1 | P a g e
PRELIMINARY REPORT
DATE: 27TH FEB 2015
Customer Name: ERB West Platform, Petronas Carigali Sdn Bhd (SBO)
Status of Call: Contractor Instruction From: En. Agku Suffian B Pg A. Razak
NATURE OF WORK
Problem Reported: Please refer to details below.
System Down: Yes / No Inspection Type: Routine Vibration Survey
Call Reported by: Muhammad Harizuan/Mohd Fazli Jaafar/Muhammad Nizamuddin Time: Day
Location of Inspection: All Area
SERVICE DETAILS
Service Rendered: Routine vibration survey on Rotating Machineries. Background: February 15 routine visit.
DIAGRAM
Analysts Summary Report: Review has been completed on below list of machine:
1.0 Event Logs:
1. REINJECTION COMPRESSOR
i. K-6260 :- Under commissioning
ii. K-6310 :- Normal
iii. K-6360 :- Normal
2. COOLER FAN (EWGA)
i. E-6270 :- Normal
ii. E-6290 :- Highest vibration at Fan Gearbox NDE Vertical axis. * Full diagnosis report will be provided.
iii. E-6320 :- Normal
iv. E-6340 :- Normal
v. E-6370 :- Normal
vi. E-6390 :- Normal
3. EWAC GAS COMPRESSOR
i. K-2410 :- Normal
4. COOLER FAN (EWDPA)
i. E-2420 Unit A :-Highest vibration at Motor NDE Horizontal axis is increased from previously 7.00mm/s to 12.83mm/s. This motor is running
in Zone D within this zone is normally considered to be of sufficient severity to cause damage to the machine.
* Full diagnosis report will be provided. ii. E-2420 Unit B :- Normal
iii. E-2450 Unit A :- Normal
iv. E-2450 Unit B :- Normal
AFCM
-
2 | P a g e
5. GAS GENERATOR
i. G-6590 :- Trending vibration level show gradually increase.
* Full diagnosis report will be provided.
ii. G-6600 :- Normal
iii. G-6610 :- Normal
6. LUBE OIL COOLER FAN
i. G-6590C :- Normal
ii. G-6600C :- Normal
iii. G-6610C :- Normal
7. COT PUMP
i. P-802 :- Normal
ii. P-803 :- Standby
iii. P-804 :- Normal
iv. P-805 :- Normal
8. INSTRUMENT AIR COMPRESSOR
i. K-5455 :- Normal
ii. K-5430 :- Normal
iii. K-6645 :- Normal
9. GLYCOL PUMP
i. P-6205 :- Unable to measure due to blasting activity
ii. P-6215 :- Unable to measure due to blasting activity
iii. P-6110 :- Unable to measure due to blasting activity
iv. P-6120 :- Unable to measure due to blasting activity
10. DIESEL FIRE WATER PUMP
i. P-6530 :- Standby
11. STANBY DIESEL GENERATOR
i. G-6720 :- Standby
2.0 Preliminary Recommendations:
1. E-6290
- Refer to diagnosis report.
2. E-2420 Unit A
- Refer to diagnosis report.
3. G-6590
- Refer to diagnosis report.
3.0 Summary:
3.1 CBM has completed routine survey on ERB West Platform. 3.2 Based on the preliminary results, only 3 machines were found with significant vibration level which required further action. 3.3 The full report will be released within 7 working days after visit completion.
-
3 | P a g e
Status after Service: (Please circle) Complete/ Incomplete/Under Observation/ Working solution provided
Events for Tomorrow: None
Start of Service: 9th Feb 2015
End of Service: 23th Feb 2015
PERSONNEL INVOLVED:
1) Muhammad Harizuan Bin Harudin - CBM Tech 2) Mohd Fazli Jaafar - CBM Tech 3) Muhammad Nizamuddin Bin Mazlan - CBM Tech