pre-feasibility report 190319environmentclearance.nic.in/writereaddata/online/tor/19...9 ep/filter...
TRANSCRIPT
-
1
PRE-FEASIBILITY REPORT
for
PROPOSED EXPANSION OF SILICA SAND PROCESSING PLANT
(GLASS GRADE), NEW FLOAT GLASS LINE 2 (INTERLINKED
PROJECT)
&
LPG STORAGE CAPACITY ENHANCEMENT FOR GLASS
MANUFACTURING UNIT of
M/s. GUJARAT GUARDIAN LIMITED
VILLAGE: KONDH, VALIA ROAD,
TAL: ANKLESHWAR - 393001, DIST: BHARUCH (GUJ.)
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
Prepared By:
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
Prepared By:
-
2
CONTENTS
Sr.
No.
Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 13
3. Project Description 14
4. Site Analysis 24
5. Planning Brief 37
6. Proposed Infrastructure 41
7. Rehabilitation and resettlement (R & R) Plan 42
8. Project Schedule & Cost Estimates 42
9. Analysis of Proposal (Final Recommendations) 43
-
3
1.0 EXECUTIVE SUMMARY
1.1 Company Profile
M/s. Gujarat Guardian Limited proposes expansion of Silica Sand production (Glass Grade), LPG
Storage capacity and the interlinked development of a second Float Glass Line (FL2) in Existing Glass
Manufacturing Unit at Village: Kondh, Valia Road, Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.). Total
Cost of the Project is Rs. 2184 Crores (Existing Operations: 584 Crores + Additional Proposed Operations: 1600
{New sand plant and LPG Storage enhancement: 86 + Float line 2 (interlinked project): 1514 Crores}. Total
Plant Area is 6,55,990.4 m2
.
1.2 Project Details
1.2.1 Products along with Production Capacity
Sr.
No.
Name of Unit Name of
Product
Existing
Capacity
Additional
Proposed
Capacity
Total
Proposed
Capacity
Remarks
1 Glass
Manufacturing
Unit
Float Glass
Mirror,
Lacquered
Glass,
Coater Glass
2,50,00,000
m2/Annum
4,00,00,000
m2/Annum
6,50,00,000
m2/Annum
-
2 Silica & Sand
Production
Unit
Silica Sand
(Glass Grade) &
By-Products
(Coarse, Fines
& Rejects)
33,120
MT/Month
53,380
MT/Month
86,500
MT/Month
-
3 LPG Storage - 225 MT
(4 x 56.25
MT of Length
= 16.2 m &
Diameter =
3200 mm)
495 MT 720 MT
(6 x 120 MT of
Design Pressure
= 21 Kg/cm2,
Overall Length =
24000 mm,
Tank ID = 4010
mm, Tank Shell
= 28 mm Thick,
Dished End= 18
mm Thick)
The Existing and LPG
Storage Yard will be
relocated to new
location with total
increased capacity
of 720 MT.
-
4
1.2.2 Raw Material Requirement
Sr.
No. Raw Material
Consumption Quantity Per Month
UOM Permitted Proposed
Additions Total
Float Glass
1 Sand MT 14,000 21,315 35,315
2 Soda Ash MT 4,500 6,900 11,400
3 Dolomite MT 3,800 5,790 9,590
4 Limestone MT 1,400 2,160 3,560
5 Feldspar MT 850 1,300 2,150
6 Salt Cake MT 215 330 545
7 Carbon MT 21 32 53
8 Cullet MT 6,000 8,500 14,500
9 EP/Filter Dust MT 0 300 300
Wet Coater
1 Raw Glass Sq. Meter 5,83,000 - 5,83,000
2 Washing & Polishing Chemicals Kg 2,062 - 2,062
3 Tin Sensitizer Litre 119 - 119
4 Palladium Sensitizer Litre 45 - 45
5 Silver Solution
Silver Nitrate
Litre
Kg
2,600
1,088
- 2,600
1,088
6 Reducer/
Silver less solution
Litre
Litre
4,830
2,920
- 4,830
2,920
7 GMPA & GMPB Litre 1,190 - 1,190
8 Paint MT 68 - 68
9 Ortho-Xylene Litre 9,971 - 9,971
10 HCL-32% Litre 11,393 - 11,393
11 Caustic-32% Litre 13,508 - 13,508
12 Ferric Sulfate Kg 256 - 256
13 Copper Sulphate Pentahydrate Kg 1,440 - 1,440
14 Potassium Sodium Tartrate Kg 20 - 20
15 Iron Powder Kg 50 - 50
16 Sulphuric Acid Kg 230 - 230
Lacquered Glass
1 Raw Glass Sq. Meter 1,50,000 - 1,50,000
2 Washing and polishing chemical Kg 200 - 200
3 Adhesion Promoter Litre 50 - 50
4 Paint MT 10 - 10
A GLASSOLUX NG 9003 PURE WHITE Kg 2,500 - 2,500
B GLASSOLUX NG 2105 Sapphire Kg 2,500 - 2,500
C GLASSOLUX NG 3004 Burgundy Kg 2,500 - 2,500
D GLASSOLUX NG 6113 Fluo green Kg 2,500 - 2,500
E GLASSOLUX NG 9005 Black Kg 2,500 - 2,500
F Ivory Kg 2,500 - 2,500
G Red Kg 2,500 - 2,500
5 Ortho-Xylene Litre 1,000 - 1,000
-
5
Sr.
No. Raw Material
Consumption Quantity Per Month
UOM Permitted Proposed
Additions Total
Sand Beneficiation Plant
1 Raw Silica Sand MT 33,120 53,380 86,500
Coater Glass
1 Raw Glass Sq Meter 5,83,333 - 5,83,333
2 Washing and polishing chemical Kg 2,000 - 2,000
3 Zr Kg 20 - 20
4 Si – 8 wt % Al Kg 300 - 300
5 Nb – 10 wt % Zr Kg 140 - 140
6 Ni – 20 wt % Cr Kg 180 - 180
7 Ag Kg 100 - 100
8 TiOx Kg 5 - 5
9 Sn Kg 80 - 80
10 Zn – 2 wt % Al Kg 20 - 20
11 Ar m3 800 - 800
12 O2 m3 100 - 100
13 N2 m3 500 - 500
14 Vacuum Pump Oil Litre 400 - 400
15 Sand Blasting Material MT 5 - 5
Emission Control System
1 Aqueous Ammonia MT 350 350
2 Hydrated Lime MT 85 85
1.3 Water Requirement, Waste Water Generation and Treatment
Total water requirement will be 2725 KL/Day (Fresh 2075 KL/Day + Recycled 650 KL/Day) (Existing 1920
KL/Day + Additional Proposed 805 KL/Day) which will be met through Valia Water Supply System (Tapi
River Canal Water). Total wastewater generation will be 1400 KL/Day (Existing – 980 KL/Day +
Additional Proposed – 420 KL/Day).
