presentation design & built
TRANSCRIPT
-
7/24/2019 Presentation Design & Built
1/39
Sunil PadmasekaraBSc(Eng),CPEng,MIE(Aust.),MIESL,MIEE(Japan),MSLEMA
Member of Association of Consulting Engineers Sri Lanka - (National body affiliated to the International Federation of ConsultingEngineers FIDIC)
1
-
7/24/2019 Presentation Design & Built
2/39
Definitions
Construction Contracts Types
Contract Documents - FIDIC
Design Build Contracts
D-B Contractor's Responsibility
Risks
Construction Insurances
Cost Variations
Post Contract Design Management
Sequence of Events
2
-
7/24/2019 Presentation Design & Built
3/39
Definitions:
Employer (=Client or Owner):
The firm who enters into a contract with a contractor forthe construction of the works
Engineer (=Consultant or Principal ):Any independentdesigner advisor or QS employed by a Contractor or
Client.
Contractor:The firm which undertaken the (design and)construction of the works.
Contract:
A legally binding agreement between two or more parties.
OFFER + ACCEPTANCE = AGREEMENT
3
-
7/24/2019 Presentation Design & Built
4/39
Construction Contracts:
What is a construction contract?
A contract can be defined as an agreement which is legally
binding document that describes the obligations, rights
(risks benefits) of the two parties(Privity in a Contract)
How are contracts formed?
Employer (Owner)issues Invitation for Bids (IFB)
Contractor prepares and submits Bid
Engineer (Consultant)reviews and accepts the Bid
A contract document is developed, reviewed, and
agreed upon by the Employer Contactor
The contract is signed by both parties(LegalBinding)
4
-
7/24/2019 Presentation Design & Built
5/39
A number of organizations prepare recommended
standard general conditions and associated forms of
Contracts.
Some of them are:
ENAA (Engineering Advancement Association of
Japan)
FIDIC (International Federation of Consulting
Engineers)
ICE (Institute of Civil Engineers, United Kingdom)
JCT (Joint Contracts Tribunal) United Kingdom
5
-
7/24/2019 Presentation Design & Built
6/39
Types of Construction Contracts:
1. Traditional Contracting (Develop
Construct)
2.
Design Build
6
-
7/24/2019 Presentation Design & Built
7/39
Types of Construction Contracts
Traditional Method- Develop & Construct
(or Design-Bid-Build)Develop the design detail from the Employers
design.
Owners design team will design the building
almost completely including obtaining
authorities' approvals/consent.
The Contractor is responsible only for theconstruction of Works.
Payment Method: Lump Sum or Schedule of
Rates basis. 7
-
7/24/2019 Presentation Design & Built
8/39
Design Build Contracts
D-B Contracts ate contractual arrangements whereby the contractor offer to do design and build a
project for a sum inclusive of both design and
construction cost.
Owners Design basically consists of performance,
requirements or design criteria of the MEP systems.
Only difference is level of contractors involvement
in Design Development is more with the TraditionalContracting Method.
8
-
7/24/2019 Presentation Design & Built
9/39
Construction Contracts:
FIDIC CONTRACTS (Standard Forms)
CONSTRUCTION
PLANT AND DESIGN-BUILD
EPC/TURNKEY PROJECTS
SHORT FORM OF CONTRACT
CLIENT/CONSULTANT MODEL SERVICES AGREEMENT
9
-
7/24/2019 Presentation Design & Built
10/3910
-
7/24/2019 Presentation Design & Built
11/39
The Red book(Design by Employer)
for Construction
The Yellow book-1999
Plant and Design-Build
The Silver book
EPC Turnkey Projects
The Green book(
-
7/24/2019 Presentation Design & Built
12/39
Design-Build Contracts: PLANT & DESIGN-BUILD
Contractor responsible for design
Engineer, working for the Employer
Provides Employers Requirements to which
contractor designs
Payment on Lump sum basis (against schedule
of payment)
Payments according to progress
Certification of payments by Engineer12
-
7/24/2019 Presentation Design & Built
13/39
Electrical & Mechanical Plant May include buildingand engineering
Design & Execution of works
Contractor designs and constructs inaccordance with Employers Requirements
Engineer Administers
13
-
7/24/2019 Presentation Design & Built
14/39
The Employer provides project requirements asdefined under item Employers Requirements (ER)
The ER are the basis for the contractor to designand build the project. Errors within the ER are the
liability of the Employer.
