHG Emission Reductions in Programs That Replicated PELP
Post-PELP Projects Tons of CO2 reduced (000)
PNEC (Post PELP Project) 10
Efficiency Lighting Initiative 14,735
Polish Efficient Motor Project 3,682
Total 18,427a See section 4.3 on Replicability for more information on these projects.b Polska 2000.c GEF, Efficient Lighting Initiative, Project Document.d GEF, Polish Energy Efficient Motors Programme (PEMP), Project Document.
Figure 4.1Energy Consumption, Intensity and GDP in Poland 1997—2002 (FEWE)
Ele
ctri
city
co
nsu
mp
tio
n [
TW
h]
&G
DP
[10
^9
PL
N]
Ele
ctri
city
co
nsu
mp
tio
n [
TW
h]
&G
DP
[10
^9
PL
N]
Year
Gross Domestic Product [10^9 PLN, price 2003]
1997 1998 1999 2000 2001 20020
100
200
300
400
500
600
700
800
900 220
210
200
190
180
170
160
Electricity intensity [kWh/10^3 PLN 2003]
Electricity total consumption [TWh]
32
Post Implementation Impact Assessment: Poland Efficient Lighting Project
remained rather constant and energy intensity
has decreased substantially. A representative
from the manufacturer Philips – who was
quite involved with PELP, was around before
the project, and has remained a significant
player in the lighting sector in Poland – af-
firmed that “PELP contributed to a general re-
duction in electricity consumption in Poland”
through its promotion and expansion of CFL
use. Figure 4.1 substantiates that electricity
consumption has stayed rather constant over
time, with minor fluctuations.
4.2.2 Impacts on Institutional
Development
While increased institutional development
and capacity was an outcome of the project
in 1998, sustainable capacity and institutional
development are important parts of this im-
pact assessment. At the overall market level,
capacity impacts can be looked at in terms
of five required capacities:
• Capacity for information management and
awareness raising on EE and DSM
• Capacity for policy making, planning, and
decision making on EE and DSM
• Institutional capacity to implement deci-
sions on EE and DSM
• Capacity to enforce legislation
• Capacity to pool resources (human, finan-
cial, ecological and technological)
This section presents, in a summary fashion,
an assessment of the various capacities that
have been developed and in some cases sus-
tained over the years since the project ended.
Although there have been impacts on institu-
tional development, various capacities at vari-
ous levels still need to be built to further EE
and DSM to induce full market transformation
in the lighting sector in Poland. In addition,
some of the challenges being encountered
in the development of EE or use of DSM are
also brought forth in this analysis.
The Study Team assessed impacts of the
project on institutional development and the
sustainability of the capacities developed or
required to sustain market transformation by
looking at the following actors in the EE/DSM
market in Poland:
• Various government ministries: level of
awareness, promotion, and use of efficient
lighting and other EE policies, plans, regu-
lations, and so on, including DSM
• Involved municipalities: level of aware-
ness, capacity, promotion, and use of ef-
ficient lighting and other EE policies, plans,
regulations, and so on, including DSM
• Electric utilities: level of awareness, capac-
ity, and use of EE in the lighting and other
sectors and of DSM approaches
• Academic institutions such as AGH Uni-
versity: level of awareness, capacity, and
promotion of EE in the lighting and other
sectors and of DSM
• Private sector actors, such as energy or en-
vironmental consulting firms, and energy
or environmental institutes or agencies,
such as FEWE: level of awareness, capac-
Impact Assessment
33
ity, and promotion of EE in the lighting
and other sectors and of DSM
• ENGOs: level of awareness, capacity, and
promotion EE in the lighting and other
sectors and of DSM
• Energy service companies (ESCOs): devel-
opment in the EE market in Poland since
the project
This assessment focuses on the current capac-
ities of these stakeholders, and capacities are
analyzed at national, county or voivodship,
and municipal levels. For ease of discussion,
the specific capacity developed by manufac-
turers and the sustainability of that capacity
is dealt with in section 4.2.3.
Capacity for Information Management and
Awareness Raising on EE and DSM
National level
Awareness raising at the national level must
have some degree of government support,
and this would require, at a minimum, that
the government is aware of and recognizes
these issues as priorities. This study has
shown that, to some degree, EE and DSM are
not current priorities of the Polish govern-
ment, although the team met stakeholders
in, for example, the Ministry of Environ-
ment who are aware of issues surrounding
EE. The government is certainly committed
to raising awareness of renewable energy,
especially in the context of EU accession and
related commitments, but is not currently
actively promoting EE or DSM specifically,
for reasons noted earlier. This view was
confirmed by numerous stakeholders in-
terviewed through the assessment mission,
which highlighted the general absence of
the government as an active player in proj-
ect implementation and afterwards in the
EE/DSM market scene.
There are, however, other places where this
capacity resides and is being exercised. For
example, AGH University and other aca-
demic institutions across the country have
expertise on EE and DSM and are spreading
it through their curriculum, building on the
PELP experience. PELP has contributed to
strengthening that capacity and AGH recog-
nition. According to academic stakeholders,
the topic is very popular now at AGH and
at many other universities and colleges,
and, through the curriculum, awareness and
expertise on EE and DSM issues are being
transferred to the student body in various
localities. There are 18 universities and 20
technical colleges that are currently involved
in this kind of curriculum in Poland. Stake-
holders noted that these courses emerged
after or during PELP.
In various universities, demonstrations were
made during and after PELP, based on the
project’s experience, about the benefits of
using CFLs. In many classrooms, this contin-
ues to this day. Academics estimate that each
year, 1,800 experts in energy (most of whom
have training in EE and DSM) graduate from
these academic institutions. The demonstra-
tions at the university have also served as
34
Post Implementation Impact Assessment: Poland Efficient Lighting Project
key awareness-raising activities for utilities,
municipalities, and other actors.
AGH University stakeholders also noted that
PELP helped them learn how to teach others
about the positive effects of DSM and EE
lighting, including how to convey an often-
complicated technical message or argument
in lay terms. This has been a key capacity
that remains and that contributes to spread-
ing further awareness of EE and DSM at the
national level.
The ENGO Polish Network “Energie Cites”
is also spreading awareness of EE and DSM
nationally and to municipalities, building on
its PELP experience. The group is currently
working through other projects, such as EU-
funded projects, on these issues. PNEC stake-
holders argued that PELP helped raise their
profile as a nexus of information and capacity
for EE and DSM, and they have since built
on this to become an important player, both
nationally and regionally, with neighboring
countries in terms of national and regional
EE projects and awareness raising campaigns.
PNEC’s association has 33 municipalities in
Poland and regional links with countries like
Romania, Hungary, and Ukraine, all of which
they currently work with. (For more informa-
tion on PNEC’s projects and partners, both
national and regional, see section 4.3.) PNEC
actions, however, remain to date almost to-
tally project-dependent. The group’s capacity
to pull in long-term and secured funding to
finance its core information management
and awareness raising agendas for EE/DSM
remains limited.
Municipal level
Capacity for awareness raising at the munici-
pal level differs among municipalities. The
relation to PELP is relatively significant here,
as stakeholders suggested that some munici-
palities that were involved with the project
(or post-PELP) activities have this capacity and
awareness. For example, the municipality of
Elk is proud of its energy efficiency practices.
It was among the more successful areas of the
project and remains committed to EE today, at
least according to stakeholders interviewed.
Many other municipalities, however, have
little to no capacity for awareness raising on
EE issues or few financial resources for such
activity, according to most stakeholders. Un-
fortunately, this capacity, and will to exercise
it, is often “person-specific,” dependent on
a particular individual’s commitment to or
awareness of EE as an issue.
The capacity to raise awareness at the
municipal level currently resides within
organizations such as FEWE and energy
consulting firms and companies, which also
depend largely on project-specific funding.
Stakeholders suggested that FEWE and energy
consulting companies have been trying to
work with municipalities to raise awareness
and knowledge of EE at municipal levels.
These organizations continue to work with
schools and other institutional entities at the
municipal level to raise awareness of EE and
Impact Assessment
35
DSM, using experiences from PELP in their
approaches.
Beyond efficient lighting, consumers are
not organized to promote quality in the EE
and DSM market in a systematic fashion.
The consumer association, for instance,
does not have the staff, strategy, incentives,
and relationship with the market required
to act and organize consumer resources to
promote further the useful products in that
market and ensure quality control from an
independent perspective. From the perspec-
tive of sustainability, the project may not
have made the best use of some available
networks where such capacity resides, like
the Polish Federation of Consumers, which
even today could make a contribution to
spreading knowledge and awareness on EE
issues and products.
It should be noted here that the manufacturer
Philips also works at the municipal level to
raise EE awareness. Of course, the motive is
sales of CFLs, but the EE arguments are still
valid and help to raise awareness.
Interestingly, some stores and in particular
hypermarkets act as key actors raising aware-
ness of the benefits of CFLs and EE lighting
for consumers. The Study Team visited some
stores that had displays (sometimes paid for
by manufacturers, such as Osram) showing
the energy efficiency of CFLs and the longer
life to be expected from the purchase of the
EE bulb. The demonstration included a lit CFL
and a regular bulb in a lighting competition,
displaying hours in use, wattage used (energy
consumption), and life left, thus clearly illus-
trating the benefits of EE and CFLs. However,
the amount of media and overall publicity on
EE and CFLs has decreased significantly since
the end of PELP; manufacturers and consum-
ers both confirmed this. The most frequent
source of initial awareness about CFLs, ac-
cording to consumers from the representative
focus group surveyed by the evaluation, was
“word of mouth” from friends or family. For
one-third of consumers, this was the most
frequent response to the question of how they
became aware of the existence of CFLs.
Many stakeholders argued that the current
state of EE awareness-raising in Poland is,
to some extent, related to the project’s em-
phasis: the focus of PELP was on the product
(CFLs) and its financial advantages, and the
need to shift toward purchasing the product,
rather than on the rationale or motivations for
environmental actions that should underlie
that shift. Early in the project, advisory com-
mittee stakeholders (including representatives
from FEWE, academic institutions, and EN-
GOs) criticized the long-term approach of the
project based on this financial emphasis and
expressed these concerns to the Study Team.
As a consequence, over the long term aware-
ness of the link between energy-efficient
behavior or personal consumption habits and
the effects on the global environment were
not widely understood. Thus the capacity
for EE awareness raising at the municipal or
36
Post Implementation Impact Assessment: Poland Efficient Lighting Project
local level will require further emphasis and
continued efforts. It is recognized, however,
that the emphasis PELP placed on achieving
market transformation was appropriate in the
Polish context, so this observation is made in
a context of learning and for potential consid-
eration before future interventions.
Capacity for Policy Making, Planning, and
Decision Making on EE and DSM
National level
The 2000 RE strategy of the government of
Poland demonstrates some capacity for EE,
indicating that “information flow and help to
the local governments in the area of supply of
energy and rational use of energy, including
renewable energy sources should be granted,
secured at minimal environmental costs.”
Similarly, other official governmental docu-
ments also encourage efficient and sustain-
able energy planning at the local level, and
this is justified by the statement in the Polish
Energy Law from 1997: “local government
is responsible for elaboration of heat sup-
ply plans … and utilisation of surplus local
energy sources.” It is not likely that PELP has
had any impact on capacity at this level, as
such strategies and documents were drafted
before or early in the implementation of
PELP. This has been confirmed by stakeholder
interviews as well.
Nevertheless, the existence of the 1997 En-
ergy Law demonstrates that capacities exist
within various ministries (such as the Minis-
try of Environment or Ministry of Economy)
for policy making for EE and DSM. Yet, as
indicated earlier, the current government
focus at the level of planning (strategies for
action) and actual support is not as much
on EE and DSM as it is on RE production
and use.
The overall assessment thus is that the re-
quired capacity for policy making is indeed
in place, but the problem is the lack of capac-
ity or, at a minimum, a willingness to plan
and implement those policies. In that sense,
the national enabling environment for EE
market transformation is still incomplete. To
complicate matters, certain laws constrain
EE and DSM at other levels in the country.
For instance, the national law on municipal
budgets prevents municipalities from using
savings from DSM investments for replica-
tion of such actions. The law states that
money has to return to the national budget.
This, naturally, impedes further EE efforts in
some cases.
Municipal level
Renewable energy is, by its nature, dispersed
and closely linked to the local environment,
and it is clear that sustainable energy plan-
ning requires the involvement of munici-
palities throughout Poland.12 Under the 1997
Energy Law, local authorities are required to
develop local energy plans taking into ac-
count locally available renewable sources of
energy. However, “the most important barrier
to addressing sustainability in local energy
planning is lack of expertise at the local level,
Impact Assessment
37
which is extremely difficult to develop and
implement, owing to the lack of knowledge,
data and skills there.”13 The responsibility
for energy planning is clearly now at the
municipal level only, but this assessment con-
firmed that generally this capacity does not
exist systematically in most municipalities. In
addition, the decision to pursue such plans
seems to be person-specific once again – that
is, if EE is a priority for a person or certain
people at the municipal level, then plans are
pursued. Creating such champions, however,
once again requires adequate awareness rais-
ing capacity up-front.
