Page 1: Ppt on tenughat thermal power plant

1

PRESENTATION ON TENUGHAT THERMAL POWER PLANT

By: ABHINAW KAPOOR 12EEJEE001 B-TECH 4th year(7th sem.) ELECTRICAL ENGG. GEC JHALAWAR

SUBMITTED TO:MR. ASHISH KHANDELWALHOD-EEGECJ

SUBMITTED TO:GOVERNMENT ENGINEERING COLLEGE JHALAWAR

Page 2: Ppt on tenughat thermal power plant

2

TENUGHAT THERMAL POWER PLANT

Page 3: Ppt on tenughat thermal power plant

3

Tenughat Vidyut Nigam Limited is a power generating company incorporated on 26.11.1989 of Jharkhand .

The project site known as Tenughat Thermal Power Station (TTPS) is located at village.Lalpania in Dist‐Bokaro. The project is situated on the bank of Tenughat reservoir.

The total installed capacity of Tenughat Thermal Power Station is 420MW having two units of 210 MW capacity each.

The daily requirement of coal for full load generation from its 2x210 MW units is a approximately 7000 MTs which is met from coal mines of CCL situated in the vicinity of plant within 50 Kms..

TTPS has an acquired land of approx. 1800 acre

ABOUT PLANT

Page 4: Ppt on tenughat thermal power plant

4

• Layout• Principle• Coal handling plant• Boiler• Steam Turbine• Economizer• Generator• Control Room

Main Parts of Tenughat Thermal Power Plant

Page 5: Ppt on tenughat thermal power plant

5

PLANT LAYOUT

Page 6: Ppt on tenughat thermal power plant

6

RANKINE CYCLE

Page 7: Ppt on tenughat thermal power plant

7

COAL:- Plant needs 7000 mt coal per day for the

running of 2x210 mw plant It is supply by coal block ccl which is 50 kms

away from the plantWATER:-Plant get water from tenughat dam

RAW MATERIALS

Page 8: Ppt on tenughat thermal power plant

8

Page 9: Ppt on tenughat thermal power plant

9

Coal Handling Plant

• Crushing system• Conveying system

Coal handling plant section

Page 10: Ppt on tenughat thermal power plant

10

CRUSHER HOUSE:- It consists of crushers which are used to crush the coal to 20 mm size.

Two typesPrimary crusher

oRail crusheroRotary breaker

Secondary crusher

Crushing system

Page 11: Ppt on tenughat thermal power plant

11

Belt are used to convey coal from coal handling plant to furnace.

Specification:-◦ Belt width : 1400mm◦ Speed : 2.2m/sec◦ Total install power : 360kw ◦ Capacity : 1350/750 ton/hr◦ No. of conveyor: 38

Conveying system

Page 12: Ppt on tenughat thermal power plant

12

It is a closed vessel in which water under pressure is converted into steam.

Hot water or steam used to transfer heat to a process.

A boiler is always designed to absorb maximum amount of heat released in process of combustion.

Furnace:- It is primary part of boiler where the fuel is burnt to liberate the heat energy.

Boiler

Page 13: Ppt on tenughat thermal power plant

13

LINE DIGRAMOF BOILER

Page 14: Ppt on tenughat thermal power plant

14

Figure Boiler

Page 15: Ppt on tenughat thermal power plant

15

TURBINE

FUNCTION- Turbine is a machine in which shaft is rotated by the impact of the working fluid such as steam, water etc.

Type – Reaction

TECHNICAL SPECIFICATION- Rated output -- 110 MW Rated speed – 3000 rpm Direction of rotation – clockwise Type -3 cylinder, impulse reaction Heat flow at rated output – 2152.5 kcal/kHz Quantity of oil - 1800 liters

Page 16: Ppt on tenughat thermal power plant

TURBINE

16

Page 17: Ppt on tenughat thermal power plant

17

GENERATOR

It converts mechanical power into electrical power.

PRINCIPLE- Electromechanical energy conversion

TECHNICAL SPECIFICATION- Active output - 110 MW Power factor – 0.85 lag Excitation voltage - 230 Volt Rated voltage – 11 KV Rated speed – 3000 rpm Phase connection – star-star

Page 18: Ppt on tenughat thermal power plant

18

ELECTROSTATIC PRECIPATOR

Used for the removal of suspended particles and fly ash from industrial flue gases PRINCIPLE- Produces an electrostatic field which attracts the ionized carbon particles and other such particulates which cause environmental pollution. 

Page 19: Ppt on tenughat thermal power plant

19

Main Equipment Of Switchyard Bus Bar Bus Coupler Isolating switch Earthling Switch Lightning Arrester Current & Potential Transformer (CT&PT) Circuit Breaker Capacitive Voltage Transformer (CVT)

220KV SWITCHYARD

Page 20: Ppt on tenughat thermal power plant

20

SWITCH YARD

Page 21: Ppt on tenughat thermal power plant

21Control Room

Page 22: Ppt on tenughat thermal power plant

22

CONCLUSION:

The first stage of training is quite fruitful and knowledgeable.we see lots of heavy machines like generator,turbine,wagon trippler e.t.c. we also see switchyard which makes us know about transmission and distribution and various connections.The architecture of powerplant make us to realise that it is not only to learn about machine and its structure but the great part is how to maintain and manage it and without proper planning it is not possible. Basically during this period we learn everything about management and operation of power plant.

Page 23: Ppt on tenughat thermal power plant

23

REFERENCE:

TTPS (www.tvnlonline.com)IEEE sitesWikipediaGeneration of electrical power by “BR GUPTA”

Page 24: Ppt on tenughat thermal power plant

24

THANKS FOR YOUR TIME