presentation instalaciones special mep facilities
TRANSCRIPT
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
1/80
COMPANY
PROFILE
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
2/80
Our strategy for the future is to achieve and maintain a clear leadership
position in all the activities, through our services quality, our market shareand our high profitability.
b
Our Group has already more than 68 years of experience and our humanresources comprise an extensive network of 180 Branch Offices in Spain and
48 abroad, with 17,102 highly skilled professionals.
Our matrix organization is formed by specialized Business Head Offices thatsupport our services-activities of engineering, construction, operation,installation and maintenance of the industrial facilities and powerinfrastructures, and which allows us to undertake any project with totalefficiency and capability anywhere in the world.
COBRA Group:
C/Cardenal Marcelo Spínola, 10
28016 Madrid
Tel 91 456 95 00
http://www.presentationpoint.de/http://www.presentationpoint.de/http://www.presentationpoint.de/http://www.presentationpoint.de/http://www.presentationpoint.de/http://www.presentationpoint.de/
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
3/80
Main Group’s Subsidiaries
A total of 180 Branch Offices are distributed throughout the national territory in order to carry out theactivities of each Business Area.
• ANDASOL-1, S.A.
• ATIL-COBRA, S.A.• CALIFORNIA SUN POWER LLC
• CATALANA DE TREBALLS PUBLICS, S.A.
• CENTRAL TÉRMICA DE MEJILLONES, S.A.
• COBRA CONCESIONES, S.L.
• COBRA GESTIÓN DE INFRAESTRUCTURAS, S.L.
• COBRA INFRAESTRUCTURAS HIDRÁULICAS, S.A
•COBRA INGENIERÍA DE MONTAJES, S.A.
• COBRA INSTALACIONES Y SERVICIOS, S.A.
• COBRA INVERSIONES Y GESTIÓN, S.L.
• COBRA SERVICIOS AUXILIARES, S.A.
• COBRA SISTEMAS DE SEGURIDAD, S.A.
• COBRA SISTEMAS Y REDES, S.A.
• COBRA UDISPORT
•DEPURADORAS DEL BAJO ARAGÓN
• ENERGÍA Y RECURSOS AMBIENTALES, S.A.
• GEROVITAE LA GUANCHA, S.A.
• GLOBAL SPA, S.L.• HUMICLIMA, S.A.
• HIDRAULICA DE MENDRE, S.A.
• IBEROAMERICANA DE HIDROCARBUROS, S.A.
• INFRAESTRUCTURAS ENERGÉTICAS ARAGONESAS, S.L.
• INJAR, S.A.
• MENCLI, SAU
• MONCOBRA, S.A.• PROCME, S.A.
• SERVICIOS Y OBRAS COMUNITARIAS, S.A.
• TECNOTEL CLIMA, S.L.
• TEDRA AUSTRALIA
• OPADE, S.A.
• SERPISTA, S.A.
•TECNICAS DE DESALINIZACIÓN DE AGUAS, S.A.
• URBAENERGÍA, S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
4/80
STAFF EVOLUTION (No. of Employees)
Human Resources
COBRA’s Human Resources are distributed on a wide network formed by 200 Branch Offices in Spain and other 60abroad. A total of 8,438 employees are working in countries of America, Europe, Africa, Asia and Oceania.
2321,068
797
2,916
1,101
10,988
Management
Engineers
Graduated
Technicians
Administratives
Other
7,344 7,5798,184
8,6399,973
12,01312,275
12,84713,887
16,17717,102
0
2.000
4.000
6.000
8.000
10.000
12.000
14.000
16.000
18.000
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
5/80
Annual Turnover (Dec, 2011)
(M €)
AUXILIARY SERVICES
INSTALLATIONS &
MAINTENANCE
INTEGRATED PROJECTS
Europe16.5%
OECDMembers
47.6%
Others35.9%
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Estim. 2012
1,2511,377
1,5951,733
2,131
2,7983,120
3,514
3,866 3,903
4,238
National
45.9
Export
54.1
39.5%13.9%
46.6%
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
6/80
International Markets
In 1978 Cobra group appeared on the international scene, in Saudi Arabia with the construction ofOHV Line for an Oil Company. Immediately, new contracts in Libya, United Arab Emirates and Omanwere awarded.