Referring to the comprehensive energy
plans and sustainable energy strategies, lo-
cal governments can apply for investment
support offered by various public funds,
including national and local environmental
funds (for example, EcoFund) as well as EU
pre-accession funds. Thus far, according to
stakeholders and data collected, interested
municipalities have drawn on the existing
capacity in organizations like FEWE or
energy consultant firms to complete these
energy plans, using the available funding.
Although municipalities are required by law
to develop these plans, this is not strictly en-
forced, however. Data suggest that, at most,
only 30—40 percent of municipalities have
such plans. In addition, some stakeholders
noted that the criteria for getting access to
funds are both complex and often chang-
ing, making access to EE funds increasingly
difficult.
Institutional Capacity to Implement Deci-
sions on EE and DSM
National level
According to data collected and stakeholders
interviewed, this capacity is not strong in the
central government, which is exemplified by
a failure to pursue EE initiatives generally.
As pointed out repeatedly, EU accession
and the harmonization of Polish legislation
within that context is almost fully occupy-
ing the central government at the moment,
leaving little time and incentive to focus on
its implementation, especially within the
context of mixed priorities for EE versus re-
newable energy.
From a technical standpoint, the capacity
for implementing EE and DSM activities or
initiatives at the national level exists mostly
within academic institutions, such as AGH
University. Again, PELP had an indirect im-
pact on the development of such capacity.
As indicated, DSM and EE knowledge and
expertise is being spread all over the country
through courses and curriculum on these sub-
jects, using PELP as an example. Academic
stakeholders (some of whom were members
of associations like the Polish Ecological
Club) are still currently involved in the imple-
mentation of EE or DSM-related initiatives in
various parts of the country.
County/voivodship level
Technical capacity for EE and DSM generally
exists in electric utilities, according to the ma-
jority of stakeholders interviewed. However,
38
Post Implementation Impact Assessment: Poland Efficient Lighting Project
because of their focus on electricity sales and
the system’s overcapacity, implementation of
EE and DSM remains marginal. During PELP,
utilities were made aware of the benefits of
DSM and EE more generally. And since the
project some utilities have made use of DSM
approaches to avoid capital investments in
their distribution systems. For example, PSE,
the Polish Power Grid Company, did use
DSM approaches rather than investing in
upgrades. PSE maintains that they have EE
contracts with 50 municipalities. But as men-
tioned earlier, this type of initiative should be
considered as the exception rather than the
rule. Utilities are mainly interested in EE and
DSM for peak shaving.
As indicated, there are organizations with
the capacity to implement EE and DSM (such
as FEWE, energy consultants, and the Polish
Association of Engineers) that can and do
work on these issues at this level. PNEC too
has this capacity, and it is also involved with
the implementation of DSM and EE-related
initiatives in various parts of the country,
some of which are discussed in section 4.3
on replicability.
Municipal level
As noted earlier, the capacity to implement
decisions does not exist systematically in mu-
nicipalities. When it is considered, munici-
palities draw on the capacities of other orga-
nizations. That is essentially what happened
in the context of the PELP pilot municipalities.
Under the laws, each municipality is required
to have one person responsible for EE, for
example. There are some isolated examples
where this capacity has been developed.
Generally speaking, however, this capacity is
not present and the law itself is not enforced,
resulting in almost no municipalities having
such a position filled at present.
FEWE has been trying to work with munici-
palities to create and build the capacity of a
position responsible for EE at the municipal
level, but the support for and enforcement of
this aspect is not strong, in the organization’s
view. This view is substantiated by represen-
tatives of municipalities met by the Study
Team. Capacity building at this institutional
level requires further efforts.
Manufacturers such as ES Systems, a lumi-
naire manufacturer and distributor, also have
the capacity to implement EE initiatives at the
municipal level. ES Systems has already im-
plemented extensive EE initiatives in Krakow
and is very busy with EE retrofitting of build-
ings, lighting systems for new buildings, and
EE activity in general. The company claims to
have benefited greatly from its experiences
in PELP in terms of the transformation of the
market, which had an impact on sales and
market share, but not specifically in terms of
capacity development.
Capacity to Enforce Legislation
As discussed, enforcement of EE-related legis-
lation is not a top priority for the government
in the present context, nor was it at the time
Impact Assessment
39
of PELP, and therefore this also remains a
capacity issue at all levels. Most stakeholders
indicated that EE-related legislation and poli-
cies “are requirements without enforcement.”
At this time, even the “legal framework for
RE development is not coherent,”14 and this
is also true of EE-related matters.
As noted by some stakeholders, the incom-
plete enabling environment is rendered more
complicated by unclear and overlapping
jurisdictions and authorities in the area of EE
for public buildings or schools (for example,
elementary schools are under municipal ju-
risdiction, while voivodships have authority
over high schools).
Capacity to Pool Resources
Generally, this capacity does exist in Poland
today. For example, energy consulting firms
and agencies such as FEWE develop projects
with final consumers to promote DSM and
EE, pooling human, financial, ecological, and
technological resources together for EE and
DSM-related activities. Some of this capacity,
stakeholders noted, was either developed
or refined through their experiences with
PELP. In addition, utilities can often pool the
required human, financial, and technological
capacity; stakeholders cited PSE as one of
several examples of this.
Hypermarkets, specialized electrical shops,
and other retail stores have indeed managed
to create a great market window for efficient
lighting and thus in fact act as pooling win-
dows for financial resources for EE. CFLs are
certainly well promoted and available ev-
erywhere to consumers, as the Study Team’s
retail survey confirmed. (For more findings
from the retail survey, see section 4.2.3.) The
survey demonstrated that, on average, 25—33
percent of lighting product shelf space in all
stores was dedicated to CFLs and 75 percent
of all promotions or sales were for CFLs rather
than regular bulbs.
However, those consumer resources pooled
do not go back in any great amount to pro-
mote further energy efficiency or into EE
measures as such, whether at the national,
voivodship, or municipal level.
The Role of ESCOs
The number and types of energy service
companies certainly increased during and
after PELP, although direct causality cannot
be established. In general, however, the
ESCO market has yet to develop in Poland.
It is facing subsidized competition from
national environment funds, county-level
funds, and so on, as described earlier. The
funds themselves invest, at subsidized rates,
in EE and DSM actions, thus not giving the
required space for ESCOs to flourish. In addi-
tion, other actors seem to be playing the role
of ESCOs at times, including manufacturers
like Philips and ES Systems, so the context
for ESCOs in Poland is not favorable overall
at present. As one stakeholder noted, “the
legal structure in Poland is not tailored for
third-party financing.” Some consider ESCOs
40
Post Implementation Impact Assessment: Poland Efficient Lighting Project
as being discriminated against in this context,
and one stakeholder noted, “theoretically, the
market is 75 percent open, but practically it
is 1 percent open.”
At the close of PELP, some funds from the
budget (primarily accumulated interest)
remained unspent. In response to a request
from the IFC, FEWE prepared a business plan
for Business Energy Ecology Sp.z o.o. (BEE), a
new lighting ESCO, in which FEWE would be
a minority shareholder. BEE principals were
all involved with the implementation of PELP,
and they drew on the knowledge, experience,
and contacts they gained through PELP to
further EE initiatives, with a particular em-
phasis on street lighting. However, it seems
the initiatives of the ESCO never quite got
off the ground. Funds that were earmarked
for furthering its initiatives are soon to be
returned to the IFC.
Conclusions
The capacity for information management
and awareness raising exists at certain lev-
els within the country, and some of it was
furthered through PELP. For example, AGH,
PNEC, and FEWE all have the capacity to un-
dertake awareness raising initiatives through-
out the country and are currently doing so.
However, groups such as FEWE and PNEC
rely on project-related funding and have little
core funding available to ensure continuity
and a strong logical framework for their ac-
tions on EE. Even if this capacity exists at the
national level in government, and appar-
ently already existed at the time of PELP, the
government does not appear to be currently
committed to EE and DSM in any forceful
manner. Municipalities are constrained in
terms of human and financial capacity for
awareness raising and must therefore draw on
institutions with that capacity, such as FEWE
and consulting firms.
As consumers have few awareness activities
focused on them, with little publicity on EE
products, further use of existing networks that
raise consumer awareness and ensure some
form of quality control on products by dis-
seminating relevant information is desirable.
As many stakeholders have made clear, PELP
focused primarily on shifting the market for
CFLs, not necessarily on raising EE awareness
or developing the capacity to do so for the
long term. As noted, this was a contextually
appropriate choice for the project’s emphasis,
but it impeded some degree of contributions
being made to long-term raised awareness
and related capacities for EE.
There may generally be capacity for policy
making, planning, and decision making for
EE and DSM, as there are national laws and
policies that address EE issues, but due to vari-
ous contextual factors such laws are not well
enforced or implemented. At the municipal
level, the capacity for planning and decision
making on EE is almost nonexistent and there-
fore needs to be addressed. At national and
municipal levels, the government’s capacity
to implement the decisions on EE and DSM
Impact Assessment
41
does not seem to be present, but this capac-
ity exists within other institutions – namely,
AGH, PNEC, FEWE – as well as within
energy consultancies. Municipalities again
draw on capacities that exist in these agencies
and others for the implementation of EE/DSM
initiatives but depend on existing national or
regional funds, which are not always easily ac-
cessed. It is evident that utilities, too, have this
capacity, but are generally not as interested
in pursuing these initiatives given the current
energy market realities in Poland.
PELP has had limited success in bringing
change to that overall situation, although it
did support pilot initiatives in certain munici-
palities that have helped further the imple-
mentation capacity of some of the groups
mentioned (AGH, PNEC, and FEWE, in
particular) in partnership with those munici-
palities. The need to broaden the experience
and reach of that capacity remains significant,
given the EE situation in the country.
The incomplete enabling environment for
pursuing EE in Poland is not conducive to
use of the capacity to enforce legislation,
which does not seem to be present at any
level. If EE is to be pursued into the future,
this capacity will need to be built up. The
capacity to pool human, technological, and
ecological resources is found in institutions
like FEWE and certain energy consultancies.
What is missing, however, is the capacity to
pool financial resources required to move EE
and DSM ahead in Poland. Utilities, which
potentially have this capacity, are not par-
ticularly interested in pursuing such EE/DSM
initiatives in the present context.
ECSOs, which normally would be key
players in pooling resources by marketing,
implementing, and structuring financing for
EE measures at various levels (and were en-
visioned as such by PELP), are not important
players in Poland. The efforts of PELP to build
an ESCO legacy as a key institutional driver
of broader and sustainable market transforma-
tion for efficient lighting in Poland in the long
run have not proved fruitful. This appears to
be due, in particular, to the absence of an
adequate market enabling environment to
allow them to flourish (such as subsidized
competition from other funding sources or a
government focus on EE rather than renew-
able energy).
Lessons Learned
If the national government does not dem-
onstrate interest in a particular issue, it
might be a good strategy to turn to other
national actors, including the private sector,
to implement a project and leverage initial
commercial interest to lead the way toward
the achievement of global environmental
objectives. However, to achieve total and
sustainable market transformation, capaci-
ties must be built not only in private sector
actors, such as manufacturers and ESCOs,
but also within central government, mu-
nicipalities, and nongovernmental actors in
that sector.
42
Post Implementation Impact Assessment: Poland Efficient Lighting Project
In a country where the macroeconomic and so-
cial context is not conducive to EE, it is difficult
to get full government commitment to steer
the process and ensure an adequate enabling
environment to allow some potential players
in EE, such as ESCOs, to flourish, and others,
such as utilities, to get actively involved.
In a country undergoing a rapid decentraliza-
tion process, building the capacity of local-
level governance institutions to plan, imple-
ment, and enforce legislation as well as to
pool adequate human and financial resources
to make this possible is paramount.
To help build this capacity at the local or
end user level and to help encourage the
central government to give adequate prior-
ity to EE, special attention must be paid to
building and sustaining the capacity to raise
awareness on EE/DSM issues and benefits at
various levels.
The promotion of benefits should not be
limited to short-term financial gains from
electricity savings but should also include
global environmental benefits and their links
to consumption habits. Although the promo-
tion of the former could in many cases be
the best way to attract consumers’ attention
and might represent a contextually feasible
means (as was the case for PELP), it should
be accompanied or at least followed by the
promotion of global environmental benefits
that can contribute to bringing a more sustain-
able, longer-term attitudinal change toward
energy-efficient practices among end users
and institutional users.
In the context of EE initiatives, it can be
beneficial to work more with end users and
final consumers, who have the most to gain
from electricity savings. PELP demonstrated
that utilities are unlikely to be strong or long-
lasting partners in a market where there is
already a surplus of energy or where profits
might be affected, and it can be beneficial
to work with municipalities. Practically, the
greatest beneficiaries of EE are end users (such
as municipalities owning buildings or local
populations), and it is important therefore
to involve them more directly in awareness
raising as well as in the development and
implementation of EE initiatives.
For sustained impact in EE or DSM, appropri-
ate champions must be identified and inte-
grated into the initiatives from various levels
of government, the private sector, munici-
palities, consumer representatives, ENGOs,
and manufacturers, as well as other relevant
stakeholders, where appropriate.
4.2.3 Impacts on the Market and
on Beneficiaries
A central aspect of the evaluation was as-
sessing the project’s long-term impacts on
beneficiaries of the project and on the mar-
ket more broadly. Assessment of these two
aspects is significantly interwoven in data
collection and analysis and is presented as
such below.
