Analysis and Design of Pre- Engineered
Buildings For Industrial Shed
![Page 2: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/2.jpg)
Submitted By:Shubham V. Parab 1202016Akshay A. Nikam 1202019Sujit H. Sonwalkar 1202015Aniket K. Mane 1202032
Under the guidance of :Prof.P.M.Mohite
![Page 3: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/3.jpg)
ObjectivesTo study pre engineered building.To prepare a model of P.E.B.To analyze structure using Staad Pro.To design sections, connections etc.To study the effect of P.E.B. for following
issues:To reduce complexity on site.To achieve accuracy.Speed of work.
![Page 4: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/4.jpg)
Pre Engineered BuildingSteel buildings in which excess steel is
avoided by Tapering the sections.Tapering is done as per Bending Moment
requirements.Components are manufactured in factory and
assembled on site.Larger plate dimensions are used in areas of
higher load effects.
![Page 5: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/5.jpg)
![Page 6: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/6.jpg)
Plan
![Page 7: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/7.jpg)
Elevation
![Page 8: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/8.jpg)
![Page 9: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/9.jpg)
Problem statementInternal dimensions of building: l=60 m, b=15
mHeight of building up to eaves level= 6 mLocation of building= Islampur (pune region)Type of roofing = G.I.sheetsArea of opening (permeability of building 5% to
20%)Angle of rafter = < 100
Spacing between two columns = 6 mNumber of frames = 10
![Page 10: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/10.jpg)
Load calculationDead load:1. Wight of purlin :5 kg/m2
2. Weight of sheeting :5 kg/m2
Total weight :10 kg/m2=0.1kN/m2
3. Self weight of tapered section
![Page 11: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/11.jpg)
Live loadLive load =0.75 kN/m2 (Angle lesthan 10
0) = 0.75*6
Live load =4.5 kN/m2
Collateral load:Collateral load = 0.2* 6 =1.2 KN/M
(Assumed)
![Page 12: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/12.jpg)
Wind load
![Page 13: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/13.jpg)
Load cominationLoad combination of strength:(D.L.+L.L.)*1.5+1.05 *C.L.(D.L.+W.L.S.)*1.5(D.L.+W.R.P.)*1.5(D.L.+W.R.S.)*1.5(D.L.+W.P.P.)*1.5(D.L.+W.P.S.)*1.5(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.L.P.(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.L.S.(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.R.P.(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.R.S.(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.P.P.(D.L.+L.L.)*1.2+1.05*C.L.+0.6* W.P.S.
![Page 14: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/14.jpg)
Load combination of serviceability: (D.L.+L.L.+C.L.)*1D.L.* 1+(L.L.+C.L+W.L.P.)*0.8D.L.* 1+(L.L.+C.L+W.L.S.)*0.8D.L.* 1+(L.L.+C.L+W.R.P.)*0.8D.L.* 1+(L.L.+C.L+W.R.S.)*0.8D.L.* 1+(L.L.+C.L+W.P.P.)*0.8D.L.* 1+(L.L.+C.L+W.P.S.)*0.8 (D.L.+W.L.P.)*1 (D.L.+W.L.S.)*1 (D.L.+W.R.P.)*1 (D.L.+W.R.S.)*1 (D.L.+W.P.P.)*1 (D.L.+W.P.S.)*1
![Page 15: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/15.jpg)
B.M.D.
CONVENTIONAL BUILDING
PRE ENGINEERED BUILDING
![Page 16: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/16.jpg)
![Page 17: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/17.jpg)
![Page 18: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/18.jpg)
![Page 19: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/19.jpg)
![Page 20: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/20.jpg)
Results Sl. No. Description PEB
CSB1 Steel Take Off (kN) 12.194 84.5952 Support Reaction (kN) 10.62 375.5823 Maximum deflection (mm) 39.48 8.6114 Maximum Shear Force (kN) 66.894 453.9815 Maximum Moment (kNm) 175.52 908.577
![Page 21: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/21.jpg)
AdvantagesPEB System is zero maintenance & superior
in strength than conventional.Lower Cost.Quality Control.Large Clear Spans.strict quality control environment, thereby
ensuring superior quality & finish.Easier to incorporate future expansions
![Page 22: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/22.jpg)
DisadvantagesNot used for multi-storey building.Technical person is required on site.Special Machinery is required.Design of member takes more time.
![Page 23: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/23.jpg)
ConclusionUsing of PEB instead of CSB may be reducing
the steel quantity.Reduction in the steel quantity definitely
reducing the dead load.Reduction in the dead load reducing the size
of Foundation.Using of PEB increase the Aesthetic view of
structure.
![Page 24: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/24.jpg)
ApplicationsWARE HOUSESINDUSTRIAL SHEDSFACTORIESWORKSHOPSOFFICESGAS STATIONSVEHICLE PARKING SHEDSSHOW ROOMSAIRCRAFT HANGERSSCHOOLSSPORTS AND RECREATIONAL FACILITIES
![Page 25: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/25.jpg)
Erecting P.E.B.
![Page 26: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/26.jpg)
![Page 27: Pre engineered building ppt rit](https://reader033.vdocuments.net/reader033/viewer/2022061610/587877b81a28ab497b8b78b7/html5/thumbnails/27.jpg)
Reference Limit State Design in Structural Steel- M. Y .
Shiyekar.Pre-Engineered metal Buildings the latest trend
in building construction‖ by K.K.Mitra – Gen. Manager (marketing) Lloyd Insulations (India) Limited
IS : 800 - 2007 :- General Construction In Steel - Code of Practice.
IS : 875 (Part 1) - 1987 :- Code of Practice for Design Loads (Other Than Earthquake) for Buildings
IS : 875 (Part 2) - 1987 :- Code of Practice for Design Loads (Other Than Earthquake) for Buildings and Structures- Live Loads.
IS : 875 (Part 3) - 1987 :- Code of Practice for Design Loads (Other Than Earthquake) for Buildings and Structures- Wind Loads.