preliminary study report for grant aid project 1. … · although ethiopia is located in the...
TRANSCRIPT
1
Preliminary Study Report for Grant Aid Project
Date 2010/04/13 1. Title of the Cooperation Project and Name of the Project Proponent 1.1 Title of the Cooperation Project
The Project for Replacement of the Bridges on Trunk Road (Modjo, Awash and Gogecha Bridges) in the Federal Republic of Ethiopia 2. Categorization and its reason 2.1 Categorization: Category B 2.2 Reason (1) The possible adverse impacts are expected due to the project.. Among them, ”serious adverse
impact” (rating A according to JICA Guidelines for Environmental and Social Considerations) is not expected and “some adverse impact” (rating B) are expected for the items in social environment (involuntary resettlement, land use and utilization of local resources, etc.), in natural environment (soil erosion, flora/fauna and biodiversity, etc.), and environmental pollution (air pollution, water pollution, etc.). However, those impacts can be avoided or minimized/mitigated by examination of the project plan including environmental management plan at the Outline Design Study stage and proper implementation of mitigation measures and monitoring.
(2) Proposed projects for relocation of three bridges correspond to upgrading/rehabilitation of existing bridges, which may cause some adverse impacts but not likely to warrant a full EIA study. Thus the projects are categorized into those requiring an IEE according to both EIA guidelines of Ethiopian Environmental Protection Authority (EPA) and Ethiopian Roads Authority (ERA). 3. Outline of the Location (Maps, Environmental and Social Condition, Problems and so on) 3.1 The Project areas Gogecha, Modjo and Awash Bridges are located at 35km, at 69 km and 225km respectively from
Addis Ababa on t he A-1 trunk road from Addis Ababa to Djibouti Port. Location of three bridges and relevant project sites are shown in Map 1 and 2.
Administrative Region/Zone/Woreda which three bridges belong to are shown in Table 1. Table 1 Administrative Region/Zone/Woreda of three bridges
Region Zone Woreda
Gogecha bridge Oromiya Region East Shewa Zone Akaki Woreda
Modjo bridge Oromiya Region East Shewa Zone Lome Woreda
Awash bridge Afar Region Administrative Zone 3 Awash Fentale Woreda
3.1.1 Social environment (1) Population - Population (2007) of administrative Region/Zone/Woreda where three bridge sites are situated are shown in Table 2.
Table 2 Population of relevant Region, Zone and Woreda relevant to three bridges Region/Zone/Woreda Area Population Urban/Rural Population Note
2
(km2) Urban % Rural %
Ethiopia 1,127,1
27 73,918,505 11,956,170 16.1 61,953,185 83.9
(1) Oromiya Region 353,632 27,158,471 3,370,040 12.2 237,884,431 87.8
1) East Shewa Zone ― 1,357,522 340,267 25.1 1,017,255 74.9
a) Akaki Woreda ― 77,829 6,669 8.6 71,160 91.4 Gogecha
Bridge
b) Rome Woreda ― 73,182 4,163 5.7 69,019 94.3 Modjo
Bridge
(2) Afar Region 96,717 1,411,092 188,973 13.4 1,222,119 86.6
1) Administrative Zone 3 198,628 58,267 29.3 140,361 70.7
a) Awash Fentale
Woreda ― 29,775 16,844 56.6 12,931 43.4
Awash
Bridge
(2) Ethnicity and religion In regional, level ethnic groups Oromo is predominant in Oromiya Region, while Afar is predominant in Afar Region. Regarding religion, Orhtodox Christians are major and others are Muslim, Protestants and traditional religions in Oromiya Region,, while Muslim is predominant in Afar Region. (3) Land use Land use of the three project areas are predominantly farmland for crop cultivation with some patches of grazing areas mainly at the hilltop and steep slopes. However, in Gogecha and Modjo Bridge sites some factories and other buildings are distributed near the bridges. 3.1.2 Natural environment (1) Topography and relief In the Gogecha Bridge site, the road from Addis Ababa shows a gradual drop down to reach the bridge, then the topography generally flat at the spot. In the Modjo Bridge site, the road to the bridge generally traverses along a rolling terrain where it shows a slight drop at the spot of the bridge until it reaches a flat topography on the way to close to Modjo Town. In the Awash Bridge site, the road traverses rather flat plains and gradually drop down to the bridge. In addition, topography near the bridge is characterized by rock outcrops and cobblestones steep slope of Awash River gorge. (2) Climate Although Ethiopia is located in the tropics, temperatures vary with altitude and large climate variation, from hot arid to cool temperate, exist in the country. Based on climate classification of Ethiopia, the Gogecha and Modjo Bridge sites are can be grouped under warm temperate climate, which means mean annual temperature of 15℃ to 20℃ and mean annual rainfall 600mm to 2,000mm. On the other hand, Awash Bridge site has a tropical semi-arid climate with mean monthly maximum temperature of 32℃ to 42℃ to minimum temperature 9.6℃ to 22℃ and with rainfall pattern of biannual type giving a mean annual rainfall of about 600 mm.