Impact Assessment
43
In terms of assessing impacts on beneficia-
ries, the following project beneficiaries were
included:
• Consumers (indicators included level of
savings from CFLs, price paid for CFLs,
availability of CFLs, satisfaction with CFLs,
level of awareness of CFLs)
• CFL and luminaires manufacturers (indica-
tors included number of old and new CFL
manufacturers, CFL sales, penetration rate,
saturation rate, sustainability of the CFL
market)
• Electric utilities (indicators included use
of DSM as a least-cost option)
• Municipalities (indicators included level
of awareness of EE and CFLs, level of use
of DSM, CFL/EE lighting penetration at the
municipal level)
By assessing the impacts on the various ben-
eficiaries, the analysis in this section sheds
light on the project’s impacts on the market
for CFLs and EE lighting, with the following
indicators also examined:
• Level of awareness for CFLs (at various
levels and for various beneficiaries)
• Degree to which consumers are commit-
ted to continuing CFL use
• Situation of manufacturers involved with
the project
• Number/type/quality of new manufactur-
ers and their CFL products
• Manufacturer’s assessments of the sector’s
past, present, and future evolution
• Change in CFL retail prices
• Change in availability of CFLs in retail
outlets, including:
• percent of shelf space in major retailers
for EE lighting
• number/type/brands of CFLs available
• degree/type of promotion of CFLs
• overall level of availability and stock
• Level/change in penetration rate (number
of households with at least one CFL in-
stalled)
• Level of market saturation
• Level/change in annual sales of CFLs
• Level/change in luminaires sales
• Comparison of sales and the market in Po-
land with other countries in the region
As the analysis will make clear, the current
CFL market has been significantly trans-
formed since the end of PELP, and there
have been some clear impacts on various
beneficiaries.
Consumers
As primary beneficiaries of PELP for the long
term, it is important to assess impacts on con-
sumers, who have witnessed a transformed
market. By assessing the various impacts on
EE lighting on consumers, long-term impacts
on the market are brought out.
Level of awareness
In Poland, it seems that awareness of CFLs
and EE lighting is widespread throughout
the country. To substantiate this perception
and collect specific data, a representative
44
Post Implementation Impact Assessment: Poland Efficient Lighting Project
consumer focus group was surveyed on is-
sues relevant to both the CFL market and
beneficiaries of the market. It found that 64
percent of the group had already bought CFL
bulbs, and 73 percent had friends or family
who had CFLs. Although a direct comparison
must be made with caution, given the sample
size, it is indicative to note that in 1998 the
final evaluation of PELP found that 33 percent
of consumers had CFLs in their homes while
67 percent knew someone with CFLs. These
data thus suggest an increase in CFL penetra-
tion, which is further substantiated by other
data presented in this section.
It is interesting to note that currently,
among the 36 percent of respondents who
never bought a CFL, exactly half of them had
friends or relatives who did use CFLs. Thus,
82 percent of the focus group in 2004 had
either bought or knew someone who had
bought CFLs, which gives a general idea of
level of awareness of CFLs today.15 This was
further confirmed in an informal way by the
Study Team: in all possible instances, the
team asked regular consumers about their
awareness and use of CFLs. Their responses
confirmed findings from this focus group
(although the findings cannot be considered
representative).
A smaller amount of formal awareness raising
about CFLs and EE was taking place gener-
ally for consumers in Poland in 2004. There
seem to be few, if any, media advertisements
or publicity for this product, as stakeholders
confirmed. Indeed, the issue of energy effi-
ciency is rarely brought up in media or other
forms of public awareness raising, according
to all stakeholders, and most agreed that such
information is more difficult to come by in
comparison to the time of PELP. This repre-
sents a shift away from the situation at the end
of PELP, when media and advertisements had
become multiple and sophisticated and built
on previous awareness campaigns.
Level of consumer satisfaction
In 2004, as Figure 4.2 demonstrates, a sig-
nificant majority of respondents (72 percent)
were satisfied with their CFL purchases, as
they claimed that CFL bulbs met their ex-
pectations. A minority (14 percent) declared
that CFLs greatly exceeded their expectations,
while that same percentage of respondents
were disappointed by the product. In 1998,
at the end of PELP, 62 percent of consumers
were “very satisfied” with CFLs. These data
confirm that consumers are generally satisfied
with CFLs in 2004, but also that there has
Figure 4.2Level of Satisfaction with
CFLs Purchased
Much better14%
Worse14%
As expected72%
Impact Assessment
45
been a significant decrease in the percent-
age of people who are “more than satisfied”
with this product. The inference is that there
has been an overall decrease in the level of
satisfaction with CFLs.
The major advantage of CFLs, according to
people who purchase them, is overwhelm-
ingly the price in the long term. Nearly two-
thirds of the consumers (63 percent)16 in 2004
were buying CFLs because of the economic
benefits they believed they would reap (here,
according to consumers, this includes both
lower electricity bills and cost savings in the
long run). From interviews, it appears that it is
also mainly the purchase price (versus regular
bulbs, in view of the life span of the bulb) that
plays in the decision to purchase CFL bulbs.
As Figure 4.3 shows, 36 percent of consumers
were also choosing CFLs for “energy savings,”
while 27 percent chose them because they
have a longer bulb life span.
Figure 4.3 illustrates that, as at the end of
PELP, a small minority (9 percent) of consum-
ers in 2004 purchased the CFLs for reasons
linked to the environment. It is worth noting,
for comparative purposes, that a consumer
energy awareness and attitude study con-
ducted in the United States in March 2003
revealed that American consumers were most
likely to say that they would pay more for
an EE product (an Energy Star product, for
example) if it saved them money. Some 55
percent of respondents said they would do
this, compared with 46 percent who would
pay more if it saved them time. Also, 36 per-
cent of respondents said that they would pay
Figure 4.3
36%
63%
27%
9%
0%
10%
20%
30%
40%
50%
60%
70%
Economicallyefficient
Lastlonger
Better for theenvironment
Advantages of CFLs - 2004
78%
62%
42%
10%
Advantages of CFLs - 1998
Saveenergy
0%
10%
20%
30%
40%
50%
60%
80%
70%
Economicallyefficient
Lastlonger
Better for theenvironment
Saveenergy
46
Post Implementation Impact Assessment: Poland Efficient Lighting Project
more for an Energy Star product if it helped
preserve the environment.17 Another study,
however, showed that only 5—8 percent of
a group of CFL consumers surveyed in Cali-
fornia bought this product for environmental
reasons,18 which is similar to findings from
the impact assessment of PELP.
Figure 4.3 representing data from the final
evaluation of PELP in 1998 shows that a simi-
lar percentage of consumers purchased CFLs
because of the economic benefits. It is inter-
esting to note the differences between 1998
and 2004 in terms of the share of consumers
choosing CFLs for energy savings, as less than
half of the percentage of consumers in 2004
bought CFLs for this reason. Similarly, fewer
consumers are purchasing CFLs because the
bulbs last longer. This may further demonstrate
what the Study Team found in Poland in 2004
– that lower-end and poorer-quality products
have flooded the market in recent years and
are not lasting as long as CFLs used to and
may not be saving as much energy as CFLs of
the past. The standards for CFLs have indeed
dropped since the end of PELP; for example,
whereas CFLs then usually had a 15,000-hour
life, the new standard lifespan today for CFLs
on the market is 8,000 hours, a significant
drop in quality.
The major disadvantages of purchasing CFLs,
according to consumers, or the reasons they
do not purchase this product include “start up
delays,” referring to the time it takes for the
lights to come on after the switch has been
flipped (36 percent of consumers), the price
of CFLs versus regular bulbs (36 percent),
and the inability to fit their light fixtures (14
percent). This last response confirms data
collected through interviews, where people
argued that sometimes the CFLs did not fit
their particular light fixture. In addition, some
felt that CFLs did not quite come in the right
color, shape, or type and did not fit in their
home. A comparison with the disadvantages
listed by consumers at the end of PELP is also
provided in Figure 4.4. The percentage of
consumers finding CFLs too expensive has
remained rather constant, while “start up
delays” has increased significantly.
In reference to the dissatisfaction of consum-
ers, when the focus group in 2004 was asked
why they needed to replace CFLs, the most
frequently given response was a normal
burnout of the bulb (34 percent). However,
nearly half of the respondents answered that
either poor lighting (22 percent) or early
burnout (22 percent) was the main reason to
replace the bulbs. In addition, while 11 per-
cent claimed that CFLs often short-circuited,
11 percent of respondents were not at all
satisfied with the CFLs for reasons not stated.
In sum, the data suggest that two-thirds of
consumers are replacing CFLs because of a
negative experience with them, further lend-
ing credence to the claim that the quality of
CFLs has dropped in the market.
It was suggested by various stakeholders
interviewed (and the data collected also sug-
Impact Assessment
47
gest this) that satisfaction might have gone
down in recent years due to the quality of the
bulbs that have flooded the market, which
have grown rapidly in number since PELP.
According to manufacturers, it is impossible
to know just how many Asian imports are in
the Polish CFL market at any given time, as
no one is tracking this. The impact assess-
ment clearly confirmed that the influx of
Asian imports to the Polish CFL market has
allowed for many lower-quality CFLs to flood
the market at lower prices, which certainly
seems to be having an impact on consumers
in various ways.
Nevertheless, even if consumers in the focus
group in 2004 noted some disadvantages
to CFLs, all of them stated that when they
had to replace their CFL bulb with a new
one, they did not consider buying a regular
bulb. (See Figure 4.5.) This demonstrates a
sustained impact from PELP, as 97 percent
of consumers intended to replace CFLs
with CFLs.
Level of consumer savings
According to the focus group, the general
quantity of wattage saved by purchasing CFLs
instead of regular bulbs is approximately 83
watts. This average takes into account the
wattage average of the regular bulbs (ap-
proximately 97 watts) that the focus group
used to purchase minus the wattage average
of all CFL bulbs (approximately 14 watts)
purchased. This is certainly not representative
or scientifically qualified data. However, all
consumers in the focus group who had CFLs
stated that they had saved money by purchas-
Figure 4.4
45% 45%
18%19%
48%
22%
7%
18%
Tooexpensive
Other Inability tofit fixture
Disadvantages of CFLs - 2004 Disadvantages of CFLs - 1 9 9 8
Start updelays
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
Tooexpensive
Other Inability tofit fixture
Start updelays
48
Post Implementation Impact Assessment: Poland Efficient Lighting Project
ing this product, due to its EE features. This
confirms what was demonstrated by FEWE in
its study in the selected municipality as part
of PELP and what was recorded as well in all
project reports and evaluations.
As indicated, financial savings is one of the
main reasons that consumers buy CFLs.
When asked, on average, how much money
they save through CFL use, some consumers
stated that they saved approximately 5 PLN
per month. Focus group consumers and most
other stakeholders noted, however, that it
is very difficult to calculate savings related
to CFLs or lighting accurately, as electric-
ity prices are constantly on the rise. And
with privatization and changes to electricity
distribution in Poland, electricity bills have
become increasingly complex and difficult
to interpret, as well as difficult to link to a
particular consumption period.
Availability of CFLs
Based on the findings of the Study Team’s
retail survey, the consumer focus group,
a review of manufacturer’s products, and
interviews with various stakeholders, it is
evident that consumers in 2004 enjoyed a
wider selection of CFL manufacturers, watt-
ages, types, styles, and availability overall
than in 1998. CFLs are literally everywhere,
from the hypermarkets to the smallest light-
ing-related shops. The increase in CFL makes
and models has resulted in a much wider
selection in terms of both price and qual-
ity and a vastly transformed and expanded
market overall.
Figure 4.5What will your next light bulb be?
0
50
100
CFL of equalwattage
CFL of greaterwattage
CFL of lesserwattage
Impact Assessment
49
The retail survey demonstrated that consum-
ers can now choose between about 12 manu-
facturers, some of whom make as many as 40
types of CFLs (and as few as 8 types), ranging
in size, quality (lasting between 3,000 and
15,000 hours, offering or not offering war-
ranties), wattage (from 6 to 25 watts) and
price (from 4 to 40 PLN) – all available in
many stores and often all in the same store.
As mentioned earlier, CFLs occupy 25—33
percent of shelf space for lighting overall and
sometimes as much as 50 percent in smaller
stores. In addition, it is primarily CFLs that
are either on sale or offered in some sort of
promotion (such as the chance to win a home
stereo system or an additional rebate).
Although CFLs are everywhere, this cannot
be directly attributed only to the project, nor
was PELP alone responsible for the expanded
CFL market found in Poland today. It was cer-
tainly the kickstart for this particular market
and for domestic demand for the product, but
technological and socioeconomic changes
were occurring at the same time, in a larger
context of rapid market economy transition.
These factors cannot be ignored.
Price of CFLs
The expansion of the CFL market was ac-
companied by an expanded range of prices
linked to a greater range of wattages, types,
and quality. The Study Team’s retail survey
found that CFL prices ranged widely, from as
low as 4 PLN for lower wattage or sometimes
short-life/lower-quality imports to as high as
42 PLN for high-quality, long-lasting CFLs. In
1998, the final evaluation of PELP noted that
the average price fell from 38 PLN to 25 PLN
during the life of the project. It is interesting to
note that the price of CFLs today is almost the
same as it was during PELP (for comparable
makes, such as Philips) even in the context of
growing inflation and a booming economy.
