August 28, 2015 6083.01 Josh Henderson Core Projects VIA E-MAIL: [email protected] Dear Mr. Henderson: Re: 445 Kingsway TAMS Schedule Bunt & Associates were retained to provide a Transportation Assessment and Management Study (TAMS) for the proposed redevelopment of 445 Kingsway, Vancouver BC. The redevelopment would result in the addition of 104 residential condo units to a redeveloped auto dealership and vehicle service amenity. The City has asked that weekday traffic counts wait until the school season has started; hence those counts are now scheduled for September 15, 2015. We expect have a draft of our report ready for Core Projects by September 18, 2015. The study will follow the City of Vancouver’s 2008 Transportation Assessment and Management Study Guidelines for Consultants document. Bunt has confirmed the TAMS scope with City staff. Parameters of the TAMS document are described below: The study will include analysis of weekday PM peak hour and Saturday mid-day peak hour periods. Study area intersections to be examined with Synchro 8 software are (also illustrated in Exhibit 1): o Kingsway & St. George Street, o Kingsway & Site Access, o St. George Street & 12 th Avenue, and o St. George & Site Access. Two time period scenarios: Existing conditions, and Existing plus Development. The TAMS will review on-site vehicle and bicycle parking supplies. Transportation Demand Management (TDM) strategies for the development will be provided.

Upload: others

Post on 24-Mar-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

August 28, 2015

6083.01

Josh Henderson

Core Projects

VIA E-MAIL: [email protected]

Dear Mr. Henderson:

Re: 445 Kingsway

TAMS Schedule

Bunt & Associates were retained to provide a Transportation Assessment and Management Study (TAMS)

for the proposed redevelopment of 445 Kingsway, Vancouver BC. The redevelopment would result in the

addition of 104 residential condo units to a redeveloped auto dealership and vehicle service amenity.

The City has asked that weekday traffic counts wait until the school season has started; hence those

counts are now scheduled for September 15, 2015. We expect have a draft of our report ready for Core

Projects by September 18, 2015.

The study will follow the City of Vancouver’s 2008 Transportation Assessment and Management Study

Guidelines for Consultants document. Bunt has confirmed the TAMS scope with City staff. Parameters of

the TAMS document are described below:

The study will include analysis of weekday PM peak hour and Saturday mid-day peak hour periods.

Study area intersections to be examined with Synchro 8 software are (also illustrated in Exhibit 1): o Kingsway & St. George Street, o Kingsway & Site Access, o St. George Street & 12th Avenue, and o St. George & Site Access.

Two time period scenarios: Existing conditions, and Existing plus Development.

The TAMS will review on-site vehicle and bicycle parking supplies.

Transportation Demand Management (TDM) strategies for the development will be provided.

use this to outline site etc

13th Avenue

ProposedSt. George Access

Guelp

hStreet

St. Geo

rge

Street

Prop

osed

King

sway

Acces

s

13th Avenue

Unsignalized

Pedestrian Signal

Traffic Signal

12th Avenue

&

Scale: NTS

N

Exhibit 1

Study Area and Preliminary Proposed Laning

445 Kingsway Auto & Residential TAMSAugust 28, 2015

445 Kingsway, Vancovuer BC – TAMS Schedule | August 28, 2015 3 S:\PROJECTS\JP\6083-01 445 Kingsway\5.0 Deliverables\Prelim Letter Aug 28 445 Kingsway.docx

We have calculated development site traffic as follows:

Table 1: Trip Generation Estimate Weekday PM Peak Hour

Land Use

Size

(sf or

units)

Rate

(per 1,000

sf, or unit)

Source % In % Out Trips

In

Trips

Out

Total

Trips

Weekday PM

Auto Sales 21,509 2.62 ITE 841 0.40 0.60 22 34 56

Auto Service 35,151 3.11 ITE 942 0.49 0.51 53 56 109

Mid-Rise Condo 104 0.39 ITE 223 0.58 0.42 24 17 41

Total 99 107 206

Saturday

Auto Sales 21,509 4.02 ITE 841 0.50 0.50 43 43 86

Auto Service 35,151 3.11* ITE 942 0.50 0.50 54 55 109

Mid-Rise Condo 104 0.39** ITE 223 0.57 0.43 23 18 41

Total 120 116 236

*No Saturday peak hour data in ITE Handbook hence Weekday PM rate was used which is 13% of ITE Saturday

daily rate.

**No Saturday peak hour data in ITE Handbook hence same rate as Weekday PM used. High-rise rate is same for

Weekday PM and Saturday peak hour.

Site access, loading and internal circulation will be examined. Attention will be provided to

parkade ramp design at the site entrance, where the residential access ramp splits off from the

access to the commercial parking to ensure that all movements can be completed safely.

445 Kingsway, Vancovuer BC – TAMS Schedule | August 28, 2015 4 S:\PROJECTS\JP\6083-01 445 Kingsway\5.0 Deliverables\Prelim Letter Aug 28 445 Kingsway.docx

We look forward to continued correspondence with all stakeholders on this project.

Best regards,

Bunt & Associates