410 (320+90) KL/day of domestic wastewater will be treated in STP: 90 KL/Day will be reused for
gardening and 320 KL/Day will be stored in soak pit or septic tank. Proposed waste water recycling
plant capacity (FL 1: 500 KLD, FL 2: 200 KLD). Total ETP or waste water recycling capacity: 700 KLD and
out of that 650 KLD will be recycled. Ultimately it is a Zero Liquid Discharge Unit and after proposed
expansion it will remain so.
-
6
1.4 Air Pollution Source and Control Management
FLUE GAS DETAILS
Sr.
No.
Sources of
Emission
Type of
Fuel
Existing Additional Total Proposed
Stack
height
APCM
1. Melting
Furnace
(Existing)
Natural
Gas
5990
m3/Hr.
-- 5990
m3/Hr.
91 m Low NOx Burner.
Low Sulphur
fuel. LPG
3.89
MT/Hr.
-- 3.89
MT/Hr.
2 Melting
Furnace
(Proposed)
Natural
Gas
-- 9985
m3/Hr.
9985
m3/Hr.
54 m Low NOx burner
and low Sulphur
fuel. In addition,
an Emission
Control System
(ECS) may be
installed if
needed to meet
SO2 and NOX
emission limits
or, alternatively,
for other
reasons even if
not required to
meet limits. If
installed, the
ECS would
consist of a
scrubber,
electrostatic
precipitator (EP),
and selective
catalytic
reduction
system or,
alternatively, a
catalyst
impregnated
ceramic filter.
LPG
-- 6.21
MT/Hr
6.21 MT/Hr
3. DG Set (2
Nos of 2.5
MW)
Diesel 1200
Lit/Hr.
- 1200
Lit/Hr.
30 m NA
4. DG Set (3
Nos of 2.1
MW)
Diesel - 1800
Lit/Hr.
1800
Lit/Hr.
30 m NA
5. DG Set (1
No. of 500
KVA)
Diesel 135 Lit./Hr. - 135 Lit./Hr. 14 m NA
6. DG Set (1
No. of 500
KVA)
Diesel - 135
Lit./Hr.
135 Lit./Hr. 14 m NA
-
7
7. LPG Hot
water
generator
(2 Nos)
LPG 0.11
MT/Hr.
- 0.11
MT/Hr.
12 m NA
8. LPG Hot
water
generator
(2 Nos)
LPG - 0.19
MT/Hr.
0.19
MT/Hr.
12 m NA
9. Diesel
Engines (1
and 2 of
155 KVA
each)
Diesel 90 Lit./Hr.
(Total for
both)
- 90 Lit./Hr.
(Total for
both)
12 m
(Existing)
NA
10. Diesel
Engines (3
and 4 of
155 KVA
each)
Diesel 90 Lit./Hr.
(Total for
both)
- 90 Lit./Hr.
(Total for
both)
11 m
(Existing)
NA
11. Diesel
Engine, (4
nos. for)
(open loop
(1),
emergency
water
system (1)
fire system
(2))
Diesel 180 Lit./Hr. - 180 Lit./Hr. 12 m
(Proposed
)
NA
12. Open loop
and
Emergency
engines
(FL2)
Diesel - 90 Lit./Hr. 90 Lit./Hr. 12 m NA
13. Glass Edge
Burner
(Existing)
Natural
Gas
10 m3/Hr. -- 10 m
3/Hr. 16 m NA
14 Glass Edge
Burner
(Proposed)
- 15 m3/Hr. 15 m
3/Hr. 16 m NA
15 Steam
Methane
Reforming
for
Hydrogen
Generation
Natural
Gas
- 150 m3/hr 150 m3/hr 16 m Some amount of
Natural Gas
would be used
for generation of
Hydrogen
through Steam
Methane
Reform process
-
8
Flue Gas Emission Parameters and Limits as per Approved CCA: Existing Operations (Float Line 1)
Sr. No. Stack attached to Parameter Applicable standards
1 Melting Furnace (Float 1) Particulate matter 0.8 Kg/MT of Product
drawn
TF 5.0 mg/NM3
2 Diesel Engine 2.5 M (2
Nosfor Float 1)
Particulate Matter 75 mg/NM3
NOx (as NO2) (at 15% O2), dry basis, in ppmv 1100
NMHC (as C) (at 15% O2), mg/NM3 150
CO (at 15% O2), mg/NM3 150
3 Diesel Engine 500 KVA
(Float 1)
Particulate Matter 0.2 g/KW-hr
NOx + HC 4.0 g/KW-hr
CO 3.5 g/KW-hr
4 LPG Hot Water Generator
Exhaust (Existing 2 nos for
Float 1)
Particulate Matter 150 mg/NM3
SO2 100 PPM
NOx 50 PPM
5 Diesel Engine, (1,2.3,4for
Float 1)
Particulate Matter 0.2 g/KW-hr
NOx + HC 4.0 g/KW-hr
CO 3.5 g/KW-hr
6 Glass Edge Burner
(Float 1)
Particulate Matter 150 mg/NM3
SO2 100 PPM
NOx 50 PPM
Flue gas Emission parameters and Limits as per “The Environment Protection Act & Rules 1986”: For Proposed
(Float Line 2)
Sr. No. Stack attached to Parameter Applicable standards
1 Melting Furnace (Float 2) Particulate matter 0.8 Kg/MT of Product drawn
SO2 500 mg/NM3
NOx 1000 mg/NM3
TF 5.0 mg/NM3
2 Diesel Engine 2.1 M (3
Nosfor Float 2)
Particulate Matter 75 mg/NM3
NOx (as NO2) (at 15% O2), dry basis, in ppmv 1100
NMHC (as C) (at 15% O2), mg/NM3 150
CO (at 15% O2), mg/NM3 150
3 Diesel Engine 500 KVA
(Float 2)
Particulate Matter 0.2 g/KW-hr
NOx + HC 4.0 g/KW-hr
CO 3.5 g/KW-hr
4 LPG Hot Water Generator
Exhaust (Proposed 2 nos
for Float 2)
Particulate Matter 150 mg/NM3
SO2 100 PPM
NOx 50 PPM
5 Diesel Engine, (5 & 6for
Float 2)
Particulate Matter 0.2 g/KW-hr
NOx + HC 4.0 g/KW-hr
CO 3.5 g/KW-hr
6 Glass Edge Burner
(Float 2)
Particulate Matter 150 mg/NM3
SO2 100 PPM
NOx 50 PPM
7 Hydrogen Generation Plant Particulate Matter Not defined in regulations
-
9
(Float 1 & 2) SO2 Not defined in regulations
NOx Not defined in regulations
DETAILS OF PROCESS VENTS
Sr.