The focus group of consumers stated that,
on average, they pay between 15 and 30
PLN per CFL bulb, close to the average price
during PELP.
All data therefore suggest that the price de-
crease of CFLs has been sustained since the
end of the project. Furthermore, with an aver-
age rate of inflation in Poland of 34 percent
from 1997 to 2003, this actually translates
into a 25 percent decrease in the price of the
average CFL, in real terms, since the project’s
end. Most stakeholders agreed that the prices
of CFLs would not have reduced that much,
and that fast, without PELP.
In terms of a standard retail comparison with
regular bulbs, 11- or 12-watt high-quality
CFLs are usually equivalent to 60-watt regular
bulbs (standard wattage comparison), and a
consumer will pay 15 PLN for the CFL (as
high as 30 PLN in more expensive shops)
compared with only 1 PLN for the regular
bulb (3 PLN in more expensive shops).
However, the high-quality CFLs last 8,000
hours (8 years) on average, and most come
with warranties, while the regular bulbs last
only 1,000 hours (1 year), and never come
50
Post Implementation Impact Assessment: Poland Efficient Lighting Project
with any warranty. These prices collected
from the retail survey confirmed the prices
the focus group paid for CFLs on the current
market (15—30 PLN). As for the higher-priced
CFLs, these represent high-end CFLs, which
last for 15,000 hours (15 years) and are of a
higher wattage (25 watts).
Manufacturers
Among the primary beneficiaries of PELP,
manufacturers have certainly felt the impacts
of PELP since the end of the project. In a
variety of ways, the drastic transformation of
the CFL market has perhaps affected Polish
CFL and luminaire manufacturers more than
any other stakeholder.
Change in number or type of manufactur-
ers and long-term impacts on them
During PELP, the biggest players in the CFL
market were Philips (a Dutch company) and
Osram (a German company). To some extent,
General Electric was also involved. Through
PELP, smaller players entered (or penetrated
further into) the CFL market, including Kania,
Maya, and Vox Detlam, and other manu-
facturers or importers and sellers of CFLs
also entered the game, taking advantage of
a rapidly expanding market. One of PELP’s
impacts was that it convinced manufactur-
ers and retailers (as well as wholesalers)
that CFLs could be sold and promoted to a
wide audience. However, it may have also
contributed to opening up the market overall
through expanded demand (and related sup-
ply opportunities), contributing to the wave
of imports flooding the emerging market.
With the cheaper products from abroad, local
manufacturers faced serious challenges and
competition.
Today, the CFL market is still clearly domi-
nated by Philips and Osram. The retail survey
conducted by the team demonstrated this,
and it was confirmed by all stakeholders and
data collected. More accurately, the market
is dominated by Philips and to a significant
degree, Pila, which may be considered a sub-
sidiary of Philips and is a small CFL company
producing in Poland. It is interesting to note
that for many average consumers, Philips and
CFLs go hand in hand. PELP must be regarded
as having at least contributed to solidifying
Philips’ CFL market share and dominance.
This is confirmed further by the focus group,
where respondents clearly had a preference
for Philips (60 percent) and Osram (40 per-
cent), as no one checked or proposed any
other CFL brand listed in the survey. Other
stakeholders also identified only these two
brands during interviews.
Yet there are other players on the market
today, including Neolux, Kanlux (Kania),
Helios, Paulman, Polux, Massive, Brilux,
Maxlux, and Dulux, and potentially others
not seen by the Study Team. It is interesting
to note that almost all these manufacturers
sell both EE and non-EE light bulbs, so they
are essentially competing against them-
selves as well as against others. These new
manufacturers are in fact mostly importers
Impact Assessment
51
of cheaper products from Asia. With some
exceptions, they are offering more of the
low-end brands, with fewer hours per bulb,
and a significant percentage come without
warranties.
There are thus more distributors of CFLs
around, but most of them are selling imported
bulbs. Local production in Poland was rather
marginal in 2004. Financing is mainly for the
distribution of imported CFLs, as manufac-
turers maintain that local production is too
expensive in this increasingly competitive
market. Some manufacturers argued that
PELP did the “hard work” of spreading
awareness and opening up the market, and
now Asian low-cost producers are taking ad-
vantage of the situation and “having it easy,”
as the market is already developed and has
been transformed.
A high-ranking director of one manufacturer/
distributor, Kania, mentioned that its sales
rose by 50 percent during PELP. However,
Kania also pointed out that since then sales
have decreased by 60—70 percent, due, in his
view, to competition in the market and the
influx of imports. At one point Kania, which
sold GE products, was the second largest
player in the CFL market in Poland. Now,
selling under the name Kanlux, Kania sells
Asian imports only and is “on the way out of
the market completely.” Another example
is Maya, a manufacturer also involved with
PELP. Maya no longer exists, as it could not
compete. It is worth noting that “Philips” is
mentioned as often as “Asian imports” as the
source of unbeatable competition in the CFL
market in Poland today. The impacts of PELP
on CFL manufacturers in Poland has therefore
been significant, in both positive and negative
ways, whether directly or indirectly.
In the luminaire market, ES Systems was
around before PELP, since 1990, with a man-
date to enhance and increase the use of EE
lighting systems in Poland. ES System argues
that its business expanded mostly because of
PELP, and today they are the market leader in
luminaire distribution. A representative of ES
Systems noted that “PELP promoted CFLs and
made EE popular, and our business in CFL
luminaires benefited then, and continues to
this day.” ES Systems sales are at $40 million
per year, and they have at least 30 percent of
the market share. They work with schools to
change to EE lighting, fit new buildings and
malls in the country with EE luminaries, and
have replaced much of the street lighting in
Krakow, acting in effect as an ESCO.
Today, with the introduction of lower-end
brands, specialized fittings, shapes, and a
wide array of wattages, prices, and quality,
there has clearly been market segmentation,
which is in itself an indication that the CFL
market overall has matured. However, there
are potentially negative aspects of this market
transformation in terms of poor quality and
consumer dissatisfaction, which may create
a backlash for manufacturers in the longer
term, as discussed further later.
52
Post Implementation Impact Assessment: Poland Efficient Lighting Project
Level of CFL sales
The market has definitely developed in a
sustainable manner, as evidenced by the
level of sales. Hypermarkets are taking the
low-end market mostly with a wide array of
styles and brands, while some manufacturers
channel their high-end products through spe-
cialized electrical shops. Other superstores,
in particular “homecenters,” have the entire
spectrum under one roof. As a result, sales
are higher than expected by the project and
its stakeholders.
In 1996, CFL sales were at approximately
2.9 million, and they were at 3.5 million in
late 1997. Manufacturers projected that the
growth in sales would be sustained, increas-
ing at least 14 percent a year. Current CFL
sales data are increasingly difficult to obtain
and track, a point made clear by all stake-
holders who had knowledge on this issue. In
addition, many stakeholders were reluctant
to share accurate market-related data. Cur-
rently, however, according to Philips (the
only source for this data in the country that
the Study Team could find), CFL sales in the
market are at 8—9 million a year. This number
is most probably underestimated because of
untracked Asian imports. Even these con-
servative estimates show the CFL market in
now four times larger than at the end of the
project, demonstrating that the final evalua-
tion projections were more or less accurate.
In terms of other countries, it was a noted
success of PELP that during the project CFL
sales were higher in Poland than in most
western countries, including the United
States. According to Philips, even today,
CFL sales in Poland are still quite compa-
rable to U.S. sales, especially if differences
in population are accounted for. Stakehold-
ers familiar with the region maintain that
Poland’s CFL sales and penetration rates
are still higher than neighboring countries
like the Slovak Republic, Slovenia, and
some Baltic states, all of which have higher
income levels. This can be explained by the
fact that CFLs were being sold and promot-
ed widely in Poland earlier (through PELP)
than other countries, with the exception
perhaps of Hungary, where GE’s presence
was and is very strong. In addition, Poland
is a bigger market, with a population of 40
million, than some of its neighbors. Poland
can currently be considered comparable
not only to Hungary and the Czech Re-
public in terms of the CFL market, but also
to West European countries, according to
manufacturers.
Market penetration
The level of market penetration of CFLs
during PELP was 19 percent, which rose to
33 percent one year after subsidies ended.
Currently, Philips estimates that penetration
is at least 50 percent of households. This is
supported by other sources. Two-thirds of the
representative focus group had bought CFLs,
and nearly three-fourths knew someone who
used CFLs. The penetration rate in Poland has
increased further as prices have continued
Impact Assessment
53
to fall (and, to some extent, as incomes have
continued to rise).
Philips estimates that most households have
60—70 percent of their lights as CFLs, if they
have CFLs in their home or apartment. Other
data tended toward estimates that were some-
what lower. Findings from the focus group
and other consumers indicate that most
people use CFLs primarily in the main areas
where lights are used the most, such as the
kitchen and bathroom.
PELP made a contribution to this market pen-
etration primarily by giving people a chance
to try CFLs through manufacturer subsidies,
which made them more attractive financially,
according to stakeholders. Not surprisingly,
penetration is higher in urban areas or cities
and much lower in the countryside. People
more involved with agricultural activity in
the rural areas generally have much lower
incomes, according to stakeholders. The
issues associated with EE lighting may not
be top priorities in that context. However,
stakeholders argued that if PELP had gone
further to raise awareness and promote CFLs
in the rural areas, market penetration might
be higher today, so the potential remains.
Market saturation
The challenge for PELP was catalyzing a shift
in the market for EE lighting. This was indeed
achieved, and perhaps beyond expecta-
tions. It sped up the market transformation
and also market saturation by at least three
years. During project implementation, the
potential size of the Polish market for CFLs
was estimated by the International Institute
for Energy Conservation to be 21—26 million
units, with annual sales reaching saturation
at 4 million units.19 As noted earlier in this
chapter, manufacturers predicted that market
saturation at an average of 2.43 CFLs per
household, implying that saturation would
occur in 2001 with PELP and in 2005 without
it. With an estimated 9 million of CFLs sold
in 2004, it is believed that market saturation
has been reached.
Sustainability of the CFL market
Although the current state of affairs for CFL
manufacturers or distributors looks positive,
when asked about the future or sustainabil-
ity of the market in Poland, manufacturers
painted a much less optimistic picture. PELP
indeed contributed to a transformation of the
market, but it also opened the CFL market
up to competition from other sources. At
the time of PELP, there seemed to be some
degree of quality standards in place and fol-
lowed. Now, according to all stakeholders
and data collected, manufacturers seem to
follow no rules and there seem to be no stan-
dards. As mentioned previously, the market
is completely open and the Asian imports
have flooded in. This has helped to lower
prices further, perhaps, but it also introduced
new lower-end types of CFLs. During PELP,
academics tested imports versus high-qual-
ity bulbs like Philips and found that savings
were reduced by 50 percent with the “other
54
Post Implementation Impact Assessment: Poland Efficient Lighting Project
EE bulbs.” Since PELP, these tests have been
repeated with similar results, according to
various stakeholders. This will, in manufactur-
ers’ view, serve to further erode the consumer
base for the product, as they decide that the
EE light is not that energy-efficient after all.
This is in addition to basic quality problems
related to low-end products and already noted
by consumers and other stakeholders.
People buying these CFLs that have no war-
ranties and that do not follow any enforced
standards are discovering that the bulbs are
burning out early and sometimes not working
at all. This may also contribute to a negative
impact on the market in the long term, as
people are “losing their confidence in EE
lighting and CFLs,” in some stakeholders’
view – confidence, stakeholders added, that
PELP worked hard to create, and that some
manufacturers have worked hard to sustain.
This will, in manufacturers’ view, push
people away from EE lighting in the future, es-
pecially as CFLs remain more expensive than
regular lighting. Manufacturers like Philips
realistically predict a significant decrease in
sales in the coming decade as opposed to the
last one. Philips will not reduce prices further
at the expense of quality, but it also has no
direct control over erosion of consumer con-
fidence in the market. Therefore, the level of
market saturation or penetration is no longer
sustainable and is being eroded. The Federa-
tion of Consumers substantiated this claim,
stating that consumers have confidence only
in certain brands such as Philips and that
lower-end products will certainly erode the
consumer base for CFLs more generally.
Consumers in the focus group who bought
CFLs from the major manufacturers (like Phil-
ips and Osram) seemed to have fewer com-
plaints about quality, although even these
manufacturers are not immune to consumer
complaints. For the consumer, who may not
be aware of the CFL’s quality, the imported
items might seem competitive and very at-
tractive for the first purchase. However, these
lamps turn out to be of poor quality, and this
is confirmed by many returns.20 Manufactur-
ers and academic stakeholders argue that this
is slowly undoing the positive impact of PELP
on the CFL market.
The overall quality of CFLs has decreased
over time. At present, the Polish government
is not focused on any standards for CFLs on
the market. Beyond contextual factors noted
earlier concerning government involvement
in EE-related initiatives and markets, this re-
luctance to enforce standards is also related
to Poland’s present economic transition and
ideological transformation. In the post-com-
munist context, stakeholders suggested that
the government does not want to seem as
though there are “special rules” for EE prod-
ucts, and it does not want to seem like it is
meddling with the market in any way on this
or any other market-related issue.