3
(3) River and hydrological situation Gogecha, Modjo and Awash Bridges on the A-1 trunk road cross over Gogecha River, Modjo River and Awash River respectively. Catchment areas corresponding to three bridges are 37.6 km2 for Gogecha River, 1,103km2 for Modjo River and 19,100 km2 for Awash River. Gogecha River is a non-perennial river that conveys surface runoff from the vicinity catchment during rainy season. Modjo River is one of the major perennial tributary that drains to Awash river. Awash River is one of the major rivers in Ethiopia. It rises at an elevation of about 3000m in the Central Ethiopian Highlands and flows northeastwards along the Rift Valley into the Afar triangle where it terminates in Lake Abbe at an elevation of 250m. The main river length is about 1,250km. Awash and Modjo River are forms gorge with deep and steep slope structures. (4) Plants, animals and ecosystem There are no environmentally sensitive areas and no precious plants and animal species in three bridge sites. However, Awash National Park is located about 10 km westward from Awash Bridge and the A-1 trunk road passes through the Park. The Park was established in 1966 and covers at least 756km2 of Acacia woodland and savanna grassland with its southern boundary along Awash River. Wildlife in the Park include about 80 species of mammals as well as over 450 bird species.
3.1.3 Environmental problems (1) Air and noise pollution Black smoke of exhaust emissions and noise generation are observed whenever heavy vehicles with mal functioned and overloaded run through the road and bridge, although there is no existing data on air quality and noise. (2) Water pollution During dry season water quality of river is deteriorated due to decrease in river flow except Awash River. (3) Others Land mine and UXOs (unexploded ordinance) are buried on the slope of Awash River gorge at the Awash bridge. 4. Legal framework of Environmental and Social Considerations 4.1 Environmental Framework Legislations 4.1.1 Environmental Management and Conservation - The Constitution of Ethiopia - Proclamation on Establishment of Environmental Protection Organs (No. 295/2002) - Proclamation on Environmental Impact Asessment (No. 299/2002) - Proclamation on Environmental Pollution Control (No. 300/2002) - Proclamation on Expropriation of Landholding and Payment of Compensation (N0. 455/2005) - Proclamation on Rural Land Administration and Land Use (No. 456/2005) - Proclamation on Research and Conservation of Cultural Heritage (No. 209/2000) - Proclamation on Forest Development, Conservation and Utilization (No. 542/2007) - Proclamation on Ethiopian Water Resources Management (No. 197/2000)
4
4.1.2 Environmental Regulation and Standards No environmental standards have yet been established. 4.1.3 Environmental Impact Assessment (1) Laws and regulations
- Proclamation on Establishment of Environmental Protection Organs (No. 295/2002) - Proclamation on Environmental Impact Asessment (No. 299/2002) - Proclamation on Environmental Pollution Control (No. 300/2002) - The Ethiopian Road Authority (ERA) Establishment Proclamation (No. 80/1997) (2) Guidlines and manuals -1 (Ethiopian Environment Protection Authority, EPA) - Environmental Impact Assessment Guideline Document (2000.5) - Environmental Impact Assessment Procedure Guideline (2003) - Draft Guideline for Environmental Management Plan (2004) - Directive issued to Determine Projects subject to Environmental Impact Assessment (2008) (3) Guidelines and manuals-2 (Ethiopian Roads Authority, ERA) - ERA Environmental Procedures Manual (2001) - ERA Environmental and Social Management manual (2008) (4) Involuntary resettlement and Land Acquisition
- The Constitution of Ethiopia - Proclamation on Expropriation of Landholding and Payment of Compensation (N0. 455/2005) - Proclamation on Rural Land Administration and Land Use (No. 456/2005) - Council of Ministers Regulation on the Payment of Compensation for Property Situated on Landholdings Expropriated for Public Purposes (No. 135/2007) - The Ethiopian Road Authority (ERA) Establishment Proclamation (No. 80/1997)
5
4.2 Procedures and requirements for Environmental Assessment Procedure of EIA approval by ERA is shown in Figure 1.
(Respond to comments)
(No) (Yes)
(No) (Yes)
Conduct full EIA study
Making full EIA report
Respond to commnets Review full EIA study
Review and commnet from EPA
EIA approval
Public Consultation
Making TOR
Review of TORReview and comment
from EPA
Review and comment from EPA
TOR accepted
No further EIA required
Conduct IEIA study
Public Consultation
Making IEIA Report
Review of IEIA Study
Require full EIA study No further EIA study required
Scoping session for TOR
Require full EIA Require IEIA
Project identification
Initial Environmental Examinaiton
Review/Categorization
Source: Hearing and referring to ERA Environmental Procedure Manual (2001)
Figure 1 Procedure of EIA Approval by ERA 4.3 Projects subject to EIA Based on EPA EIA Guideline Documents (2000.5) and ERA Environmental Manual 2001,
categorization of projects subject to EIA are as follows: (1) Category 1 Projects: Require full EIA - Projects which may have adverse and significant environmental impacts may require full EIA. - For the road sub-sector, these include “major urban roads, rural road programs and
trans-regional and international highways.” - All projects in environmentally sensitive areas irrespective of the nature of the project.
