Page 1: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Namaste and Good Afternoon ! 

Presentation from Nepal UNESCAP_Kazakhstan, Dec 2017

Aman ChitrakarDevi Prasad Sharma

Page 2: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

TIMELINE

• 1927: Raxaul Amlekhgunj Railway construction started and was in operation till 1970 AD

• 1937: Feb 16 Jaynagar‐Janakpur‐Bijalpura 51 km came into operation but in the year 2000 due to washout of Bigi Bridge, the service remained limited only to Janakpur (29km)

2

Page 3: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Initiatives• 2006: Nepal signed Trans Asian Railways (TAR) Agreement

• 2008: East West Electrified Railway Project Office Established.

• 2009: Feasibility study of East‐West(945km), Kathmandu ‐Pokhara(187km), Anbukhaireni‐Bharatpur link(72km) completed.

• 2010 : MoU between GOI and GON signed for cross border 

railway connectivity at 5 different locations.

3

Page 4: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Contd,

• 2011 : In June 15 Department of Railways established.

• 2012 :Feasibility study of KTM Valley MRT completed

• 2013 : Detailed Project Report of Simara‐Bardibas and Birgunj link completed (136km)

• 2014 : Construction Began for track bed, RUB and ROB in Bardibas‐Lalbandi section 

4

Page 5: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

5

Nepal became a member of Trans Asian Railways (TAR)GoN signed on 10 November, 2006

Ratification on 6 March, 2012 

`

Page 6: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

6

National Plan of Railroad

China

India

Page 7: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Railway length as per Feasibility Study Report (2008)

7

Section Length (km)MechI-Mahakali 945

Kathmandu-Pokhara 187

Anbukhaireni-Tamsaria 72

Simra-Birgunj 33

Butwal –Bhairhwa-Lumbini 44

Kohalpur - Nepalgunj 14

Itahari-Biratnagar 22

Total 1317

Page 8: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Cross Border Railway Project Progress

1. Jaynagar‐ Janakpu‐Bardibas ( 69km) 

80% of Earthwork and Culverts completed, 50% of Bridge works complete, Station Building works are underway  in Jaynagar‐Janakpur Section,

65% of Earthwork and Culverts completed, 20% of Bridge works complete, Station Building works are underway  in Janakpur‐Bijalpura Section

Construction of Staff’s quarters are in progress

Recently started with Track laying work8

Page 9: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Cross border Railway Projects Contd.

2. Bathnaha‐Jobbani‐Biratnagar (5+13km)

Track bed, bridge and culvert works in progress.

Station Building and staff’s quarters in progress.

9

Page 10: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

• Towards implementation of the consensus reached by theleaders of China and Nepal, a delegation team comprisingof members from National Railway Administration (NRA) ofPRC and other related agencies of China, visited Nepal from6‐10 Nov 2017.

• During this visit, the NRA delegation held meetings withthe Secretary and the Senior Officials of Ministry ofPhysical Infrastructure and Transport (MoPIT)andDepartment of Railways in Nepal.

• The delegation team also conducted some field survey.

10

Page 11: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Progress  Achieved till date DPR Preparation : Bardibas‐Butwal – 300 km, Simara‐Birgunj 28 km, Butawal –Lumbini 44 km completed. 

Bardibas‐Kakarvitta including Itahari Biratnagar Link (262 km) completed.

Butwal ‐Mahakali Section (412km) is underway.

Feasibility Study of Nijgadh‐Hetauda‐Bharatpur completed in Sep 2016 and Kathmandu‐Birgunj is under evaluation process

11

Page 12: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction: (East‐West Railway)

Construction of Trackbed, RUB and Bridges in the 30 kmsection of East West Railway (Bardibas‐Lalbandi) are ongoing

12

Page 13: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction Works in Cross Border Links

Page 14: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Jaynagar Station

Construction Works in Cross Border Links

Page 15: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

STATION BUILDING AT JAYNAGAR

Construction Works in Cross Border Links

Page 16: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction Works in East West Railway

Railway Bridge

Page 17: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction Works in East West Railway

Embankment Filling

Page 18: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction Works in East West Railway

Slope Compaction

Page 19: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Construction Works in East West Railway

Bio-Engineering

Page 20: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

20

Page 21: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

21

Page 22: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Freight Service component• Operated under India‐Nepal Rail Service Agreement. 

• Rail service between Kolkata/Haldia(India)‐Birganj(Nepal) via Raxaul(India) inter‐change

• This 5 km long Broad Gauge rail service is connected with ICD of Nepal.

• Out of 5 km long only about 800 m is in Nepal.• Agreement prevail Transit Traffic to and from Birganj ICD(Nepal) and Kolkata/Haldia (India) and Visakhapatnam (India).

Page 23: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Contd..

• Open timing, without any published schedules • There is no passenger service on this  section.• Railway receipt is the transport documents for carriage of goods issued from Kolkata.

• Transit Customs procedure and specific documents are mention on annexure of agreement.   

• Duty secured bond and /or a bank guarantee required.   

Page 24: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Contd..• One time lock provision on all Export and Import container.

• Preparation of CTD automation and electronic exchange of documents is going on.

• HTPL is working as TMC at ICD Birganj. • Total service of last three year,  

Year No of TEUS Break bulk cargo

2016‐17 25733  962035 MT.

2015‐16 36604 1150671 MT

2014‐15 22104 682862 MT

Page 25: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Import Procedure

Page 26: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Export Produre

Page 27: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

Nepal Custom Procedure

Authorize Customs Agent or Representative Declare electronically with Invoice, B/L, CTD, Packing list, Insurance, L/C or payment documents, CO

Authorize Customs Agent or Representative Declare electronically with Invoice, B/L, CTD, Packing list, Insurance, L/C or payment documents, CO 

Custom Office

Customs Office Verification and 

Assessment Payment of Duty Get pass by 

Customs for Exit

Verify by HTPL for release Cargo Documents from shipping agent, Documents from CONCOR, Customs House Paper and Nepal Customs paper/ Get Pass. 

Page 28: Presentation from Nepal - UN ESCAP · Birganj(Nepal) via Raxaul(India) inter‐change • This 5 km long Broad Gauge rail service is connected with ICD of Nepal. • Out of 5 km long

28

Thank You !