presentation design & built

Upload: madurangaglt

Post on 23-Feb-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Presentation Design & Built

    1/39

    Sunil PadmasekaraBSc(Eng),CPEng,MIE(Aust.),MIESL,MIEE(Japan),MSLEMA

    Member of Association of Consulting Engineers Sri Lanka - (National body affiliated to the International Federation of ConsultingEngineers FIDIC)

    1

  • 7/24/2019 Presentation Design & Built

    2/39

    Definitions

    Construction Contracts Types

    Contract Documents - FIDIC

    Design Build Contracts

    D-B Contractor's Responsibility

    Risks

    Construction Insurances

    Cost Variations

    Post Contract Design Management

    Sequence of Events

    2

  • 7/24/2019 Presentation Design & Built

    3/39

    Definitions:

    Employer (=Client or Owner):

    The firm who enters into a contract with a contractor forthe construction of the works

    Engineer (=Consultant or Principal ):Any independentdesigner advisor or QS employed by a Contractor or

    Client.

    Contractor:The firm which undertaken the (design and)construction of the works.

    Contract:

    A legally binding agreement between two or more parties.

    OFFER + ACCEPTANCE = AGREEMENT

    3

  • 7/24/2019 Presentation Design & Built

    4/39

    Construction Contracts:

    What is a construction contract?

    A contract can be defined as an agreement which is legally

    binding document that describes the obligations, rights

    (risks benefits) of the two parties(Privity in a Contract)

    How are contracts formed?

    Employer (Owner)issues Invitation for Bids (IFB)

    Contractor prepares and submits Bid

    Engineer (Consultant)reviews and accepts the Bid

    A contract document is developed, reviewed, and

    agreed upon by the Employer Contactor

    The contract is signed by both parties(LegalBinding)

    4

  • 7/24/2019 Presentation Design & Built

    5/39

    A number of organizations prepare recommended

    standard general conditions and associated forms of

    Contracts.

    Some of them are:

    ENAA (Engineering Advancement Association of

    Japan)

    FIDIC (International Federation of Consulting

    Engineers)

    ICE (Institute of Civil Engineers, United Kingdom)

    JCT (Joint Contracts Tribunal) United Kingdom

    5

  • 7/24/2019 Presentation Design & Built

    6/39

    Types of Construction Contracts:

    1. Traditional Contracting (Develop

    Construct)

    2.

    Design Build

    6

  • 7/24/2019 Presentation Design & Built

    7/39

    Types of Construction Contracts

    Traditional Method- Develop & Construct

    (or Design-Bid-Build)Develop the design detail from the Employers

    design.

    Owners design team will design the building

    almost completely including obtaining

    authorities' approvals/consent.

    The Contractor is responsible only for theconstruction of Works.

    Payment Method: Lump Sum or Schedule of

    Rates basis. 7

  • 7/24/2019 Presentation Design & Built

    8/39

    Design Build Contracts

    D-B Contracts ate contractual arrangements whereby the contractor offer to do design and build a

    project for a sum inclusive of both design and

    construction cost.

    Owners Design basically consists of performance,

    requirements or design criteria of the MEP systems.

    Only difference is level of contractors involvement

    in Design Development is more with the TraditionalContracting Method.

    8

  • 7/24/2019 Presentation Design & Built

    9/39

    Construction Contracts:

    FIDIC CONTRACTS (Standard Forms)

    CONSTRUCTION

    PLANT AND DESIGN-BUILD

    EPC/TURNKEY PROJECTS

    SHORT FORM OF CONTRACT

    CLIENT/CONSULTANT MODEL SERVICES AGREEMENT

    9

  • 7/24/2019 Presentation Design & Built

    10/3910

  • 7/24/2019 Presentation Design & Built

    11/39

    The Red book(Design by Employer)

    for Construction

    The Yellow book-1999

    Plant and Design-Build

    The Silver book

    EPC Turnkey Projects

    The Green book(

  • 7/24/2019 Presentation Design & Built

    12/39

    Design-Build Contracts: PLANT & DESIGN-BUILD

    Contractor responsible for design

    Engineer, working for the Employer

    Provides Employers Requirements to which

    contractor designs

    Payment on Lump sum basis (against schedule

    of payment)

    Payments according to progress

    Certification of payments by Engineer12

  • 7/24/2019 Presentation Design & Built

    13/39

    Electrical & Mechanical Plant May include buildingand engineering

    Design & Execution of works

    Contractor designs and constructs inaccordance with Employers Requirements

    Engineer Administers

    13

  • 7/24/2019 Presentation Design & Built

    14/39

    The Employer provides project requirements asdefined under item Employers Requirements (ER)

    The ER are the basis for the contractor to designand build the project. Errors within the ER are the

    liability of the Employer.