No.
Stack attached to Existing
number
of
stacks
Proposed
number
of stacks
Total
Stacks
Stack height
in Meters
for
proposed
stack
Pollutant
Emitted
APCM
1. Ammonia Cracking
Plant
1 - 1 21 PM,
Ammonia
Stack,
Nitrogen
Purging
2. Hydrogen
Generation Plant
- 1 1 16 PM, SO2,
NOx
Stack
3. Mirror Line Plant 7 8 15 12 Ammonia,
VOC
Stack
4. SO2 Vent (Float 1) 1 - 1 17 SO2 Stack
5. SO2 Vent (Float 2) - 1 1 17 SO2 Stack
6. Batch House Raw
Materials DCF Vents
(Float 1)
9 - 9 36 PM Dust Collector
7. Batch House Raw
Materials DCF Vents
(Float 2)
- 9 9 16 PM Dust Collector
8. Batch House Raw
Materials DCF Vents
at Basement (Float
1)
2 - 2 9 PM Dust Collector
9. Batch House Raw
Materials DCF Vents
at Basement (Float
2)
- 2 2 16 PM Dust Collector
10. Batch House
Unloading DCF Vent
(Float 1)
1 - 1 9 PM Dust Collector
11. Batch House
Unloading DCF Vent
(Float 2)
- 1 1 16 PM Dust Collector
12. Cullet Return
System DCF Vent
(Float 1)
1 - 1 9 PM Dust Collector
13. Cullet Return
System DCF Vent
(Float 2)
- 2 2 16 PM Dust Collector
14. Hot Air Exhaust
(Float 1)
5 - 5 16 PM Not Required
15. Hot Air Exhaust
(Float 2)
- 5 5 16 PM Not Required
16. Dust collector of
cullet sorting
1 - 1 16 PM Dust Collector
17. Dust Collectors for - 2 2 16 PM Dust Collector
-
10
Cullet Transport
18. Dust collector of
tunnels
- - 3 16 PM Dust Collector
19. Coater tempering
furnace stack
1 - 0 - - -
20. Dust collector of
Coater sand blasting
1 - 1 15 PM Dust collector
21. Dust collector of
hydrated lime
storage (Float 2)
1 1 18 PM Dust collector
22. Dust collector of
EP/Filter dust
storage (Float 2)
1 1 16 PM Dust collector
1.5 Hazardous Waste Generation and Disposal
Sr.
No.
Items Category
as per HW
Rules
Existing Additional
Proposed
Total Treatment and Disposal
Method
1 Used Oil 5.1 25 KL/Year 25
KL/ Year
50
KL/ Year
Collection, Storage,
transportation, Sending
to Registered Refiners
for recycle / reuse /
Incineration
2 Waste residue containing oil 5.2 20
MT/ Year
20
MT/ Year
40
MT/ Year
Collection, Storage,
transportation, Send to
GPCB registered TSDF
for land Filling or
Incineration
3 Process wastes, residues &
debris from production
and/or industrial use of
paints, pigments, lacquers,
varnishes, plastics and inks
21.1 20
MT/ Year
- 20
MT/ Year
Collection, Storage,
transportation, Send to
licensed disposal
company
Recycle as a fuel or
Incineration
4 Spent solvents from the
production and/or industrial
use of solvents
20.2 5 MT/ Year - 5 MT/ Year Collection, Storage,
transportation, Send to
licensed disposal
company
Recycle as a fuel or
Incineration
5 Discarded Containers &
barrels contaminated with
hazardous wastes/chemicals
33.1
240
MT/ Year
- 240
MT/ Year
Collection, Storage,
transportation, Disposal
by selling to Registered
Vendors for recycle/
reuse
6 Discarded Bags / Liners
contaminated with
hazardous wastes/chemicals
7 Furnace/reactor residue and
debris
1.1 60
MT/ Year
90
MT/ Year
150
MT/ Year
Collection, Storage,
transportation, Disposal
by landfill at authorized
TSDF
-
11
8 Inorganic Tin compounds B 17 1
MT/ Year
1.5
MT/ Year
2.5
MT/ Year
Collection, Storage,
transportation, Send to
licensed disposal
company for Recycling /
landfill
9 Spent catalyst and molecular
sieves
1.6 4
MT/ Year
- 4
MT/ Year
Collection, Storage,
transportation, Send to
licensed disposal
company for Recycling /
landfill
10 Spent ion exchange resin
containing toxic metal
(upcoming 1200 KL Ro resin
to be added
35.2 15
MT/ Year
- 15
MT/ Year
Collection, Storage,
transportation, Disposal
by landfill at authorized
TSDF or recycle
11 Chemical sludge from waste
water treatment
35.3 5
MT/ Year
695
MT/ Year
700
MT/ Year
Collection, Storage,
transportation, Disposal
by landfill at authorized
TSDF
12 Coater Sand Blasting Debris Z32 75
MT/ Year
- 75
MT/ Year
Collection, Storage,
transportation, Disposal
by landfill at authorized
TSDF
Solid (Non-Hazardous) Wastes
Sr.
No
Waste Type Existing Proposed
Additions
Total Disposal Method
1. Mirror and Lacquered
Cullet
100
MT/Month
- 100 MT/Month Collection, Storage,
transportation, Sell as
non-hazardous waste
for recycling / reuse
2. Bad Batch 100
MT/Month
150 MT/Month 250 MT/Month Collection, Storage,
transportation,
Recycling/reuse /Landfill
3. G-Core 100 KG/Month 150 KG/Month 250 MT/Month Collection, Storage,
transportation, Reuse
in-house for water
neutralization / landfill /
recycling / reuse
4. Rejected Sand 2200
MT/Month
3500 MT/Month 5700 MT/Month Collection, Storage,
transportation,
Recycling in house /
selling to water
treatment plant and
construction industry /
Landfill
5. Lagoon reclaim waste 9200
MT/Month
5800 MT/Month 15000
MT/Month
Collection, Storage,
transportation,
Recycling in house by
having sales to various
end users like foundries,
-
12
resin coated sand
manufacturers, ceramics
and tiles manufacturers,
filter bed
manufacturers,
construction industry etc
/ and /or at construction
Landfill
6. Cullet 2500 MT/
month
4000 MT/Month 6500 MT/Month Collection, Storage,
transportation,
Recycling in house / Sell
to recyclers
7. Sludge Generation
from STP
1 MT/Month 1 MT/Month 2 MT/Month Collection, Storage,
transportation, Using as
manure in-house
8. Furnace refractory
waste, Wool, Mud,
Cement etc.
