pre-qualification documentfabiconkw.com/wp-content/uploads/2020/05/prequalifier-fabicon.pdfco. ltd...

19
PRE-QUALIFICATION DOCUMENT FABICON General Trading & Contracting Co. W.L.L Phone: +965 24349597, 24349795 Address: Galleria Complex, Gate 3 Mezzanine Floor, Office 13 Al-Dajeej, Farwaniya, Kuwait Email: [email protected] Website: www.fabiconkw.com

Upload: others

Post on 16-Mar-2021

40 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

PRE-QUALIFICATION DOCUMENT

FABICON

General Trading & Contracting Co. W.L.L

Phone: +965 24349597, 24349795

Address: Galleria Complex, Gate 3

Mezzanine Floor, Office 13

Al-Dajeej, Farwaniya, Kuwait

Email: [email protected]

Website: www.fabiconkw.com

Page 2: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

2

CONTENTS

PAGE NO.

1 INTRODUCTION 3

2 QHSE POLICY 4

3 ORGANIZATIONAL CHART 5

4 BUSINESS FIELDS 6

5 TRADE LICENSES & REGISTRATIONS 13

6 LIST OF PROJECTS 18

Page 3: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

3

INTRODUCTION

FABICON is a general contracting company, which provides service to the industrial, commercial and residential sectors in a high quality standard, using the latest value engineering processes. We have the manpower, equipment and experience to execute any work in specialized areas, particularly in Installation, Mechanical and Finishing works in heavy Civil construction, Oil, Industrial and Commercial Sector. Geographically based in Kuwait, our services have extended to other Middle Eastern regions too as part of projects undertaken. In general, FABICON is managed and operated by a team of professionals with unique talents from apt backgrounds. This supports our insistence to quality and customer service at the forefront of operations. As FABICON continues to grow and expand, the founding philosophy of constant quality solutions is more prominent than ever.

Our Principles

•Integrity. We are honest, consistent, fair in all aspects of our concern, and we communicate openly and directly.

•Customer Satisfaction. We strive to exceed customers’ expectations and will dedicate our time and efforts to deliver quality service to clients.

•Commitment to Innovation. We consider learning and development to be a continuous process and always adopt state-of-the-art technology and practices to enhance the efficiency of our operations.

•Safety. Our employees are our most important assets. Therefore, we offer safe and sustainable working conditions for them.

•Team Work. We seek to create an environment where individual growth is the foundation of company growth. For this we attract and develop leading talents in the concerned fields.

Page 4: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

4

QHSE POLICY The Health, Safety and Welfare of Employees are of prime importance to the Company. The responsibility for safety at work rests upon all sectors of management, and the Company will ensure that this policy is pursued through the organization. The Company will take all reasonably practicable precautions to ensure the health, safety and welfare at work of its Employees by providing:

• A safe working environment by the design, construction, operation and maintenance of all plant, equipment and facilities.

• Safe systems of work. • Adequate instruction, information, training and supervision. • Control of all situations likely to cause damage of properly and equipment. • Effective facilities for the treatment of injuries that occur at work. • Effective fire prevention and fire control procedure. • Adequate facilities for consultation between Management and Employee

representatives.