    The contract is for a fixed sum and not re-measured.

    The contract is administered on behalf of theEmployer by the Engineer,

    Provision is made for variations by the Engineer.

    The general conditions (clauses 1 to 20), exceptclauses 5 & 12, are principally the same as red book.

    14

  • 7/24/2019 Presentation Design & Built

    15/39

  • 7/24/2019 Presentation Design & Built

    16/39

    Employers Requirements (ER)

    Fully describe the works or lay down theparameters which the contractor shalldesign the remaining parts of the works.

    Means the document entitled employersrequirements (specifies the purpose,scope, and/or design and/or othertechnical criteria for the Works), asindicated in the contract, and any

    additions and modifications to suchdocument according to the contract.

    16

  • 7/24/2019 Presentation Design & Built

    17/39

    Contractors Proposal CP):

    Means the document describe the proposal which the

    contractor submitted with the Letter of Tender, asincluded in the Contract. Such document may includeContractors preliminary design proposal also.

    Fully describe the works or lay down the

    Parameters

    Design:Includes the drawings and specifications which definethe scope and nature of the works

    17

  • 7/24/2019 Presentation Design & Built

    18/39

    Design-Build ContractsFIDIC Condition of Construct The yellow Bookfor Plant and Design Build

    Constructor responsible for the design of

    the works and the plant. Lump Sum Contract with Payments from

    the schedules

    Employers Requirement, ContractorsProposal, Schedule of Payment andSchedule of Guarantees are key words.

    The employer appoints an Engineer for

    the Construct Administration. Provisions for variations

    18

  • 7/24/2019 Presentation Design & Built

    19/39

    Contract Documents of D&B Contract: A contract = Offer +Acceptance

    Letter of Intent FIDIC contract document including Appendices,

    1. Employers Requirements2. Contractors Proposal

    3. Contract sum Analysis4. Optional Claims5. Appendices

    Preparation of Contract Documents consisting of, Contract Drawings

    Specification Time Schedule Schedule of Activities (Contract Bills)

    19

    FIDIC Y ll B k

  • 7/24/2019 Presentation Design & Built

    20/39

    FIDIC-Yellow Book

    Design-Build Contracts - Priority of Documents

    The Contract Agreement

    The Letter of Acceptance The Letter of Tender

    The Particular Conditions

    General Conditions

    The Employers Requirements -ER(RB-specs) The Schedules (RB-Drawings)

    The Contractors Proposal (CP)and any otherdocuments forming part of the contract

    The documents of a tender are to be taken as mutually explanatory ofone another (complementary),but should there be discrepanciesthe contract may say that a stipulated order of superioritydetermines which part governs.

    20

  • 7/24/2019 Presentation Design & Built

    21/39

    Traditional(Design Bid

    Build)

    Design Build

    (D-B)

    D-B (Two -Stage)

    D-B & Manage

    Turnkey

    Employers/OwnersInput

    Contractors

    Input

    Different types of Contracting

    Methods

    21

  • 7/24/2019 Presentation Design & Built

    22/39

    Design - Build (Two Stage Tender)

    Owners design requirements are limited only

    to Building information and usually consist of

    accommodation/ usage requirements. No

    MEP services drawings are available.

    They rarely engage a design team and

    contractor has to do complete design

    proposal. Owner may, however, engage

    consultants to assists in the design check/evaluation of contractors proposal.

    22

  • 7/24/2019 Presentation Design & Built

    23/39

    Design-Build & ManageThe owner selects a contractor at the inception stage

    of the project by means other than competition, toundertake the complete design and construction ofproject.(At first it may seem strange for an owner to select a contractor withoutcompetition, but in practice many projects undertaken in this way. Owneragrees to pay target cost or a guaranteed maximum price.)

    Owner usually adopts this method for one of thefollowing reasons.

    1. A follow on contract is similar to earlier one

    2. Due to lack of specialist contractors(MEPServices,etc)3. When the contractor has specific design

    capabilities/ expertise.

