presentation 14 – guidance on financial analysis of cleaner production options 1 presentation 14...
TRANSCRIPT
1Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Presentation 14Presentation 14
Guidance on Financial Analysis of Cleaner Production Options
2Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
What will we learn here?
Guidance on Financial Analysis of Cleaner Production Options
Introduction: The Need for Financial Analysis
Objectives of this Presentation
Use of Cost Benefit Analysis in Financial Analysis
Introduction to Cost Benefit Analysis
Elements of Cost Benefit Analysis
Case Study #1
Case Study #2
Criteria for Selection of Projects
3Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Introduction: The Need for Financial Analysis
NextSlide
4Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Introduction: The Need for Financial Analysis
Cleaner production options not only avoid and reduce waste generation, but also offer a direct cost advantage to the business.
However, cleaner production options are typically long term, involving medium to high investment, and hence are perceived as a larger business risks than end-of-pipe solutions. The crux of the problem is that this risk is often not clearly quantified and predicted.
Thus, financial analysis of cleaner production options becomes necessary.
5Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Objectives of this Presentation
NextSlide
6Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Objectives of this Presentation
To understand the basics of financial analysis
To implement fundamental principles of financial analysis for cleaner production options
To screen cleaner production options based on financial aspects
7Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Introduction to Cost Benefit Analysis (CBA)
NextSlide
8Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Introduction to Cost Benefit Analysis (CBA)
• The costs and benefits (environmental, social or economic) must be quantified in monetary terms to the maximum extent possible. Typically, CBA is used as a tool in feasibility studies for selection of an alternative together with for e.g., life cycle assessment, audits, etc.
• Thus, CBA is used in financial analysis to estimate the profitability of a potential investment for a cleaner production option.
• CBA facilitates the comparison of alternatives in terms of the monetary costs involved and the benefits obtained.
9Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Elements of CBA
NextSlide
10Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Elements of CBA
Cash flow
Present value (PV)
Measures of Profitability
Payback Period
Net Present Value (NPV)
Internal Rate of Return (IRR)
Profitability Index
Depreciation
11Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Cash Flow
A Cash Flow is meant to illustrate incomes (“cash inflows”) and expenses (“cash outflows”). They may be conventional and non-conventional. Each arrow represents the time period of a year in this case.
Non-Conventional Cash Flow
-2Cash Inflows
Cash Outflows
$12,000
$7,500. . . . . . . . . . . . . . $7,500
$3,900 $2,600
-1 0
$10,000$8,000
8
Conventional Cash Flow
0 5Cash Inflows
Cash Outflows
$2,000
$600$600$600$600$600
12Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Present Value (PV)
PV is a way of comparing the value of money now with the value of money in the future. A dollar today is worth more than a dollar in the future, because inflation erodes the buying power of the future money, while money available today can be invested to grow.
Calculation of the PV requires the use of “interest rate”. Interest rate is typically a percentage used to calculate the PV. It reflects the time value of money. Generally, this interest rate is taken as equal to the prevailing bank interest rate.
Assuming an interest rate of 10%, the PV of $100 three years from now is approximately $133.
13Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Payback Period
As the name suggests, the Payback Period is the length of time required to recover the cost of an investment.
It is calculated with the formula below:Payback period = $ Invested
$ Return per year
Drawbacks -
The payback period ignores the time value of money
The payback period ignores cash flows after the initial investment has been recouped
14Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Payback Period
If the initial cost of the investment or $ invested = $ 20,000 and the net savings or $ return per year = $ 2,200; then
Payback period = 20,000 / 2,200 = 9.09 years
(say 9.1 years)
15Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Net Present Value (NPV)
NPV may be defined as the difference between the total present value of the cash inflows and the total present value of the cash outflows.
NPV compares the value of the dollar today versus the value of that same dollar in the future, after taking inflation and returns into account.
If the NPV of a prospective project is positive then it should be accepted (i.e. NPV > 0)
However, if the NPV of a prospective project is negative, then the project should be rejected because cash flows are negative (i.e. NPV < 0)
If the NPV of a prospective project is zero then it should probably be rejected as it generates exactly the return that is expected (i.e. NPV = 0)
16Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Net Present Value (NPV)
Let us calculate the NPV from a series of cash flows. The formula is given below.
NPV = -CFo + CF1 + CF2 + CF3 + CFn
(1+r)1 (1+r)2 (1+r)3 (1+r)n
where CFX = cash flow in year x, n = number of periods (n=3), r = interest rate (say, 10%)
NPV = -500,000 + 100,000 + 150,000 + 200,000 = -$134, 861 (1+0.1)1 (1+0.1)2 (1+0.1)3
0
$500,000
$100,000 $150,000 $200,000
3(positive cash flows)
(negative cash flow)
17Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Internal Rate of Return (IRR)
The IRR method of analyzing a project or option allows one to find the interest rate that is equivalent to the dollar returns expected from the project or option.