In the end, however, the market for CFL could
become unsustainable in the long run unless
Impact Assessment
55
measures are taken before consumer trust and
confidence are further eroded. It should be
noted that country-specific standards in the
EU context is not likely. “Green” labeling is
one EU mechanism that could potentially be
deployed, where Ministries of Environment
usually help set the standards for this designa-
tion. They could probably incorporate light
bulb quality and performance into their label-
ing criteria to help distinguish market products
with higher standards that produce greater
environmental benefits. Green labeling com-
bined with active marketing by the higher-
quality brands receiving this designation (with
the sellers bearing the cost of this work) is a
potential win-win combination to influence
consumer awareness and behavior.
Utilities
PELP intended to demonstrate to electric
utility companies such as PSE that DSM
approaches could be pursued, rather than
capital investments, to improve distribution
networks. Most utilities face distribution
losses. PSE, for example, faces transmission
and distribution losses in its system of about
12 percent. Even in the face of such losses,
for most utilities DSM is not attractive as it
is perceived as being solely about reducing
energy consumption, which translates into
fewer sales. In addition, as there is general
overcapacity in the electricity sector, reasons
for pursuing EE and DSM seem weaker to
most utility companies. They do not necessar-
ily have EE or the environment as a top prior-
ity. In most cases, they need to be convinced
of the benefits. Some have been shown the
economic benefits and savings in terms of
investments, but many more need to be made
aware. It is also difficult to convince them to
invest in an uncertain economic climate.
As the IFC/GEF Poland Efficient Lighting
Project: Demand-Side Management Pilot
– Final Report states, two conferences were
held during the PELP Project to show its
successes and findings in terms of distribu-
tion systems advantages. They were very
successful, attended by many utilities and
other stakeholders from Poland as well as
other countries. They demonstrated the
cost-effectiveness side of DSM approaches
for electric utilities. As the final evaluation
and other project documents argue clearly,
peak demand for electricity was reduced up
to 15 percent in target areas and municipali-
ties through DSM approaches with utilities.
The PELP approach helped to take pressure
off the system during peak times, and it also
presented benefits for consumers in the form
of electricity savings.
In addition, one of the big achievements of
PELP noted by academics, the private sec-
tor, and utilities alike was that it convinced
utilities and electricity distributors that CFLs
would not have a negative impact on the
grid (or cause surges) due to CFLs comprising
nonlinear loads. The “load” argument was a
central aspect of early opposition to PELP and
the use of CFLs and EE lighting by utilities
and electric companies. This was disproved
56
Post Implementation Impact Assessment: Poland Efficient Lighting Project
through the project, which opened the door
to utility collaboration.
Today there are electricity utilities, such as
PSE, who did and continue to use DSM ap-
proaches rather than investing in upgrades.
PSE provides electricity to 130 municipali-
ties in Poland and works currently with five
distribution company networks, covering
60,000 square kilometers. According to a
high-ranking representative of this utility,
PSE has EE contracts with 50 municipalities.
The company acts as an ESCO and has con-
tracts with municipalities to supply EE street
lighting for a fixed number of years. The PSE
representative noted that it was PELP that
made his company aware of the benefits of
such DSM approaches.
It is worth mentioning that the DSM approach
has caught on and worked well with some
heating utility companies in Poland, as there
is more competition in that sector, and some
companies collaborate due to fear of losing
clients to gas companies. This demonstrates
some (indirect) impacts of PELP beyond the
EE and lighting sector exclusively. In addi-
tion, some stakeholders (energy consultants
or agencies like FEWE) mentioned that some
utility companies have approached them to
do EE or DSM activities, as they are interested
in peak shaving.
Municipalities
As noted earlier, certain municipalities are
aware of the benefits of EE lighting in public
buildings, schools, and so on and have de-
manded such a shift. For institutional final
users, such as municipalities, as the PSE
experience has shown, EE street lighting
can bring municipalities’ costs down by 40
percent, after the three-year payback period
for the installation of the new bulbs. This
represents substantial electricity cost savings.
Many municipalities became aware of these
benefits through PELP activities. However,
both ES Systems and Philips, as well as
energy consultants and FEWE, reiterated
that the situation in municipalities is very
difficult in terms of the enabling environ-
ment and enforcement. (This is discussed
at length in section 4.2.2 on institutional
development.)
Municipalities that were involved with PELP,
such as Elk, seem to have experienced an
even higher and continued penetration of
CFLs at both retailer and consumer levels.
Residents of Elk can still remember the
project and the PELP logo, and they recall
how much CFLs were promoted at that time.
However, this awareness and CFL use has
spread well beyond municipalities targeted
by PELP, which offers further evidence of
other PELP impacts.
• A post-project initiative, which replicated
PELP and grew out of it, was executed by
PNEC and addressed awareness raising for
CFLs and EE lighting in the municipality
of Miedzna. The results of this post-PELP
activity can be considered as impacts of
Impact Assessment
57
PELP (see discussion on replicability in
section 4.3).
• As stated earlier, PSE currently has EE street
lighting contracts with 50 municipalities.
As PSE notes tht it adopted more EE ac-
tivities and DSM approaches due to PELP,
benefits to municipalities who switch to EE
lighting may also be considered as indirect
impacts of PELP.
• Energy consultants and agencies like FEWE
also noted that they are currently working
with at least some municipalities on EE
lighting in public buildings and schools.
In addition, ES Systems worked with
Krackow to modernize and retrofit many
buildings and introduce EE lighting.
• The retail study of the Study Team further
confirms some degree of spread of aware-
ness and CFL use, as CFLs were found
in many buildings visited in Warsaw,
Krackow, and Katowice. The survey shows
generally that the penetration of CFLs
into the consumer market for lighting is
comprehensive and extensive in many
municipalities.
Conclusions
For consumers, there have been many di-
rect and indirect benefits from PELP in the
long term. As the market for CFLs has been
transformed, the availability and selection
of CFLs has increased dramatically. Not all
aspects are attributable to PELP directly, but
contributions were made. The CFL market
today enjoys a wide range of types, wattages,
and prices to choose from. The price of CFLs
has remained at similar levels since the end
of PELP (which means a lower price in real
terms). Consumers are still enjoying energy
savings by using CFLs, even though it is dif-
ficult to calculate such savings in the current
Polish context of rising electricity prices
and a rapidly evolving electricity sector.
However, cheaper and lower-quality CFLs,
imported from Asia, are less energy-efficient,
and many consumers are attracted to their
lower price.
Generally, consumers are aware of the ben-
efits of CFLs and are purchasing them, but
there is a need to increase awareness raising
because there is very little publicity and in-
formation available to average consumers on
CFLs and EE lighting. And consumers need to
be further informed about the differences be-
tween high-quality and low-quality CFLs. In
addition, changing to more environmentally
sustainable and energy-efficient behavior
and consumption requires a foundation of
knowledge of the benefits of energy-efficient
practices, both in terms of savings and the
global environment, as such a transformation
cannot be sustained through price reduction
alone. Although consumers are still generally
satisfied with CFLs, indications are that their
level of satisfaction has decreased since PELP,
as lower-quality bulbs on the market burn out
early or do not work properly.
Some manufacturers have benefited greatly
from this market transformation, while oth-
ers have experienced significant challenges.
58
Post Implementation Impact Assessment: Poland Efficient Lighting Project
Sales overall are very high, as is the penetra-
tion rate, and the market has experienced
some degree of saturation. Philips and Osram
continue to dominate the CFL market, as
they did at the time of the project. Philips
has certainly benefited directly from PELP
(as did ES Systems in the luminaire market),
while Osram and other manufacturers have
benefited indirectly through a transformed
market and increased sales overall. However,
the market opened up by PELP contributed to
a flood of cheaper Asian imports entering the
Polish market. Local manufacturers have not
been able to compete with this or with the
big established players. There are more “lo-
cal players” in the market now, but they are
mostly distributors of imported goods, and
they do not see their business as sustainable.
In addition, the sustainability of the CFL mar-
ket is in question, as consumer confidence
is eroding due to lower-quality products
and the absence of adequate mechanisms to
control quality.
Some electric utilities have benefited from
PELP over time and have adopted DSM and
EE to avoid large investments. However,
this is usually only for peak shaving and is
certainly not widespread. Through PELP and
initiatives that grew from it, municipalities
continue to reap the benefits of EE, as the
awareness and use of CFLs has spread to
many municipalities beyond those targeted.
The impacts of PELP on the CFL market
are evident in many ways in Poland today.
However, there is a need to continue efforts
to raise awareness and knowledge at various
levels and to put in place mechanisms that
would guarantee CFL quality and energy ef-
ficiency in order to ensure a sustained market
transformation for EE lighting in Poland well
into the future.
Lessons Learned
• The development of an appropriate en-
abling environment for energy efficiency
actions (supportive energy and ownership
regulations, laws, policies, and strategies;
supportive business and legal environ-
ment; and so on) is important. Enforce-
ment is a key issue here, referring to:
• The need for enforcement of EE-related
laws, policies, and plans at various levels,
with an emphasis on ensuring that govern-
ments are taking steps to follow through
on laws and policies aimed at promoting
EE and environmental sustainability
• The need for mechanisms to ensure the
quality of the products on the market, as
market transformation for efficient lighting,
to be sustainable, must be accompanied
by the development of institutions with
the capacity to develop mechanisms to
help sustain demand in the long term
through support of consumer confidence
and through the assurance of a minimum
level of quality (and energy savings)
• Direct incentives to manufacturers can
be an efficient way to bring about mar-
ket transformation in favor of a given EE
product.
Impact Assessment
59
• In a rapidly changing and opened econ-
omy, adequate attention must be paid to
the capacity to compete with imported
products and the effects this might have,
in the long run, on local manufacturing
capacity and the local market for the prod-
uct, in view of the global environmental
objectives sought. This may play a role in
the selection criteria for the manufacturers
to receive incentives.
4.2.4 Mainstreaming Global
Environmental Concerns
In an attempt to assess the degree to which
global environmental concerns have been
mainstreamed into Poland’s national and
sectoral policies, the Study Team met with
key ministerial representatives and lobby
groups and conducted a thorough and up-
dated review of key national and sectoral
policies, laws, or plans. The following indica-
tors were used:
• General level of awareness on global en-
vironmental benefits of EE measures, such
as the use of efficient lighting in ministry
offices
• Number, type, and quality of laws, poli-
cies, frameworks, and plans developed or
strengthened that address efficient lighting
or other EE measures
• Evidence of attribution to the project
It is clear from existing legislation, such as
the 1997 Energy Act, that the government
is aware of EE and global environmental
issues, and to various degrees these have
been mainstreamed into national and sec-
toral laws and policies. However, although
PELP was widely known, well received, and
served to raise awareness of EE, the project
came too late to have a direct impact on
those laws. Nevertheless, PELP did have
a significant impact on the education sec-
tor, as discussed later in this section. The
mainstreaming of global environmental
concerns into other sectors is also discussed
briefly.
National Environment Laws, Policies,
and Plans
In order to meet EU standards concerning
emissions of sulfur oxide (SOx), nitrogen
oxide (NOx), and particulates, the Polish gov-
ernment in 1998 enacted new environmental
regulations for emissions from boilers, requir-
ing installation of sulfur control technology
(such as scrubbers or fluidized bed boilers).
The government’s facility-specific compli-
ance determinations option awards tariff
reductions to power plants that are certified
as environmentally EU-compliant earlier than
other plants, a policy aimed at encouraging
early adoption of EU requirements. Accord-
ing to the Ministry of Environment, since
the late 1990s there have also been similar
laws against polluting companies, who must
pay according to their level of pollution or
emission.
For the most part, however, global environ-
mental issues were already mainstreamed
60
Post Implementation Impact Assessment: Poland Efficient Lighting Project
into national plans and policies at the time
PELP took place. The level of mainstreaming,
in terms of precise actions to be undertaken
in years to come on EE and DSM, has not
improved since PELP.
National Energy Laws, Policies, and Plans
In the Guidelines for Energy Policy of Po-
land Until 2020, approved by the Council
of Ministers in 2000, it is mentioned that the
Minister of Economy shall promote technolo-
gies that are particularly significant for energy
policy, including highly efficient lighting
systems (sources of light, frames, lighting
management systems).21
The most significant piece of energy-related
legislation is the 1997 Energy Act, which,
although primarily concerned with supply-
side issues, contained a number of Articles
relevant to energy efficiency.22 Article 45 ex-
plicitly created the framework for DSM activi-
ties by stating that energy tariffs “may include
costs of co-financing by energy enterprises of
projects and services the purpose of which is
to reduce energy and fuel consumption by
customers.” The Energy Act also provides the
basis for EE labeling of equipment. Article 52
requires that manufacturers and importers of
equipment specify EE in technical documenta-
tion and that EE be displayed on a label. The
detailed requirements regarding EE labeling
will be determined through future secondary
legislation, but given Poland’s accession to
the EU, labeling laws will certainly be based
closely on European Directive 92/75/EEC
and its subsidiaries, which also cover lighting
sources, lamps, and fixtures. Although the ap-
proval of the new Energy Act in April 1997
coincided with the implementation phase of
the PELP DSM Pilot,23 direct causal linkages
could not be found through this assessment.