10 MT/Month 20 MT/Month 30 MT/Month Collection, Storage,
transportation, Sent for
Construction site land
filling/recycle/reuse
9. Cullet Dust 40 MT/Month 60 MT/Month 100 MT/Month Collection, Storage,
transportation, Sent for
Construction site land
filling/recycle/reuse
10. E-waste 250 KG /
Month
400 KG / Month 650 KG / Month Collection, Storage,
transportation, Sold to
GPCB approved recycler
11. Trash and Packaging
material waste
20 MT/Month 30 MT/Month 50 MT/Month Collection, Storage,
transportation, Sold to
scrap vendor
12. Metal Scrap 10 MT/Month 25 MT/Month 35 MT/Month Collection, Storage,
transportation, Sold to
scrap vendor
13. Solid waste from flue
gas treatment (EP or
Filter Dust)
- 300 MT/Month 300 MT/Month Collection, Storage,
transportation, Reused
as a raw material
1.6 Green Belt
Total plant area is 6,55,990.4 m2. The proposed expansion will be done within the existing plant
premises, except that we are exploring possibility of buying (not yet finalized) a small tract of land for
parking of vehicles near the existing premises. Out of the total plant area, 1,18,040 m2 (17.99%) land
shall be developed as Green Belt/ Plantation. Total Colony Area is 3,74,456.4 m2 out of which 3,12,047
-
13
m2 (83.33%) is the existing green belt. Total Plant + Colony Area is 10,30,446.8 m
2 out of which
4,30,087 m2 (41.74%) will be green belt.
1.7 Power & Fuel Requirements
TOTAL POWER REQUIREMENT & SOURCE OF POWER
Power requirement (New sand plant + Float line 2 + Existing operation) will be 14.7 MW (Existing = 8.7
MW + Additional Proposed = 6 MW) which will be taken from GEB.
4 Nos. of (155 KVA each) and 2 Nos. of (2.5 MW each), 2 Nos. of (500 KVA) & 3 Nos. of (2.1 MW each).
DG Sets will be kept for emergency power back up.
Company also has 34 wind mills installed at Dwarka (Gujarat).
FUEL REQUIREMENT
Sr.
No.
Fuel Quantity Remark
Existing Additional Total Proposed
1 Natural Gas 6000 m3/hr 10150 m3/hr 16150 m3/hr Some amount of Natural
Gas would be used for
generation of Hydrogen
through Steam Methane
Reform process
2 LPG 4 MT/hr 6.4 MT/hr 10.4 MT/hr
3 Diesel 1515 Ltrs /Hr 2025 Ltrs/Hr 3540 Ltrs /Hr
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a copy of mining
lease/letter of intent should be given.
Identification of the project
M/s. Gujarat Guardian Limited proposes relocation and expansion of Silica Sand production (Glass
Grade) and LPG Storage capacity and development of interlinked Float Glass Line (FL2) in Existing Glass
Manufacturing Unit at Village: Kondh, Valia Road, Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.).
Identification of the project proponent
Sr. No. Name of the Director Designation
1 Mr. Vinay Kumar Modi Chairman
-
14
2 Mr. Kevin William Baird Director
3 Mr. Alok K. Modi Joint Managing Director
4 Mr. A. M. Surana Finance Director
5 Mr. P. K. Gera, IAS Nominee Director
6 Mr. Arun Kumar Solanki, IAS Additional Director
7 Mr. Vincent Pringiers Director
8 Mr. Thomas V Jacobs Director
9 Mr. Merritt Edward Gaunt Director
10 Ms. Melanie Adele Henry Director
2.2 Brief description of nature of the Project
Proposed relocation and expansion of Silica Sand production (Glass Grade) and LPG Storage capacity
and development of interlinked Float Glass Line (FL2) in Existing Glass Manufacturing Unit
2.3 Need for the project and its importance to the country and/or region
The demand for products intended to be manufactured by the interlinked FL2 is increasing in the
country, by expanding float glass manufacturing capacity, M/s Gujarat Guardian Limited will be able to
meet the demand of the product locally and/or Internationally. This will also generate direct and
indirect employment opportunity for various levels of people.
2.4 Demands-Supply Gap
Based on our informal survey of the market with our current customers and various traders, we have
found that there is a big potential for the range of the products we are planning.
2.5 Imports vs. Indigenous production
Shall be envisaged.
Gujarat Guardian Limited may import glass from other guardian facility based on the needs.
2.6 Export possibility
Shall be envisaged.
Export of all category of glass would be done based on commercial viability.
2.7 Domestic/Export Markets
Major portion of the product will be used for domestic market and some portion of the product may
be exported depending on the international market.
2.8 Employment Generation (Direct and Indirect) due to project.
M/s Gujarat Guardian Limited will give direct employment to local people based on qualification and
requirement. In addition to direct employment, indirect employment shall generate ancillary business
to some extent for the local population.
3.0 Project Description
-
15
3.1 Type of Project including interlinked and interdependent projects, if any.
Proposed expansion of Silica Sand production (Glass Grade) and LPG Storage capacity and
development of interlinked Float Glass Line (FL2) in Existing Glass Manufacturing Unit. Expansion of
silica sand production is Category 2(b). Expansion of LPG storage capacity is Category 6(b).
-
16
3.2 Location (map showing general location, specific location and project boundary & project site
layout) with coordinates.
Map showing general location
Project
Site
-
17
Project Site (Google Map)
-
18
LOCATION OF THE PROJECT SITE (10 KM RADIUS)
-
19
Plot Layout
Existing LPG
Storage Area
Proposed
LPG Area
Float Line-1
New Sand Plant Area
Float Line-2
-
20
LPG STORAGE LAYOUT (EXISTING)
-
21
LPG STORAGE LAYOUT (PROPOSED)
-
22
3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the
environmental considerations gone into should be highlighted.
It is expansion within existing premises. No alternate site is considered.
Major factors involved in the selection of site are listed below:
• Minor site clearance activities shall be carried out to clear shrubs and weed.
• The project site is located on level ground, which does not require any major land filling for area
grading work.
• Proximity to raw material suppliers.
• Site is very well connected by road.
• Availability of power, water, etc.
Modern infrastructure support and amenities at par in other global markets, including:
� Efficient transport facilities.
� Environment-friendly zone as we are away from Ankleshwar industrial area.
� Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Section-1.2.1, Page No. 3.
3.5 Project Description with process details (a schematic diagram/flow chart showing the project
layout, components of the project, etc. should be given)
Please refer Form-I, Annexure-III.
3.6 Raw Material required along with estimated quantity, likely source, marketing area of final
product/s, mode of transport of raw material and Finished product.
For raw material required along with quantity; Please refer Section-1.2, Page No. 4 through 5.
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly
outlined.