The contract is for a fixed sum and not re-measured.
The contract is administered on behalf of theEmployer by the Engineer,
Provision is made for variations by the Engineer.
The general conditions (clauses 1 to 20), exceptclauses 5 & 12, are principally the same as red book.
14
-
7/24/2019 Presentation Design & Built
15/39
-
7/24/2019 Presentation Design & Built
16/39
Employers Requirements (ER)
Fully describe the works or lay down theparameters which the contractor shalldesign the remaining parts of the works.
Means the document entitled employersrequirements (specifies the purpose,scope, and/or design and/or othertechnical criteria for the Works), asindicated in the contract, and any
additions and modifications to suchdocument according to the contract.
16
-
7/24/2019 Presentation Design & Built
17/39
Contractors Proposal CP):
Means the document describe the proposal which the
contractor submitted with the Letter of Tender, asincluded in the Contract. Such document may includeContractors preliminary design proposal also.
Fully describe the works or lay down the
Parameters
Design:Includes the drawings and specifications which definethe scope and nature of the works
17
-
7/24/2019 Presentation Design & Built
18/39
Design-Build ContractsFIDIC Condition of Construct The yellow Bookfor Plant and Design Build
Constructor responsible for the design of
the works and the plant. Lump Sum Contract with Payments from
the schedules
Employers Requirement, ContractorsProposal, Schedule of Payment andSchedule of Guarantees are key words.
The employer appoints an Engineer for
the Construct Administration. Provisions for variations
18
-
7/24/2019 Presentation Design & Built
19/39
Contract Documents of D&B Contract: A contract = Offer +Acceptance
Letter of Intent FIDIC contract document including Appendices,
1. Employers Requirements2. Contractors Proposal
3. Contract sum Analysis4. Optional Claims5. Appendices
Preparation of Contract Documents consisting of, Contract Drawings
Specification Time Schedule Schedule of Activities (Contract Bills)
19
FIDIC Y ll B k
-
7/24/2019 Presentation Design & Built
20/39
FIDIC-Yellow Book
Design-Build Contracts - Priority of Documents
The Contract Agreement
The Letter of Acceptance The Letter of Tender
The Particular Conditions
General Conditions
The Employers Requirements -ER(RB-specs) The Schedules (RB-Drawings)
The Contractors Proposal (CP)and any otherdocuments forming part of the contract
The documents of a tender are to be taken as mutually explanatory ofone another (complementary),but should there be discrepanciesthe contract may say that a stipulated order of superioritydetermines which part governs.
20
-
7/24/2019 Presentation Design & Built
21/39
Traditional(Design Bid
Build)
Design Build
(D-B)
D-B (Two -Stage)
D-B & Manage
Turnkey
Employers/OwnersInput
Contractors
Input
Different types of Contracting
Methods
21
-
7/24/2019 Presentation Design & Built
22/39
Design - Build (Two Stage Tender)
Owners design requirements are limited only
to Building information and usually consist of
accommodation/ usage requirements. No
MEP services drawings are available.
They rarely engage a design team and
contractor has to do complete design
proposal. Owner may, however, engage
consultants to assists in the design check/evaluation of contractors proposal.
22
-
7/24/2019 Presentation Design & Built
23/39
Design-Build & ManageThe owner selects a contractor at the inception stage
of the project by means other than competition, toundertake the complete design and construction ofproject.(At first it may seem strange for an owner to select a contractor withoutcompetition, but in practice many projects undertaken in this way. Owneragrees to pay target cost or a guaranteed maximum price.)
Owner usually adopts this method for one of thefollowing reasons.
1. A follow on contract is similar to earlier one
2. Due to lack of specialist contractors(MEPServices,etc)3. When the contractor has specific design
capabilities/ expertise.
