August 28, 2015
6083.01
Josh Henderson
Core Projects
VIA E-MAIL: [email protected]
Dear Mr. Henderson:
Re: 445 Kingsway
TAMS Schedule
Bunt & Associates were retained to provide a Transportation Assessment and Management Study (TAMS)
for the proposed redevelopment of 445 Kingsway, Vancouver BC. The redevelopment would result in the
addition of 104 residential condo units to a redeveloped auto dealership and vehicle service amenity.
The City has asked that weekday traffic counts wait until the school season has started; hence those
counts are now scheduled for September 15, 2015. We expect have a draft of our report ready for Core
Projects by September 18, 2015.
The study will follow the City of Vancouver’s 2008 Transportation Assessment and Management Study
Guidelines for Consultants document. Bunt has confirmed the TAMS scope with City staff. Parameters of
the TAMS document are described below:
The study will include analysis of weekday PM peak hour and Saturday mid-day peak hour periods.
Study area intersections to be examined with Synchro 8 software are (also illustrated in Exhibit 1): o Kingsway & St. George Street, o Kingsway & Site Access, o St. George Street & 12th Avenue, and o St. George & Site Access.
Two time period scenarios: Existing conditions, and Existing plus Development.
The TAMS will review on-site vehicle and bicycle parking supplies.
Transportation Demand Management (TDM) strategies for the development will be provided.
use this to outline site etc
13th Avenue
ProposedSt. George Access
Guelp
hStreet
St. Geo
rge
Street
Prop
osed
King
sway
Acces
s
13th Avenue
Unsignalized
Pedestrian Signal
Traffic Signal
12th Avenue
&
Scale: NTS
N
Exhibit 1
Study Area and Preliminary Proposed Laning
445 Kingsway Auto & Residential TAMSAugust 28, 2015
445 Kingsway, Vancovuer BC – TAMS Schedule | August 28, 2015 3 S:\PROJECTS\JP\6083-01 445 Kingsway\5.0 Deliverables\Prelim Letter Aug 28 445 Kingsway.docx
We have calculated development site traffic as follows:
Table 1: Trip Generation Estimate Weekday PM Peak Hour
Land Use
Size
(sf or
units)
Rate
(per 1,000
sf, or unit)
Source % In % Out Trips
In
Trips
Out
Total
Trips
Weekday PM
Auto Sales 21,509 2.62 ITE 841 0.40 0.60 22 34 56
Auto Service 35,151 3.11 ITE 942 0.49 0.51 53 56 109
Mid-Rise Condo 104 0.39 ITE 223 0.58 0.42 24 17 41
Total 99 107 206
Saturday
Auto Sales 21,509 4.02 ITE 841 0.50 0.50 43 43 86
Auto Service 35,151 3.11* ITE 942 0.50 0.50 54 55 109
Mid-Rise Condo 104 0.39** ITE 223 0.57 0.43 23 18 41
Total 120 116 236
*No Saturday peak hour data in ITE Handbook hence Weekday PM rate was used which is 13% of ITE Saturday
daily rate.
**No Saturday peak hour data in ITE Handbook hence same rate as Weekday PM used. High-rise rate is same for
Weekday PM and Saturday peak hour.
Site access, loading and internal circulation will be examined. Attention will be provided to
parkade ramp design at the site entrance, where the residential access ramp splits off from the
access to the commercial parking to ensure that all movements can be completed safely.
445 Kingsway, Vancovuer BC – TAMS Schedule | August 28, 2015 4 S:\PROJECTS\JP\6083-01 445 Kingsway\5.0 Deliverables\Prelim Letter Aug 28 445 Kingsway.docx
We look forward to continued correspondence with all stakeholders on this project.