It is a Zero Liquid Discharge Unit. Total wastewater generation will be 1400 KL/Day (Existing – 980
KL/Day + Additional Proposed – 420 KL/Day).
410 (320+90) KL/day of domestic wastewater will be treated in STP and 90 KL/Day will be reused for
gardening & 320 KL/Day stored in soak pit or septic tank. Proposed waste water recycling plant
-
23
capacity (Float plant 1: 500 KLD, Float Plant 2: 200 KLD). Total ETP (Effluent Treatment Plant) or waste
water recycling capacity: 700 KLD and out of that 650 KLD will be recycled. Ultimately it is a Zero Liquid
Discharge Unit and after proposed expansion it will remain ZLD.
3.8 Availability of water its source, energy/power requirement and source should be given.
Water Source
Total water requirement is met through Valia Water Supply System (Tapi River canal water). The
system has enough capacity to meet the increased need.
Power & Fuel Requirement
Power requirement (New sand plant+ Float line 2 + Existing operation) will be 14.7 MW (Existing = 8.7
MW + Additional Proposed = 6 MW) which will be taken from GEB. 4 Nos. of (155 KVA each) & 2 Nos.
of (2.5 MW each), 2 Nos. of (500 KVA) and 3 Nos. of (2.1 MW each). DG Sets will be kept for emergency
power back up.
FUEL REQUIREMENT
Sr.
No.
Fuel Quantity
Existing Additional (New
sand plant +
Float line 2)
Total Proposed
(Existing operations +
New sand plant +
Float line 2)
Remark
1 Natural
Gas
6000 m3/hr 10150 m3/hr 16150 m3/hr Some amount of
Natural Gas would be
used for generation of
Hydrogen through
Steam Methane
Reform process
2 LPG 4 MT/hr 6.4 MT/hr 10.4 MT/hr
3 Diesel 1515 Ltrs
/Hr
2025 Ltrs/Hr 3540 Ltrs /Hr
-
24
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Kindly refer the Annexure V & VI of Form 1.
3.10 Schematic representations of the feasibility drawing which give information of EIA purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT
MARKET ASSESSMENT
FINANCIAL REPORT
PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE
LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS
& BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH
LOCALS
BASELINE
ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE
CENTRAL GROUND WATER BOARD
GUJARAT POLLUTION CONTROL BOARD (GPCB)
PUBLIC HEALTH ENGINEERING DEPT.
AGRICULTURE DEPARTMENT
FOREST DEPARTMENT
IRRIGATION DEPARTMENT
EMPLOYMENT EXCHANGE
HEALTH CENTER
CENSUS DEPT.
INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC
STATUS &
INFRASTRUCTURE
PROPOSED
PLANT
FACILITY DESCRIPTION
IMPACTS
METHODOLOGY OF
IMPACT
ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS
EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF
E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL
MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR
POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT,
GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS
STUDIES &
DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY
DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
-
25
4.0 Site Analysis
4.1 Connectivity
Site is very well connected by road and rail
4.2 Land Form, Land Use and Land Ownership
1) Total Plant Area = 6,55,990.4 m2
Green Belt = 98,436 m2
(Existing)
= 1,18,040 m2 (Total Proposed) (17.99%)
2) Total colony area = 3,74,456.4 m2
Green Belt = 3,12,047 m2
(Existing) (88.33%)
2) Grand Total area (Plant + Colony) = 10,30,446.8 m2
Grand Total Green Belt (Plant + Colony) = 4,30,087 m2
(41.74%)
Sr. No. Land Use Proposed Plant
Area (m2)
1 Production Plants 113311.10
2 Parking 16187.30
3 Security Building 404.6825
4 Utility + Tank 40468.25
5 Tank Farm Area
6 Raw Material and Finished Products Storage 250443.31
7 Gas Tonner Storage 40468.25
8 Green Belt 118040.00
9 Road 76667.51
Total 655990.40
The land is owned by Gujarat Industrial Development Corporation and leased to Gujarat Guardian
Limited for 99 years.
-
26
4.3 Topography (along with map)
TOPOSHEET
-
27
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under
CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park,
wild life sanctuary, eco sensitive areas, water bodies (distance from HFL of the river), CRZ. In case of
the notified industrial area, a copy of the Gazette notification should be given.
AREAS UNDER DIFFERENT LAND USE
Courtesy: Data Purchased from Environmental Information Centre, New Delhi
SR.
NO.
LANDUSE
CLASSIFICATION
AREA WITHIN 10 KM
OF PROJECT LOCATION
(SQ.KM.)
PERCENTAGE OF
TOTAL AREA
1 Agriculture 80.32 25.56
2 Fallow Land 135.48 43.11
3 Habitation, Settlement 31.34 9.97
4 Marshy Land 0.20 0.06
5 Miscellaneous Land 28.44 9.05
6 Degraded Vegetation 1.98 0.63
7 Water 2.36 0.75
8 Open & Barren Land 33.37 10.62
9 River 0.74 0.24
Total 314.23 100.00
-
28
LAND USE / LAND COVER WITH VILLAGE LOCATIONS
4.5 Existing Infrastructure
Existing Infrastructures facilities are listed below:
Site is very well connected by road and rail.
The Valia Water Supply System delivers Tapi River canal water to the facility.
We have taken dedicated two power supply lines from DGVCL (Dakshin Gujarat Vidut Company
Limited).
-
29
4.6 Soil Classification
SOIL CHARACTERISTICS UNDER PROJECT AREA
Mapp
ing
Categ
ory
Area
in (Sq
km) Description
Taxonom
y1
Taxonom
y2
Class Subclas
s
Soil
Unit
(Orde
r)
Physiog
raphy Depth Erosion
Draina
ge
Surface
Textur
e pH
Salinity/
Alkalinity
Calca
reous
ness Fertility
B 54.85
Very deep,
moderately well
drained, fine soils
on very gently
sloping basalic
interfluves with
slight erosion;
associated with
deep well
drained,
calareous fine
soils with slight
erosion
Fine,
montrmo
rillonitic,
hyperther
mic Typic
Chromust
erts
Fine,
montmori
llonitic
(calcareo
us)
hyperther
mic Vertic
Ustochre
pts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
interflu
ves
Vertis
ol/
Incept
isol
Very
Gently
sloping
Very
Deep-
Deep Slight
Mod.
Well Fine
Ne
utr
al Nil
Calca
reous Medium
C 0.12
Very deep,
moderately well
drained, fine soils
on very gently
sloping basaltic
interfluves with
moderate
erosion;
associated with
very deep, well
drained, fine soils
with moderate
erosion
Fine,
montmori
llonitic,
hyperther
mic Typic
Chromust
ers
Fine,
montmori
llonitic,
hyperther
mic Vertic
Ustochre
pts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
interflu
ves
Vertis
ol/
Incept
isol
Very
Gently
sloping
Very
Deep
Moder
ate
Mod.