23
-
7/24/2019 Presentation Design & Built
24/39
Turnkey (D&B + Financing)-Package DealsWhere the, Contractor does everything..
The owner has to do is Turn the Key to use hisbuilding
The owner, under a Turn Key contract, usually placesthe responsibility with the contractor for the
1. Complete Design
2. Construction
3. Fit out and T&C
till the contractor fulfill his responsibilities up tocompletion in response to the performance of theworks as a whole.
This form of contract usually applied to major powerplants, industrial plants, etc.
24
-
7/24/2019 Presentation Design & Built
25/39
Comparison of the different work stagesUSA System UK System (RIBA)
1. Concept A. Inception
B. Feasibility
2.Preparation
3.Brief
C. Outline Proposals
4.Design Development D. Scheme Design
E. Detail
F. Production Information
G. BOQ
5.Tender Documents and Tender
Action
H. Tender Action
J. Planning
K. Operation on Site
25
/
-
7/24/2019 Presentation Design & Built
26/39
Contractors Responsibilities/Risks(Legal Liability of D &B Contractor)
Clause 4.1 of FIDIC Yellow Book
Reasonable skill and care (D&B Contractors design proposal meet theapplicable standards expect from a professional designer)
& Professional negligence (Liable only for the defect which was a non-
negligent error)
Fitness for purpose, when completed the Works shall be fit for thepurposes for which the Works are intended as defined by the Employer's
Requirements. (tougher obligation to meet , some contracts performanceguarantee covers this requirement also)
(If design errors not fall under contractors negligence or beyond his reasonableskill and care , contractor must safeguard his position by pointing outshortcomings of Employers Requirements in the tender documents)
Design to comply with statutory Requirements In traditional contracting specialist contractors are usually nominated or at
least named by the architect. But In D-B contract, MEP Contractor assume fullresponsibility of his specialist subcontractors. Therefore, D_B Contractor mustensure about specialist subcons Design Responsibility requirements duringinitial stage of the project.
26
-
7/24/2019 Presentation Design & Built
27/39
Pricing Risk
In traditional contracting the BOQ is prepared by ownersQS and contractor prepares his costing according to theowners BOQ.
In contrast, the D-B contractor is entirely at risk for the
quantities which he measures. Pricing Risk to be evaluated:
Elimination of Omission and gaps.
Coordination between Elements.
Fees and other DB costs
Fees to the Local Authority Cost of tests
Cost of specialist consultants, Licensed engineers approvals
27
-
7/24/2019 Presentation Design & Built
28/39
Contract Documents by DB contractor (ContractorsProposal)
Basically 4 parts (they should fully describe the scope of works / or laydown parameter for designing remaining parts of the works to thegeneral aspects)
1. Drawings2. Schedules3. Particular specification and Scope of work
4. General specification
Check if the Owners Requirements contains a clause such as willprovide materials, etc of the best standards available or That willbe fir for the purpose intended
The contract sum BOQ in contract document, better to include costdata to be used for valuing variation or/and calculating variation (ifapply) or calculate monthly bill during construction period of theproject.
28
-
7/24/2019 Presentation Design & Built
29/39
Design Build Contract Forms:1. FIDIC Yellow Book-19992. BS/JCT 1981
Letter of Intent (LOI) Once an owner and a contractor reached agreement in
principle, the owner will normally issue a letter, to thecontractor, this letter is usually called a Letter of Intent
The contractor should check the contents of the letter ofIntent carefully to satisfy him on the following question.
1. What if the work get delay due to owners / Maincontractors decisions/delays? Will the contract acceptthe penalties?
2.
Does the LOI cover for ordering materials/equipments?3. The contractor will need to check with his specialist sub contractors about back to back design responsibilities.
29
What do the FIDIC contract forms cover ?
