precision240™, precision320™ nut system...important inspect spindle to ensure threads are clean...

1
IMPORTANT Inspect spindle to ensure threads are clean and free of damage and distortion. Ensure bearings are lubricated prior to installation. STEP 1 STEP 2 STEP 3 STEP 9 Inspect STEP 4 STEP 5 STEP 10 End Play STEP 6 STEP 7 STEP 8 Properly seated Interlock Washer Button-head Cap Screw (2 ea) Torque to 200 ft. lbs. (271 Nm) while rotating hub 3 full turns 4A: Back-off nut 1 full turn Back-off nut 1 / 6 turn (60°) Outer bearing Spindle nut Interlock washer Tang Spindle keyway slot Fully engaged Tang Spindle nut Cap screw Spindle nut 4B: Rotate hub 1 full turn Torque to 50 ft. lbs. (68 Nm), then rotate hub 3 full turns. Repeat torque and rotations three more times. See note 1. See note 2 60° Questions? Call Hendrickson Trailer Technical Services Department In United States and Canada at 866-RIDEAIR (743-3247) or e-mail HTTS@Hendrickson-intl.com Trailer Commercial Vehicle Systems 2070 Industrial Place SE Canton, OH 44707-2641 USA 866.RIDEAIR (743.3247) 330.489.0045 Fax 800.696.4416 Hendrickson Canada 250 Chrysler Drive, Unit #3 Brampton, ON Canada L6S 6B6 905.789.1030 Fax 905.789.1033 Hendrickson Mexicana Circuito El Marqués Sur #29 Parque Industrial El Marqués Pob. El Colorado, Municipio El Marqués, Querétaro, México C.P. 76246 +52 (442) 296.3600 Fax: +52 (442) 296.3601 PRECISION240™, PRECISION320™ NUT SYSTEM T71005 Installation Procedures March 2016 Revision C T71005 Rev C 03-16 ECN 25127 © 2016 Hendrickson USA, L.L.C. All Rights Reserved Information contained in this literature was accurate at the time of publication. Product changes may have been made after the copyright date that are not reflected. FAILURE TO FOLLOW THESE INSTRUCTIONS COULD CAUSE WHEEL TO COME OFF AND CAUSE BODILY INJURY. OVER-TIGHTENING NUT COULD CAUSE BEARINGS TO RUN HOT AND BE DAMAGED. WARNING SPINDLE NUT SOCKET CAP SCREW HEX PRECISION240™ 3 13 / 16 " 5 / 32 " PRECISION320™ 4 7 / 8 " 3 / 16 " Wheel bearings should be set within 0.001" to 0.005" end play. Following this procedure will consistently produce a bearing setting of 0.001" to 0.003" end play. Precision Spindle Nut System Components SPINDLE NUT SCREW TORQUE ft. lbs. Nm PRECISION240™ 10 ± 2 13.5 ± 2 PRECISION320™ 15 ± 2 20 ± 2 Rotate hub at least five revolutions. Use a dial indicator to verify end play is within 0.001" to 0.005". Adjust nut as necessary to achieve acceptable end play. If required, refer to applicable wheel-end maintenance procedures. NOTES : 1. These steps must be performed four times to ensure bearings are fully seated. 2. If reusing existing screws, apply a small amount of Loctite ® Threadlocker Blue to screw threads. DO NOT ROTATE NUT If washer and nut teeth do not align, flip interlock washer over, then install.

Upload: others

Post on 23-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

IMPORTANTInspect spindle to ensure threads are clean and free of damage and distortion. Ensure bearings are lubricated prior to installation.

STEP 1 STEP 2 STEP 3

STEP 9 Inspect

STEP 4 STEP 5

STEP 10 End Play

STEP 6

STEP 7 STEP 8

Properly seated Interlock Washer

Button-head Cap Screw (2 ea)

Torque to 200 ft. lbs. (271 Nm) while rotating hub 3 full turns

4A: Back-off nut 1 full turn

Back-off nut

1/6 turn (60°)

Outer bearing

Spindle nut

Interlock washer

Tang

Spindle keyway slot

Fully engaged

Tang Spindle nut

Cap screw

Spindle nut

4B: Rotate hub 1 full turn

Torque to 50 ft. lbs. (68 Nm), then rotate hub 3 full turns. Repeat torque and rotations three more times. See note 1.

See note 2

60°

Questions?Call Hendrickson Trailer Technical Services Department

In United States and Canada at 866-RIDEAIR (743-3247) or e-mail [email protected]

Trailer Commercial Vehicle Systems2070 Industrial Place SECanton, OH 44707-2641 USA

866.RIDEAIR (743.3247)330.489.0045Fax 800.696.4416

Hendrickson Canada250 Chrysler Drive, Unit #3Brampton, ON Canada L6S 6B6905.789.1030Fax 905.789.1033

Hendrickson MexicanaCircuito El Marqués Sur #29Parque Industrial El MarquésPob. El Colorado, Municipio El Marqués, Querétaro, México C.P. 76246+52 (442) 296.3600Fax: +52 (442) 296.3601

PRECISION240™, PRECISION320™ NuT SySTEM T71005

Installation Procedures March 2016 Revision C

T71005 Rev C 03-16 ECN 25127 © 2016 Hendrickson USA, L.L.C. All Rights Reserved Information contained in this literature was accurate at the time of publication. Product changes may have been made after the copyright date that are not reflected.

FAILuRE TO FOLLOW THESE INSTRuCTIONS COuLD CAuSE WHEEL TO COME OFF AND CAuSE BODILy INJuRy. OVER-TIGHTENING NuT COuLD CAuSE BEARINGS TO RuN HOT AND BE DAMAGED.

WARNING

SPINDLE NuT SOCKET CAP SCREW HEXPRECISION240™ 3 13/16" 5/32"PRECISION320™ 4 7/8" 3/16"Wheel bearings should be set within 0.001" to 0.005" end play.Following this procedure will consistently produce a bearing setting of 0.001" to 0.003" end play.

Precision Spindle Nut System Components

SPINDLE NuT SCREW TORQuEft. lbs. Nm

PRECISION240™ 10±2 13.5±2PRECISION320™ 15±2 20±2

Rotate hub at least five revolutions. Use a dial indicator to verify end play is within 0.001" to 0.005".Adjust nut as necessary to achieve acceptable end play. If required, refer to applicable wheel-end maintenance procedures.

NOTES:

1. These steps must be performed four times to ensure bearings are fully seated.

2. If reusing existing screws, apply a small amount of Loctite® Threadlocker Blue to screw threads.

DO NOT ROTATE NuTIf washer and nut teeth do not align, flip interlock washer over, then install.