Well Fine
Ne
utr
al Nil Nil Medium
-
30
D
103.3
3
Very deep,
moderately well
drained, fine soils
on nearly level
alluvial plain with
slight erosion and
slight salinity;
associated with
deep, moderately
well drained
calcareous fine
soils with slight
erosion and slight
salinity
Fine,
montmori
llonitic,
isohypert
hermic
Vertic
Ustropept
s
Fine,
montmori
llonitic
(calcareo
us),
isohypert
hermic
Vertic
Ustropept
s
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Incept
isol
Nearly
level
alluvial
V.Deep
-Deep Slight
Mod.
Well Fine
Slig
htly
alka
line
Slight
Salinity
Calca
reous Medium
G 63.34
Very deep,
moderately well
drained, fine soils
on very gently
sloping alluvial
plain with
moderate
erosion;
associated with
very deep,
moderately well
drained, fine soils
on nearly level
lands with slight
erosion.
Fine,
montmori
llonitic,
hyperther
mic Typic
Chromust
ers
Fine,
montmori
llonitic,
hyperther
mic Vertic
Ustochre
pts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Vertis
ol
Very
gently
sloping
Very
Deep
Sligt-
Mod.
Mod.
Well
Fine
Soil
Slig
htly
alka
line Nil Nil Medium
-
31
H 80.95
Very deep,
moderately well
drained, fine soils
on nearly level
alluvial plain with
slight erosion;
associated with
very deep
moderately well
drained,
calcareous, fine
soils on gently
sloping lands with
severe erosion
Fine,
montmori
llonitic,
hyperther
mic Typic
Chromust
erts
Fine,
montmori
llonitic
(calcareo
us),
hyperther
mic Typic
Chromust
erts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Vertis
ol
Nearly
level
alluvial
Very
Deep
Slight-
Severe
Mod.
Well
Fine
Soil
Slig
htly
alka
line Nil Nil
Low-
Medium
J 1.36
Very deep,
moderately well
drained, fine soils
on very gently
sloping alluvial
plain with
moderate erosion
and moderate
salinity;
associated with
very deep,
moderately well
drained
calcareous, fine
soils with
moderate erosion
Fine,
montmori
llonitic,
isohypert
hermic
Typic
Chromust
erts
Fine,
montmori
llonitic,
(calcareo
us),
hyperther
mic Udic
Chromust
erts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Vertis
ol
Very
gently
sloping
Very
Deep
Moder
ate
Mod.
Well
Fine
Soil
Slig
htly
alka
line
Moderat
e Nil
Low-
Medium
-
32
K 7.83
Moderately deep,
moderately well
drained, fine soils
on nearly level
alluvial plain with
slight erosion and
moderate salinity;
associated with
very deep,
moderately well
drained,
calcareous, fine
soils with slight
erosion and slight
salinity
Fine,
montmori
llonitic,
isohypert
hermic
Typic
Chromust
erts
Fine,
montmori
llonitic,
(calcareo
us),
isohypert
hermic
Udic
Chromust
erts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Vertis
ol
Nearly
level
Mod.
Deep-
V.
Deep
Slight
Erosion
Well-
Mod.
Fine
Soils
Slig
htly
alka
line
Moderat
e Nil Medium
L 1.31
Very deep,
moderately well
drained, fine soils
on nearly level
alluvial plain with
slight erosion and
moderate salinity;
associated with
very deep,
imperfectly
drained,
calcareous, very
fine soils with
slight erosion and
moderate salinity
Fine,
montmori
llonitic,
isohypert
hermic
Typic
Chromust
erts
Very-fine,
montmori
llonitic
(calcareo
us),
isohypert
hermic
Udit
Chromust
erts
Soils of
west
coast
(soils of
Gujarat
plain)
Soils of
alluvial
plains
Vertis
ol
Nearly
level
Very
Deep
Slight
Erosion
Weel
Draine
d-
Fine
Soils-
V.Fine
Soils
Slig
htly
alka
line
Moderat
e Nil Medium
(Courtesy: Data Purchased from Environmental Information Centre, New Delhi)
-
33
SOIL CHARACTERISTICS MAP
4.7 Climatic data from secondary sources
Primary source: our own weather station and secondary sources: Indian Meteorological
Department, Ahmedabad. We will include the details in EIA report.
4.7.1 MICRO-METEOROLOGY OF THE AREA
The climate of Gujarat is varied, as it is moist in the southern districts and dry in the
northern region. The Arabian Sea and the Gulf of Cambay in the west and the forest-
covered hills in the east soften the rigors of climatic extremes, consequently reducing the
temperature and render the climate more pleasant and healthy. Bharuch lies along the
southern part of the state and experiences a climate with aridity index of 15 to 20 per cent
indicating adequate moisture availability in the soils for most part of the year. (Courtesy:
Environmental Information Centre, New Delhi).
-
34
4.7.1.1 TEMPERATURE DETAILS
Minimum, Maximum and Average Temperatures for Surat Station (own weather station
installed) of the year 2016 are given in Table below:
TEMPERATURE DATA
Month
(2016)
Minimum
Temperature
(0C)
Maximum
Temperature
(0C)
Average
Temperature
(0C)
January 17 34 25
February 19 37 28
March 19 40 29
April 25 39 31
May 28 41 32
June 26 37 31
July 25 33 29
August 25 32 29
September 8 33 28
October 19 37 28
November 17 34 25
December 15 35 24
4.7.1.2 RELATIVE HUMIDITY (RH)
Minimum, Maximum and Average Monthly Relative Humidity for Surat Station (own
weather station installed) of the year 2016 is given in Table below:
RELATIVE HUMIDITY DATA
Month
(2016) Minimum R.H.% Maximum R.H.% Average R.H.%
January 6 55 25
February 6 100 25
March 6 82 28
April 6 70 30
May 6 69 37
June 11 77 34
July 19 94 52
August 65 100 91
September 16 100 72
October 6 97 39
November 6 39 15
December 6 39 14
-
35
4.7.1.3 RAINFALL
Rainfall data collected of Surat station (own weather station installed) of the year 2016 is
presented in below table.
RAINFALL DATA
Month
(2016)
Monthly Total
(mm) Numbers of Rainy Days
January 0 0
February 0 0
March 0 0
April 0 0
May 0 0
June 19.7 3
July 312.0 11
August 98.6 4
September 109.8 5
October 77.0 4
November 0 0
December 0 0
Total 617.1 27
Total rainfall, during the monsoon period, has been recorded as 617.1 mm.
