powerpoint presentation€¦ · cag 4 presentation website . resources. 1. welcome/introduction 2....
TRANSCRIPT
WELCOME
IL 47
Community Advisory Group Meeting #4
Waubonsee Community CollegeTuesday, November 15, 2016
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
CAG Binder Agenda CAG 3 Summary CAG 4 Presentation
Website www.sugargroveinterchange.org
RESOURCES
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
CAG MEETING #3 REVIEW
March 10, 2016 Reviewed the Purpose and Need Presented a Tool Box on Highways and Interchanges Developed Initial Range of Alternatives
PUBLIC MEETING #2 REVIEW
May 3, 2016 Reviewed Purpose and Need Presented the Initial Range of Alternatives Obtained Input
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
Where does IL 47 go?
What does IL 47 look like?
IL 47 ALTERNATIVES
Typical Sections
Alignment
Existing Alignment
SymmetricalAsymmetrical
Widening East
New Alignment
EastWest
{Forest Preserve Avoidance}
IL 47 ALIGNMENT ALTERNATIVES
M-1 M-2 M-3 M-4
SECTION 4(f) The Department of Transportation Act (DOT Act) of 1966
includes a special provision - Section 4(f) - which stipulates that FHWA and other DOT agencies cannot approve the use of land from publicly owned parks, recreational areas, wildlife and waterfowl refuges, or public and private historical sites unless the following conditions apply: There is no feasible and prudent avoidance alternative to the
use of land; and the action includes all possible planning to minimize harm to the property resulting from such use;
OR The Administration determines that the use of the property
will have a de minimis impact.
FOREST PRESERVE AVOIDANCE ALIGNMENT ALTERNATIVE
West{Forest
Preserve Avoidance}
Alternative M-3
Alternative M-4
Alternative M-1 Alternative M-2Symmetrical
Asymmetrical Widening
East
East
West{Forest Preserve
Avoidance}
M-1
M-2
M-3
M-4
IL 47 TYPICAL SECTION ALTERNATIVES
RURAL TYPICAL SRA SECTION – 50’ MEDIAN
OUTSIDE DITCH
SHARED USE PATHOR SIDEWALK
OUTSIDE SHOULDER
DITCH MEDIAN
INSIDE SHOULDER
TRAVEL LANES
50 FEET
IL 47 TYPICAL SECTION ALTERNATIVES
SUBURBAN TYPICAL SRA SECTION – 30’ MEDIAN
SHARED USE PATHOR SIDEWALK
OUTSIDE DITCH
OUTSIDESHOULDER
RAISED MEDIANTURF OR PAVED CURB AND GUTTER
AND STORM SEWER
TRAVEL LANES
30 FEET
11
IL 47 TYPICAL SECTION ALTERNATIVES
MODIFIED TYPICAL SRA SECTION – 6’ MEDIAN
TRAVEL LANES
OUTSIDE SHOULDER
OUTSIDE DITCH
CURB AND GUTTER AND
STORM SEWER
SHARED USE PATH
OR SIDEWALK
RAISED CURB
MEDIAN
6 FEETMINIMIZE FOREST
PRESERVE 4(f) IMPACTS
ACCESS
Access Management Medians Intersection Spacing Right-In/Right-Out (RI/RO)
Entrance Relocation Access Consolidation ¾ Access
¼ MILE MINIMUM SIGNAL OR FULL ACCESS SPACING
RIGHT-IN/RIGHT-OUT
¾ ACCESSRIGHT-IN/RIGHT-OUT
AND LEFT-IN
ACCESS MANAGEMENTC
OLL
EGE
DR
PROPOSED ACCESS TYPEFULL ACCESS
OAK
LEAF
DR
NO
TTIN
GH
AM D
R
OLD
MID
LOTH
IAN
RDI-88 EB
EXIT RAMP
I-88 WB ENTRANCE RAMP
PARTIAL ACCESS(RIGHT-IN/ RIGHT-OUT)U-TURN
Alternative Alignment Typical Section
M-1A Existing AlignmentSymmetrical Widening 30’ Median
M-1B Existing AlignmentSymmetrical Widening 50’ Median
M-1C Existing AlignmentSymmetrical Widening
30’ Median with 6’ Median in Forest Preserve {4(f)} Areas
M-2A Existing AlignmentAsymmetrical Widening to East 30’ Median
M-2B Existing AlignmentAsymmetrical Widening to East 50’ Median
M-2CExisting Alignment
Asymmetrical Widening to East; Except symmetrical at Forest Preserve
30’ Median with 6’ Median in Forest Preserve {4(f)} Areas
M-3 New Alignment East 50’ Median
M-4 New Alignment West{Forest Preserve Avoidance Alternative} 30’ Median
IL 47 ALTERNATIVE COMBINATIONS
QUESTIONS?