Today, the COBRA group is present in five continents.
Permanent Branch Offices in 22 countries, allowing us to better offer our wide range ofservices .
Execution of large projects: EPC, BOT, Concessions, etc. anywhere in the world.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
7/80
BUSINESS AREAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
8/80
INSTALLATIONS &
MAINTENANCE
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
9/80
Annual Turnover
Evolution and Distribution (Dec, 2011)
(M €)
INSTALLATIONS
48.2%
MAINTENANCE
12.8%
ENGINEERING0.4%
MECHANICAL WORKS
19.9%
AIR CONDITIONING
14.7%
AIRPORTS
3.9%
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Estim 2012
320376
402451
579616
680 639
536543
613
NATIONAL
76.2%
EXPORT
23.8%
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
10/80
COBRA Group offers an integral solution for the industry and building sectors
(Communication networks, Surveillance & Control Systems, as well as all type
of electromechanical works).
ELECTRICAL
INSTALLATIONS
Industrial Installations
Instrumentation & Control
Building works
Public Sector
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
11/80
ALL TYPES OF INSTALLATIONS RELATED TO POWER AND CONTROL
FACILITIES FOR THE DIFFERENT AREAS OF THE INDUSTRY SECTOR:
Iron and Steel Industry
Automotive Industry
Food Industry
Power Industry
Industrial
Installations
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
12/80
Local Networks Data
Audiovisual & Communication Systems
Remote Control, Video-surveillance
Intrusion and robberies Security Systems
Toll and Access Control
Instrumentation and
Control
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
13/80
Lighting & Power Supply
Communications and Local Networks
Fire Protection System
Plumbing works
Electromechanical Works
Thermal and Acoustical Insulation
Building Sector
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
14/80
Roads and Highways Lighting Systems
Bus and Railways Terminals Lighting
Airports Electrical Infrastructures
Beaconing Systems
Public Sector
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
15/80
Switchgears
Generating Sets
Connection panels
Illumination, electricity rate & emergency installations
Miscellaneous
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
16/80
Moncobra, COBRA Group’s Subsidiary, is a contracting company specialized
in assembly and erection works with a large participation in relevant energy
projects.
MECHANICAL
WORKS
Heavy Structures assembly
Industrial sector
Maintenance and Operation Assistance
EPC Contracts
http://www.esi2.us.es/~lhmnlc03/puentes.jpghttp://www.azo-group.com/aplicacion/turbinas%20de%20vapor/gif/turbinas-de-vapor.jpghttp://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gifhttp://www.erenovable.net/blog/wp-content/uploads/2008/10/turbinapelton04.jpg
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
17/80
Singular structures assembly
Ship-building and off-shore construction
Electrical Power Plants
Entertainment Centers
Pipelines and Pumping Stations
Heavy Structures
http://www.esi2.us.es/~lhmnlc03/puentes.jpghttp://www.azo-group.com/aplicacion/turbinas%20de%20vapor/gif/turbinas-de-vapor.jpghttp://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
18/80
Cement Industry
Pharmaceutical & Food Industry
Chemical & Petrochemical Industry
Iron & Steel Industry
Storage Tanks
Cellulose, Paper and Derivatives Industry
Automotive & Transformation Industry
Industrial
Sector
http://www.esi2.us.es/~lhmnlc03/puentes.jpghttp://www.azo-group.com/aplicacion/turbinas%20de%20vapor/gif/turbinas-de-vapor.jpghttp://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
19/80
Continuous Maintenance works
Dismantling Works
Combustible reloading
Operation & Maintenance of Power Plants
Maintenance &
Operating Assistance
http://www.esi2.us.es/~lhmnlc03/puentes.jpghttp://www.azo-group.com/aplicacion/turbinas%20de%20vapor/gif/turbinas-de-vapor.jpghttp://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
20/80
Mini-hydro power plants
Co-generation power plants
Biomass energy application
Special energy sources
Turnkey
Projects
http://www.esi2.us.es/~lhmnlc03/puentes.jpghttp://www.azo-group.com/aplicacion/turbinas%20de%20vapor/gif/turbinas-de-vapor.jpghttp://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
21/80
This activity, until now developed by Atil-Cobra, is already complemented by a
new specialized subsidiary, Humiclima, more involved in “Large Facilities”.