    23

  • 7/24/2019 Presentation Design & Built

    24/39

    Turnkey (D&B + Financing)-Package DealsWhere the, Contractor does everything..

    The owner has to do is Turn the Key to use hisbuilding

    The owner, under a Turn Key contract, usually placesthe responsibility with the contractor for the

    1. Complete Design

    2. Construction

    3. Fit out and T&C

    till the contractor fulfill his responsibilities up tocompletion in response to the performance of theworks as a whole.

    This form of contract usually applied to major powerplants, industrial plants, etc.

    24

  • 7/24/2019 Presentation Design & Built

    25/39

    Comparison of the different work stagesUSA System UK System (RIBA)

    1. Concept A. Inception

    B. Feasibility

    2.Preparation

    3.Brief

    C. Outline Proposals

    4.Design Development D. Scheme Design

    E. Detail

    F. Production Information

    G. BOQ

    5.Tender Documents and Tender

    Action

    H. Tender Action

    J. Planning

    K. Operation on Site

    25

    /

  • 7/24/2019 Presentation Design & Built

    26/39

    Contractors Responsibilities/Risks(Legal Liability of D &B Contractor)

    Clause 4.1 of FIDIC Yellow Book

    Reasonable skill and care (D&B Contractors design proposal meet theapplicable standards expect from a professional designer)

    & Professional negligence (Liable only for the defect which was a non-

    negligent error)

    Fitness for purpose, when completed the Works shall be fit for thepurposes for which the Works are intended as defined by the Employer's

    Requirements. (tougher obligation to meet , some contracts performanceguarantee covers this requirement also)

    (If design errors not fall under contractors negligence or beyond his reasonableskill and care , contractor must safeguard his position by pointing outshortcomings of Employers Requirements in the tender documents)

    Design to comply with statutory Requirements In traditional contracting specialist contractors are usually nominated or at

    least named by the architect. But In D-B contract, MEP Contractor assume fullresponsibility of his specialist subcontractors. Therefore, D_B Contractor mustensure about specialist subcons Design Responsibility requirements duringinitial stage of the project.

    26

  • 7/24/2019 Presentation Design & Built

    27/39

    Pricing Risk

    In traditional contracting the BOQ is prepared by ownersQS and contractor prepares his costing according to theowners BOQ.

    In contrast, the D-B contractor is entirely at risk for the

    quantities which he measures. Pricing Risk to be evaluated:

    Elimination of Omission and gaps.

    Coordination between Elements.

    Fees and other DB costs

    Fees to the Local Authority Cost of tests

    Cost of specialist consultants, Licensed engineers approvals

    27

  • 7/24/2019 Presentation Design & Built

    28/39

    Contract Documents by DB contractor (ContractorsProposal)

    Basically 4 parts (they should fully describe the scope of works / or laydown parameter for designing remaining parts of the works to thegeneral aspects)

    1. Drawings2. Schedules3. Particular specification and Scope of work

    4. General specification

    Check if the Owners Requirements contains a clause such as willprovide materials, etc of the best standards available or That willbe fir for the purpose intended

    The contract sum BOQ in contract document, better to include costdata to be used for valuing variation or/and calculating variation (ifapply) or calculate monthly bill during construction period of theproject.

    28

  • 7/24/2019 Presentation Design & Built

    29/39

    Design Build Contract Forms:1. FIDIC Yellow Book-19992. BS/JCT 1981

    Letter of Intent (LOI) Once an owner and a contractor reached agreement in

    principle, the owner will normally issue a letter, to thecontractor, this letter is usually called a Letter of Intent

    The contractor should check the contents of the letter ofIntent carefully to satisfy him on the following question.

    1. What if the work get delay due to owners / Maincontractors decisions/delays? Will the contract acceptthe penalties?

    2.

    Does the LOI cover for ordering materials/equipments?3. The contractor will need to check with his specialist sub contractors about back to back design responsibilities.

    29

    What do the FIDIC contract forms cover ?

