preparing for the unexpected: transmission planning in...

12
2014 Transform TX January 29, 2014 Hala N. Ballouz, PE Electric Power Engineers, Inc. Preparing for the unexpected: Transmission Planning in ERCOT

Upload: doandung

Post on 11-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

2014Transform TX

January 29, 2014

Hala N. Ballouz, PEElectric Power Engineers, Inc.

Preparing for the unexpected: Transmission Planning in ERCOT

Page 2: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

In business since 1968

Consulting to electric utilities and private generators

• Transmission grid deliverability analysis• Management of grid interconnection• Congestion and curtailment analysis• Market pricing and nodal analysis• Design & Equipment grid compliance• Owner’s Engineer, testing, inspection

Page 3: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

3

1990’sERCOT Generation Interconnection

Customer:

Hey, I have a 50 MW generator at Friend Ranch

ISO

We should be fine, plenty of capacity there.

….will run a study anyways!

Page 4: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

4

2014ERCOT Interconnection Process

Source: ERCOT Guide To The Interconnection Process Version 1.0

Outage Scheduling

Coordinated & Commissioning Plan submitted

Meteorologicaltower

requirements are met

Compliance with

Operating Stds. checked

SCADAConfirmed

Request to

commissionPOI

approved

Registration of RE

(IE Transitions to an RE)

Proposed Energization Date (PED) identified

Model Ready Date (MRD) identified

RE submits

RARF

EPS meter design

proposal from TSP

GINRRequest

(FEE)

Screening Study (SSR if required)

90 Day Limit45 day target

Resource Decision to

Proceed180 day limit

FISRequest

(Fee)

FISScope

Meeting

Request For initial

synch.approved

QSE Ptslist received

from QSE based on Scada Plan

TelemetryAdditions

set up for MRD

TestReactive

Capability

Request To begin

CommercialOperationsapproved

EPSmeterdesign

proposal date

ESIID active

In Loadstar

Full InterconnectStudies

SS; FaultDynamic; Fac.<Economic>;

<SSR>

TSPERCOT

Review FIS& ERCOT Approval

NegotiationOf

Interconnection Agreement

180 day limit

ERCOT Assess

standards 60 day limit

First time to be

energized

Initial Synchronization

Commercial Operation

Date(COD)

Screening Study

delivered to IE

IE commits

to proceed

FIS Scope agreed

upon (IE and TSP)

FIS complete

IA signed by TSP and

IE

ERCOT Standards

Review delivered

to IE

Page 5: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

5

1990sTechnical Grid Requirements

Are the conductors large enough?

Page 6: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

6

2014Technical Grid Compliance Requirements

1. Thermal Limitations (Are the Conductors Large Enough!)

2. Voltage Ride-Through (VRT) Requirements for IRRs (Nodal Operating Guides Section 2.9)

3. Frequency Relaying Requirements (Nodal Operating Guides section 2.6.2)

4. Reactive Power Support Requirements (Nodal Protocols section 3.15)

5. Ramp-up Rate Requirements (Nodal Protocols section 6.5.7.10)

6. Primary Frequency Response (PFR) Requirements (Nodal Protocols section 8.5.1.1)

7. Sub-Synchronous Interaction (SSI) – Section 5 of ERCOT Planning Guides

Page 7: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

7

GINR ProjectName County

IA Capacity (MW)

FC Capacity (MW)

IA Signed Date

Projected COD

11INR0050 Moore Wind 1 Crosby 149 0 7/12/2012 8/8/201413INR0005 Conway Windfarm Carson 600 600 10/24/2012 12/1/201414INR0023 Longhorn Energy Center Briscoe 361 361 12/10/2012 12/1/201414INR0030a2 Panhandle Wind Carson 218 218 12/19/2012 8/1/201413INR0010a Mariah Wind Parmer 200 0 1/31/2013 10/30/201413INR0010b Mariah Wind Parmer 200 0 1/31/2013 12/31/201513INR0010c Mariah Wind Parmer 200 0 1/31/2013 12/31/201613INR0048 Spinning Spur Wind Two Oldham 161 161 2/27/2013 6/1/201414INR0012a Miami Wind 1 Project Gray 289 289 3/1/2013 7/31/201414INR0012b Miami Wind 1 Project Gray 112 0 3/1/2013 8/15/201513INR0059a Hereford Wind Castro 200 200 6/10/2013 9/4/201413INR0059b Hereford Wind Castro 300 300 6/10/2013 4/15/201512INR0029 Comanche Run Wind Swisher 500 0 7/24/2013 12/31/201614INR0030b Panhandle Wind (Ph2) Carson 182 182 10/2/2013 9/1/201414INR0032a Route66 Wind Randall 150 0 10/31/2013 12/1/201412INR0018 Pampa Wind Project Gray 500 0 11/12/2013 3/31/201714INR0053 Spinning Spur Wind Three Oldham 194 194 12/10/2013 12/31/2014

4,516 2,505

Panhandle Wind Signed IA ProjectsIA: Interconnection AgreementFC: Financial CommitmentCOD: Commercial Operating Day

Page 8: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

8

Roadmap- Panhandle Export LimitTransmission Upgrades needed

Page 9: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

9

Large Generator Interconnection Process Issues?

TimeCost

Transmission Reliability Limitations

Page 10: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

10

Resource Mapping

Collaboration

In Resource Development

Map the Resources

Provide Ancillary Services

OPTIMIZE

Page 11: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

11

Resource Side PlanningLessons Learned

Understanding of the intricate interconnection process and requirements is key to project success

Being informed about the transmission grid present and future limitations for choosing LOCATION for a resource

Collaboration amongst all Resource Sectors in sketching a map for successful co location of resources

E N E R G Y STO R A G E

HOUR OF DAY

Actual Load Cycle

STORAGE CHARGE

STORAGE DISCHARGE

Levelized Load Cycle

Page 12: Preparing for the unexpected: Transmission Planning in ERCOTpublish.generationhub.com/document/2014/02/03/TransF… ·  · 2014-02-03Preparing for the unexpected: Transmission Planning

12

QUESTIONS

Hala Ballouz, President

[email protected]