Range of Alternatives
Analyzed Interchanges1. Conventional Diamond2. Conventional Diamond
with Roundabouts3. Diverging Diamond 4. Partial Cloverleaf NE Quad
5. Partial Cloverleaf NE and SW Quadrant
6. Partial Cloverleaf SW Quad7. Partial Cloverleaf – Loop
Ramp terminating at Finley Road
INTERCHANGE ALTERNATIVES
QUESTIONS?
Range of Interchange Alternatives
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
ALTERNATIVE EVALUATION AND SCREENING PROCESS
Develop Initial Alternatives
Round 2 ScreeningLevel of Service, Right-of-Way, Environmental
Concerns, Stakeholder Input, Cost
Fatal Flaw Screening
Round 1 ScreeningLevel of Service, Right-of-Way, Environmental
Concerns, Stakeholder Input
Purpose & Need Screening
Eliminated Alternatives
PREFERRED ALTERNATIVE
Alternatives Carried Forward
Alt ResidentialDisplacements
ROW(acres)
NWIWetlands
(acres)
Flood-plains (acres)
Forest (acres)
Farmland (acres)
Forest Preserve
4(f) (acres)
No-Build 0 0 0 0 0 0 0
M-1A 7 11.1 0.2 3.5 1.1 5.8 0.8
M-1B 11 15.1 0.3 4.2 1.6 6.5 1.2
M-1C 7 10.6 0.2 2.8 0.6 5.8 0.3
M-2A 1 12.7 0.2 3.5 1.6 7.4 1.1
M-2B 1 15.1 0.4 4.2 2.7 8.6 1.6
M-2C 0 11.7 0.3 2.6 1.2 7.3 0.3
M-3 1 37.5 1.2 5.1 6.7 25.9 1.2
M-4 11 40.7 2.5 9.2 5.2 17.2 0
IL 47 ROUND 1 SCREENING
0
5
10
15
20
25
30
35
40
45
Potential Residential Displacements ROW (acres)
Property Impacts
M-1A M-1B M-1C M-2A M-2B M-2C M-3 M-4
IL 47 ROUND 1 SCREENING
Existing Alignment Symmetrical and New
Alignment to West had the most displacements
New Alignments had the most ROW impactExisting Alignment
Symmetrical (50’ Median) and New Alignment to West
had the most potential displacements
0
1
2
3
4
5
6
7
8
9
10
NWI Wetlands (acres) Floodplains (acres)
Water Resource Impacts
M-1A M-1B M-1C M-2A M-2B M-2C M-3 M-4
IL 47 ROUND 1 SCREENING
New Alignments had the largest wetland impacts
New Alignments had the most
floodplain impacts
0
1
2
3
4
5
6
7
8
Forest (acres) Forest Preserve 4(f) (acres)
Forest Related Impacts
M-1A M-1B M-1C M-2A M-2B M-2C M-3 M-4
IL 47 ROUND 1 SCREENING
New Alignments had the largest forest impacts Existing Alignment Asymmetrical
Widening to the East with 50’ Median had the most Forest
Preserve 4(f) impacts
AltRes.