AIR-CONDITIONING
Air Management Systems
Maintenance & Automation
Hotels & Resorts Equipment
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
22/80
Pressurization
Ventilation & Extraction
Fluid Mechanical Systems
Fire Protection Systems
Sanitary Systems
Industrial Cooling Systems
Air Management
Systems
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
23/80
Preventive & Corrective Maintenance
Facilities Supervision and Control
Pipelines and Integral Maintenance
Building Management
Maintenance &
Automation
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
24/80
Air-Conditioning
Air-Cooling
Refrigerating Appliances
Hotels & Resorts
Equipment
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
25/80
Maintenance activity is consolidated by a large service diversification carried out
for different sectors.
MAINTENANCE
Building sector
Industry sector
Infrastructures
Other services
http://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.construible.es/images/empresas/instalacion468.gifhttp://www.totgas.com/2002_0824_080344AA.JPGhttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gifhttp://www.totgas.com/2002_0824_080344AA.JPG
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
26/80
Combustible reloading
Plumbing
Fire Protection Systems
Electricity
Communications
Civil Works
Building
Maintenance
http://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.construible.es/images/empresas/instalacion468.gifhttp://www.totgas.com/2002_0824_080344AA.JPGhttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
27/80
Chemical, Petrochemical and Refinery Industry
Iron, Steel and Metallurgy Industry
Cellulose, Paper and Derivatives
Cement and Mining
Automotive Production
Pharmaceutical Industry
Food Industry
Shipbuilding
Electronics
Industrial
Sector
http://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.construible.es/images/empresas/instalacion468.gifhttp://www.totgas.com/2002_0824_080344AA.JPGhttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
28/80
Electrical Facilities
Power Transformation and Distribution infrastructures
Electromechanical works
Infrastructures
Maintenance
http://www.avep.es/control/editor/userimages/electricidad.jpghttp://www.construible.es/images/empresas/instalacion468.gifhttp://www.totgas.com/2002_0824_080344AA.JPGhttp://www.clubciclistaferrol.com/ccferrol/Imagenes/navedentro1.gif
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
29/80
INTRADEL, Cobra Group’s Subsidiary, is an Engineering & Consultancy Company
with more than 30 years experience in Studies and Projects activities.
ENGINEERING
Electrical and electromechanical projects
Substations Projects
Passengers Transportation Systems
Telecommunications Projects
Environmental Projects
Power Co-generation
https://www.dst.usb.ve/Decanatos/Pre-grado/Electrica/images/cie-Yudith.jpg
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
30/80
Consultancy – Feasibility Projects
Basic and As-building Engineering
Technical Specification and Manuals
Material Inspection, Testing and Final Reception
Quality Control
Programming and Site Technical Assistance
Works Supervision and Control
Health and Safety Reports
Standardization Reports
Testing and Commissioning
Programs and Schedules
Digitalization and Drawings
https://www.dst.usb.ve/Decanatos/Pre-grado/Electrica/images/cie-Yudith.jpg
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
31/80
HOTELSHOTELS
REFERENCESREFERENCES
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
32/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel LE MÉRIDIENOrán, Argelia
CLIENT
OBRASCON HUARTE LAIN (OHL)
AMOUNT
10.900.000 - €
DEADLINE
2009
SCOPE OF WORKS
Cooling System Building Management System Water and Sewerage Heating System Solar Energy Gas and Diesel Facilities
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
33/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel OSUNAMadrid
CLIENT
CORPORACION HISPANOHOTELERA
AMOUNT
172.000 - €
DEADLINE
2009
SCOP OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
34/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
2ª Phase REAL MADRID YOUNGPLAYERS RESIDENCEValdebebas, Madrid
CLIENT
BEGAR CONSTRUCCIONES YCONTRATAS S.A.
