policy, tariff regime, and incentives for solar energy - pv market
TRANSCRIPT
Policy, tariff regime, and incentives
for solar energy
Waqas Bin Najib
1 Solarenergie in Pakistan – Munich; September 11 2012
Contents
Solarenergie in Pakistan - Waqas Bin Najib 2
Overview of situation
Power sector – Institutional structure
Grid-connected Independent Power Projects (IPPs)
Tariff structure for grid-connected IPPs
Fiscal incentives for RE IPPs
Status of solar power projects
Market opportunity overview
An attractive market
4
Fast track - project development at highest
Priority
Guaranteed purchase of electricity backed by
Government of Pakistan
Modes of ownership Public Private Partnership
models available ‘OR ‘
Independent power producer (IPP)
Price setting model employed - “Cost plus
tariff” over 18% ROE guaranteed net of taxes
(USD based) Many of the variable operating cost are
passed-on in the tariff model
Special incentives Tax benefits (capital-gains tax,
income tax and turnover tax exemption)
Grid interconnection is the responsibility of power
purchaser
Policy Document can be found at:
http://www.aedb.org/Policy/REpolicy.pdf
Energy deficit is 5000MW and rising
World Class Power Policy
Source: Private Power & Infrastructure Board
– Supply & Demand Position 2020
Solarenergie in Pakistan - Waqas Bin Najib
Excellent Solar Resource
5
2,000 hectares land
for a cluster of solar
power projects
Solarenergie in Pakistan - Waqas Bin Najib
Power sector – Institutional structure
8
Direct sale to distribution companies possible
Wheeling and distributed generation code is being approved
Roadblocks to RE power projects are being removed by wind IPPs
Solarenergie in Pakistan - Waqas Bin Najib
Power policies
Solarenergie in Pakistan - Waqas Bin Najib 9
Conventional Power Projects
Policy for Power Generation Projects 2002
Renewable Energy Power Projects
Policy for Development of Renewable Energy for Power
Generation – 2006 (Short-term policy)
Alternative and Renewable Energy Policy 2011 – DRAFT
(Medium-term policy)
Medium-term policy has been
made more attractive than the
short-term policy
Unsolicited RE-IPP processing route
11
Unsolicited Expression of
Interest Issuance of LoI
Submission of feasibility study
Indicative/reference tariff approval
Energy Purchase Agreement
Issuance of LoS
Execution of security package
and power/energy purchase agreement
Financial Close
Final tariff approval Start of
construction
Solarenergie in Pakistan - Waqas Bin Najib
Unsolicited RE-IPP processing route
12
Activity Indicative Process time Submission of proposal on raw site by sponsors
Review of proposal and intimation of
qualification of sponsors by AEDB Within 30 days from date of receipt of complete proposal
Issuance of LOI for an initial period of 24
months Within 7 days of receipt of acceptable bank guarantee
Completion of Feasibility Study Within the time specified in LOI (Maximum of 18 Months)
Procurement of Generation License Any time within the validity period of LOI
Procurement of tariff from NEPRA Any time within the validity period of LOI.
NEPRA announces its determination within 90 days
Issuance of LOS by AEDB for a period of 18
months
Within 7 days of receipt of acceptable Performance
Guarantee
Execution of Security Package Any time during validity of LOS
Financial Close Within the time allowed in the LOS
Achieve Construction Start Within the time allowed in the LOS/Security Package
Commissioning of Project Within the time allowed in the LOS/Security
Package
Solarenergie in Pakistan - Waqas Bin Najib
Cost-Plus tariff model
14
Energy Tariff (PKR/kWh)
Non-escalable component
Debt servicing
Floating interest rate
Exchange rate variation (PKR-
US$)
Return on equity (ROE)
Exchange rate variation (PKR-
US$)
Escalable component
Fixed O&M costs
Inflation (WPI)
Variable O&M costs
Inflation (WPI)
80:20 Debt to
Equity ratio
>18% Return
on Equity
Coverage of
currency risk
Cost escalation
coverage
Solarenergie in Pakistan - Waqas Bin Najib
Tariff for solar PV based power projects
Solarenergie in Pakistan - Waqas Bin Najib 15
A feed-in/upfront tariff is being considered by the
regulator (NEPRA)
Negotiated tariff (cost-plus) would still be available for
project sponsors, if preferred
Upfront tariff for solar-PV based power projects is
expected to be around 0,22 US$/kWh
Incentives
Solarenergie in Pakistan - Waqas Bin Najib 17
An attractive tariff model with sound guarantee structures for the RE power projects Additional guarantee structures being put up my multilateral agencies for
RE power projects in the country
Guaranteed power purchase (100% of produced electricity is mandatory for Power Purchaser to off-take)
State Bank of Pakistan (SBP) has soft credit line for small renewable energy power projects
Zero rated import of all renewable energy plant, machinery, equipment, and spares (including electronics, batteries, and other machinery)
Exemption from income tax, including turnover rate tax and withholding tax on imports.
Repatriation of equity along with dividends freely allowed, subject to rules and regulations prescribed by the State Bank of Pakistan.
Information Source(s): AEDB, PPDB
Status of solar power projects
19
Growing electricity supply-demand gap. Over 5,000 MW power shortage
Policy/regulations well established
Cost-plus tariff model with minimum 18% ROE guaranteed net of taxes (US$ based); 30-50 years concession
Solar grid code, draft EPA, and other documents already prepared
Licenses for 5 solar power projects issued and feasibility is being conducted (LoIs)
International companies part of the project consortium implementing the solar power projects DACC (US)
CWE (China)
Wellbeing Green (Aus)
TechAccess (UAE)
Solarenergie in Pakistan - Waqas Bin Najib