Page 5: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

5

ORGANIZATION CHART

Page 6: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

6

BUSINESS FIELDS

CIVIL CONSTRUCTION RELATED WORKS

MECHANICAL WORKS

EQUIPMENT & MANPOWER SUPPLY

Our Services

CIVIL CONSTRUCTION WORKS

Earthworks & Land preparation

Asphalt road works

Kerbs, Barriers and Pavement works

All types of concrete construction works

Manholes and Inspection chambers

Temporary facility works

MECHANICAL WORKS

Steel structure works

Piping, Fabrication & Field Erection works

Thermal and acoustic insulation

Protective coatings or claddings

Design, installation, rental and removal of all types of access scaffolding

MANPOWER & EQUIPMENT SUPPLY

Man power supply services

Equipment supply services

Support services for all construction

SPECIAL SERVICES

Customized buildings & Portacabins

Concrete cutting & Coring works

Demolition & Site clearance works

Page 7: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

7

CIVIL CONSTRUCTION WORKS

Earthworks & Land preparation

Asphalt road works

Kerbs, Barriers and Pavement works

Page 8: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

8

Concrete construction works

Manholes and Inspection chambers

Temporary facility works

Page 9: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

9

MECHANICAL WORKS

Steel structure works

New Refinery Project, Mina Al Zour

Page 10: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

10

Piping, Fabrication & Field Erection works

Light pole erection Pipe laying works

Protective coatings or claddings

Insulation works

Design, installation, rental and removal of all types of access scaffolding

Page 11: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

11

Customized buildings & Portacabins

Portacabins being assembled at our yard

Page 12: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

12

Concrete cutting & Coring works

Concrete diamond saw cutting

Demolition & Site clearance works

Demolition and site clearance of steel bridge at Jamal Abdel Nasser Street Project with ROBT JV

Page 13: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

13

TRADE LICENSES & REGISTRATIONS

Chamber of Commerce Registration

Page 14: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

14

Ithma thokia

Page 15: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

15

Ithma thokia

Page 16: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

16

Commercial License

Page 17: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

17

Commercial License

Page 18: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

18

LIST OF PROJECTS

SCOPE CLIENT YEAR

Valve and Flange Insulation Box work Tecnicas Reunidas, Sinopec5,

Hanwha JV - (KIPIC) - NRP, Mina

Al Zour.

Ongoing

Steel Structure Modification works Tecnicas Reunidas, Sinopec5,

Hanwha JV - (KIPIC) - NRP, Mina

Al Zour.

2019

Fabrication of site office at New

Refinery

Tecnicas Reunidas, China Eleventh

Chemical Construction Co. LTD –

(KIPIC) - NRP, Mina Al Zour.

2019

Pipe support Tecnicas Reunidas, China Eleventh

Chemical Costruction Co. LTD -

(KIPIC) - NRP, Mina Al Zour.

2019

Cladding work Tecnicas Reunidas, Sinopec5,

Hanwha JV - (KIPIC) - NRP, Mina

Al Zour

2019

600 Ton Steel Structure Erection

works of GC-32 Gathering Centre

Project

Sinopec10, Petrofac - GC32 project 2019

4000Tons Steel structure Erection

works including Coating, Blasting &

Erection at New Refinery Project

Tecnicas Reunidas, Sinopec5,

Hanwha JV – (KIPIC) - NRP, Mina

Al Zour.

2019

Fabrication of temporary facility and workers accommodation

Sinopec 10 – LFHOD Project Abdally (KOC) 2019

Fabrication works at New Maternity Hospital Project Pizzarotti - Italy 2018

Fabrication works for New Power station at Mina Al Zour

MEW/SEPCO III Electric Power Construction Corporation 2018

Fabrication of Temporary Facilities works for SINOPEC Fifth Construction Co. LTD at KNPC Al Zour New Refinery Project

KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV 2018

Fabrication of Portable cabins & Management Accommodation

KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV 2017

Fabrication of Chinese Mess Hall, Foreign Mess Hall & Kitchens

KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV 2017

Page 19: PRE-QUALIFICATION DOCUMENTfabiconkw.com/wp-content/uploads/2020/05/Prequalifier-FABICON.pdfCo. LTD at KNPC Al Zour New Refinery Project KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV

19

LIST OF PROJECTS

SCOPE CLIENT YEAR

Fabrication of Admin Office building for Tecnicas Reunidas at Mina Abdulla TR GT 5 Project

KNPC / Tecnicas Reunidas, Sinopec5, Hanwha JV 2016

Fabrication of Warehouse building for Tecnicas Reunidas at Mina Abdulla TR GT 5 Project

Tecnicas Reunidas / BAT EMAN 2016

Fabrication of Medical Facilities for Saipem for NRP Project Saipem / Al Hajran 2016

Fabrication of T7 Wash Bay Gulf Spic / Al Hajran 2016

Fabrication of T2 Vehicle Maintenance Building Gulf Spic / Al Hajran 2016

Fabrication of Gantry and Car parking

OHL Rizzani JV (Jamal Abdel Nasser Street Project) 2015

Concrete cutting & Core Drilling of box culverts

OHL Rizzani JV (Jamal Abdel Nasser Street Project) 2015

Airport road bridge demolition near KOTC building

OHL Rizzani JV (Jamal Abdel Nasser Street Project)

2015

Fabrication of Temporary Facilities of site Office

OHL Rizzani JV (Jamal Abdel Nasser Street Project)

2014