6
(2) Category 2 Projects: Require an IEIA (Initial Environmental Impact Assessment)* in order to determine whether full EIA is necessary or not. * IEIA is similar to IEE (Initial Environmental Examination) of JICA Guidelines
- Projects whose type, scale or other relevant characteristics have the potential to cause some significant environmental impacts but are not likely to warrant a full EIA.
- For the road sub-sector, these include “upgrading/rehabilitation of major rural roads.” (3) Category 3 Projects: Projects which would have no impact and does not require EIA. - For the road sub-sector, these may include “capacity building and institutional improvement of
road related organizations.”
According to the above categorization, the cooperation projects for relocation of three bridges are categorized into category 2 projects and are required an IEIA. Thus IEIA study on the cooperation project is going on by ERA.
4.4 Competent Agency
In Ethiopia EPA is designated to competent agency to evaluate, review the Project Report and the EIA Study Report and issue EIA approval by Proclamation on Establishment of Environmental Protection Organs (No. 295/2002). Organization chart of EPA is shown in Figure 2. However, at present EPA can not fulfill sufficiently its function as a competent agency because regulations regarding implementation of the Proclamation have not been approved by Environmental Protection Council and the means of execution such as budget and human resources are not enough. In the mean time of this process, the implementing agencies have the authority to endorse and issue the EIA instead of EPA. Thus, with respective to road development, rehabilitation and operation and maintenance activities, the competent agency is ERA as authorized by The Ethiopian Road Authority (ERA) Establishment Proclamation (No. 80/1997). In the ERA Environmental Management Branch of Planning Division is in charge of EIA issues. Thus ERA is a proponent and also plays a role of the competent agency to review and make
approval of the EIA for road projects.
7
(Environmental Protection Authority)
Environmentaleconomicsand social
affairs Dept.
EnvironmentalInformation Center
Environmental policy andlaw Dept. Gender affairs Dept.
Manpower, resources andorganization and
management Dept.
Ecosystem Dept. Regional affairs service Environmental Laboratory
Environmental pollutioncontrol Dept. Finance Dept. Environmental education
Dept.
Prime Minister's Office
Environmentalprotection Council**
Director General
Impact AssessmentService*
Planning andprogramming service
Audit service
Deputy Director General
Note: * in chareg of EIA issues, ** supervising and legislative organ to EPA Source: Hearing an EPA officer and EPA document Figure 2 Organization chart of Ethiopian Environmental Protection Authority (EPA) 4-5 Information Disclosure and Public Participation
According to the ERA, the public consultation is a pre-requisite to all the projects to provide different stakeholders with an opportunity to raise their concerns from the project scoping stage to the approval of EIA Licence. Provision of intense public participation and consultation has been made mandatory for EIA through public consulting during scoping and public hearing after draft report preparation. Such participation of the related stakeholders should take place through entire period of preparation and reviewing of both the Project Report and EIA Study Report 5. Outline of the Relevant Agency and Institution which implement Project, EIA so on. 5.1 Name of the Project Proponent -The responsible agency is the Ministry of Works and Urban Development -The implementing organization is the Ethiopian Roads Authority (ERA). In ERA Environmental Monitoring & Safety Branch of Engineering & Regulatory Department is in charge of EIA issues.
8
- The organization chart of ERA with respect to EIA issues is shown in Figure 3.
ERA Board
Director General
Network ManagementDivision
Construction, ContractImplementation
Division
Human Resources &Finance Department
Engineering service,Procurement, Design& Technical Support
Division
EnvironmentalMonitoring Branch*
Operation Department
District EngineeringDivision
Engineering &RegulatoryDepartment
Planning andProgramming Division
Note: * Organization in charge of EIA implementation (Categorization, review and approval)
Source: ERA
Figure 3 Organization Chart of Ethiopian Roads Authority (ERA) 6. Outline of the Project and Analysis of Alternatives 6.1 Outline of the Project The objective of the proposed project is to improve the smoothness and safety of transport on the A1 Trunk Road through the replacement of Modjo, Awash and Gogecha Bridges. 6.2 Analysis of Alternatives Analysis of alternatives was examined for following two cases. (1) Zero Option (without project)
Zero Option means existing bridges are left in severely damaged and unsafe conditions and/or lacks bearing capacity resulting in collapse easily by bridge failure. If the bridge failure occurs, the consequences for the traffic corridor will be crucial, and it will take long time to re-establish a temporary bridge. In addition, existing alternative roads are through mountainous areas, which are significantly difficult to pass for heavy transports.
