presentation-mcfa
TRANSCRIPT
2
Summer Internship
By Rajat Saxena
3
OVERVIEW
Make Vs Buy
ASSIGNMENTS MANAGER STATUS
Sop Design - Mast Assembly Ricky G. Completed
Plant Layout -fabrication shop Saul Completed
Time Study- EOS fabrication Afework Completed
Time- Kibo EM Kutty Completed
Design & Prototype for bench vise installation
Dinesh Completed
Design & prototype of Hose Support Yonas Completed
C.G.- Tilt Table Dinesh Completed
Make vs. Buy Yonas Completed
4
Approach
Assignment-1 (Standard Operating Procedure- Mast Assembly)
Take pictures Use drawing Spec. from the drawing
Match the drawing part
nos. with B.O.M.
Check the parts no. with ASO
400
Updates the SOP with correct drawing no.
5
Sample SOP
No.
54
8 3
8 2
8 1
Qty No.
4
3
2
1
0 RS
CHG Init.
Legend: Visual Check Torque Requirement Critical DimensionQuality Control Special Requirement Jig/Fixture IndicatorSafety Environment Procedure Setup/Repeat
9421010912
9421010911
Part Number
9421111800
Mast Assembly- 5M25C37 1/6
6/11/2015
Date
Review for initial release
Description of Change
Document Name Page
N/A
EO - MO
Note
Shim T-0.5
For all three channels
Shim T-1.0
Roller Main
Part Name
Any shim can be used as per requirement
Bearing should have proper fit with item 2
Mitsubishi Caterpillar Production System Standard Operating Procedure
Procedure Quality Point
1 Placing shim(item 1) onto inner shaft 2 of middle and outer channel.
Lubricate no.2 before installations
2
Installing roller main (item 3) with the help of pnematic bering press(item4) onto inner shaft of outer and middle channel.
Step # 1 Step # 1
Step # 2 Step # 2
1
3
2
4
6
Suggestion1. Flow Diagram
7
2. Control Plan
Prototype Prelaunch Model Document noPart name Person incharge Prepared byPart no. Customer name Checked byDrg. Name Supplier name Approved byDrg no. Core team
Size Freq. Y/N SIZE94111-07500 Shim - 0.5 0.1mm Filler guage 494111-07400 Shim - 1.0 0.1mm Filler guage 4
Line operatorInstalling the shim
onto the shaft1
CONTROL PLAN
Through hands
Sample ReccordingPart/
Process no.
Process name/ Operation description
M/C Jigs, Tools for
MFG
Part No. Product Name Process
Clas
s Product/Process specification
tolerance
Characteristic
Evaluation measurement
technique
Method
Photo
Insp
ecte
d By
Control Method
Reaction Plan
Revision no.Date org.Date rev.
ProductionMast Assembly
Page no
8
1. Layout of fabrication shop
Assignment-2 Fabrication Layout
9
Old Layout
Progress
10
New Layout
Progress
11
Approach Dimension of fabrication layout Studied the flow Studied the Constraints Layout Design
Constraints
Robots are fixed
Space
Conveyors are fixed
Space for fork lift movement
Magellan and Victoria should be
closed to Robot
One directional Flow
Electrical Connections
Budget
12
Total Flow Dimension Required for each shop
Studies Required
ModelNo. of units produced
Total Flow
Magellan/Victoria 739 739Atlas/Kibo 124 124Centaur/EOS 80 80Mercury 79 79Apollo 23 23
Planned AreaVertical Horizontal Area Vertical Horizontal Area
EOS Weld 29 26 754EOS Fabrication 29 20 580Polaris 29 23 667 31 23 713Centaur 29 27 783 35 23 805Mercury/Mars 29 79 2291 66 35 2310Apollo 29 82 2378 29 83 2407Atlas 29 98 2842 30 100 3000Helios 29 28 812 29 30 870
30 23 69054 15 810
Total Area 12298 12991
Current DimensionShop Name
66 21 1386
Dashboard 29 41.06 1191
13
Material Handling
Punch Press, Laser and plasma
Frame Fabrication
Robot StampingShot Blasting
Paint Storage
SchedulingMaterial HandlingPunch Press, Laser and plasma Frame Fabrication
Robot
Stamping
Shot Blasting
Paint
From
Atlas/ M
adge
lla/ V
ictoria
To
Material Handling
Punch Press,
Laser and plasma
Frame Fabricatio
nStamping
Shot Blasting
Paint Storage
SchedulingMaterial HandlingPunch Press, Laser and plasma Frame Fabrication
`
StampingShot Blasting
Paint
From
EOS/
POLA
RIS/
CEN
TAUR/
MAR
S & M
ERCU
RY/ A
POLLO/
HELIOS
To
From- To Chart Analysis
14
Suggestion 3
15
Creo Drawing Model
Assignment-3 Design Table for Bench-vise Installation
16
Assignment-4 Time Study for EOS Mast (Sample)
17
Time Measurement Used stop Watch to measure the time. Machine Time Loading & Unloading Time Average time
Challenges faced Shift Changes No specific schedule followed by the
supervisor Machining time is different for similar cut Operator has to wait for the forklift to flip the
part.