AMOUNT
940.000 - €
DEADLINE
2008
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
35/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel JUAN DE AUSTRIAMadrid
CLIENT
M. F. TURISCONTROL S.L.
AMOUNT
290.000 - €
DEADLINE
2007
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
36/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Rehab. Hoteles VINCCI COSTAGOLF , en Chiclana de la Frontera,(Cádiz) y en La Rábida, (Sevilla).
CLIENT
VINCCI HOTELES COSTA GOLFS.A.
AMOUNT
824.000 - €
DEADLINE
2007
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
37/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel GRAN PEÑAGran Via 2, Madrid
CLIENT
CORPORACION HISPANOHOTELERA
AMOUNT
543.000 - €
DEADLINE
2007
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
38/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Propiedad Sirenis Hotel en RivieraMaya (México)
CLIENT
Sirenis Hotel
AMOUNT
5.000.000 - €
DEADLINE
2006
SCOPE OF WORKS
Electrical Facilities Transformer Stations Low Voltage Network Medium Voltage Network
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
39/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel VINCCIGran Vía 66, Madrid
CLIENT
VINCCI HOTELES COSTA GOLFS.A.
AMOUNT
1.598.000 - €
DEADLINE
2006
SCOPE OF WORKS
Heating and Cooling Mechanical Facilities Electrical Facilities
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
40/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel BARCELÓAvda. Manoteras 20, Madrid
CLIENT
METROVACESA
AMOUNT
1.098.000 - €
DEADLINE
2006
SCOPE OF WORKS
Heating and Cooling Protection Against Fire Plumbing
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
41/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel MARIA ELENA PALACE
Madrid
CLIENT
CORPORACIÓN HISPANOHOTELERA
AMOUNT
1.225.000 €
DEADLINE
2004
SCOPE OF WORKS
Heating
Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
42/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel ALDIANA TROPICAL
Motril, Granada
CLIENT
FALSTACEN
AMOUNT
1.830.000 €
DEADLINE
2004
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
43/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel CENTER
Valencia
CLIENT
FERROVIAL- AGROMAN
AMOUNT
409.000 €
DEADLINE
2004
SCOPE OF WORKS
Heating and Cooling
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
44/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel LAS LOMAS
Cartagena, Murcia
CLIENT
INMOGOLF
AMOUNT
764.000 €
DEADLINE
2003
SCOPE OF WORKS
Heating and Cooling/Ventilation
Protection Against Fire
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
45/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel Sirenis Cocotal Resort, enMacao - República Dominicana
CLIENT
MATURSA
AMOUNT
1.262.125 - €
DEADLINE
2001
SCOPE OF WORKS
Electrical Facilities Substation Transformer Stations Low Voltage Networks Lighting System Low Voltage Switchboards
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
46/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel HESPERIA
Pº Castellana, nº 53 - Madrid
CLIENT
LUZ PALACIO
AMOUNT
1.238.085 €
DEADLINE
2001
SCOPE OF WORKS
Low Voltage Electrical Facilities
Medium Voltage ElectricalFacilities
Weak current and Special
Facilities
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
47/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel Jandia - Playa de Fuerteventura
CLIENT
JANDIA
AMOUNT
637.072 - €
DEADLINE
2000
SCOPE OF WORKS
Electrical Facilities
Weak current and SpecialFacilities
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
48/80
COBRA INSTALACIONES Y SERVICIOS S.A.COBRA INSTALACIONES Y SERVICIOS S.A.
DESCRIPTION
Hotel Riu Atlántico Isla Canela -Huelva
CLIENT
PRYCOMSA
AMOUNT
2.494.720 €
DEADLINE
2000
SCOPE OF WORKS
Electrical Facilities
Weak Current and SpecialFacilities
HVAC
ProtectionAgainst Fire
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
49/80
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
50/80
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
51/80
SCOPE
COBRA INSTALACIONES Y SERVICIOS S.A.