(2) Replacement of the existing bridges
Three bridges are inevitable to maintain both international and domestic road transportation for goods resulting to ensure proper delivery in time and amount of import and export goods and products.
Comparison of alternatives for each bridge was tentatively examined from environmental and social considerations and finalizing alignment is subject to further examination of Outline Design Study.
9
7. Adverse Environmental and Social Impacts 7.1 Envisioned adverse environmental and social impacts (Environmental Scoping) Envisioned adverse environmental and social impacts due to the project are identified, predicted
and evaluated with rating for 32 items of social environment, natural environment and environmental pollution according to the scoping procedure of JICA Guidelines for Environmental and Social Considerations, and summarized in Table 2.
Table 2 Results of Environmental Scoping and Countermeasures for adverse impacts
Environment item
*, **
Rating ***
Scoping (Identified impacts and
reasons)
Measures for adverse impacts
Gog
echa
brid
ge
Mod
jo b
ridge
Aw
ash
brid
ge
Further necessary
baseline study
Mitigation measures and
monitoring
(1) Social Environment
Involuntary
Resettlement
B B B
(P) Land acquisition is expected to
secure land for ROW (Right-of-way) of
new bridge and approach road based on
the proposed relocation plan. However,
resettlement of house or people is not
expected.
(P) 1) Finalizing the
alignment of new
bridge and approach
road. 2) sites for
construction office
and camps, storage
and construction
materials and waste.
3) Survey on
ownership, usage
and usufruct right of
the sites. 4) Identify
eligible PAPs and
affected property for
compensation. 5)
Formulation of RAP.
6) Examine the
consistency of
compensation policy
by ERA with those
required by JICA
Guidelines.
(P, C, O) 1) Re-examine the
project plan to avoid and/or
minimize the occurrence of
involuntary resettlement and land
acquisition. 2) If it is
unavoidable, from early stage of
the plan, provide adequate
information to PAPs and consult
with stakeholders including PAPs
to make agreement or thorough
understanding of the issues as
much as possible. 3) Conduct
necessary procedures for
compensation such as
identification of PAPs, survey on
land and property, and estimation
compensation payment by
Evaluation Committee. 4) Consult
with PAPs and stakeholders to
make agreement on
compensation. 5) Monitor and
evaluate result of compensation
after project implementation.
B B B
Secure ROW (30m width) for new
bridge and approach road
(permanently).
(P) 1) Compensate for PAPs who
have usufruct right to the
acquired land. 2) Compensate for
crop loss from the occupied land,
10
if any.
B B B Secure ROW (30m width) for new
bridge and approach road (temporary).
(P) 1) Compensation for PAPs
who have usufruct right to
temporary occupied land. 2)
Compensate for crop loss from
the temporary occupied land, if
any. 3) Rehabilitate the land used
temporary at the end of
construction stage.
B B B
Secure land for construction related
facilities (office, worker's camp,
material storage, waste disposal.
Local economy
such as
employment and
livelihood etc. D D D
(C) Beneficial impacts such as creation
of employment opportunity for public
works. (O) Function of important
transport corridor will be secured and
resulting in enhancing local economy
as well as national economy.
(C) Give local residents
preference to have a chance to
construction work.
Land use and
utilization of local
resources B B B
(P, C) Water for construction work
including worker's camp may compete
with existing water resources.
(P) Survey on
existing land &
water resources
(surface water and
groundwater) use
and regulation.
(P, C) Consult with people,
community and local
governments to make consensus
of water use.
B B B
(P, C) Quarries, borrow pits will be
used for procurement of construction
materials.
(P) Survey on
quarries and borrow
pits around the site.
(P, C) Consult with owners and
local governments for
procurement and pay proper
compensation, if necessary.
Social institutions
such as social
infrastructure and
local
decision-making
institutions
B B B
(P, C, O) If information disclosure of
the project plan, and procedure and
public participation are not properly
conducted, anxieties and complaints
may spread over the people and
communities resulting in difficulties for
obtaining thorough understanding of
the project and consensus with them.
(P) Survey on
community
structures, procedure
of decision-making,
and opinion leaders
in the project area.
(P, C, O) Information disclosure
and public participation should be
fully considered for all the
stakeholders from early stage of
planning for obtaining thorough
understanding and consensus of
the people and communities.
Existing social
infrastructures
and services B B B
(C) Construction works may obstruct
non-motorized delivery means such as
ass and horse and by walk.
(P) Survey on
non-motorized
transport in the
project area.
(P) Ensure to keep space for
non-motorized transport and
sidewalk on ROW, if necessary.
B B B
(C) Water use for construction work
may compete with community water
supply.