-
7/24/2019 Presentation Design & Built
30/39
The 20 common clauses / sections in all FIDIC contract forms are
1. general provisions, definitions,
2. employers (owners) responsibilities
3. contract administration procedures, day works and changes in law
4. contractors general obligations
5. design obligations and documents
6. staff and labour requirements
7. plant materials workmanship
8. time, program, progress and delays
9. completion tests
10.hand over requirements
11.defects and costs
12.tests after completion
13.Variations
14.payments, certificates and contract sum
15.termination by the owner / employer
16.termination by the contractor
17.risks responsibilities limits of liability
18.insurance requirements
19.force majeure, notices, consequences
20.claims, disputes, arbitration
30
-
7/24/2019 Presentation Design & Built
31/39
31
-
7/24/2019 Presentation Design & Built
32/39
CAR
CONTRACTOR ALL RISK
Damages to the
Work
PlantMaterials
(By Negligence Fire,
Whether. etc.)
Against Liability for Injury
(Accident), Death to persons
employed by the
contractor
CLIENT
PUBLIC LIABILITY
Damages to public
not associated with
the work
PROFESSIONAL
INDEMNITY
(For Design party)
Design problems
(BY SUB CONTRACTOR)
Workmen Compensation
(Sub / MEP Contractor)
Damages to sub construction works
Or property (Vehicles, Plant)
CONSTRUCTION INSURANCE
Associated
with the
works
1 2
3
4
1
3
4
Usually by General Contractor2
Design Party (by consultant or D-B contractor)
Sub Contractor
RESPONSIBILITY
32
-
7/24/2019 Presentation Design & Built
33/39
Contractors Works:insurance against damage orloss of the construction works Public Liability: against liability which causes
property damage to others or personal injury tothird party.
Workers Compensation: liability against death orinjury of contractors own employees (on the jobor in transit to or from it).
Professional Indemnity-coverage for Design work Contractors Plants Marine-Sea Freight Equip & Material supply Transit- Coverage for goods and equipment
transported by air or road.
33
-
7/24/2019 Presentation Design & Built
34/39
Bid Bonds: guarantee that the tenderer will carry
out the work ( to cover the cost of tenderingprocedure) Performance Bond: guarantee that the contract
will be completed as per the contract Payment Bond:gurantee that contractors,
suppliers and workers will be paid Warranty Bonds: guarantee that the warranties
will be honoured and that maintenance will becarried out.
Indemnity- Promise , only one party is liable
Bond-Promise ,Both has liability (Collateral) Novation: Risk undertaken by 3 parties.(Risk between Employer & Main Contractor
followed through to the Sub Contractor).
34
-
7/24/2019 Presentation Design & Built
35/39
Contract Doc. Check Items (By D-B Contractor)1. Discrepancies within the document and
Contractors proposal.
2. Element or requirements which may have beenintroduced and not provided for in the contract sum
3. The inclusion of any provisional sums by the owner4. Any additional risk or costs to be covered (as part of
the contract)more than the previous agreementbetween owner and DB contractor.
Once a contract is signed, the DB contractor will have
no redress if he failed to notice anything contained inthe owners requirements that could cause him lossand expense for which he had made no provision inthe contract sum.
35
-
7/24/2019 Presentation Design & Built
36/39
Cost Variation of the DB Contract(One of the greatest drawbacks of the DB system)
Variation may occur due to changes of Employersrequirements-ER (addition or omission to the originally
agreed scope of work).
Some variations are due to new Authority
requirements (Reimbursement of the addition cost tothe contractor depends on term of the contract).
Normally variation will add cost + time to the
programmed.
But some may reduce the cost + time (VE Inputs duringDesign Development stage).
36
-
7/24/2019 Presentation Design & Built
37/39
-
7/24/2019 Presentation Design & Built
38/39
Issue of
the
Tender
Document
s
Submission
of the
Tender
Issue of the
Letter of
Acceptance
8.1 Com-
mencement
Date
TenderPeriod
8.2 Time For Completion1
28d 28d
4.2 Issue ofthePerformanceSecurity
Base
Date
9.1 Testson2Compltion. . .
Delay attributableto the Contractor
PRACTICAL
HANDING
OVER
10.1 Issue of
Taking-Over
Certificate
Defects Notification Period3
11.9 Issue of
Performance
Certificate
-
7/24/2019 Presentation Design & Built
39/39