ppt underground wp
TRANSCRIPT
-
8/10/2019 Ppt Underground Wp
1/57
Gale Associates, Inc.E n g i n e e r s a n d P l a n n e r s
Waterproofing Below Grade in
High Water Table Conditions
ICRI 2013 Spring Convention
James E. Saizan, AIA and Marc A. Loranger, P.E.
March 20, 2013
-
8/10/2019 Ppt Underground Wp
2/57
Presentation Outline
Type of Structures and Specific Concerns
Approaches to Sub-grade Waterproofing
Design and Product Considerations
Case Study Examples
-
8/10/2019 Ppt Underground Wp
3/57
Hydrostatic pressure weight of water
Storm water
Capil lary action
Sub-grade Structures and Concerns
-
8/10/2019 Ppt Underground Wp
4/57
Foundation walls and footings
Slabs on grade / spli t / mud
Sump / elevator pits
Pile and matt slab foundations
Retaining walls
Tunnels
Parking garages / slurry walls
Occupied below grade spaces
Sub-Grade Structures and Concerns
-
8/10/2019 Ppt Underground Wp
5/57
Code requirements
Tolerance to moisture
Risk of leakage
Redundancy in system
Key Concepts
-
8/10/2019 Ppt Underground Wp
6/57
Control of Ground and Storm Water
Footing drains
Under slab drains
Dewatering during excavation
Pumps and wells
Back up power for pumps
Approach to Sub-Grade
Waterproofing
-
8/10/2019 Ppt Underground Wp
7/57
-
8/10/2019 Ppt Underground Wp
8/57
Positive Side
Bentonite clay
Composite polymers
Reinforced fluid
Sheet membrane
Cementitious
Soil injection
Approach to Sub-Grade
Waterproofing
-
8/10/2019 Ppt Underground Wp
9/57
-
8/10/2019 Ppt Underground Wp
10/57
-
8/10/2019 Ppt Underground Wp
11/57
-
8/10/2019 Ppt Underground Wp
12/57
-
8/10/2019 Ppt Underground Wp
13/57
-
8/10/2019 Ppt Underground Wp
14/57
Negative Side
Crystalline
Metall ic oxide
Cementitious
Injection
Approach to Sub-GradeWaterproofing
-
8/10/2019 Ppt Underground Wp
15/57
Integral Concrete Waterproofing
Secondary / tertiary redundancy
Primary waterproof ing for duct banks
Dams, waterways, containment tanks
.002 crack bridging capabil ity
Approach to Sub-GradeWaterproofing
-
8/10/2019 Ppt Underground Wp
16/57
Joint Water Stops
Hydrophilic
Bulb
Consider joint movement
Retrofit applications
New to existing building transitions
Approach to Sub-Grade
Waterproofing
-
8/10/2019 Ppt Underground Wp
17/57
-
8/10/2019 Ppt Underground Wp
18/57
-
8/10/2019 Ppt Underground Wp
19/57
Code Requirements
MA Building Code (5thedition): 1224.4;Groundwater Investigation
2010 Florida Building Code
IBC/CT Building Code not less than 12 abovethe maximum elevation of the groundwater table
Dampproofing vs. waterproofing
Occupied spaces
Design Considerations
-
8/10/2019 Ppt Underground Wp
20/57
Geotechnical Data
Design groundwater elevation seasonalhighs and lows
Backfill type and acceptabili ty
Soil backfi ll requirements
Controlled compaction requirements
Damage control
Design Considerations
-
8/10/2019 Ppt Underground Wp
21/57
Soil / Water Contamination and Testing
Saltwater
Brackish water / sulfates
Petroleum
Other chemicals (dry cleaning PCE, highalkaline, hard and soft water)
PH testing
Design Considerations
-
8/10/2019 Ppt Underground Wp
22/57
Structural Configuration and Behavior
Active
Passive
System transitions
Design Considerations
-
8/10/2019 Ppt Underground Wp
23/57
Environmental Conditions
Minimum application temperatures
Freezing temperature; surface and ambient
Precipitation
Dust control
Design ConsiderationsDesign Considerations
-
8/10/2019 Ppt Underground Wp
24/57
Surface Preparation
Concrete (honeycombing, form oils, formties and t ie wires, curing compounds, finish
considerations, cold joints) Soil / fills (compaction, correct aggregate
size, free draining, no clay in sub-base)
Forms (soldier pile and lagging, sheet pi ling
joints, tie-backs) Priming requirements
Design Considerations
-
8/10/2019 Ppt Underground Wp