(P) Survey on
existing water use
and resources
(P) Ensure means of water supply
through consultation with
community, water supplier and
11
local government.
B B B
(C) There are connection lines of
utilities such as high voltage electric
lines, water pipes, telephone line on
and/or underneath the bridge and road.
(P) Survey on set up
place of utilities at
the site.
(C) Remove and re-install utility
lines at proper place of relocated
bridge and road, if necessary.
The poor,
indigenous of
ethnic people
B B B
(C) Water use for construction works
may give rise some impedance to the
poor and vulnerable groups who have
difficulties in access to water.
(P) Survey on
fetching means and
usage of water of
vulnerable social
groups such as the
poor, women and
children and
indigenous ethnic
people.
(P) Ensure means of water supply
and water right through
consultation with people
including vulnerable groups,
community, water supplier and
local government.
B B B
(C, O ) The poor and other vulnerable
groups who mostly utilize
non-motorized transport will be
somewhat suffered from inconvenience
for getting around during construction
and operation stage.
(P) Survey on usage
of non-motorized
transport.
(C) Set sidewalk space on the
bridge or secure proper detour
near the site.
B B B
(C) There is some possibility that
relocation space in Awash and Modjo
Bridge sites are partly farmland and
grazing land.
(P) Survey on land
use, and ownership
and usufruct right of
the land in the
project area.
(P, C, O) If the poor and
indigenous of ethnic people are
expected to become PAPs, their
rights in relation to land and
resources must be respected and
efforts should be made to obtain
the consent of them with fully
considerations to compensate
properly or support to restore the
present living condition.
Misdistribution of
benefit and
damage
B B B
(P, C, O) There is some possibility of
misdistribution of benefit and damage,
if the project plan, procedures of the
implementation and involuntary
resettlement/land acquisition matters
are not properly disseminated and
consulted with residents and
community and other stakeholders.
(P) Survey on past
experiences and
causes which may
give rise to the
misdistribution of
benefit and damage
in the communities.
Consultation with stakeholders
including PAPs and community
organizations, should be planned
from early stage to obtain
understanding and consent among
the stakeholders in order to share
equal benefit and damage.
12
Local conflict of
interests
B B B
(P, C, O) There is some possibility of
local conflict of interests, if the project
plan, procedures of the implementation
and involuntary resettlement/land
acquisition matters are not properly
disseminated and consulted with
residents and community and other
stakeholders.
(P) Survey on the
causes and solutions
of local conflicts of
interests in the
project area.
Consultation with stakeholders
including PAPs and community
organizations, should be planned
from early stage to obtain
understanding and consent among
the stakeholders in order to avoid
or minimize local conflict of
interests.
Cultural property
and heritage
B B B
(C) There are no cultural property and
heritage sites.
(C) If any cultural property and
heritage are found, consult with
Ministry of Youth, Sports and
Culture and local government for
treatment and preservation of
them.
Water usage or
Water rights and
Rights of
Common
B B B
(P) Water rights, fishery right and
rights of common are not known in the
project area.
(P) Survey on water
rights, fishing
rights and rights of
common in the
project area.
(P) Promote participation of those
who have the rights and making
consent in the course of the
stakeholder meeting.
Public health and
Sanitation
B B B
(C, O) Air pollution due to increase of
traffic volume may cause some adverse
effect to health conditions of residents,
especially to respiratory organs.
(P, C, O) Survey on
public health
including prevalence
and cause of
diseases, and
sanitary condition in
the project area.
(P, C, O) Monitoring health and
sanitary conditions of residents in
the project area.
Infectious
diseases such as
HIV/AIDS
B B B
(C) Road construction workers, and
truck drivers are considered as having
high potential for the spread of sexually
transmitted diseases (STDs) and
HIV/AIDS virus due to their mobility.
It was reported infection with
HIV/AIDS and venereal disease at
worker's camp during road construction
stage in Ethiopia and other African
countries.
(P) Survey on
existing cases and
cause of HIV/AIDS
in the project area.
(P, C)1) Monitoring cases of
HIV/AIDS before and after the
construction phase, 2)
Enlightenment and campaign of
prevention and cure of
HIV/AIDS.
Hazards (cyclone,
drought, etc.) and
risk D D C
(C) No additional risk of disasters are
not expected due to the project.
However, Awash bridge site is located
in depression of African Rift Valley
where unstable ground condition, some
awareness of land slide and erosion.
(P) Survey on cases
of natural disasters
such as flooding,
drought, landslide.
2) Stability of
ground in Awash
(P, C) 1) Avoid the area of
unstable ground conditions. 2)
Measures for prevention of
collapse and landslide at the
construction site
13
bridge site.
Accidents
B B B
(C, O) Stability and performance of the
bridge will be upgraded due to
relocation of existing bridge. However,
there is awareness of increasing in
traffic accidents during construction
and operation stage, if proper traffic
management measures including traffic
manners of both drivers and pedestrians
are not arranged.
