Powering Seattle through the 21st Century Denny Substation Program WHAT’S NEXT? In the third quarter of 2018, crews will continue to restore neighborhood streets and sidewalks as duct bank installation nears completion. Other upcoming visible work in and around the substation includes completing alley concrete paving on the east side of the substation, wrapping up work on the elevated walkway and installing project art. We will also continue to advance the Cascade Neighborhood Street Improvements. CONSTRUCTION SCHEDULE 2016 2017 2018 2019 2020 Denny Substation Substation Energized Denny Network VISIT OUR WEBSITE: www.seattle.gov/light/dennysub SEND US AN EMAIL: [email protected] CALL OUR HOTLINE: (206) 257-2142 Denny Substation and Denny Network Construction Map 5 8TH AVE 9TH AVE BOREN AVE TERRY AVE 7TH AVE 7TH AVE 6TH AVE 9TH AVE BOREN AVE 8TH AVE 7TH AVE 6TH AVE 5TH AVE PINE ST PIKE ST STEWART ST VIRGINIA ST BLANCHARD ST BELL ST OLIVE WAY MERCER ST MERCER ST REPUBLICAN ST HARRISON ST DENNY WAY THOMAS ST FAIRVIEW AVE N ROY ST ROY ST WESTLAKE AVE N 9TH AVE N 8TH AVE N TERRY AVE N BOREN AVE N YALE AVE N MINOR AVE YALE AVE DENNY PARK MINOR AVE N MELROSE AVE E PONTIUS AVE N CASCADE PLAYGROUND CASCADE P-PATCH HOWELL ST JOHN ST DENNY SUBSTATION WESTLAKE AVE LENORA ST STEWART ST Ramps to and fro m I-5 Key Planned Duct Bank Completed Duct Bank Completed Duct Bank and Roadway Restoration Completed Duct Bank, Roadway Restoration, and Final Driving Surface Vault DV-08 DV-09 DV-10 DV-11 DV-05 DV-06 DV-07 DV-12 HV-02 HV-01 DV-13 DV-21 DV-22 DV-23 DV-40 DV-31 DV-20 DV-33 DV-27 DV-28 DV-29 DV-30 DV-34 DV-35 DV-36 DV-37 DV-39 DV-26 DV-24 DV-25 DV-32 DV-38 DV-41 HV-03 Veer Lofts Via 6 Larned Apts. Westlake Hotel Westin North Westin South Stewart Court Hotel Max Cosmopolitan Dekko Apts. Aspira Apts. Balfour Apts. Harbor House Julie Apts. 502 Minor Cascade Apts. AMLI Stack House Alcyone Apts. Mirabella Casa Pacifca Lakeview Apts. Brewster Colwell Apts. Alley 24 Apts. Alley 24 North SCCA 215 Pontius 219 Pontius Minor Ave Children’s Metropolitan Project map showing progress of work for Denny Substation and Denny Network construction. Powering Seattle through the 21st Century Denny Substation Program QUARTERLY REPORT 2ND QUARTER | 2018 THE FINISH LINE IS IN SIGHT! With two quarters of 2018 already behind us, it’s hard to contain our excitement. Every day brings us closer to project completion! Recent noteworthy milestones include: starting the energization process in the substation, restoring and re-opening John Street, and installing new sidewalks and curb ramps throughout the Cascade Neighborhood. Community benefits that took take shape this quarter include the off-leash areas, handrails, and the waterproof membrane for the elevated walkway. If you’ve followed along since the beginning of the project, the most anticipated times are yet to come. Let’s hear it for the sprint to the finish line! Keepin’ it green: In May, we installed solar panels atop the substation. These will provide electricity to the community spaces and interior buildings and will help us live up to our reputation as the nation’s greenest utility.

Upload: others

Post on 27-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Powering Seattle through the 21st Century WHAT’S NEXT ... · energization process by bringing high-voltage electricity into the substation’s three transformers and testing them

Powering Seattle through the 21st Century

Denny Substation Program

WHAT’S NEXT? In the third quarter of 2018, crews will continue to restore neighborhood streets and sidewalks as duct bank installation nears completion. Other upcoming visible work in and around the substation includes completing alley concrete paving on the east side of the substation, wrapping up work on the elevated walkway and installing project art. We will also continue to advance the Cascade Neighborhood Street Improvements.

