Power Africa
Geothermal Road Show
September 2014
Presented by
David Kagiri
![Page 2: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/2.jpg)
1
Outline of Presentation
1.Summary of power sector and country investment
environment
2. Detailed summary of geothermal resources
3. Geothermal enabling environment, procurement procedures
and financial incentives
4. Specific opportunities for geothermal project investors
5. Current Corporate funding initiatives and future funding goals
6. Key Contacts
JOH-KGN001-20070825-JvW-P1
![Page 3: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/3.jpg)
2
1. ORGANISATION: POWER SECTOR IN KENYA
Ministry of Energy (MoE)
(responsible for policy matters)
ELECTRICITY
(single-buyer model)
Energy Regulatory Commission(ERC) (responsible for regulating the entire energy sector)
Source: KenGen;
KPC
(Transport)
KPRL
(Refinery)
NOCK
(Marketer)
Private
Marketers
PETROLEUM
KETRACO – Kenya Electricity Transmission Company Ltd REA – Rural Electrification Authoirity KPLC – Kenya Power & Lighting Company Ltd GDC – Geothermal Development Company Ltd IPPs – Independent Power Producers KPC – Kenya Pipeline Company Ltd KPRL – Kenya Petroleum Refinery Ltd NOCK – National Oil Company of Kenya
GDC
(Geo-
Resource
Assess-
ment)
IPPs
(Power
Gene-
ration)
KenGen
(Power
Gene-
ration) KE-TRACO
( New Trans-
mission)
REA
(Rural
Elec-
trification)
KPLC
(Dis-
tribution &
Existing
Trans-
mission
Generation Transmission &
Distribution
KenGen have ~80% installed
capacity market share and
IPPs ~20%
Nuclear
Electricity
Project
(NEP)
![Page 4: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/4.jpg)
3
Summary of power sector and country
investment environment
Source: The Tanzanian Energy Sector: ILO, IEEJ : June 2012
Geothermal Potential >10,000MW
(425MW developed) Excluding 140MW OLK 1AUs under
commissioning)
Coal Under exploration
(Mui Basin)
Oil & Natural
Gas
Under exploration across the country
Proven resource in Turkana, Wajir, Lamu
Hydro Potential > 2.1 GW
(Around .9GW developed)
Solar &
Wind
Solar under exploration,
Wind potential > 4,000MW
Developed 25.1 MW
Biogas Developed 22MW
![Page 5: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/5.jpg)
4
PROJECTED POWER DEMAND IN KENYA
![Page 6: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/6.jpg)
5
THE 40- MONTH 5000+MW Strategy
NEW CAPACITY ADDITIONS (MW)
TIME IN MONTHS 6 12 18 24 30 36 40 TOTAL
Hydro 24 - - - - - - 24
Thermal 87 163 - - - - - 250
Geothermal 90 176 190 50 205 150 785 1,646
Wind - - 20 60 300 250 - 630
Coal - - - - 960 - 960 1,920
LNG - - - 700 350 - - 1,050
Co-Generation - - 18 - - - - 18
Total 201 339 228 810 1,815 400 1,745
Cumulative
Additions 201
540
768 1,578
3,393 3,793 5,538
The Energy sector Strategy is derived from the Government Development agenda; principally the Vision 2030
and the Jubilee Government manifesto
61% is Renewable Capacity
![Page 7: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/7.jpg)
6
2. Geothermal Resources
JOH-KGN001-20070825-JvW-P1
![Page 8: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/8.jpg)
7
2.Geothermal Fields Development
FIELD FIELD POTENTIAL DRILLED
(MW)
DEVELOPED
OLKARIA > 1,000 655 425
EBURRU > 60 3.5 2.4
MENENGAI ? ? ?
JOH-KGN001-20070825-JvW-P1
Fields where Geothermal development is more advanced
- Appraisal drilling / power production complete
![Page 9: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/9.jpg)
8
3. Geothermal enabling environment
• The Government of Kenya has enacted the following policies
and Laws/regulation with regard to Geothermal
• Energy Act – 2006 – Formation of GDC & KETRACO
Company to accelerate Geothermal development and power
evacuation.