25/57
Construction Sequence
Pits prior to slabs
Footings / mats prior to walls
Membrane laps and transit ions
Open time and exposure subject to damage
Design Considerations
-
8/10/2019 Ppt Underground Wp
26/57
Remedial Techniques
Dril l and pressure injection (high pressure)
Exterior soil injection / curtain walling (lowpressure)
Negative side cementitious and crystalline
Water plugs / patches
Positive side (Extensive)
Design Considerations
-
8/10/2019 Ppt Underground Wp
27/57
Leak sources: slab penetrations andwall/floor joints
Buoyant pressures caused heaving andbuckling during storm related rising watertables
Exist ing system: composite HDPE/Bentoniteon positive/blind side, well point system
Case Study Example FloridaCourthouse Basement
-
8/10/2019 Ppt Underground Wp
28/57
-
8/10/2019 Ppt Underground Wp
29/57
-
8/10/2019 Ppt Underground Wp
30/57
-
8/10/2019 Ppt Underground Wp
31/57
Restoration options: injection, internal trench,
raised floor, eliminate floor penetrations
Lessons learned: design buoyant slab, detailslab penetrations, well-points needed back-up,continuity of waterproofing system
Case Study Example FloridaCourthouse Basement
-
8/10/2019 Ppt Underground Wp
32/57
Leak sources: wall and floor joints,penetrations and openings
Issues: storm impact on rising water table, ageof existing construction and impracticalpositive-side solutions
Existing system: multi-ply membrane withoutsub-surface drainage, urethane foam seals atpenetrations
Case Study Example Electrical
Vault Florida
-
8/10/2019 Ppt Underground Wp
33/57
-
8/10/2019 Ppt Underground Wp
34/57
-
8/10/2019 Ppt Underground Wp
35/57
-
8/10/2019 Ppt Underground Wp
36/57
-
8/10/2019 Ppt Underground Wp
37/57
-
8/10/2019 Ppt Underground Wp
38/57
Restoration options: negative-side crystalline
slurry, seal open penetrations with hydrophilicsealant, manage water intrusion
Lessons Learned: sub-surface drainage, pumpsystem needed as back-up
Case Study Example ElectricalVault Florida
-
8/10/2019 Ppt Underground Wp
39/57
Leak sources: slab and wall condensation
Conditioning and condensate on poorlyinsulated concrete
Specified system: bentonite sheet and dualwaterstop
Case Study Example Connecticut Beach Foundation
-
8/10/2019 Ppt Underground Wp
40/57
-
8/10/2019 Ppt Underground Wp
41/57
-
8/10/2019 Ppt Underground Wp
42/57
-
8/10/2019 Ppt Underground Wp
43/57
-
8/10/2019 Ppt Underground Wp
44/57
-
8/10/2019 Ppt Underground Wp
45/57
-
8/10/2019 Ppt Underground Wp
46/57
-
8/10/2019 Ppt Underground Wp
47/57
-
8/10/2019 Ppt Underground Wp
48/57
Restoration options: venti lation, cementitious orcrystalline
Lessons learned: peer review and dew pointanalysis could have identified potential issues,add vapor retarder
Case Study Example Connecticut Beach Foundation
-
8/10/2019 Ppt Underground Wp
49/57
Potential leak sources: pile and matt slab
foundation, wall to slab transitions Water cut off wall did not function as intended
Specified system: dual slab Bentonite at blindside,PVC/Bentonite composite on walls and
Bentonite/HDPE on plaza
Case Study Example BostonSchool Parking Garage
-
8/10/2019 Ppt Underground Wp
50/57
-
8/10/2019 Ppt Underground Wp
51/57
-
8/10/2019 Ppt Underground Wp
52/57
-
8/10/2019 Ppt Underground Wp
53/57
CMU BLOCK WALLS
-
8/10/2019 Ppt Underground Wp
54/57
-
8/10/2019 Ppt Underground Wp
55/57
Restoration options: injection or negative side
Lessons learned: prepare for worst case andpotential movement, on-site constructionmonitoring required
Case Study Example BostonSchool Parking Garage
-
8/10/2019 Ppt Underground Wp
56/57
Summary
Manage Storm and Groundwater
Code, Tolerance, Risk and Redundancy
Design Details
Construction Monitoring
Negligence
-
8/10/2019 Ppt Underground Wp
57/57
Negligence