4.7.1.4 WIND SPEED
Wind speed for Surat Station (own weather station installed) of the year 2016 is given in
Table below:
WIND SPEED DATA
Sr. No. Month
(2016)
Average Wind speed
(KMPH)
1. January 0.4
2. February 0.9
3. March 1.5
4. April 3.0
5. May 6.0
6. June 6.7
7. July 5.3
8. August 6.9
9. September 4.1
10. October 1.9
11. November 1.8
12. December 2.6
Average 3.425
-
36
Site-specific meteorological data is given in below Table. A meteorological station was
installed at the project site to know temperature, relative humidity, hourly wind speed,
direction, and rainfall at the project site during the study period:
(PERIOD – OCTOBER’ 17 TO DECEMBER’ 17)
METEOROLOGICAL PARAMETER MONTH
OCTOBER’ 17 NOVEMBER’ 17 DECEMBER’ 17
Temperature (0C)
Min.
Max.
Avg.
18
36
28
15
35
25
11
33
22
Relative Humidity (%)
Min.
Max.
Avg.
18
98
57
22
99
57
21
88
52
Wind Speed (km/h)
Min.
Max.
Avg.
0
19
4
0
28
6
0
21
5
There was no rainfall during the study period. Diurnal shift in wind direction was not
observed during study period.
4.8 Social infrastructure available
Infrastructure resource base of the surveyed villages with reference to education, medical,
water resources, post and telegraph, communication, power supply is presented in below
table. There are 35 villages within study area of 10 km radius of plant site. Significant
observations with respect to availability of amenities in study area are as follows.
All of the villages have primary schools, 3 villages have both primary and secondary
education schools. 8 villages have adult education facility. 20 villages in the impact zone
have community health workers, 12 villages have primary health sub center, 4 villages have
registered private practitioners while 5 villages have family planning center, 2 villages have
-
37
primary health center. One maternity home, four child welfare centers, one nursing home,
two dispensaries and one hospital are also available in the impact zone.
In the study area drinking water facilities are good as tap water and well water is available
almost in all the villages, 4 villages have hand pumps. Tank water is available in 10 villages, 2
villages get water from tube well, 5 from canal and one from Nallah. Post office facility is
available in 27 villages while one village has post and telegraph facility. Telephone facility is
available in 17 villages. 35 villages are well connected through a network of Pucca road. 30
villages have Kuccha approach road. Bus is the main mode of transportation and is available
in 38 villages, while 4 villages are connected with railways. All the villages get electricity for
all purpose i.e. domestic, agriculture and industrial.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation, etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed expansion of Silica Sand production (Glass Grade) and LPG
Storage capacity and development of interconnected Float Glass Line (FL2) in Existing Glass
Manufacturing Unit.
This facility is located outside the notified industrial area of Ankleshwar.
5.2 Population Projection
POPULATION DENSITY
Name Population
(Persons)
Population Density
(Person / sq. km.)
Sex ratio
(No. of females per
1000 males)
Taluka Ankleshwar (2001) 262823 198 870
Taluka Ankleshwar (2011) 315596 238 882
District Bharuch (2001) 1370104 210 920
District Bharuch (2011) 1551019 238 925
Within 5 km Radius (2001) 39100 293 912
Within 10 km Radius (2011) 92136 498 925
(Courtesy: Census Dept., GOI)
-
38
5.3 Land use planning (breakup along with green belt etc.)
1) Total Plant Area = 6,55,990.4 m2
Green Belt = 98,436 m2
(Existing)
= 1,18,040 m2 (Total Proposed) (17.99%)
2) Total colony area = 3,74,456.4 m2
Green Belt = 3,12,047 m2
(Existing) (88.33%)
2) Grand Total area (Plant + Colony) = 10,30,446.8 m2
Grand Total Green Belt (Plant + Colony) = 4,30,087 m2
(41.74%)
Sr. No. Land Use Proposed Plant
Area (m2)
1 Production Plants 113311.10
2 Parking 16187.30
3 Security Building 404.6825
4 Utility + Tank 40468.25
5 Tank Farm Area
6 Raw Material and Finished Products Storage 250443.31
7 Gas Tonner Storage 40468.25
8 Green Belt 118040.00
9 Road 76667.51
Total 655990.40
-
39
5.4 Amenities/Facilities
Taluka Village Educational Medical Drinking
Water
Post &
Telegraph
Commu
nication
Approach
to Village
Nearest
Town
Power
Supply
Ankleshwar Bharan P(2) CWC, PHS T, W PO BS PR, KR Kosamba- 8 EA
Amboli P(2) -(- 5 KMS.) W, TK PO, Phone BS PR, KR Ankleshwar-1 EA
Boidara P(2) -(- 5 KMS.) T, W PO, Phone BS PR, KR Ankleshwar-1 EA
Nangal P(2) CHW T, W PO, Phone BS PR, KR Ankleshwar-6 EA
Hajat P(2), Ac -(- 5 KMS.) T, W PO, Phone BS PR, KR Ankleshwar-12 EA
Adol P(2) PHS, FPC,
CHW
T, W PO BS PR, KR Ankleshwar-11 EA
Umarwada P(3), O PHS, RP T, W, HP PO, Phone BS PR, KR Ankleshwar-6 EA
Kapodara P(2),O PHS, CHW,
FPC
T, W PO, Phone BS PR Ankleshwar-7 EA
Bhadkodara P(2) CHW T, W PO, Phone -(- 5
KMS.)