Transformation Centers
Medium Voltage Grid
Low voltage distribution Fire Detection
Communication
Voice data
Megaphone
CLIENT
JOINT VENTURE ACS –
CONSTRUCCIONES
SAN JOSÉ
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
52/80
COBRA INSTALACIONES Y SERVICIOS S.A.
SCOPE
Transformation Centers
Low voltage distribution
CLIENT
DRAGADOS
AMOUNT
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
53/80
COBRA INSTALACIONES Y SERVICIOS S.A.
Transformation Centers
Medium Voltage Grid ow vo tage str ut on
Fire Detection
Communication
Voice data
Megaphone
CLIENT
AMOUNT
COBRA – TECM – MONRABAL
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
54/80
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
55/80
COBRA INSTALACIONES Y SERVICIOS S.A.
Individual rooms: The new Hospital La Fe has 1,000 beds and single rooms, more c
patients and escorts.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
56/80
COBRA INSTALACIONES Y SERVICIOS S.A.
Patient-oriented Building: The building is much more spacious and bright, with a total o
offers greater comfort for patients and offers leisure spaces and services open to the com
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
57/80
COBRA INSTALACIONES Y SERVICIOS S.A.
,
inpatient.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
58/80
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
59/80
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
60/80
SCOPE
COBRA INSTALACIONES Y SERVICIOS S.A.
Transformation Centers
Medium Voltage Grid
Fire Detection
Communication
o ce ata
Megaphone
CLIENT
JOINT VENTURE HOSPITAL SON
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
61/80
COBRA INSTALACIONES Y SERVICIOS S.A.
The Hospital Universitario Son Espases occupies a floor space of over 172 square m
two and half times more than the Hospital Universitario Son Dureta), has a capacity
, , , ,
consultations ...
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
62/80
HOSPITAL PUERT
SCOPE
COBRA INSTALACIONES Y SERVICIOS S.A.
Transformation Centers
Power Generator
Switching and distribution center General Protection Center with Transformer
Distribution General lines
Fire Detection, Communication, Access Control
Voice Data
Megaphone
CLIENT
AMOUNT
JOINT VENTURE DRAGADOS-SACYR-BOVIS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
63/80
HOSPITAL PUER
The hos ital has an area of 165 000 m². It has four floors and a low surface area. Your d
COBRA INSTALACIONES Y SERVICIOS S.A.
horizontal, modern and functional, surrounded by greenery and vials for users. The diffwith a central corridor, where are located the administrative units of services.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
64/80
HOSPITAL PUER
COBRA INSTALACIONES Y SERVICIOS S.A.
e u ng as s nc areas o : osp a za on, consu a ons, enera erv ces, an Research, Teaching and Administration. It also has an auditorium with capacity for 400underground parking spaces and a surface of 450 seats, and a heliport.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
65/80
HOSPITAL PUE
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
66/80
HOSPITA
COBRA INSTALACIONES Y SERVICIOS S.A.
Transformation Center
Power
g t ng
CLIENT
NECSO
AMOUNT
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
67/80
HOSPITA
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
68/80
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
69/80
HOSPITA
COBRA INSTALACIONES Y SERVICIOS S.A.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
70/80
HOSPITAL INCA PA
COBRA INSTALACIONES Y SERVICIOS S.A.
SCOPE
Transformation Centers
Medium Voltage Grid Low voltage distribution
Fire Detection
Communication
Voice data
Megaphone
CLIENT
DRAGADOS – MELCHOR MASCARO
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
71/80
HOSPITAL MATERN
COBRA INSTALACIONES Y SERVICIOS S.A.
SCOPE
Transformation Center
Power Lighting
CLIENT
JOINT VENTURE HOSPITAL
O´DONNELL
AMOUNT
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
72/80
HOSPITAL MATERN
COBRA INSTALACIONES Y SERVICIOS S.A.