  • 7/24/2019 Presentation Design & Built

    30/39

    The 20 common clauses / sections in all FIDIC contract forms are

    1. general provisions, definitions,

    2. employers (owners) responsibilities

    3. contract administration procedures, day works and changes in law

    4. contractors general obligations

    5. design obligations and documents

    6. staff and labour requirements

    7. plant materials workmanship

    8. time, program, progress and delays

    9. completion tests

    10.hand over requirements

    11.defects and costs

    12.tests after completion

    13.Variations

    14.payments, certificates and contract sum

    15.termination by the owner / employer

    16.termination by the contractor

    17.risks responsibilities limits of liability

    18.insurance requirements

    19.force majeure, notices, consequences

    20.claims, disputes, arbitration

    30

  • 7/24/2019 Presentation Design & Built

    31/39

    31

  • 7/24/2019 Presentation Design & Built

    32/39

    CAR

    CONTRACTOR ALL RISK

    Damages to the

    Work

    PlantMaterials

    (By Negligence Fire,

    Whether. etc.)

    Against Liability for Injury

    (Accident), Death to persons

    employed by the

    contractor

    CLIENT

    PUBLIC LIABILITY

    Damages to public

    not associated with

    the work

    PROFESSIONAL

    INDEMNITY

    (For Design party)

    Design problems

    (BY SUB CONTRACTOR)

    Workmen Compensation

    (Sub / MEP Contractor)

    Damages to sub construction works

    Or property (Vehicles, Plant)

    CONSTRUCTION INSURANCE

    Associated

    with the

    works

    1 2

    3

    4

    1

    3

    4

    Usually by General Contractor2

    Design Party (by consultant or D-B contractor)

    Sub Contractor

    RESPONSIBILITY

    32

  • 7/24/2019 Presentation Design & Built

    33/39

    Contractors Works:insurance against damage orloss of the construction works Public Liability: against liability which causes

    property damage to others or personal injury tothird party.

    Workers Compensation: liability against death orinjury of contractors own employees (on the jobor in transit to or from it).

    Professional Indemnity-coverage for Design work Contractors Plants Marine-Sea Freight Equip & Material supply Transit- Coverage for goods and equipment

    transported by air or road.

    33

  • 7/24/2019 Presentation Design & Built

    34/39

    Bid Bonds: guarantee that the tenderer will carry

    out the work ( to cover the cost of tenderingprocedure) Performance Bond: guarantee that the contract

    will be completed as per the contract Payment Bond:gurantee that contractors,

    suppliers and workers will be paid Warranty Bonds: guarantee that the warranties

    will be honoured and that maintenance will becarried out.

    Indemnity- Promise , only one party is liable

    Bond-Promise ,Both has liability (Collateral) Novation: Risk undertaken by 3 parties.(Risk between Employer & Main Contractor

    followed through to the Sub Contractor).

    34

  • 7/24/2019 Presentation Design & Built

    35/39

    Contract Doc. Check Items (By D-B Contractor)1. Discrepancies within the document and

    Contractors proposal.

    2. Element or requirements which may have beenintroduced and not provided for in the contract sum

    3. The inclusion of any provisional sums by the owner4. Any additional risk or costs to be covered (as part of

    the contract)more than the previous agreementbetween owner and DB contractor.

    Once a contract is signed, the DB contractor will have

    no redress if he failed to notice anything contained inthe owners requirements that could cause him lossand expense for which he had made no provision inthe contract sum.

    35

  • 7/24/2019 Presentation Design & Built

    36/39

    Cost Variation of the DB Contract(One of the greatest drawbacks of the DB system)

    Variation may occur due to changes of Employersrequirements-ER (addition or omission to the originally

    agreed scope of work).

    Some variations are due to new Authority

    requirements (Reimbursement of the addition cost tothe contractor depends on term of the contract).

    Normally variation will add cost + time to the

    programmed.

    But some may reduce the cost + time (VE Inputs duringDesign Development stage).

    36

  • 7/24/2019 Presentation Design & Built

    37/39

  • 7/24/2019 Presentation Design & Built

    38/39

    Issue of

    the

    Tender

    Document

    s

    Submission

    of the

    Tender

    Issue of the

    Letter of

    Acceptance

    8.1 Com-

    mencement

    Date

    TenderPeriod

    8.2 Time For Completion1

    28d 28d

    4.2 Issue ofthePerformanceSecurity

    Base

    Date

    9.1 Testson2Compltion. . .

    Delay attributableto the Contractor

    PRACTICAL

    HANDING

    OVER

    10.1 Issue of

    Taking-Over

    Certificate

    Defects Notification Period3

    11.9 Issue of

    Performance

    Certificate

  • 7/24/2019 Presentation Design & Built

    39/39