National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Pre-Bid Meeting 1 INTRODUCTION AND ORIENTATION
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Introduction
Agenda
1 Introduction & Overview
2 Space Program
3 Schematic Design
4 Special Building Features
2
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Overview
University of the Philippines SystemPremier institution for education and government service
Land Area = 16,000 hectares UP Manila = 14 hectares UP Diliman = 493 hectares UP Los Banos = 15,000 hectares
ManilaHealth Sciences Center Philippine General HospitalNational Institutes of HealthExtension Services
LeyteKoronadalAurora
Los Banos Open University
Diliman Olongapo Pampanga
Baguio Visayas
Cebu Iloilo City Tacloban Miagao
Mindanao
2013 endowment = $238 M
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Overview
Building Project OrganizationUniversity of the Philippine Manila - National Institutes of Health
Special Bids and Awards Committee
(SBAC)
Technical Working Group
(TWG)
Construction Management TeamOn-Site Supervision – Architecture, Engineering, Commissioning Cx
(Public Bidding)
UP Manila National Institutes
of HealthEnd Users
Design and Construction Team for Design-Build Contract
(Public Bidding)
3
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Agenda
1 Introduction & Overview
2 Space Program
3 Schematic Design
4 Special Building Features
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
TotalOffice and
Office SupportShared
AmenitiesLaboratory
BSL-2Laboratory
BSL-3Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Net Assignable Program Area (SM) 17,755 2,499 11,774 2,639 93 451 110 191Area Type as % of Total 14.1% 66.3% 14.9% 0.5% 2.5% 0.6% 1.1%
Building Support 2,189Parking Space 5,508
Mechanical Systems 2,165Horizontal Circulation 4,542
Vertical Circulation 2,227
Estimated Gross Floor Area 34,386
Building Efficiency 51.63% = Net Area/ Gross Area
NIH Space Program - Summary
4
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
NIH Space Program – Shared Amenities
Office and Office
Support
Shared Amenities
Laboratory BSL-2
Laboratory BSL-3
Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Office of the Vice Chancellor for Research (OVCR) 389National Institutes of Health (NIH)
NIH Offices (Administration, RDITC, IT/Server Rooms) 573 191Conference Rooms, Meeting Rooms, Training Rooms 674Technology Business Incubator (TBI) Space 3,845Central Sample Collection 86Mail Room 12Central Storage Room 60Service Pantry 87Fitness Center 117Clinical Trial Center 738Clinical Research Room 117Central Laboratory 116Laboratory Support Areas 425Lobbies/Lounge Areas 1,912Concessions/ Staff Dining Area 549Auditorium 908Speakers' Lounge 84Breakout Rooms 863Executive Dining Hall 147Roof Deck Garden 576
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Office and Office
Support
Shared Amenities
Laboratory BSL-2
Laboratory BSL-3
Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Institute of Molecular Biology and Biotechnology (IMBB) 109 608 93 113 110Institute of Aging (IA) 63Institute of Child Health and Human Development (ICHHD) 81
Institute of Clinical Epidemiology (ICE) 99
Institute of Health Policy and Development Studies (IHPDS) 81Institute of Herbal Medicine (IHM) 91 263 78Institute of Human Genetics (IHG) 576 1,079Institute of Ophthalmology (IO) 153 138Institute of Pharmaceutical Sciences (IPS) 109 275Philippine National Ear Institute (PNEI) 109 162National Telehealth Center (NTHC) 153Newborn Hearing Screening Reference Center (NHSRC) 90Newborn Screening Reference Center (NSRC) 398College of Medicine Vivarium 259
NIH Space Program – Dry and Wet Laboratories
5
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Agenda
1 Introduction & Overview
2 Space Program
3 Schematic Design
4 Special Building Features
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
6
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
7
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
8
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
9
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
10
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
11
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
12
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
13
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
14th FL (13th level) Mechanical Room access space enclosed conditioned for
12th FL
14
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
15
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
16
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Introduction
Agenda
1 Introduction & Overview
2 Schematic Design
3 Space Program
4 Special Building Features