Integrated in one building two different hospitals, Maternity and Children's Hospita
peculiarities. Internal circulations are divided, but share some health care areas. Ent
.
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
73/80
HOSPITAL MATERN
COBRA INSTALACIONES Y SERVICIOS S.A.
The interior of the building offers a warm and tidy,
nothing to do with the rest of the hospitals in the capital
an mos o e res o pa n . ac oor o e new
hospital are illuminated from 8 courtyards, making
natural light on art spaces and hallways of the building.
The exterior looks and metallic glass, offering a hygienic
and sophisticated image away from hospital standards. A
u ng w ou an are a esp e s apparen
simplicity who gets to please take a moment to observe
more closely
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
74/80
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
75/80
REFERENCIAS
Filial Instalaciones
WorksWorks ReferencesReferences
FerialFerial BuildingsBuildings
CommercialCommercial WarehousesWarehouses
FebruaryFebruary 20132013
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
76/80
REFERENCIAS
Filial Instalaciones
DESCRIPTION
Madrid Ferial Arena Ampliation.Electrical and Especials Facilities.Domes 12 and 14.
CLIENT
IFEMA
AMOUNT
7.399.505,88 €.
DEADLINE
2008
SCOPE OF WORKS
New Pavilions 12 and 14, bothincluding: Electrical facilities Smoke detection systems Estructured cable Public address and
communications Electronic communications
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
77/80
REFERENCIAS
Filial Instalaciones
DESCRIPTION
Ciudad de las Artes y de las Ciencias deValencia
CLIENT
C.A.C., S.A.
AMOUNT
5.500.000 €UTE PARQUE OCEANOGRÁFICO
DEADLINE
2004
SCOPE OF WORKS
Subterranean line Medium Voltage,distribution centers and transformationcenters.
Main distribution Switchboards, Buildingsswitchboards, Secondary and TerciarySwitchboards.
Infraestructures and Feeding lines. External and Internal Lighting.
Weak current facilities: communications,public address, access control, etc..
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
78/80
REFERENCIAS
Filial Instalaciones
DESCRIPTION
New Ferial Domes/Buildings at Bilbao
CLIENT
BILBAO EXHIBITION CENTRE.
AMOUNT
100 - M €Total amount of full works. JVCA withInabensa, Cymi, Axima, Ikusi y Amenabar
DEADLINE
2004
SCOPE OF WORKSTotal enclosure area consists in 6 domes of78.000 sq.m, plus 18.000 sqm of additionalservices. HVAC Facilities Electrical Facilities Transformer centers (Medium Voltage) UPS Systems
Optical fiber Public address systems, telephony facilities,
etc… Security and access control systems Personal Identification systems.
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
79/80
REFERENCIAS
Filial Instalaciones
DESCRIPTION
King Juan Carlos I Park, Ampliation - Phase II.
CLIENT
IFEMA
AMOUNT
7.51 M€.
(total amount of full works,performerd by JVCA: COBRA,ISOLUX y CRESPO y BLASCO)
DEADLINE
2001
SCOPE OF WORKS
New pavilions 9 and 10, CongressBuildings, completing in all: Electrical facilities (lighting and power
supply) Installation of 5 transformer stations UPS System Alumbrado exterior
External lighting Public address system, internetsystems, etc…
REFERENCIAS
-
8/16/2019 Presentation Instalaciones Special MEP Facilities
80/80
REFERENCIAS
Filial Instalaciones
DESCRIPTION
King Juan Carlos I Ferial Park,at Madrid
CLIENTE
IFEMA
IMPORTE
36,03- M€.(total amount of full works,performerd by JVCA: COBRA,ISOLUX y CRESPO y BLASCO)
DEADLINE
1991
ALCANCE
Office Building and Facilities and Plant Room Building of new
ferial buildings , including :
Electrical facilities at pavilions 1 to 8.
Electrical facilities for lighting and power supply.
Installation of electrical substation 45 kV yMedium Voltage network15 kV.
UPS System
External Lighting
Public address system, communication systems,etc...