In addition, as noted earlier, the govern-
ment’s renewable energy strategy clearly
includes energy supply issues and the need
to plan for EE at the municipal level. Each
municipality and voivodship is supposed to
draft and implement an energy efficiency plan
and a sustainable development plan. The
energy sector laws, policies, and plans are
also clear about municipalities’ responsibility
for having someone oversee EE issues for the
municipality. However, these EE-related ob-
jectives are more a function of EU accession
than any contribution from PELP. In addition,
both the plans and the positions are rarely
implemented, and government enforcement
of EE-related legislation and policies is not
strong in the current context.
It is worth noting that ES Systems mentioned
that foreign companies operating in Poland
have environmental and energy “rules to
follow” (in reference to unspecified laws
and policies) and must adhere to regulations
for EE lighting. The luminaire manufacturer
noted that a good proportion of its business
comes from these companies who are look-
ing for EE lighting systems for their build-
ings, in adherence to the Polish regulatory
framework.
Impact Assessment
61
Economic and Industrial Development
Laws, Policies, and Plans
In the economic and industrial development
sector as well, the wheels of mainstream-
ing of environmental or EE-related issues
into economic policies, laws, and plans
seemed to already be in motion at the time
of PELP. As discussed, there are various
policies, laws, and plans related to renew-
able energy.
Despite the contextual realities of the produc-
tion and use of coal in Poland mentioned ear-
lier, the government has taken some notable
recent steps in relation to this key source of
energy in Poland. The coal sector has been
forced into a heavy restructuring process to
stem overproduction, and the government
plans to shed thousands of mining jobs. In
early July 2004, the government announced
plans to grant its coal industry 9.5 billion PLN
(2 billion euros) worth of aid between 2004
and 2010 and said it would press on with
a restructuring plan. The Deputy Economy
Minister said the aid was compatible with the
rules of the EU. However, he told a news con-
ference that an upturn in the sector’s fortunes
after years of being heavily in debt would not
lead Poland to abandon the restructuring plan
the government agreed to as part of its prepara-
tions to join the EU. The price of a ton of coal
increased on average by 25 percent over the
first four months of 2004 compared with the
same period in 2003. “This breath of optimism
does not allow us to give up the restructuring
of the mining industry. On the contrary we
have to continue, without hesitation, reducing
production capacities,” he said.
Education Laws, Policies, and Plans
There is not much data from the Ministry of
Education on this aspect. However, this is
one sector and area in which the contribu-
tions from PELP are direct and measurable;
perhaps not in laws and policies per se, but
certainly in the courses and curricula at vari-
ous levels of schooling in the country. This
was discussed briefly in section 4.2.2. but is
expanded upon here.
At the university level, stakeholders sug-
gested that PELP had a significant and lasting
impact in terms of mainstreaming EE into the
curriculum. Courses at AGH in Krackow, for
example, now include lectures and weeks of
study on:
• Adjustable speed drives: students are
presented with different aspects of energy
savings and methods of efficient energy
supply
• Power quality and efficiency utilization of
electrical energy, with PELP as a central
case study
• Power engineering, during which efficient
lighting systems are discussed at length
According to these stakeholders – teachers
who were very much involved with PELP –
these courses emerged during and after PELP,
and the contributions from the project to the
education system are direct. These stakehold-
62
Post Implementation Impact Assessment: Poland Efficient Lighting Project
ers have been teaching students many of the
lessons and experiences they had with PELP.
They further noted that for a Masters in energy
management at the university, there is always
at least one lecture solely dedicated to the
experience and lessons of PELP. Currently,
60—70 percent of Masters theses in AGH
University are about energy efficiency issues.
Overall, they noted, this kind of curriculum
and topic is very popular now at AGH and
some other universities and colleges.
In addition, the Polish Ecological Club stated
that there are environmental awareness activi-
ties and courses in high schools as well and,
in some exceptional cases, in elementary
schools. This was confirmed by some uni-
versity professors, as they noted that often
teachers have two jobs, one in the university
and the other at secondary schools.
Conclusions
Although some stakeholders believe that PELP
may have indirectly contributed to bringing
some EE-related issues to the surface and
to the attention of the central government,
they also recall that while the government
was officially supportive of EE and PELP, it
was not involved in the project and no active
relationship or mechanism was in place to
ensure feedback of PELP experience at the
policy level. Poland’s current accession to
the EU is the main impetus for the laws and
policies in Poland, which are more focused
on RE rather than EE. EE has therefore not
been mainstreamed into Poland’s laws and
policies to the extent that could be expected.
Where it has, enforcement of legislation has
been lacking and requires attention. In addi-
tion, PELP did not have an observable impact
on legislation development and in most cases
occurred too late to have one.
Nevertheless, PELP did have a significant
impact on the development of EE-related
curricula at various levels of schooling in
the country, although this is not reflected in
education laws or policies per se. PELP cata-
lyzed an educational and intellectual focus
on EE-related issues in Poland, and its impacts
can be observed in the wide array of courses
and curricula dealing with this topic and the
greatly expanded number of graduates and
experts who have emerged.
4.2.5 Impacts on Local Environment
and Health
This section aims to discuss briefly some of
the health and environment-related impacts
associated with the achievements of PELP in
the long term. Attributing such impacts to
PELP specifically is a challenge, one that is
compounded by an almost complete lack of
data on this in Poland. However, the impact
assessment brought to light a key health
impact of PELP’s sustained CFL and EE light-
ing market transformation, as well as more
general benefits that the project may have
contributed to.
Generally speaking, the extensive use of
fossil fuels like coal means increased emis-
Impact Assessment
63
sions of CO2, which contributes to climate
change and indirectly affects human health
negatively. Although climate change can
have serious consequences for human health
overall, high levels of exposure to the by-
products of coal combustion, particularly
NOx, SOx, and mercury, can also have
significant consequences on the health of
people living near high-emitting power
plants. Local pollutants directly affect the
health, life expectancy, and quality of life of
anyone who is exposed to them at moderate
or high levels,24 particularly children and
elderly people.
Another related health matter in this context
is acid rain, which is caused by smoke and
gases that are given off by factories and cars
that run on fossil fuels. When these fuels are
burned to produce energy, the sulfur that is
present in the fuel combines with oxygen
and becomes SOx; some of the nitrogen in
the air becomes NOx. These pollutants go
into the atmosphere and become acid. SOx
and NOx are produced especially when coal
is burned for fuel, for example, to produce
electricity, and the more electricity that
people use, the more coal is burned. Many
living and nonliving systems are harmed or
damaged as a result of acid rain. Humans
can become seriously ill and can even die
from the effects. One major health effect of
acid rain for humans is respiratory problems.
Asthma, along with dry coughs, headaches,
and throat irritations, can be caused by acid
rain. The rain can be absorbed by plants
(through soil or direct contact) and animals
(from things they eat or directly contact).
When people eat these plants or animals,
the toxins they take in can affect them. Brain
damage, kidney problems, and Alzheimer’s
disease have been linked to people eating
“toxic” animals or plants.
Evaluation of the impact of PELP on the local
environment and people’s health requires
an even more sophisticated investigation
than evaluation of reduced GHG emissions,
which could not be comprehensively car-
ried out in the context of this impact assess-
ment. Nevertheless, it is clear that energy
efficiency projects that reduce the quantity
of electricity produced by coal-fired power
plants will have a positive impact on the lo-
cal population’s health. Since the project has
contributed to reducing the need to expand
coal power plants, which would have pro-
duced more NOx and SOx, there are some
impacts from PELP in this area. In the long
term, however, the isolated impact of PELP
might be minimal.
Yet the impact assessment shed light on an
important health issue with regards to public
lighting in schools. Some ENGOs such as
PNEC, academics such as AGH, and agencies
like FEWE maintained during PELP that EE
lighting initiatives in schools were crucial for
the health of children, because of the harm-
ful long-term effects of non-EE lighting on
children’s eyesight. Research done by FEWE
during the last years shows that the light in
64
Post Implementation Impact Assessment: Poland Efficient Lighting Project
most Polish schools is in very bad condition,
according to FEWE. In many schools the light
intensity is much lower than required, and
the inadequate luminaries and accompanying
discomfort lead to what is known as “school
short sightedness.”25 Preserved or improved
eyesight for children in schools due to the
installation of brighter lamps with the same
energy consumption (or less) has been one
impact of PELP, as well as of more recent
initiatives that have built on PELP. Although
there are no statistical data to support the
claim to improved eyesight, stakeholders
are certain that PELP has helped to contrib-
ute, in the long term, to such improvements
in children who are or were in the schools
involved in EE lighting initiatives during or
after PELP.
Thus when dealing with lighting in schools,
in cases where lighting was insufficient to
start with, the argument about children’s
eyesight and its relation to proper lighting
can be a convincing factor in bringing social
support for EE lighting initiatives.
4.3 Replicability
A significant number of projects developed
in Poland and elsewhere have been inspired
by the PELP experience at local, national, and
regional levels, some of which are discussed
in this section. Replication of GEF-supported
projects in other countries beyond the origi-
nal project locations – a key goal of the long-
term strategies of GEF – is also occurring and
will be mentioned here as well.
In Poland, the Study Team’s findings confirm
that many initiatives and projects have repli-
cated the PELP experience and learned from
the project. For example, PNEC developed
a project based on the methods and experi-
ences of PELP, with a particular focus on DSM
in the context of EE. The idea was to copy
the “target promotion of CFLs,” in which a
significant saturation of households with CFLs
would be ultimately achieved, but without
external subsidies. DSM approaches such
as the use of coupons to enhance awareness
and demand were used. The project was
tailored as a low-profile attempt to establish
a revolving fund located at PNEC. The initial
input was provided from GEF as a post-PELP
activity.
Two municipalities, Miedzna and Nowy Sacz,
took part in the initiative, led by PNEC but
with the cooperation of corresponding mu-
nicipal governments. The small project ended
with success: a revolving fund of $3,200 has
been established and may serve as an example
of the feasibility of such an approach, which
relies on municipal governments’ involve-
ment and support. In addition, the mayor
of Miedzna notes that in 2000 the initiative
covered 10,000 out of 15,000 households in
the municipality. It also sponsored meetings
at schools on CFL use, demonstrations were
held displaying CFL benefits, and brochures
were distributed to the public. The mayor
mentioned that even two years after the proj-
ect, in 2002, residents would approach him
about the issue and EE products.
Impact Assessment
65
PNEC suggests that it has replicated PELP
approaches and lessons in other projects in
Poland as well, such as the School Building
Integrated Energy Development Operation.
This focuses on EE lighting in 15 schools and
10 municipalities in Poland, and stakehold-
ers noted that their experiences with PELP
formed the basis for the overall approach
once again. PNEC also stated that it is cur-
rently involved in many other climate change
and energy efficiency awareness activities,
including the promotion of CFLs, in schools
and municipalities, all of which draw on PELP
lessons and experiences to some degree.
This is confirmed by Philips, which provided
the CFLs for many post-PELP initiatives and
which agrees that PELP was a success that
was replicated and led to many spinoffs, both
direct and indirect.
Replication of approach also spread beyond
the efficient lighting sector. In 2004 the Pol-
ish Efficient Motor Project (PEMP) project
was launched. This project was based on the
application of the experiences and lessons
of PELP but focused on electrical motors.
Despite obvious differences, PEMP had a
number of common features with PELP:
• It explored the possibility of deferring
investments of the electricity supply grid
in a cost-effective manner.
• It promised economic benefits for the
electricity user.
• It was based on the existence in Poland
of production capacity of efficient motors
(which are presently exported to western
countries) with limited domestic demand
(which was the situation of CFLs manufac-
tured in Poland before PELP).
• It recognized the need for a market push by
a temporary reduction of price to increase
demand.
• It recognized the need for an intensive ed-
ucational and informational campaign.
The main lesson retained by PEMP is that a
market push provided by a temporary sub-
sidy at the “factory gate” to manufacturers is
an economically effective mechanism that
substantially reduces the retail prices due to
reduction of wholesaler and retailer markups
and relevant taxes. FEWE notes that it took
the approach from PELP but adjusted it to fit
the particular product market context.
According to university and academic stake-
holders involved with the project, PELP has
been replicated many times on a small scale
in Poland. Some projects and initiatives
adopted a similar approach in the universi-
ties, catalyzing CFL bulb replacement for
entire buildings and dormitories. In one
initiative at AGH University in Krackow,
over 1,000 bulbs were replaced in a single
small project.
Replication at the international level can be
seen in the follow-up GEF project known as
the Efficient Lighting Initiative (ELI). During
implementation of PELP, numerous regional
demonstrations of successes and lessons
66
Post Implementation Impact Assessment: Poland Efficient Lighting Project
learned were held with other countries. The
IFC received requests from numerous coun-
tries wishing to host a similar CFL promotion
program; these requests prompted IFC to
design ELI, a $15-million regional initiative.
Although ELI has been implemented in seven
countries (Argentina, the Czech Republic,
Hungary, Latvia, Peru, the Philippines, and
South Africa), the IFC received expressions
of interest in replicating Poland’s experience
from many other countries, including Brazil,
Bulgaria, Egypt, India, Lithuania, and Russia.