PR, KR Ankleshwar-7 EA
Piraman P(3), Tr, O PHS T, W PO, Phone BS PR, KR Ankleshwar-1 EA
Kosamadi P(6), O PHS, RP(3) T, W, HP PO, Phone BS PR, KR Ankleshwar-12 EA
Bakrol P(2) CHW T, W, HP -(-5 KMS) BS PR, KR Ankleshwar-8 EA
Sanjali P(2), O CHW T, W PO, Phone BS, RS PR, KR Ankleshwar-10 EA
Alonj P(2), O CHW T, W, HP PO BS PR, KR Ankleshwar-15 EA
Piludara P(2) -(10+ KMS) T, W PO, Phone BS PR Ankleshwar-13 EA
Telva P(2), Ac, O CHW T, W -(-5KMS) BS PR Ankleshwar-16 EA
Pardi Idris P(2) CHW T, W Po BS PR, KR Ankleshwar-12 EA
Adadara P(2) CHW T, W -(-5 KMS.) BS PR Kosamba-7 EA
Utiyadara P(2) -(-5 KMS) T, W -(-5 KMS) BS PR Kosamba-3 EA
Karmali P(2),O -(-5 KMS) T, W Phone BS PR Ankleshwar-13 EA
Ravidra P(2), O PHC, CHW T, W PO, Phone BS PR Ankleshwar-10 EA
Panoli P(3), H, O H, MH,
CWC, PHS,
D, FPC, NH,
RP, SMP,
CHW
T, W PTO, Phone BS, RS PR Ankleshwar-10 EA
Kharod P(3), H, O CWC, PHC,
CHW
T, W PO, Phone BS PR, KR Ankleshwar-10 EA
Bhadi P(2), O -(-5 KMS) T, W PO BS PR, KR Ankleshwar-12 EA
Jitali P (3), H, AC (4),
O
PHC, RP,
SMP, CHW
T, W, HP PO, PHONE BS PR, KR Ankleshwar-10 EA
Dodwada P(2) PHS, FPC,
CHW
T, W PO BS PR, KR Ankleshwar-11 EA
Siludi P(2) CHW T, W, HP -(-5 KMS) BS PR, KR Ankleshwar-8 EA
Mangrol Hathuran P(3), Ac(3) PHS T, W, TK,
TW, C
PO, Phone BS, RS PR, KR Kosamba-5 EA
Nana Borsara P, Ac -(5-10 kms) T, W, TK -(-5 KMS.) -(-5KMS) KR Kosamba-5 EA
Dhamdod P, Ac, O CHW T, W, TK PO BS PR, KR Kosamba-5 EA
Nandvav P, Ac(2) PHS, CHW T,W, TK,
C, N
PO BS PR, KR Kosamba-10 EA
Moti Pardi P, Ac CWC, CHW T, W, TK,
C
-(5-10 Kms) BS PR, KR Kosamba-16
Dinod P PHS, FPC,
CHW
T, W, TK PO BS KR Kosamba-8 EA
-
40
Boridara P CHW T, W, TK PO BS KR Kosamba-15 EA
Mahuej P, Ac(2), O PHS T, W, TW,
TK, C
PO, Phone BS PR, KR Surat-31 EA
Hansot Ghodadara P(2), O CHW T, W, TK,
C
PO BS PR, KR Ankleshwar-8 EA
Valia Kondh P(4), H, O PHS, D, FPC,
RP, CHW
T, W PO BS PR, KR Ankleshwar-12 EA
(Courtesy: Census Dept., GOI)
ABBREVIATIONS
1. Education
P-Primary Elementary School
H-Matriculation or Secondary
O-Other Educational Institution
PUC-Higher Secondary/Intermediate/pre-University/junior College
Ac- Adult Literacy Class
Tr-Training School
2. Medical Facilities
RP-Registered Private Practitioner
PHS-Primary Health Sub-Centre
FPC-Family Planning Centre
PHC-Primary Health Centre
D- Dispensary
CHW - Community Health Worker/Health Worker
H - Hospital
NH - Nursing Home
MH - Maternity Home
PHC - Public Health Centre
CWC - Child Welfare Centre
TB - T.B Clinic
O – Others
3. Drinking Water
T-Tap Water
HP-Hand Pump
TK-Tank Water
W-Well Water
R-River Water
C-Canal
N - Nallah
S – Spring
TW- Tube well Water
4. Post & Telegraph
PO-Post Office
PTO-Post & Telegraph
Phone-Telephone Communication
5. Communication
BS-Bus Station
NW-Navigable Waterway
6. Approaches to Village
PR-Pucca Road
KR-Kuchcha Road
7. Power Supply
EA-Electricity for all purposes
EAG - Electricity for Agriculture
ED - Electricity for domestic
EO - Electricity for other purpose like Industrial, Commercial etc.
-
41
6.0 Proposed Infrastructure
6.1 Processing Zone = 5,37,950.4 m2
(This would include the existing operations, new sand
plant and Float Line 2 operation)
6.2 Non- Processing Zone = 1,18,040 m2
(This is including existing as well as proposed
green belt and plantation)
6.3 Green Belt
Company has developed an effective green belt within the factory and on periphery of the
factory. Total Plant Area is 6,55,990.4 m2 out of which 98,436 m
2 is the existing green belt
and 19,604 m2
is proposed green belt area development. The cumulative green belt would
be 1,18,040 m2 (17.99%). Total Colony Area is 3,74,456.4 m
2 out of which 3,12,047 m
2
(83.33%) is the existing green belt. Total Plant + Colony Area is 10,30,446.8 m2 out of which
4,30,087 m2 (41.74%) will be green belt.
6.4 Social Infrastructure
This will be addressed as part of CSR (corporate social responsibility) program and the
details of the CSR program will be addressed in the EIA report.
6.5 Connectivity (Traffic and Transportation Road/Rail/Metro/Water Ways, etc.)
Site is very well connected by road and rail
6.6 Drinking Water Management (Source & Supply of water)
Total water requirement is met through Valia Water Supply System (Tapi River Canal
Water). We treat the water before using for drinking.
6.7 Sewerage System
Sewage pipes are laid in entire factory (offices, canteen and domestic use) conveyed to
sewage treatment plant for treatment and reused back in land irrigation/gardening.
Please refer Annexure IV of Form 1 for more details on STP plant.
6.8 Solid Waste Management
Please refer Section 1.5 (Page No. 10 through 12).
-
42
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home
oustees, land oustees and landless laborers (a brief outline to be given)
There is no habitation on the proposed expansion project activity area, and it is open
industrial land, so R & R policy is not applicable to this project. There shall not be
displacement of any population in project area. Any major activity that may lead to
resettlement of the people is considered as permanent impact. Hence, there is no
permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
We shall start construction of sand beneficiation plant only after getting environmental
clearance which we are anticipating by 30th
December 2019 and expecting the start of
construction of new sand plant by 20th
January 2020 and operation of new sand plant by
31st
August 2020, we have already received the Consent to Establish approval for the sand
beneficiation plant from Gujarat Pollution Control Board. We shall start production of new
sand beneficiation plant upon making application for CCA.
Note: In the existing premises, we already have operational float glass manufacturing unit
and existing sand beneficiation plant since 1993.
-
43
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total Cost of the Project is Rs. 2184 Crores (Existing Operations = 584 Crores + Additional
Proposed Operations = 1600 {New sand plant and LPG Storage enhancement: 86 + Float line
2 (interlinked project): 1514 Crores}. Total Plant Area is 6,55,990.4 m2
.
Break up of Additional Project Cost
Sr.
No.
Particulars Estimated Cost
(In INR crores)
1 Land and Site Development 283
2 Building 208
3 Plant and Machineries 1074
4 Environment protection measures (includes cost of ETP, Tree
Plantation, Evaporator System and Rain Water Harvesting etc.)
35
TOTAL 1600
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people
including tribal population, if any, in the area.
Employment would be as per prevailing norms of state government for skilled and unskilled
people for the proposed expansion project.
Social Welfare shall be done.
Cordial relation with the industry shall be established and representation shall be made to
villagers for help for creation of facilities related to health, education, etc. This will be
addressed through CSR program during and after the project execution.