ppt underground wp

Upload: devinderchawla

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Ppt Underground Wp

    1/57

    Gale Associates, Inc.E n g i n e e r s a n d P l a n n e r s

    Waterproofing Below Grade in

    High Water Table Conditions

    ICRI 2013 Spring Convention

    James E. Saizan, AIA and Marc A. Loranger, P.E.

    March 20, 2013

  • 8/10/2019 Ppt Underground Wp

    2/57

    Presentation Outline

    Type of Structures and Specific Concerns

    Approaches to Sub-grade Waterproofing

    Design and Product Considerations

    Case Study Examples

  • 8/10/2019 Ppt Underground Wp

    3/57

    Hydrostatic pressure weight of water

    Storm water

    Capil lary action

    Sub-grade Structures and Concerns

  • 8/10/2019 Ppt Underground Wp

    4/57

    Foundation walls and footings

    Slabs on grade / spli t / mud

    Sump / elevator pits

    Pile and matt slab foundations

    Retaining walls

    Tunnels

    Parking garages / slurry walls

    Occupied below grade spaces

    Sub-Grade Structures and Concerns

  • 8/10/2019 Ppt Underground Wp

    5/57

    Code requirements

    Tolerance to moisture

    Risk of leakage

    Redundancy in system

    Key Concepts

  • 8/10/2019 Ppt Underground Wp

    6/57

    Control of Ground and Storm Water

    Footing drains

    Under slab drains

    Dewatering during excavation

    Pumps and wells

    Back up power for pumps

    Approach to Sub-Grade

    Waterproofing

  • 8/10/2019 Ppt Underground Wp

    7/57

  • 8/10/2019 Ppt Underground Wp

    8/57

    Positive Side

    Bentonite clay

    Composite polymers

    Reinforced fluid

    Sheet membrane

    Cementitious

    Soil injection

    Approach to Sub-Grade

    Waterproofing

  • 8/10/2019 Ppt Underground Wp

    9/57

  • 8/10/2019 Ppt Underground Wp

    10/57

  • 8/10/2019 Ppt Underground Wp

    11/57

  • 8/10/2019 Ppt Underground Wp

    12/57

  • 8/10/2019 Ppt Underground Wp

    13/57

  • 8/10/2019 Ppt Underground Wp

    14/57

    Negative Side

    Crystalline

    Metall ic oxide

    Cementitious

    Injection

    Approach to Sub-GradeWaterproofing

  • 8/10/2019 Ppt Underground Wp

    15/57

    Integral Concrete Waterproofing

    Secondary / tertiary redundancy

    Primary waterproof ing for duct banks

    Dams, waterways, containment tanks

    .002 crack bridging capabil ity

    Approach to Sub-GradeWaterproofing

  • 8/10/2019 Ppt Underground Wp

    16/57

    Joint Water Stops

    Hydrophilic

    Bulb

    Consider joint movement

    Retrofit applications

    New to existing building transitions

    Approach to Sub-Grade

    Waterproofing

  • 8/10/2019 Ppt Underground Wp

    17/57

  • 8/10/2019 Ppt Underground Wp

    18/57

  • 8/10/2019 Ppt Underground Wp

    19/57

    Code Requirements

    MA Building Code (5thedition): 1224.4;Groundwater Investigation

    2010 Florida Building Code

    IBC/CT Building Code not less than 12 abovethe maximum elevation of the groundwater table

    Dampproofing vs. waterproofing

    Occupied spaces

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    20/57

    Geotechnical Data

    Design groundwater elevation seasonalhighs and lows

    Backfill type and acceptabili ty

    Soil backfi ll requirements

    Controlled compaction requirements

    Damage control

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    21/57

    Soil / Water Contamination and Testing

    Saltwater

    Brackish water / sulfates

    Petroleum

    Other chemicals (dry cleaning PCE, highalkaline, hard and soft water)

    PH testing

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    22/57

    Structural Configuration and Behavior

    Active

    Passive

    System transitions

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    23/57

    Environmental Conditions

    Minimum application temperatures

    Freezing temperature; surface and ambient

    Precipitation

    Dust control

    Design ConsiderationsDesign Considerations

  • 8/10/2019 Ppt Underground Wp

    24/57

    Surface Preparation

    Concrete (honeycombing, form oils, formties and t ie wires, curing compounds, finish

    considerations, cold joints) Soil / fills (compaction, correct aggregate

    size, free draining, no clay in sub-base)