CONSTRUCTION SCHEDULE

2016 2017 2018 2019 2020

Denny Substation

Substation Energized

Denny Network

VISIT OUR WEBSITE:www.seattle.gov/light/dennysub

SEND US AN EMAIL:[email protected]

CALL OUR HOTLINE:(206) 257-2142

Denny Substation and Denny Network Construction Map

5

8TH AVE

9TH AVE

BOREN AVE

TERRY AVE

7TH AVE

7TH AVE

6TH AVE

9TH AVE

BOREN AVE

8TH AVE 7TH AVE

6TH AVE 5TH AVE

PINE ST

PIKE ST

STEW

ART ST

VIRGIN

IA ST

BLANCHARD ST

BELL ST

OLIVE WAY

MERCER ST

MERCER ST

REPUBLICAN ST

HARRISON ST

DENNY WAY

THOMAS ST

FAIRVIEW

AVE N

ROY ST

ROY ST

WESTLA

KE AVE N

9TH AVE N

8TH AVE N

TERRY AVE N

BOREN

AVE N

YALE AVE N

MINOR AVE

YALE AVE

DENNY PARK

MIN

OR AVE N

MELRO

SE AVE E

PON

TIUS AVE N

CASCADEPLAYGROUND

CASCADEP-PATCH

HOWELL

ST

JOHN ST

DENNYSUBSTATION

WESTLA

KE AVE

LENORA ST

STEWART ST

Ramps to and from I-5

Key

Planned Duct Bank

Completed Duct Bank

Completed Duct Bank and Roadway Restoration

Completed Duct Bank, Roadway Restoration, and Final Driving Surface

Vault

DENNY NETWORK ONGOING CONSTRUCTION

DV-08

DV-09

DV-10

DV-11

DV-05

DV-06

DV-07

DV-12

HV-02

HV-01

DV-13

DV-21 DV-22 DV-23

DV-40

DV-31

DV-20

DV-33

DV-27 DV-28 DV-29 DV-30

DV-34 DV-35 DV-36

DV-37 DV-39 DV-26

DV-24

DV-25

DV-32

DV-38

DV-41

HV-03

Veer Lofts

Via 6

Larned Apts. Westlake

Hotel

WestinNorth

WestinSouth

StewartCourtHotel

Max

Cosmopolitan

DekkoApts.

Aspira Apts.

BalfourApts.

HarborHouse

JulieApts.

502Minor

CascadeApts.

AMLI

Stack House

AlcyoneApts.

Mirabella

CasaPacifca

LakeviewApts.

Brewster Co

lwell A

pts.

Alley 24 Apts.

Alley 24North

SCCA

215Pontius

219PontiusMinor

AveChildren’s

Metropolitan

Project map showing progress of work for Denny Substation and Denny Network construction.

Powering Seattle through the 21st Century

Denny Substation Program

QUARTERLY REPORT 2 N D Q UA R T E R | 2 0 1 8

THE FINISH LINE IS IN SIGHT!With two quarters of 2018 already behind us, it’s hard to contain our excitement. Every day brings us closer to project completion! Recent noteworthy milestones include: starting the energization process in the substation, restoring and re-opening John Street, and installing new sidewalks and curb ramps throughout the Cascade Neighborhood. Community benefits that took take shape this quarter include the off-leash areas, handrails, and the waterproof membrane for the elevated walkway.

If you’ve followed along since the beginning of the project, the most anticipated times are yet to come. Let’s hear it for the sprint to the finish line!

Keepin’ it green: In May, we

installed solar panels atop the

substation. These will provide

electricity to the community spaces

and interior buildings and will help

us live up to our reputation as the

nation’s greenest utility.

Page 2: Powering Seattle through the 21st Century WHAT’S NEXT ... · energization process by bringing high-voltage electricity into the substation’s three transformers and testing them

INSIDE THE SUBSTATION:

STEPPIN’ UP OUR GAME…Stairs have been installed at the southwest corner of the substation to provide pedestrian access through the site. The stairs lead to Denny Way, where a new signalized crosswalk will improve connections between the Denny Triangle and Cascade neighborhoods.

The wooden forms constructed by crews in the first picture are stripped away after the concrete is poured. The second picture shows the freshly formed stairs, which will soon be ready for the public to walk on.

Denny Substation ProgramPowering Seattle through the 21st Century

ENERGIZATION PROGRESS REPORTRemember these? In late April, crews began the energization process by bringing high-voltage electricity into the substation’s three transformers and testing them under electrical load. This is a crucial step in “turning on” the substation and making sure it can safely deliver power to customers.

The substation’s three transformers have undergone extensive testing and will soon be transforming high voltage electricity into voltages that can be used by customers.

RESTORE GALORERepaving is a good sign —it means the underground work is wrapping up and the end of construction is near. Who doesn’t love the ride of a smooth freshly paved road?

An asphalt paving crew restores the roadway on Pontius Ave N near John Street after a network distribution line was installed near the substation.

After duct bank installation, the concrete crew restored the roadway in the intersection of 9th Ave N and Thomas Street.

AROUND THE SUBSTATION:

A LUSH CASCADE NEIGHBORBOODCommunity improvements continued in the Cascade Neighborhood. In addition to the new street lighting, sidewalks, and curb ramps, landscaping and trees were recently installed. Improvements still to come include more landscaping during the fall planting season. Crews prepare to plant a tree

in the planting strip next to the Cascade Playground.

Landscaping and a rain garden in the Cascade Neighborhood are among the improvements being made to make the neighborhood greener and a more inviting place to walk.