Displac-ement
ROW(acres)
NWIWetlands
(acres)
Flood-plains (acres)
Forest (acres)
Farmland (acres)
Forest Preserve
4(f) (acres)
CarryForward
No-Build 0 0 0 0 0 0 0 Yes
M-1A 7 11.1 0.2 3.5 1.1 5.8 0.8 Yes
M-1B 11 15.1 0.3 4.2 1.6 6.5 1.2 Yes
M-1C 7 10.6 0.2 2.8 0.6 5.8 0.3 Yes
M-2A 1 12.7 0.2 3.5 1.6 7.4 1.1 Yes
M-2B 1 15.1 0.4 4.2 2.7 8.6 1.6 Yes
M-2C 0 11.7 0.3 2.6 1.2 7.3 0.3 Yes
M-3 1 37.5 1.2 5.1 6.7 25.9 1.2 No
M-4 11 40.7 2.5 9.2 5.2 17.2 0 No
IL 47 ROUND 1 SCREENING
Alt
PotentialResidentialDisplace-
ments
Concep-tual Cost
($mil-lions)
ROW(acres)
INHS Wetlands
(acres)
Flood-plains (acres)
Farm-land (acres)
Forest Preserve (acres)
No-Build 0 0 0 0 0 0 0
M-1A 7 16.5 11.1 1.9 3.5 5.8 0.8
M-1B 11 17.2 15.1 2.2 4.2 6.5 1.2
M-1C 7 16.5 10.6 1.3 2.8 5.8 0.3
M-2A 1 18.3 12.7 2.1 3.5 7.4 1.1
M-2B 1 18.8 15.1 2.5 4.2 8.6 1.6
M-2C 0 18.3 11.7 1.3 2.6 7.3 0.3
IL 47 ROUND 2 SCREENING
All Build Alternatives Operate Acceptably and have the same approximate WOUS impact
0
2
4
6
8
10
12
14
16
Potential Residential Displacements ROW (acres)
Property Impacts
M-1A M-1B M-1C M-2A M-2B M-2C
IL 47 ROUND 2 SCREENINGExisting Alignment
Symmetrical with 50’ median had the most
displacements
50’ Medians had the most ROW impact
50’ Medians had the most ROW impact
15
15.5
16
16.5
17
17.5
18
18.5
19
19.5
20
Conceptual Cost in 2016 Dollars ($ millions)
Construction Cost
M-1A M-1B M-1C M-2A M-2B M-2C
IL 47 ROUND 2 SCREENINGExisting Alignment with
Asymmetrical Widening to the East had the largest cost
$$$
0
0.5
1
1.5
2
2.5
3
Wetlands (acres)
Wetland Impacts
M-1A M-1B M-1C M-2A M-2B M-2C
IL 47 ROUND 2 SCREENING
50’ medians had the largest wetland impacts
50’ medians had the largest wetland impacts
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
Floodplains (acres)
Floodplain Impacts
M-1A M-1B M-1C M-2A M-2B M-2C
IL 47 ROUND 2 SCREENING
50’ medians had the largest wetland impacts
50’ medians had the largest floodplain impacts
0
2
4
6
8
10
12
Farmland (acres)
Farmland Impacts
M-1A M-1B M-1C M-2A M-2B M-2C
IL 47 ROUND 2 SCREENING
Asymmetrical Widening to the east had the largest
farmland impacts
Alt
PotentialResidentialDisplace-
ments
Con-ceptual
Cost($mil-lions)
ROW(acres)
INHSWetlands
(acres)
Flood-plains (acres)
Farm-land
(acres)
Forest Preserve (acres)
Carry Forward
No-Build 0 0 0 0 0 0 0 Yes
M-1A 7 16.5 11.1 1.9 3.5 5.8 0.8 Yes
M-1B 11 17.2 15.1 2.2 4.2 6.5 1.2 No
M-1C 7 16.5 10.6 1.3 2.8 5.8 0.3 Yes
M-2A 1 18.3 12.7 2.1 3.5 7.4 1.1 No
M-2B 1 18.8 15.1 2.5 4.2 8.6 1.6 No
M-2C 0 18.3 11.7 1.3 2.6 7.3 0.3 Yes
IL 47 ROUND 2 SCREENING
QUESTIONS?