• Public Procurement & Disposal Act 2005, Regulation 2006
• Public Private Partnership Act- 2013
• Draft Energy & Petroleum Policy 2014 - Energy Bill 2014
–Energy resource areas
–Industrial Parks
JOH-KGN001-20070825-JvW-P1
![Page 10: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/10.jpg)
9
3. Geothermal enabling environment
• The Government of Kenya through the Ministry of Energy
allocates geothermal drilling blocks to investors
– MoEP has allocated blocks to investors for geothermal development-
Examples : Ormat, Agil, Akiira
• The Government of Kenya formed Geothermal Development
Company (GDC) to undertake upfront geothermal activities
to reduce risk to investors
–These include risks associated with planning and logistics, surface
exploration, exploratory drilling, appraisal drilling and feasibility studies,
and production drilling
JOH-KGN001-20070825-JvW-P1
![Page 11: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/11.jpg)
10
3. Geothermal Financial Incentives
• The Government of Kenya provides incentives in the form
of:
Full cost recovery of their investment through
- Power Purchase Agreements (PPA)
- Steam Supply Agreements
Feed-in-Tariff Policy
Government Guarantees - Letters of Comfort to
Investors
JOH-KGN001-20070825-JvW-P1
![Page 12: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/12.jpg)
11
3. Geothermal Procurement Procedures
• KenGen is guided by the provisions of the Government PPD Act
- 2005 and according to the source of funding
JOH-KGN001-20070825-JvW-P1
Source of Funding/ Development Procurement Procedure
1 Corporate Balance Sheet International competitive bidding
Multilateral/ Bilateral Financing Expression of Interest /Prequalification
Tendering for Consultant/Contractor
2 Public Private Partnership (PPP) International competitive bidding
(Guided by PPP Act) - 2013 Expression of Interest /Prequalification
Tendering for Investors/ Partners
Unsolicitated proposals
3 Direct Procurement Under special circumstances
![Page 13: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/13.jpg)
12
4a. Opportunities for Geothermal Investors
JOH-KGN001-20070825-JvW-P1
• Rigs, Geo-exploration tools and equipment
• Drilling materials and services
• Steam field design, equipment supply and steam pipeline construction services
• Consulting services including feasibility studies
• Direct use of geothermal resource
• Supply of Power plants and equipments
Supplies and Services
• Specialized engineering services
• Development of generation equipment; wellhead and conventional power plants
• Transmission and substation construction
• Civil and infrastructure development
Development Opportunities
![Page 14: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/14.jpg)
13
4b. Opportunities for Geothermal Investors -
KenGen Project Name Opportunities Capacity
(MW)
Comments
Olkaria I Unit 6 Contractors 70 Financing Stage
Olkaria –V Contractors 140 Financing Stage
Olkaria –VI Consultants/
Contractors/
Investors/
Developers
140 PPP – Tender/drilling
Stage
Additional Olkaria
Projects –VII,VIII
Consultants/
Contractors/
Investors/
Developers
280 PPP – Drilling stage
Eburru Geothermal Contractors 25 Pre-feasibility stage
Training Consultants
TOTAL 655
![Page 15: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/15.jpg)
14
5. Corporate Funding Initiatives and
Future Funding Goals
• Geothermal
• Wind, Hydro
• Solar, Fossils
Energy
Sources Conversion
(Generation)
Transportation
(Transmission) Delivery
(Distribution)
End Users
(Consumers)
1. Wider Capital Markets (Equity & Fixed Income
instruments e.g. Asset Backed Securities,
Infrastructure Bonds).
2. Development Financial Institutions (DFIs):
AfD, ADB, IDA, JICA, EIB, and others.
3. Commercial & International Project Finance
Banks – Export/Import Banks.
4. Joint Ventures.
5. BOT/BOOT/Concessions.
6. Government of Kenya
7. Carbon Credits
Financing Options/Sources PIBO
> US$ 300m
DFIs
~US$ 1,300m
-
Pursuing JVs for
development of new
capacity (Coal, Wind,
Solar and Geothermal)
![Page 16: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/16.jpg)
15
5. Key Contacts
• David Kagiri - KenGen
• Geoffrey Muchemi - KenGen
• Elizabeth Njenga - KenGen
JOH-KGN001-20070825-JvW-P1
![Page 17: Power Africa Geothermal Road Showgeo-energy.org/reports/EAG/KenGen Geothermal Roadshow Presentati… · Power Africa Geothermal Road Show ... POWER SECTOR IN KENYA Ministry of Energy](https://reader034.vdocuments.net/reader034/viewer/2022052608/5a7f74467f8b9a571e8bb221/html5/thumbnails/17.jpg)
16 Source: KenGen;
THANKS