(P) Collect and
analyze accidents
data due to
construction work
and existing vehicle
transport.
(C) 1) Proper management to
prevent and minimize accidents
due to construction work and
vehicle transport after operation.
2) Enlightenment and education
of traffic manner to drivers and
residents.
Security
C C B
(P) There are buried landmines and
UXOs (unexploded ordnance), which
have been left untreated since civil
wars near Awash bridge site.
(P) Investigate spots
of buried landmines
and UXOs at Awash
bridge site.
(P) Clear all the landmine and
UXOs around the site with
certificate from EMAO before the
arrival of the Outline Study Team
(Awash bridge site).
(2) Natural Environment
Topography and
Geology
B B B
(C) No large-scale land cutting and
filling are expected. However, if
improper cutting and filling likely to
cause collapse and landslide in rainy
season, especially in Awash bridge site
located in the range of depression of
the African Rift Valley.
(P) 1) Detailed
geological survey. 2)
Detailed survey on
ground conditions
(stability, strength,
etc.) of sites.
(P, C) 1) Avoid the area of
unstable ground conditions. 2)
Measures for prevention of
collapse and landslide at the
construction site.
Soil erosion
B B B
(C) No large-scale land cutting and
filling are expected. However, if
improper cutting and filling likely to
cause soil erosion in rainy season.
(P) Survey on the
area of susceptible to
soil erosion
(P, C) 1) Avoid the site of
susceptible to soil erosion. 2)
Measures for prevention of soil
erosion at construction site.
Groundwater
C C C
(C) There is some possibility of
pumping up of groundwater, if water
for construction works is not available.
(P) Survey on
groundwater
(capacity, quality,
aquifer materials
etc.)
(C ) Proper measures to prevent
penetration of polluted water to
underground.
Hydrological
situation/Drainage
pattern
B B B
(C) Excavation and dredging works of
bottom and sides of the river for
construction of the bridge may result in
changes of hydro-geological situation
of the river.
(P) Survey on
hydrological features
of rivers crossing the
relocated bridge
(flow rate, water
level, water quality,
flood etc.).
(C, P) 1) Proper measures for
prevention of spill over soil, sand
and rocks due to construction
works. 2) Construct proper water
drainage facilities along the
bridge and road. 3) Monitoring
flow and water quality of river.
14
B B B
(C, O) There is some awareness of river
scouring at the bridge site. Scour action
will be especially strong during flood.
(C) 1) Proper measures to prevent
river scouring. 2) Periodical
monitoring by bridge site
examination.
Coastal zone
D D D
(P) The Project area is not located in
coastal zone.
Fauna, Flora and
Biodiversity
C C C
(P, C, O) 1) The natural vegetation
around three bridge sites has been
mostly transformed into cultivated
lands, grazing lands and settlement
areas. Only some scattered trees are
remained in the cultivated lands. In
grazing lands livestock such as cows,
sheep and goats are pastured. 2) No
endangered or endemic plant and
animal species (terrestrial and aquatic)
were observed during the site visit.
However, there is little information
about precious plant and animal species
at present.
(P) 1) Survey on
protected and/or
precious plant and
animal species
(terrestrial and
aquatic) in the
project area.
(P, C) 1) To avoid ecologically
sensitive/fragile sites and habitats
of precious plant and animal
species in alignment selection. 2)
Even common trees like
Eucaliptus and Acacia species, to
avoid cutting down as much as
possible. If it is unavoidable,
proper measures such as
relocation and/or re-planting of
similar trees should be
implemented. 3) Plant trees and
shrubs along approach road.
D D B
(P, C, O) There are no sensitive area or
protected area in the three bridge sites.
However, Awash bridge site is located
about 10 km east of Awash National
Park and A-1 trunk road passes through
the Park for about 15km. Thus it is
necessary to pay attention to wildlife
conservation in the Park during
construction and operation stage.
(P) 1) Survey on
habitat and
movement of
precious animal
species in the Park.
2) Survey on cases
and causes of injured
animals by traffic
accidents
(C, P) 1) Post appropriate signs of
crossing animals along A-1 trunk
road in the Park area. 2) Instruct
construction workers and drivers
awareness of wildlife
conservation in Awash National
Park area. 3) Particular attention
to animals for safe crossing the
road in the night.
Sensitive Area
(Protected Area) D D D
(P) There are no sensitive area or
protected area in the three bridge sites.
D D B
(P) Awash bridge site is located about
10 km east of Awash National park and
A-1 trunk road passes through the Park
for about 15km..
(P) 1) Survey on
valuable animal
species in Awash
National Park. 2)
Tourist activities. 3)
Wildlife
management for
protection of
wildlife.
(C) Enlighten construction
workers and drivers on
importance of National Park
conservation.