Organizations from Zimbabwe, Botswana,
and Mozambique also approached ELI team
members to get advice on how to run similar
lighting programs locally. The implementa-
tion team has floated ideas about exporting
ELI to other countries in the region. Although
the particular design of the program in each
country is not a blueprint copy of PELP,
because ELI adapts EE initiatives to suit local
contexts, it is evident that the general ap-
proaches used in PELP are being replicated
through ELI in other countries.
PNEC noted that it had shared many times its
findings, experiences, and lessons from the
PELP project experience with other countries
as well. PNEC continues to build PELP les-
sons and experiences into its involvement
in EE initiatives at the regional level in co-
operation with partners in countries such as
Romania and Hungary.
Overwhelmingly, it is clear that the successes
of PELP were due to a variety of coinciding
and contextual factors that are no longer
present in Poland and are not necessarily
replicable in other contexts or at the present
time. Some of these factors included rapid
industrial transformation, a rapidly expand-
ing consumer and market base, quickly
expanding consumerism (including stores,
products, consumption), rising incomes,
rapid accession to the EU, and the fact that
the environment was more of a priority at
that time due to smog over cities and the
discovery of the harmful effects of coal, which
people were becoming more aware of. PELP
also drew on very specific cultural/national
factors that are less evident and that may not
be replicable elsewhere, such as the Polish
tradition of poster art. The project used the
traditional method of transferring messages
and found a “space” for publicity between
government propaganda and advertising
of the day, both of which were familiar to
people at the time.
The context has changed dramatically in Po-
land since PELP, and such a project could not
even be replicated within the country today.
In addition to the fact that the factors just
described are no long present, there is now
a much higher availability of CFLs, as well as
a variety, including much cheaper products.
The whole raison d’être for PELP was bring-
ing down the price of CFLs, which used to
be considered more of a “luxury item.” It is
no longer considered as such, with prices as
low as 4 PLN, and CFLs are found in almost
every major store. Thus a replication of the
Impact Assessment
67
PELP approach would be misplaced in the
Poland of today.
In terms of replication in other countries, it is
quite difficult to compare the PELP case with
other countries or other cases, because the
context of PELP in Poland at that time was
so unique. Certain “methods” that coincided
with that time may not be applicable in other
countries. For example, the use of coupons as
an approach to widening awareness of con-
sumption of a product, may not be effective in
countries that are currently not going through
similar economic transitions or at different
income levels. Indeed, they would certainly
not be as effective as they were in Poland in
2004. For comparable countries, such as the
Ukraine, however, such approaches might
still be quite relevant. As ELI demonstrates,
different approaches must be used in different
contexts, as appropriate.
In addition, it is worth noting that many of
the problems that have emerged in Poland
in relation to the CFL market and EE light-
ing are similar to challenges being faced
in other countries. The lack of mechanisms
to reduce the influx or control the quality
of cheap products from Asia is a challenge
for countries like Slovakia, Latvia, and even
Germany. Indeed, this is a global challenge,
evident in all parts of the world and in a wide
variety of markets. Any “replication” activity
must therefore try to mitgate such impending
risks in the context of open, often unregulated
markets for such products.
Today, there is further opportunity for rep-
lication of PELP with the availability of EU
structural funds for such initiatives. In addi-
tion, EU laws and requirements might make
utilities, for example, as well as others – in-
cluding the government – more interested
in DSM and EE. Furthermore, impending
competition from other countries in energy
supply might also make EE/DSM and the
objectives and approaches of PELP generally
more interesting.
The challenge for replication of PELP lies in
the unique context within which the project
took place and the need to adapt the ap-
proach to implement similar initiatives in
dissimilar contexts. Although lessons from
and approaches used in PELP are relevant, the
unique set of contextual factors of a country
in rapid economic (and other) transition is not
present everywhere. However, the long-term
challenges in the EE lighting market in Poland
are relevant to all countries.
69
The impact assessment of PELP has generated
lessons on two levels: for energy efficiency
sector projects (long-term impacts) and for
project management and implementation of
such projects.
5.1 Lessons for Energy Efficiency
Sector Projects
An overarching lesson from this impact as-
sessment of PELP is that there are key chal-
lenges that must be considered and addressed
in market transformation toward energy ef-
ficiency in developing economies. First, it is
important to develop an appropriate enabling
environment for energy efficiency actions
(that is, supportive energy and ownership
regulations, laws, policies, and strategies and
a supportive business and legal environment).
In a country where the macroeconomic and
social context is not conducive to EE, it is
difficult to get full government commitment
to steer the process and ensure the environ-
ment that allows other potential players in EE,
such as ESCOs, to flourish, and others, such
as utilities, to get actively involved. Enforce-
ment is a key issue here, in terms of:
• The need for enforcement of EE-related
laws, policies, and plans at various levels,
with an emphasis on ensuring that govern-
ments are taking steps to follow through
on laws and policies aimed at promoting
EE and environmental sustainability
• The need for a mechanism to ensure the
quality of the products on the market
– market transformation for efficient light-
ing, for example, to be sustainable must
be accompanied by the development of
institutions with the capacity to devise a
mechanism that will help sustain demand in
the long term through support of consumer
confidence and the assurance of a minimum
level of quality (and energy savings).
In a country undergoing a rapid decentral-
ization process, it is paramount to build the
capacity of local-level governance institutions
5 LESSONS LEARNED
70
Post Implementation Impact Assessment: Poland Efficient Lighting Project
to plan, implement, and enforce legislation as
well as to pool adequate human and financial
resources to make this possible. To help build
this capacity at the local/end user level and
lead central government to give adequate pri-
ority to EE, special attention must be paid to
building and sustaining the capacity to raise
awareness on EE/DSM issues and benefits at
various levels.
The promotion of benefits should not be
limited to discussion of short-term financial
gains from electricity savings but should also
include global environmental benefits and
their links to consumption habits. Although
promoting short-term financial gains could
in many cases be the best option to attract
consumers’ attention and induce a market
shift (as was the case for PELP), it should be
accompanied by the promotion of global
environmental benefits that can contribute
to bringing a more sustainable, longer-term
attitudinal change toward energy-efficient
practices among end users and institutions.
Sustaining raised awareness to have a long-
term impact on changing attitudes and
behaviors requires that adequate emphasis
be placed on information dissemination and
education in an ongoing manner and at all
levels.
If the national government does not dem-
onstrate interest in a particular issue, it
might be a good strategy to turn to other
national actors, including the private sector,
to implement a project and leverage initial
commercial interest to lead the way toward
the achievement of global environmental
objectives. However, to achieve total and
sustainable market transformation, capacities
must be built not only in private sector actors,
such as manufacturers and ESCOs, but also in
central government, municipalities, and non-
governmental actors active in the sector.
In a rapidly changing and opened economy,
adequate attention must also be paid to the
capacity to compete with imported products
and the effects this might have, in the longer
run, on local manufacturing capacity and the
local market for the product, in view of the
global environmental objectives sought. This
may play a role in the selection criteria for the
manufacturers to receive incentives.
In addition, direct incentives to manufactur-
ers can be an efficient way to bring about
market transformation in favor of a given EE
product. For sustained impact in EE or DSM,
appropriate champions must be identified
and integrated into the initiatives from vari-
ous levels of government, the private sector,
municipalities, consumer representatives,
ENGOs, and manufacturers.
In the context of EE initiatives, it can be ben-
eficial to work more with end users and final
consumers who have the most to gain from
electricity savings. PELP demonstrated that
utilities are unlikely to be a strong partner in
a market where there is already a surplus of
Lessons Learned
71
energy and where profits might be affected,
and the project chose instead to work with
municipalities. Practically, the greatest ben-
eficiaries of EE are end users (end consumers
such as local people or municipalities owning
buildings), and they must be involved more
directly in the awareness raising as well as
in the development and implementation of
EE initiatives.
When dealing with lighting in schools, in
those cases where lighting was insufficient
to start with, the argument about health
– namely, the relation of children’s eyesight
to proper lighting – can be a convincing fac-
tor in bringing public support for EE lighting
initiatives.
5.2 Lessons in Project Management and
Implementation of EE Initiatives
Assessing PELP in the long term helped to
identify some lessons for improving on the ex-
periences of the project. For instance, when
promoting a new product such as CFLs (and
especially in economies in transition), having
an “objective” promoter of the product to the
public, someone who is seen as independent,
is an effective promotional tool.
Contextually appropriate project executors
and partners are key factors in the short-term
and the long-term success of EE initiatives.
Many successes of PELP in the short term,
and its larger impacts in the longer term, are
due to the involvement of particular persons
and their level of interest, enthusiasm, and
commitment. This is especially significant in
the absence of a conducive enabling environ-
ment. For example, in this case, the IFC was
a well-known and respected body – an im-
portant factor in the project’s success – and
was able to bring government and the private
sector on board. The IFC was the credible
“big business” patron for the project.
Furthermore, the involvement of appropriate
local resources in the design of the project
helps ensure that the intricacies of the lo-
cal context are taken into account and that
initiatives are tailored to beneficiaries in
question. For EE initiatives, this refers to the
need to plan and work with end users and
consumers in an iterative and collaborative
manner. In addition, to ensure the project is
allowing for lessons to be learned throughout
implementation and for (often changing) con-
textual environments to be considered in an
ongoing manner, it is important to make the
most appropriate use of available resources
and to involve them in the project. For ex-
ample, several members of the PELP’s advi-
sory committee expressed dissatisfaction and
disappointment with project implementation
and long-term impacts as the project did not
make sufficient use of the resources on the
committee for serving its purpose.
Project implementation approaches must be
contextually appropriate (such as incentive
measures or methods of reaching target popu-
lations) in cultural, temporal, ideological,
and political terms. For example, the DSM
72
Post Implementation Impact Assessment: Poland Efficient Lighting Project
approach used in PELP coincided, at the time,
with some post-communist ideas for demand-
side approaches (the use of coupons).
Consider planning for additional follow-up
activities. Follow-up can allow for certain
emerging constraints to be identified and
potentially addressed. In the case of PELP,
follow-up could have included continued
awareness raising, especially beyond the
geographic scope of the project. In ad-
dition, follow-up could have focused on
targeting public buildings, schools (where
electricity for light and heat account for
75 percent of costs, and almost all school
lighting systems are old), or the enabling
environment for ESCOs and other players
to take their full measure. In this sense,
follow-up can help immediately build on
successes overall.
73
These recommendations aim to address a
sustained market transformation for energy
efficiency and are presented in order to have
a positive effect on future EE-related initiatives
of the World Bank-GEF. Although some are
specific only to the Polish context, many can
be understood as applicable to a variety of
contexts.
• Further use of existing networks in Poland
that raise consumer awareness should be
built on as part of a larger effort in aware-
ness raising on EE at local and municipal
levels.
• Although the primary and initial focus of
awareness raising efforts toward end users
might have to be on economic benefits
(as was the case for PELP), some level of
awareness raising efforts should also be
on the links between personal habits and
the global environment to help ensure
the sustainability of behavioral change.
A phased strategy in terms of consumer
awareness is therefore recommended,
focusing perhaps initially on economic
aspects to induce a shift, but then focusing
on global environmental aspects in order
to address sustainability.
• Municipalities in Poland should be made
more aware of available funds for EE ini-
tiatives, and related capacities should be
built to facilitate access to those funds.
• The enabling environment, including the
legal structure and enforcement, must
be considered as part of a larger effort
to address capacity development for EE-
related policy making, implementation,
and enforcement. When this sort of ac-
tivity is outside the scope of the project
for financial or strategic reasons, project
management should recommend follow-
up activities or projects to be undertaken
by the World Bank-GEF, other donor agen-
cies, or national institutions concerned
with the issue.
• Future EE initiatives should look at the
development of mechanisms to ensure
CFL quality and heightened EE savings
6 RECOMMENDATIONS
74
Post Implementation Impact Assessment: Poland Efficient Lighting Project
in the long run and at consumers’ better
satisfaction with CFLs, thus contributing
to sustained market transformation for EE
lighting.
• Awareness raising initiatives in Poland
must move beyond urban areas to rural
ones and must begin to target municipali-
ties and areas where CFLs and EE generally
have yet to emerge.
75
APPENDIX A
Project Organizational Chart
Global Environment FacilityProject Finance
International Finance CorporationProject Finance & Management
IFC Technical & EnvironmentDepartment
Environment Division
Netherlands Energy Company, B. V.(NETENCO)Utility Partner
PELP AdvisoryCommitte
Monitoring & EvaluationConsultant
Polish TechnicalTesting Facility
Polish ProjectMarket Research
Backgroundcalculations
(FEWE)
Monitoring & EvaluationComponent
Pilot DSMComponent
LuminaireDevelopment &
Subsidy Component
IIEC & LightingDesign Consultants
LuminaireManufacturers
Pilot DSMConsultant
Battelle/PNL, andPNEC
Polish Cities andRegional Electric
Distribution
Chelmno
Elk
Zywiec
Detlam Polish AdvertisingAgency Studio P
Public EducationComponent
CFL SubsidyComponent
CFL Manufacturers
GE Polska
Maya
Philips Lighting Poland
Vox
Electra
ES-System
Philips LightingFarel Mazury
GE Polska
Netherlands EnergyEfficient Lighting, B. V.