Approach
18
Advantages
• Reduce waste of time• Forklift Operator can see the flag from
any part of the plant.• It is also helpful for the maintenance
department
Suggestion-4 Flag interpretation to call forklift operator to avoid time waste
19
Formula Used Momentum M1R1 + M2R2 = (M1 + M2)R
R = M1R1 + M2R2/ (M1 + M2
Moment of body A Area of square / 2 * Area of triangle 10 *38.05/8 *38.08 = 5/4 Mass of rectangle = 5/9*500 =277 Mass of two triangles = 500- 277 =223Center of gravity with reference to plane A C.G. of the body A = (277 * 19.04 + 223 * 12.69)/ 500 =14.3 C.G. of the whole body (A and B) = (268 * 40.08 + 500 * 14.3)/768= 23.29 Center of gravity with reference to plane B C.G. of the whole system (A+B+C) = ((12+5)*4500 + (272+23.29)*(500+268))/ (500+268+4500) = 57.75
Drawing
Assignment-5 Center of Gravity of Tilt Table
20
Challenges Faced
Hanging hoses create disruption during the processes.
Hose- Stand in not utilized well Existing are not perfectly aligned Hoses are entangle with each other
Assignment-6 Design for new Hose Support- Kaizen
21
Creo Drawing Prototype
Design in Creo & Prototype
22
TOTAL STUDY TIME:
Date:
Serial No. Process Start Time End Time Cycle Time 1 Gear oil (Differential) filling to the front axle 0:00:00 0:05:40 0:05:40
2 Engine Oil (Motor oil) filling 0:00:45 0:02:30 0:01:453 Coolant(ATF) filling to the radiator 0:02:10 0:04:30 0:02:204 Coolant(ATF) filling to the reserviour tank 0:04:50 0:05:08 0:00:185 Hydraullic oil filling 0:00:40 0:06:02 0:05:226 Bolting the front axle 0:06:40 0:07:50 0:01:107 Bolting the hydrallic tank 0:08:01 0:08:18 0:00:178 Instal floor plate L.H. with insulator 0:09:26 0:11:52 0:02:26
0:11:520:01:00
Total cycle time ( filled simultaneously)Total motion time
MCFA Time & Motion StudyPRODUCT DESCRIPTION: KIBO EMERGING MARKET PERFORMED BY : RAJAT
OPERATION DESCRIPTION: OIL FILLING STUDY BY:
START TIME :
Assignment 7 Time Study for the Kibo Truck
23
Approach Recorded the video for each station. Calculated the start time and end time for
each process. Calculated the material Handling time for
motion study.
Challenges faced Part Shortage Mismatch in scheduling plan vs action plan Waiting for the frame or other parts
24
Table
Process Total Cycle Time Total Motion Time Total TimeSub-Assembly 4:12:34 1:24:50 5:37:24Power Station 1&2 0:47:56 0:09:34 0:57:30Power Station 3 & 4 1:00:11 0:35:22 1:35:33Main line Station 1 & 2 1:09:17 0:53:09 2:02:26Main line Station 3 & 4 1:23:09 0:48:52 2:12:01Main line Station 5 0:46:23 0:07:24 0:53:47Main line Station 6 0:11:52 0:01:00 0:12:52Total 9:31:22 4:00:11 13:31:33
Graph
Results
Sub-A
ssembly
Power Sta
tion 1&2
Power Sta
tion 3 & 4
Main lin
e Stati
on 1 & 2
Main lin
e Stati
on 3 & 4
Main lin
e Stati
on 5
Main lin
e Stati
on 60:00:00
1:12:00
2:24:00
3:36:00
4:48:00
6:00:00
Total Cycle TimeTotal Motion TimeTotal Time
25
Suggestion 5 - For Scheduling
26
Total Cost
Make BuyOrdering Cost 3,250.00$ 101,000.00$ Total cut Cost 91,617.03$ Holding Cost 6,673.03$ 2,200.61$ Total Uncut Cost 58,672.54$ Labour Cost 6,100.38$ Total Cost 74,695.95$ 194,817.64$
Graphical Representation
Assignment 8 Make Vs Buy for the Hose Cut
Ordering Cost
Total cut Cost
Holding Cost
Total Uncut Cost
Labour Cost
Total Cost
$-
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
Chart Title
Buy Make
27
Suggestions
28
Suggestion 6- for sensitive machines
29
Questions?