AlternativesCarried Forward
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
INTERCHANGE SCREENING
# Alternative ROW(acres)
Conceptual Cost
($millions)
Bridge Impacts (square
feet)
Wet-lands
(acres)
WOUS(linear feet)
Flood-plains (acres)
Forest (acres)
Farm-land
(acres)
NB No-Build 0 0 0 0 0 0 0 0
I-1 Conventional Diamond 0.7 16.2 2622 <0.1 0 0 <0.1 0.9
I-2 Conv. Diamondw/Roundabout 0 15.9 1261 <0.5 10 0 <0.1 <0.1
I-3 DDI 0 15.8 0 <0.1 0 0 <0.1 0
I-4 Parclo NE 0.7 19.8 2606 <0.1 0 0.1 0 0.8
I-5 Parclo NE SW 2.9 21.7 3218 <0.6 <100 0.1 0.2 3.3
I-6 Parclo SW 2.3 20.3 2608 <0.6 <100 0 0.2 2.5
I-7 Parclo to Finley 7.5 20.2 2608 <0.1 <1000 0 2.4 6.1
0
1
2
3
4
5
6
7
8
ROW (acres)
Property Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
Parclo to Finley had the highest
ROW impact
0
5
10
15
20
25
Conceptual Cost in 2016 Dollars ($ millions)
Construction Cost
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
The Parclo’s had the highest cost
$$$
0
500
1000
1500
2000
2500
3000
3500
Area of Impact (square feet)
IL 47 Bridge over I-88 Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
The Roundabout and DDI had the
least bridge impacts
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
Wetlands (acres)
Wetland Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
The Roundabout and Parclo SW had the highest wetland impacts
The Roundabout and Parclo SW had the highest wetland impacts
0
200
400
600
800
1000
1200
WOUS (linear feet)
Waters of the United States (WOUS) Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENINGParclo to Finley had significantly more impacts to
WOUS
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
Floodplains (acres)
Floodplain Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
Parclos in the NE were the only alternatives
with potential floodplain impacts.
0
0.5
1
1.5
2
2.5
3
Forest (acres)
Forest Impacts
Conv. Diamond Roundabout DDI Parclo NE Parclo NE SW Parclo SW Parclo to Finley
INTERCHANGE SCREENING
The Parclo to Finley had high forested impacts.
INTERCHANGE SCREENING
# Alternative ROW(acres)
Conceptual Cost
($millions)
Bridge Impacts (square
feet)
Wet-lands
(acres)
WOUS(lineal feet)
Flood-plains (acres)
Forest (acres)
Farm-land
(acres)
NB No-Build 0 0 0 0 0 0 0 0
I-1 Conventional Diamond 0.7 16.2 2622 <0.1 0 0 <0.1 0.9
I-2 Conv. Diamondw/Roundabout 0 15.9 1261 <0.5 10 0 <0.1 <0.1
I-3 DDI 0 15.8 0 <0.1 0 0 <0.1 0
I-4 Parclo NE 0.7 19.8 2606 <0.1 0 0.1 0 0.8
I-5 Parclo NE SW 2.9 21.7 3218 <0.6 <100 0.1 0.2 3.3
I-6 Parclo SW 2.3 20.3 2608 <0.6 <100 0 0.2 2.5
I-7 Parclo to Finley 7.5 20.2 2608 <0.1 <1000 0 2.4 6.1
INTERCHANGE SCREENING
# Interchange Alternative Carried Forward
NB No-Build Yes
I-1 Conventional Diamond Yes
I-2 Conv. Diamond w/Roundabout Yes
I-3 DDI Yes
I-4 Parclo NE Yes
I-5 Parclo NE SW No
I-6 Parclo SW No
I-7 Parclo to Finley No
QUESTIONS?
Interchange AlternativesCarried Forward
1. Welcome/Introduction2. Review Previous Public Involvement3. Range of Alternatives4. IL 47 Analysis and Screening5. I-88 Interchange Analysis and Screening6. Closing Remarks/Next Steps
MEETING AGENDA
PHASE I STUDY ELEMENTS
Human and Natural
Environment
Hydraulics, Drainage &
BridgeRoadway, Geometrics
& Traffic
Vehicular/Pedestrian
Safety
Data Collection
Purposeand
Need
Evaluate Alternatives
Define Alternatives
and Evaluation
Criteria
Select Preferred
Alternative
2015 2016 2017
Stakeholder Outreach
Reviewed AlternativesAlternative ScreeningAlternatives Carried
Forward
TASKS COMPLETED
Public Meeting #3 – Tentative Spring 2017 Present Alternatives Screening Results Present Alternatives Carried Forward Present Alternative Evaluation Solicit InputCAG Meeting #5 – Tentative Spring 2017 Evaluate Alternatives Identify CAG Preferred Alternative
NEXT STEPS
PROJECT STUDY TIMELINE
QUESTIONS?
THANK YOU!