15
Landscape
C C C
(C) There is a possibility to cause an
adverse impact on landscape depending
on alignment and design of new bridge
and approach road.
(P) Survey on
important landscape
in the project sites.
(C) To make bridge design
harmonizing with surroundings.
Meteorology D D D
(C) No large-scale topographical
alteration are expected.
Global Warming
D D D
(C, O) Increase in greenhouse gases
such as CO2 is expected to be
negligible amount due to increase of
traffic volume.
(3) Environmental Pollution
Air pollution
B B B
(C) Emission of air pollutants from
vehicles and machines for construction
work are expected. (O) Poor emission
control of many vehicles due to
insufficient maintenance and inspection
may accelerate to spew out air
pollutants (exhaust particulate, NOx,
etc.) long the road.
(P) 1) Inventory
survey on major air
pollution sources, 2)
Collect data of
complaint about air
pollution.
(C) Control of emission of air
pollutants (dust, NOx , etc.) from
construction machines and
vehicles due to construction
work. (O) Proper management for
control of vehicle exhaust
emission and establish
inspection system of exhaust gas
emission
Water pollution
B B B
(C) 1) Water pollution due to spilling
over soil and sand from construction
work (cutting, filling, excavation and
dredging, etc.) and wastewater from
worker' camps is somewhat expected.
2) Toxic materials such as asphalt
emulsifiers may spill over to rivers. 3)
Water pollution load may increase due
to addition of drainage water especially
in rainy seasons.
(P) 1) Inventory
survey on major
water pollution
sources, 2) Survey
on water quality of
rivers and streams in
both dry and rainy
season.
(C, O) 1) Proper treatment of
water pollutants generated from
construction work to comply with
water quality regulation, 2) Water
quality monitoring of rivers.
Soil
contamination
B B B
(C) Toxic materials such as asphalt
emulsifiers utilized for bridge and road
construction may give rise to soil
contamination.
(P) Survey on
present situation of
soil contamination in
the project area.
(C) 1) Prevent to accumulate of
toxic materials in soil during
construction and operation phase.
2) Monitoring of soil
contamination around the sites of
earth moving and construction
work sites.
Bottom sediment
B B B
(C) Sedimentation and accumulation of
water pollutants including toxic
materials in the river and may result in
pollution of bottom sediments.
(P) Survey on
present situation of
bottom sediment
pollution in the
project area.
(C, O) 1) Monitoring of bottom
sediment pollution in the river.
16
Waste
B B B
(C) Generation of soil, sand and
construction waste is expected at
quarry, borrow pits, site of bridge and
road construction work and worker's
camp, etc.
(P) 1) Survey on
present situation and
institutional
structures of waste
management system
in the Project area,
2) Establish proper
management system
of waste during
construction stage.
(C) Proper planning and
management for construction
work to minimize waste
generation.
Noise and
Vibration
B B B
(C) Generation of noise and vibration
from construction machines and
vehicles is expected. (O) Increase of
noise and vibration due to increase in
traffic volume is expected.
(C, O) 1) Inventory
survey on generation
source of noise and
vibration. 2) Collect
data of complaint
about noise and
vibration.
(C, P ) 1) Use low-noise and
vibration equipments. 2) Examine
construction schedule and avoid
working in night time. 3)
Installation of soundproof walls
and buffer zones, if necessary.
(O) Countermeasures to minimize
noise and vibration from running
vehicles.
Ground
Subsidence C C C
(C) No major reclamation nor pumping
up of groundwater in a large quantity is
expected. However, stability of ground
is unknown at present.
(C, O) Survey on
ground conditions
strength of
foundation
(C, P ) Monitoring of ground
subsidence.
Offensive odor
D D D
(C, O) There is some possibility of bad
smell spreading over along the road due
to poor emission control of
construction machines and vehicles.
However, impact is expected to be
negligible because houses and public
facilities are scarcely and found around
the site.
Note 1: * Environmental items in the scoping are prepared based on the JICA Guidelines for Environmental and Social Considerations (2004) with some modifications as referred to the
Environmental Guidelines for Infrastructures Projects (1992). Note 2: ** Regarding the impacts on "Gender" and "Children's Right" might be related to all criterion (items) of Social Environment.
Note 3: Rating; *** In general, both beneficial and adverse impacts are expected due to the project
activities. However, adverse impacts only are the subject of considerations according to the JICA Guidelines. A-Serious impact is expected, B- Some impact is expected, C - Extent of impact is unknown
or not clear (Further examination is needed. It should be taken into consideration that impacts may
become clear as study progresses.) , D - Negligible or No impact is expected. IEE/EIA is not necessary.
17
Note 4: **** P) Planning Stage, C) Construction Stage, O) Operation stage
As shown in Table 2, no item of “serious impact” (rating A) is expected. However, “some impact” (rating B) are expected for most of the items of Social and Natural Environment, and Environmental Pollution. Therefore, the project is classified as category B according to categorization of the JICA
Guidelines.
