power[1]

33
MEP Fundamentals Power

Upload: jennifer-kleinhenz

Post on 25-May-2015

19 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Power[1]

MEP FundamentalsPower

Page 2: Power[1]

MEP FundamentalsPower

Page 3: Power[1]

MEP FundamentalsPower

Page 4: Power[1]

September, 2007

1. What is AIC?

2. If 3-phase is better, why not 4 or 5?

3. Do all tenants have a transformer? Why or why not?

Examples of Questions we will answer:

MEP TrainingPower

Page 5: Power[1]

September, 2007

Electricity is created by:Nature - lightningBattery - chemicalGenerator- mechanical Creates alternating

current as it rotates Why three phases, why

not four?

Motor in reverse

MEP TrainingPower

Page 6: Power[1]

September, 2007

Generation:Heat > steam > turbine > generatorVoltage boosted for distanceSubstations step down to 7,200-15,000vOn-site transformer steps down to 480 or 208v

MEP TrainingPower

Page 7: Power[1]

September, 2007

Ground:

The earth safely absorbs electricityNot just one of those NEC things

MEP TrainingPower

Page 8: Power[1]

September, 2007

Grounding and bonding:Ground is a connection to the earth that only carries current when there is a short (green wire)Bond is connection between components to the groundGrounding is required: At service initiation At low voltage side of transformer

Initiation of new voltage (480v to 208v)

Grounds need to be where inspectors can find them

MEP TrainingPower

Page 9: Power[1]

September, 2007

Transformers:

MEP TrainingPower

Page 10: Power[1]

September, 2007

Fault Current:How much current will flow when a fault (short) occurs?What limits the current?Common panel/breaker rating is 10,000 ampsHow do you know? Utility company transformer

available fault current Fuses in landlord or tenants main

MEP TrainingPower

Page 11: Power[1]

September, 2007

Transformers Typically 480/277 to 208/120

30 KVA to 83 Amps (290 Lbs.) $ 2,300

45 KVA to 125 Amps (400 Lbs.) $ 2,800

75 KVA to 208 Amps (500 Lbs.) $ 4,000

MEP TrainingPower

Page 12: Power[1]

September, 2007

Breakers vs. Fuses

MEP TrainingPower

Page 13: Power[1]

September, 2007

Types of Landlord distribution equipment:Utility metered Wireway Switchgear Meter Center

Landlord redistribution, no meters Distribution Panelboard / Switchboard Buss duct

MEP TrainingPower

Page 14: Power[1]

September, 2007

Wireway (Utility Metered)

MEP TrainingPower

Page 15: Power[1]

September, 2007

Switchgear (Utility Metered)

MEP TrainingPower

Page 16: Power[1]

September, 2007

MEP TrainingPower

Meter Center (Utility Metered)

Page 17: Power[1]

September, 2007

DistributionPanelboard/Switchboard

MEP TrainingPower

(Landlord Redistribution, no meters)

Page 18: Power[1]

September, 2007

Buss duct

MEP TrainingPower

(Landlord Redistribution, no meters)

Page 19: Power[1]

September, 2007

CT’s / CT Cabinet

Page 20: Power[1]

September, 2007

Load Center Residential Not bolt-on breakers Breakers not switch duty rated

Panelboards Grouping of 20A breakers

Distribution Panelboards Larger breakers, 60A – 400A

Switchboards Distribution panelboard with fused switches

Switchgear Large utility rated equipment

MEP TrainingPower

Page 21: Power[1]

September, 2007

Breakers:

Rating (maximum continuous current)Some appliances create short duration surges at start-up(ex. electric motor)

MEP TrainingPower

Page 22: Power[1]

September, 2007

Ground fault:

Hot conductor connected to groundCreate arc/sparkCaution: intermittent fault will not trip breakerGround fault interrupters

MEP TrainingPower

Page 23: Power[1]

September, 2007

Common voltages:Single phase: 120v – household outlet

Three phase: 240v = 120v x 2 wires for larger load (dryer) 208v/120v/3ph/4w 480v/277v/3ph/4w

What’s the last number? Three wires are power Four wire – neutral Ground isn’t counted, it’s assumed

MEP TrainingPower

Page 24: Power[1]

September, 2007

Neutral Another path to ground

(white wire) One hot (black) wire plus

neutral = single phase 277v or 120v

Why not 277v x 3 or 120v x 3 for three phase? Power triangle, really is

geometry.

MEP TrainingPower

Page 25: Power[1]

September, 2007

Load calculation:NEC rules

No consideration for diversity permitted. Actual load rarely exceeds 65% of service size

Actual rating of equipment/lighting is required Equipment nameplates Lighting ballast inefficiencies must be considered

Continuous loads (operating for three + hours) Rated load x 1.25 Lights What about AC and heat?

Track lighting considered 75 watts per foot for service size, but not branching size

MEP TrainingPower

Page 26: Power[1]

September, 2007

Loadcalculation:

MEP TrainingPower

Page 27: Power[1]

September, 2007

Wire size:Sized like pipe (velocity, diameter and pressure)Continuous loads de-rate wire capacity

Heat Defined as 3+ hours (lights)

Multiple conductors de-rate wire capacity Heat (more wires = more heat)

Voltage drops Wire acts as resistor based on

length of wire Long distance with continuous

load = larger diameter

MEP TrainingPower

Page 28: Power[1]

September, 2007

Wire size:

MEP TrainingPower

Page 29: Power[1]

September, 2007

Wire size / Voltage Drop:How long? Wire can run as far as voltage (ex. 480v = 480 feet)

Single phase in out and back Three phase is out only Don’t ask why

Conduit sizing Never consume more than 40% of cross-sectional

area Heat Pulling wire through conduit 40%

Max

MEP TrainingPower

Page 30: Power[1]

September, 2007

Electrical formulas:Energy = power for a period of time Energy = usage, watts x time Electric meters use this measurement Units are watt hours

Power = voltage x amperage Similar to auto horsepower Power = demand, kilowatts (1 kw = one thousand

watts) Voltage = the pressure (pushing) on the current Amperage = current, the flow rate

MEP TrainingPower

Page 31: Power[1]

September, 2007

Electrical formulas continuedExamples of calculations Single Phase: 2.4 kw = 120v x 20 amperes

What is 115v or 110v? Three phase: 16.6 kw = 480v x 20 amperes x 1.73

1.73 is the square root of three (for three phase)

MEP TrainingPower

Page 32: Power[1]

September, 2007

Rules of thumb:20 watts per square foot for retail tenants with their own rooftop units. 15 watts per square foot for retail tenants with landlord central air conditioning. 40 watts per square foot for sit-down restaurants. 100 watts per square foot for food court type tenants.

MEP TrainingPower

Page 33: Power[1]

September, 2007

1. What is AIC?

2. If 3-phase is better, why not 4 or 5?

3. Do all tenants have a transformer? Why or why not?

MEP TrainingPower