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Vivarium and Biosafety Level 3 – Containment Stack
BSL-3, ABSL 2, ABSL 3 Future Fit-out12 th FLOOR
Mechanical Penthouse with AHU’s for 12th floor accessible bubble type dampers, BAS, HEPA filters,
electrical, plumbing, water14 th FLOOR (13th Level)
Effluent Decontamination and Shell Space/ Future Labs 10 th & 11 th FLOORs
17
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Laboratory Hazards
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Chemical:Flammables, acids, corrosives, reactive chemicals, carcinogens, mutagens, teratogens, toxins, compressed gases
Radiological:Radionuclides and equipment that produces ionizing radiation
Physical:Lasers, magnetic fields, moving parts, high voltage, high noise, ultraviolet light, extreme heat or cold, high pressure vessels
Biological:Etiologic agents, material containing etiologic agents, organisms with recombinant DNA, toxins, allergens
Special Building Features
Laboratory Hazards
18
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Administrative - Public
Clerical - Semi Public
Laboratory - Restricted Access
Lab Support - Restricted Access
NonHazardous
Hazardous
Public &Personnel
SpecimensMail &Deliveries
Receiving & Accessioning
WasteHolding
Processing
SampleStorage
Media PrepSupplies
DisposalControl
Control
Special Building Features
Mixed-Used Building Planned for Safe Circulation
Control
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Dense Urban Site Conditions
West – view of Manila Bay
East – view of LRT and Taft Avenue
North – view of NIH, project site, PGH complex
19
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Dense Urban Site Conditions
Exterior Studies
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Dense Urban Site Conditions
Significant Protected Tree
20
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Dense Urban Site Conditions
Front Left Oblique View
Front – Bird’s Eye View Rear– Bird’s Eye View
Right Side – Bird’s Eye View
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Open Laboratory Concept
100% Laboratory Exhaust Air
Variable Air Volume System
LEED /Labs 21 Energy Saving Strategies
21
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Flexibility
Fume Extraction for Instrument Laboratories
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Flexibility
Equipment Zones with Supplemental Air Units
Sterilizers with Canopy Hoods
Local Gas Storage Rooms with Safety Alarms
22
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Lighting Views and Daylight Lighting Levels Glare Control
Ventilation Temperature Control Air Movement and Ventilation Humidity Control Air Quality
Structure Contamination Control Vibration Isolation Noise Attenuation
Quality of Space Facilitation of Interaction Attracting and Retaining Staff Multidisciplinary Facility Flexible and Adaptable
Special Building Features
Quality Environment
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Quality Environment – Containment Devices
Future Vivarium exhaust hood Future Vivarium downdraft table
23
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Quality Environment – Training Labs and Classrooms
Laboratory exhaust in Training Laboratories
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Temperature & Humidity Control
• Equipment heat locally controlled with dedicated exhaust arms
• Room level temperature and humidity controls
Mock-up of selected laboratory casework materials and furnishings prior to rapid installation schedule.
24
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Airflow design according to ventilation guidelines
Example 1:
Incorrectly Modified Canopy Hood
Example 2:
Air Supply grille too near biosafety cabinet
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Strategies for Flexibility Overhead Utility Carriers and Mobile Tables
Metal casework & epoxy resin benchtopsLaboratory mock-ups are required
25
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Building Utilities – More Power and Data
Shell Laboratories 20 watts/ sq. meter? Reliable power?
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Construction cost savings strategies
26
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Special Building Features
Consider sustainable design goals
• Office space can benefit from natural ventilation; cool air travels in through operable windows and out through the garden space.
• Light shelves reflect light from western exposure.
• PV panels can collect prominent solar radiation, and store it’s energy for later use during blackouts.
Rainwater collection for irrigation and toilet flushing.
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
August 15, 2013
Questions?
Pre-Bid Meeting 2: To be scheduled.
Pre-Bid Meeting 3: To be scheduled.