8. Envisioned mitigation measures and monitoring 8-1 Mitigation measures and monitoring The above mentioned adverse impacts should be fully taken into considerations to conduct further necessary baseline survey and examine the countermeasures including avoidance, minimization and mitigation and monitoring as much as possible as shown also in Table 2. Baseline survey will be done to make further understanding of existing environment and the
effects expected to be caused by the project activities. Countermeasures will avoid, minimize or mitigate the adverse impact to an acceptable level
through the planning, construction and operation phases. Monitoring is required to ensure that the specified mitigation measures are properly carried out through construction and operation stages. 9. Consultation 9-1 Results of joint meeting on environmental and social considerations with Ethiopian side In the joint meeting with ERA, the Ethiopian side agreed with followings: -To take JICA Guidelines for Environmental and Social Considerations fully into consideration when they would conduct EIA study of the Project and get EIA approval from responsible authorities according to the relevant laws and regulations of the Ethiopian Government. - To get the budget allocation for land acquisition, resettlement and compensation for the Project Affected Persons (PAPs) as soon as possible, and to take necessary measures for PAPs and secure land three months before the commencement of the construction. -To hold the stakeholder meetings for each site by April, 2010 by the attendance of the project related authorities and people to explain the outline of the project, to obtain basic agreement for the project and to submit the minutes of the meetings to JICA Ethiopia office. - To put the cut-off-date for eligible criteria for land acquisition, resettlement and compensation in consultation with the Outline Design Study team. 9-2 Joint meeting with ERA environment officers
The joint meeting with ERA officers in charge of EIA and land acquisition was held to identify expected adverse impacts due to the projects and corresponding mitigation measures in view of both ERA’s EIA Guideline and JICA Environmental and Social Considerations in the course of Preparatory Survey. 9-3 Public consultation and participation by ERA ERA was independently conducting EIA study on the rehabilitation and construction project for
18
Gogecha and Modjo Bridges, although the scope of the project is somewhat different from the cooperation project. In the study, public consultations were carried out with concerned stakeholders including representatives of the local communities and administrations. According to the study report (draft), the majorities of the community were aware of the project and highly appreciate the project due to possible social and economic benefit. However, most people were worried about matters concerned with land acquisition such as minimizing land acquisition, receiving fair compensation and ensuring adequate land allocation and livelihood restoration. 10. Social Acceptability in case of Involuntary Resettlement and Land Acquisition To make agreement and obtain consensus with PAPs and stakeholders for involuntary resettlement
and land acquisition, proper information disclosure and public consultation are inevitable. Thus ERA should endeavor to do following matters as much as possible: (i) To re-examine measures for avoidance or minimizing occurrence of involuntary
resettlement and land acquisition in the project plan, (ii) Information dissemination of the project about the possibility of involuntary resettlement
and land acquisition through public meeting and other means, if they are unavoidable, (iii) Public consultation with PAPs and their representatives, and other stakeholders including
local leaders, Representatives of Community, NGO etc. should be held from early stage of the project plan and whenever necessary including field observations, inspections and valuations In addition, PAPs and stakeholders shall be encouraged to participate in all the process of consultations.
(iv) To formulate RAP complying with both Ethiopian laws and JICA Guidelines. (v) To facilitate implementation of RAP and monitor result of compensation, restoring living
conditions and livelihood after implementation. 11. Important Notice on Outline Design Study (1) To confirm each item of agreements in joint meeting with ERA as mentioned above (9-1). (2) To review the result of EIA study by ERA and to decide whether a full EIA study and/or
additional study is further required or not. (3) To revise the result of IEE prepared in the Preparatory Study (4) To fill in Environmental Checklist for road sector and monitoring form according to JICA
Guidelines. (5)To arrange another consultant in charge of Environmental and Social Considerations to Outline
Design Study Team 12. Other relevant Information 12.1 References - Grontmij/Carl Bro (2009.6) Detailed Engineering Design and Rehabilitation Measures and Construction Supervision of the existing Awash River Bridge and Adaitu River Bridge and Detailed Engineering Design and Construction Supervision for new Alternative Bridges of the two Bridges “Detailed Engineering Design Final Preliminary Hydrology/Hydraulics assessment Report” - Transport construction Design Share Company (2009.10) Consultancy Service for Detail
19
Engineering Design, Tender Document preparation and Construction Supervision of Modjo & Gogecha Rivers bridges “Preliminary Hydrology/Hydraulics Report – Modjo & Gogecha bridges” - ERA (2009.10): Consultancy Services for Detail Engineering Design, Tender Document Preparation and Construction Supervision of Modjo & Gogecha Rivers Bridges - Draft Environmental impact Assessment Report (by Transport Construction Design Share Company)
(End)