    Forms (soldier pile and lagging, sheet pi ling

    joints, tie-backs) Priming requirements

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    25/57

    Construction Sequence

    Pits prior to slabs

    Footings / mats prior to walls

    Membrane laps and transit ions

    Open time and exposure subject to damage

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    26/57

    Remedial Techniques

    Dril l and pressure injection (high pressure)

    Exterior soil injection / curtain walling (lowpressure)

    Negative side cementitious and crystalline

    Water plugs / patches

    Positive side (Extensive)

    Design Considerations

  • 8/10/2019 Ppt Underground Wp

    27/57

    Leak sources: slab penetrations andwall/floor joints

    Buoyant pressures caused heaving andbuckling during storm related rising watertables

    Exist ing system: composite HDPE/Bentoniteon positive/blind side, well point system

    Case Study Example FloridaCourthouse Basement

  • 8/10/2019 Ppt Underground Wp

    28/57

  • 8/10/2019 Ppt Underground Wp

    29/57

  • 8/10/2019 Ppt Underground Wp

    30/57

  • 8/10/2019 Ppt Underground Wp

    31/57

    Restoration options: injection, internal trench,

    raised floor, eliminate floor penetrations

    Lessons learned: design buoyant slab, detailslab penetrations, well-points needed back-up,continuity of waterproofing system

    Case Study Example FloridaCourthouse Basement

  • 8/10/2019 Ppt Underground Wp

    32/57

    Leak sources: wall and floor joints,penetrations and openings

    Issues: storm impact on rising water table, ageof existing construction and impracticalpositive-side solutions

    Existing system: multi-ply membrane withoutsub-surface drainage, urethane foam seals atpenetrations

    Case Study Example Electrical

    Vault Florida

  • 8/10/2019 Ppt Underground Wp

    33/57

  • 8/10/2019 Ppt Underground Wp

    34/57

  • 8/10/2019 Ppt Underground Wp

    35/57

  • 8/10/2019 Ppt Underground Wp

    36/57

  • 8/10/2019 Ppt Underground Wp

    37/57

  • 8/10/2019 Ppt Underground Wp

    38/57

    Restoration options: negative-side crystalline

    slurry, seal open penetrations with hydrophilicsealant, manage water intrusion

    Lessons Learned: sub-surface drainage, pumpsystem needed as back-up

    Case Study Example ElectricalVault Florida

  • 8/10/2019 Ppt Underground Wp

    39/57

    Leak sources: slab and wall condensation

    Conditioning and condensate on poorlyinsulated concrete

    Specified system: bentonite sheet and dualwaterstop

    Case Study Example Connecticut Beach Foundation

  • 8/10/2019 Ppt Underground Wp

    40/57

  • 8/10/2019 Ppt Underground Wp

    41/57

  • 8/10/2019 Ppt Underground Wp

    42/57

  • 8/10/2019 Ppt Underground Wp

    43/57

  • 8/10/2019 Ppt Underground Wp

    44/57

  • 8/10/2019 Ppt Underground Wp

    45/57

  • 8/10/2019 Ppt Underground Wp

    46/57

  • 8/10/2019 Ppt Underground Wp

    47/57

  • 8/10/2019 Ppt Underground Wp

    48/57

    Restoration options: venti lation, cementitious orcrystalline

    Lessons learned: peer review and dew pointanalysis could have identified potential issues,add vapor retarder

    Case Study Example Connecticut Beach Foundation

  • 8/10/2019 Ppt Underground Wp

    49/57

    Potential leak sources: pile and matt slab

    foundation, wall to slab transitions Water cut off wall did not function as intended

    Specified system: dual slab Bentonite at blindside,PVC/Bentonite composite on walls and

    Bentonite/HDPE on plaza

    Case Study Example BostonSchool Parking Garage

  • 8/10/2019 Ppt Underground Wp

    50/57

  • 8/10/2019 Ppt Underground Wp

    51/57

  • 8/10/2019 Ppt Underground Wp

    52/57

  • 8/10/2019 Ppt Underground Wp

    53/57

    CMU BLOCK WALLS

  • 8/10/2019 Ppt Underground Wp

    54/57

  • 8/10/2019 Ppt Underground Wp

    55/57

    Restoration options: injection or negative side

    Lessons learned: prepare for worst case andpotential movement, on-site constructionmonitoring required

    Case Study Example BostonSchool Parking Garage

  • 8/10/2019 Ppt Underground Wp

    56/57

    Summary

    Manage Storm and Groundwater

    Code, Tolerance, Risk and Redundancy

    Design Details

    Construction Monitoring

    Negligence

  • 8/10/2019 Ppt Underground Wp

    57/57

    Negligence