(NECEL)Polish Foundation for
Energy Efficiency (FEWE)
IFC Warsaw
77
Name of Stakeholder Organization Role in Project
Andrzej Jarosz PELP project manager
Russel Sturm International Finance Corporation Consultant
Mark Ledbetter Battelle PNL Involved in DSM component
Chris Granda Vermont Energy Investment Project manager/consultant Corporation
Longina Lewandowska-Borowka Federation of Consumers
Professor Dr. Maciej Sadowski Institute of Environmental Protection PELP Advisory Committee
Ewaryst Hille SPEC Involved with project
Roman Janiczek Polish Power Grid Company – PSE Involved with DSM component
Prof. Krzysztof Zmijewski Procesy Inwestcyjne PELP Advisory Committee, former President of PSE, President of the Polish National Energy Conservation Agency
Prof. Adam Gula AGH University Polish Foundation for Energy Efficiency, involved in DSM component
Maria Stankewicz Polish Network Energie-Cites PNEC, involved with project and post-PELP activities
Andrzej Stancyk Kompania Weglowa Mayor of Miedzna, involved in post-PELP activities
Prof. Fijat Polish Ecological Club, AGH Univeristy
APPENDIX B: INTERVIEWEES
78
Post Implementation Impact Assessment: Poland Efficient Lighting Project
Marek Zabarowski MARR, MAES Member of Polish Ecological Club, PELP Advisory Committee
Prof. Zbigniew Hanzelka AGH University Involved in DSM component
Prof. Maciej Tondos AGH University
Mr. Piotr Switilski ES Systems Luminaire Manufacturer involved with project
Damian Wilczek Kania CFL Manufacturer involved with project
Bogdan Rogala Philips CFL Manufacturer involved with project
Bogdan Slek Philips CFL Manufacturer involved with project
Slawomir Pasierb FEWE FEWE, involved with project
Szymon Liszka FEWE, PEMP Project Manager
Roman Glaz Ministry of Environment
79
Aron, C. J., and R. Woodward. 2000. Final
Report IFC/GEF Poland Efficient Lighting
Project (PELP).
Bamberger, M., and N. Fujita. 2003.
Impact Evaluation of Development As-
sistance. A Practical Handbook for De-
signing Methodologically Sound Impact
Evaluations under Budget, Time, and Data
Constraints, FASID Evaluators Handbook.
FASID. Tokyo.
Bamberger, M., and J. Valadez. 1994. Moni-
toring and Evaluating Social Programs in
Developing Countries. A Handbook for
Policymakers, Managers, and Researchers.
Economic Development Institute, World
Bank. Washington, DC.
Bamberger, M., J. Rugh, M. Church, and
L. Fort. 2004. Shoestring Evaluation: De-
signing Impact Evaluations under Budget,
Time and Data Constraints. American
Journal of Evaluation 25(1):5—37.
Bialowolski, P., and S. Dudek 1th Quarter
of 2004. The State of the Households.
Warsaw School of Economics/Research
Institute of Economic Development. Bul-
letin no 46.
Birner, S., and C. Granda. 2002. The IFC/GEF
Poland Efficient Lighting Project (PELP):
Evaluation Results and Next Steps.
Birner, S., and Martinot, E. 2002. The GEF
Energy-Efficient Product Portfolio: Emerg-
ing Experience and Lessons. World Bank.
Washington, DC.
Campbell, F. A. 2004. Poland Shows What
a Little Light Bulb Can Do.
Central Statistical Office of Poland. House-
hold Projection of Poland 2003—2030.
Council of Ministers of Poland. 2000. Guide-
lines for Energy Policy of Poland Until
2020.
Duczkowska-Malysz, K., and Malysz, J.
4th Quarter of 2003. The State of The
Households. Warsaw School of Econom-
ics/Research Institute of Economic Devel-
opment. Bulletin no 45.
Duke, R., and S. Ryder. 2004. Public Pro-
motion of Private Investment in Efficient
Lighting
APPENDIX C: BIBLIOGRAPHY
80
Post Implementation Impact Assessment: Poland Efficient Lighting Project
EcoFund Foundation. 2002. Polish Dept-for-
Environment Swap.
EEI Market Research. 1996. CFL – Retail
Shop Survey. Warsaw.
EEI Market Research. 1996a. Philips – Ran-
dom Proof of Performance. Warsaw.
EEI Market Research. 1997b. Consumer Re-
sponse Cards Survey. Warsaw.
Export Council for Energy Efficiency. 2004. The
Market for Energy Efficiency in Poland.
Global Environment Facility (GEF). Energy
Efficiency Portfolio Review and Practitio-
ners’ Handbook. World Bank. Washing-
ton, DC.
Global Environment Facility. 1997. Frame-
work and Work Program for GEF’s
Monitoring, Evaluation and Dissemination
Activities. Washington, DC.
Global Environment Facility. 2000. Measur-
ing Results from Climate Change Pro-
grams: Performance Indicators for GEF.
Washington, DC.
Global Environment Facility. 2002. Monitor-
ing and Evaluation Policies and Proce-
dures. Washington, DC.
Granda, C. 1997. Case Study: The IFC/GEF
Poland Efficient Lighting Project (PELP).
Right Light 2(4):271—7.
Griffiths, J., et al. 2004. Stories of Rural
Regeneration From Central Europe. Ru-
ral Livelihoods for Sustainability. Czech
Republic.
Groupe-conseil Baastel. 2002. Global Envi-
ronment Facility. Climate Change Case
Study #1: Poland Efficient Lighting Project
(PELP). Gatineau. Baastel.
Gula, A., Z. Hanzelka, and P. Rudzki. 1998.
The Polish Efficient Lighting in Buildings
Initiative. Draft Concept Paper
Gula, A., Z. Hanzelka, M. Ledbetter, R. Pratt,
and P. Rudzki. 1998. Results and Possible
Dissemination of the Polish Efficient Light-
ing Project - the DSM Pilot.
Institute for Sustainable Communities.
1997. Polish National Environmental Ac-
tion Program Pilot Project. Montpelier,
VT.
International Energy Agency. 2001. Tech-
nology without Borders. Case Studies of
Successful Technology Transfer. Paris:
Organisation for Economic Co-operation
and Development.
International Finance Corporation (Techni-
cal and Environment Department and
Environment Division). 1996. Republic of
Poland. Poland Efficient Lighting Project.
Washington, DC.
International Finance Corporation. 2004.
Poland Efficient Lighting Project (PELP).
Washington, DC.
International Institute for Energy Conser-
vation. 1998. Review and Synthesis of
Lighting Market Transformation Programs.
Washington, DC: GEF and Rockefeller
Foundation.
International Institute for Energy Conserva-
tion. 1999. The Market for Energy Effi-
ciency in Poland.
Kania P.D.H. Sp. zo.o.
Ledbetter, M., R. Pratt, A. Gula, P. Rudzki,
Z. Hanzelka, M. Filipowicz, R. Rudek, P.
Stana, and A. Puza. 1998. IFC/GEF Poland
Appendix B
81
Efficient Lighting Project: Demand-Side
Management Pilot - Final Report. Sep-
tember. 2000
Majchrzak, K. 2nd Quarter of 2002, Business
Activity in Trade, Research Institute of
Economic Development, Warsaw School
of Economics.
Malgorzata P. 1997. Lighting Education and
Information. Polish Foundation for Energy
Efficiency. Warsaw.
Martinot, E. 1998. Monitoring and Evaluation
of Market Development in World Bank-
GEF Climate Change Projects. Framework
and Guidelines. World Bank. Washington,
DC.
Martinot, E. and N. Borg. 1998. Energy-Ef-
ficient Lighting Programs: Experience
and Lessons from Eight Countries. Energy
Policy 26(14):1071—81.
Martinot, E. and M. T. El-Ashry. 2004. Suc-
cesses in Technology Transfer for the
Global Environment. World Bank. Wash-
ington, DC.
Ministry of the Environment. 2001. Develop-
ment Strategy of Renewable Energy Sector.
Poland.
Navigant Consulting Inc. 1999. Evaluation
of the IFC/GEF Poland Efficient Lighting
Project CFL Subsidy Program. Final Re-
port. Chicago, IL.
Nowicki, M. 2002. Debt-for-Environment in
Practice. Agencja Reklamowo-Wydawnic-
za. EcoFund. Warsaw.
Oniszk-Popawska, A. Renewable Energy
Supporting Strategies in Poland. EC Baltic
Renewable Energy Centre.
Oniszk-Popawska, A., and G. Sokowski. Lo-
cal Sustainable Energy Planning – Polish
Case Study. EC Baltic Renewable Energy
Centre.
Operations Evaluation Department, Opera-
tions Evaluation Group, and Operations
Evaluation Unit. 2003. Private Sector De-
velopment in the Electric Power Sector. A
Joint OED/OEG/OEU Review of the World
Bank’s Assistance in the 1990s. World
Bank. Washington, DC.
Polish Foundation for Energy Efficiency.
1996. Poland Efficient Lighting Project.
Polska S. 2000. Energie. Post PELP Final
Report. Krakow. June.
Popiolek, M. 1997. Lighting Education and
Information. Right Light 2(4):165—7.
Streicher, A., and D. Keith. 1993. Demand-
side Management in Poland: Final Report
– Part 1: National Assessment. Haqler
Baily Services, Inc., for U.S. Agency for
International Development. Washington,
DC.
Ulrich Research Services, Inc. 2003. Con-
sumer Energy Awareness and Attitude
Study. March.
United Nations Department of Economic and
Social Affairs and Division for Sustain-
able Development. 2004. Success Stories
2000. The Poland Efficient Lighting Project
(PELP).
United Nations Development Programme
and Global Environment Facility. 2004.
Measuring and Demonstrating Impact.
UNDP/GEF Resource Kit (No. 2). New
York/Washington, DC.
82
Post Implementation Impact Assessment: Poland Efficient Lighting Project
United Nations Framework Convention on
Climate Change. Report on the In-depth
Review of the Third National Communica-
tion of Poland. FCCC/IDR.3/POL.
World Bank (Operations Evaluation Depart-
ment). 1997. Poland Country Assistance
Review. Volume 1: Main Report. Wash-
ington, DC.
World Bank. 1998. Fuel for Thought: A New
Environment Strategy for the Energy Sec-
tor. Washington, DC.
World Bank. 1999. Country Assistance Strat-
egy. Poland Country Assistance Progress
Report. Washington, DC.
World Bank. 2002. Memorandum of the
President of the International Bank for
Reconstruction and Development and the
International Finance Corporation to the
Executive Directors on the Country Assis-
tance Strategy for the Republic of Poland.
Washington. DC.
World Bank. 2004. Project Details: Poland
Efficient Lighting Project (PELP – IFC).
World Bank and Global Environment Facil-
ity. 1997. Project Implementation Review.
Washington, DC.
World Bank (Environment Department and
Energy, Mining and Telecommunications
Department) and International Finance
Corporation. 2000. Fuel for Thought. An
Environmental Strategy for the Energy Sec-
tor. Washington, DC.
Xenergy Inc. 2002. Phase 4: Market Effects
Study of California Residential Lighting
and Appliance Program. April.
83
NOTES
1. EIA Country Analysis Brief, Poland: En-
vironmental Issues, June 2003.
2. Birner and Martinot 2002; Aron and
Woodward 2000.
3. Ledbetter et al. 1998.
4. Ibid.
5. Oniszk-Popawska, undated.
6. United Nations Framework Convention
on Climate Change, undated.
7. See section 3.2.1 of this report and
section 2 of Navigant Consulting Inc.
1999.
8. Granda 1997.
9. It was assumed that the sales growth rate
in 1996 and 1997 without PELP would
be the same as the average sales growth
rate that IAEEL estimated for all of East-
ern Europe, including Poland (about 30
percent) and that the PELP did not have
any impact on the sales growth rate after
the end of the project, which are both
certainly conservative assumptions.
10. Central Statistical Office of Poland, un-
dated.
11. See section 4 of Navigant Consulting Inc.
1999.
12. Oniszk-Popawska and Sokowski, un-
dated.
13. Ibid.
14. Oniszk-Popawska, undated.
15. The representative sample was formed
of people living in urban Warsaw (60
percent) but a significant minority (40
percent) were from surrounding rural
areas. There were a balanced number
of males and females, covering ages
20—70.
16. Consumers in the focus group were al-
lowed to pick more than one choice,
which is why percentages do not add
up to 100 percent cumulatively, as each
percentage represents the share of re-
spondents who picked that advantage.
17. Ulrich Research Services, Inc. 2003.
18. Xenergy Inc. 2002.
19. Granda 1997.
20. Polska 2000.
21. Guidelines for Energy Policy of Poland
84
Post Implementation Impact Assessment: Poland Efficient Lighting Project
Until 2020, Document approved by the
Council of Ministers on February 22,
2000.
22. International Institute for Energy Conser-
vation 1999.
23. Gula, Hanzelka, and Rudzki 1998.
24. World Bank 1998.
25. Popiolek 1997.
World Bank Global Environment Facility
Coordination Team Environment Department
THE WORLD BANK
1818 H Street, NW
Washington, D.C. 20433, USA
Telephone: 202.473.1816
Fax: 202.522.3256
Email: [email protected]
Web: www.worldbank.org/gef