Once you know the IRR, you can compare it to the rates you could earn by investing your money in other projects or options.
If the IRR is less than the cost of borrowing used to fund the project, the project will clearly be a money-loser.
However, usually a business owner will insist that in order to be acceptable, a project must be expected to earn an IRR that is at least several percentage points higher than the cost of borrowing, to compensate the company for its risk, time, and trouble associated with the project.
18Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Internal Rate of Return (IRR)
As an example of how IRR works, let us say you are looking at a project costing $7,500 that is expected to return $2,000 per year for five years, or $10,000 in total. The IRR calculated for the project would be 10 percent.
If your cost of borrowing for the project is less than 10 percent, the project may be worthwhile.
If the cost of borrowing is 10 percent or greater, it will not make sense to do the project (at least from a financial perspective) because, at best, you will be breaking even.
19Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Internal Rate of Return (IRR)
The formula used for calculating the IRR is very similar to the formula used for calculating the NPV.
The main difference is that in the IRR formula, you must solve for the interest rate “r”.
0 = -CFo + CF1 + CF2 + CF3 + CFn
(1+r)1 (1+r)2 (1+r)3 (1+r)n
where CFX = cash flow in year x, n = number of periods, r = interest rate (to be solved for)
20Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Profitability Index (PI)
The PI is the ratio of the PV of future cash inflows by the PV of cash outflows
PI = PV of cash inflows PV of cash outflows
If the 0 < PI < 1, the project or option should be rejected
If the PI > 1, the project or option should be accepted
21Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Depreciation
Depreciation is defined as the decline in the value of an asset with the passage of time, due to general wear and tear or obsolescence
Depreciation is a part and parcel of cash flow calculations
Depreciation may be accounted for in the net annual savings of a cleaner production option
22Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case study #1
NextSlide
23Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1: Financial Analysis of a Cleaner Production Option in a Bottle Washing Plant
Background
Bottle washing plant BWP utilizes a large quantity of water and caustic soda for bottle washing and rinsing operations
As a cleaner production option, a certain percentage of the caustic soda is to be recovered from the resulting caustic solution, through the use of a membrane filtration (MF) system
The recovered caustic will then be resold at the prevailing market price
Let us examine the financial feasibility of installing the MF system
24Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 - Calculations for the Value of Recoverable Caustic ($ / year)
Data
* The overall caustic recovered from the MF system is 65% by volume
** The number of recovery runs at BWP is 4 times a year and the concentration of caustic by weight is 2.5% or 25 kg/m3
*** The cost of 1 kg of pure caustic solution is $0.5
Volume of caustic
(m3)“A”
Volume of caustic recovered per run*
(m3)“B” = “A” X 0.65
Mass of caustic recovered
per year** (kg/m3)“C” = “B” X 4 X 25
Value of caustic recovered per
year***($ / year) = “C” X
0.5
210 136.5 13,650 6,825
Table 1:
25Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Installation Cost for the MF System
System component
Cost ($)
Membrane 7,000
Feed pump 800
High pressure pump
1,600
Cartridge and power
400
Permeate tank 200
Pipes, valves, etc.
8,000
Total investment:
18,000
Table 2
In addition to the initial investment, the manufacturer states that the membrane for the MF system will need to be replaced once in 3 years. The associated cost for this will work out to be $7,500. The total life of the MF system is 12 years.
26Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 - Calculations for the Net Annual Uniform Savings
Net annual uniform savings =
Cost recovered from the sale of caustic annually – annual depreciation cost of the MF system – annual operating costs
Here, depreciation cost of the MF system (assuming nil salvage value at the end of the 12 year period = (18,000 – 0) / 12 = $1,500
Also, annual operating costs = cost for power and the cartridge = $400 (from Table 2)
So, net annual uniform savings = 6,825 – 1,500 – 400 = $4,925 (approx.)
27Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Cash Flow Diagram for the Proposed MF System
Cash Inflows (Net annual Uniform Savings)
Cash Outflows (Initial Investment and Replacement Cost)
0
12
$7,500 $7,500 $7,500$18,000
$4,925…………………………………………………………$4,925
Initial one-time investment = $18,000
Membrane replacement cost (once every 3 years) = $7,500
Net annual uniform savings = $4,925 / year
28Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Calculation for NPV
Assuming an interest rate of 10% ( r = 10 / 100 = 0.1), PV of cash inflows 12= 4,925 1 = $33,557 t=1 (1 + 0.1)t
PV of cash outflows = 18,000 + 7,500 + 7,500 + 7,500 = $31,049 (1+0.1)3 (1+0.1)6 (1+0.1)9
NPV = PV of cash inflows – PV of cash outflows = $33,557 - $31,049 = $2,508
Since the resultant NPV > 0, the cleaner production option is financially viable.
29Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Calculation for IRR
IRR would need to be solved through iteration:
12 0 = 4,925 1 – 18,000 – 7,500 – 7,500 – 7,500 t=1 (1+r)t (1+r)3 (1+r)6 (1+r)9
Taking r = 12% (i.e. 12/100 = 0.12), Left Hand Side (LHS) = 664.63
Taking r = 13% (i.e. 13/100 = 0.13), LHS = -152.49
30Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Solving for the Exact Value of IRR
Taking r = 12% (i.e. 12/100 = 0.12), LHS = 664.63
Taking r = 13% (i.e. 13/100 = 0.13), LHS = -152.49
Solving for the exact value of IRR through interpolation:
r – 12 = 0 – 664.63 r – 14 -152.49-664.63
IRR = 12.63%
Since the IRR is greater than 10% (i.e. the rate of interest that the money would earn in the bank, investing in this cleaner production option is worthwhile.
31Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #1 – Calculating the PI
Calculating for the PI:
PI = PV of cash inflows = 33,557 = 1.08 PV of cash outflows 31,049
Since PI > 1, this cleaner production option can be accepted; i.e. it is financially viable
32Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case study #2
NextSlide
33Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2: A Tweak on Case Study #1 (Pessimistic Scenario)
Background
The background for Case Study #2 stays the same as that for Case Study #1.
However, there will be one change… let us say, that the prevailing market price of the recovered caustic falls to $0.35 per kg (previously, for Case Study #1, the said value was $0.5 per kg).
Let us also say that the manufacturer’s claim for membrane replacement does not hold true, and that the membrane requires replacement once every two years.
Let us examine the financial feasibility of installing the MF system for Case Study #2.
34Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2 - Calculations for the Value of Recoverable Caustic (Pessimistic Scenario)
Data
* The overall caustic recovered from the MF system is 65% by volume
** The number of recovery runs at BWP is 4 times a year and the concentration of caustic by weight is 2.5% or 25 kg/m3
*** The cost of 1 kg of pure caustic solution is $0.35
Volume of caustic
(m3)“A”
Volume of caustic recovered per run*
(m3)“B” = “A” X 0.65
Mass of caustic recovered
per year** (kg/m3)“C” = “B” X 4 X 25
Value of caustic recovered per
year***($ / year) = “C” X
0.35
210 136.5 13,650 4,778
Table 3:
35Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2 - Calculations for the Net Annual Uniform Savings (Pessimistic Scenario)
Net annual uniform savings =
Cost recovered from the sale of caustic annually – annual depreciation cost of the MF system – annual operating costs
Here, depreciation cost of the MF system (assuming nil salvage value at the end of the 12 year period = (18,000–0)/12 = $1,500 (same as Case Study #1)
Also, annual operating costs = cost for power and the cartridge = $400 (from Table 2, same as Case Study #1)
So, net annual uniform savings = 4,778 – 1,500 – 400 = $2,878 (approx.)
36Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2 – Cash Flow Diagram for the Proposed MF System (Pessimistic Scenario)
Cash Inflows (Net annual Uniform Savings)
Cash Outflows (Initial Investment and Replacement Cost)
0
12
$7,500 $7,500 $7,500$18,000
$2,878…………………………………………………………$2,878
Initial one-time investment = $18,000
Membrane replacement cost (once every 2 years) = $7,500
Net annual uniform savings = $2,878/ year
$7,500$7,500
37Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2 – Calculation for NPV (Pessimistic Scenario)
Assuming an interest rate of 10% ( r = 10 / 100 = 0.1), PV of cash inflows 12= 2,878 1 = $19,610 t=1 (1 + 0.1)t
PV of cash outflows = 18,000 + 7,500 + 7,500 + 7,500 + 7,500 + 7,500 = $39,945 (1+0.1)2 (1+0.1)4 (1+0.1)6 (1+0.1)8 (1+0.1)10
NPV = PV of cash inflows – PV of cash outflows = $19,610 - $39,945 = - $20,335 (i.e. negative)
Since the resultant NPV < 0, the cleaner production option is not financially viable.
40Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Case Study #2 – Calculating the PI (Pessimistic Scenario)
Calculating for the PI:
PI = PV of cash inflows = 19,610 = 0.49 PV of cash outflows 39,945
Since PI > 1, this cleaner production option cannot be accepted; i.e. it is not financially viable
41Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Other Scenarios
Similarly, it is possible that there may be other pessimistic scenarios
In fact, there could be a permutation-combination of pessimistic scenarios, depending on the market and in-house conditions
The World Wide Web provides certain tools to calculate the NPV and IRR values
Thus the CBA becomes a very important tool is assessing the financial feasibility of the cleaner production project / option
Such analysis will help all concerned (CPC, business / enterprise / industry, financial institution, stakeholders in the option) decide on further steps to be taken for making a bankable project.
42Presentation 14 – Guidance on Financial Analysis of Cleaner Production Options
Thank you