presentation outline dma building pavel likhonin · 2010-05-05 · presentation outline...

30
Presentation Outline •Introduction •CHP Analysis •Electrical Analysis •Acoustical Analysis •Thermal Storage Analysis •System Optimization Analysis •Conclusion •Acknowledgements •Questions DMA Building Fort George G. Meade, MD Pavel Likhonin Mechanical Option Thesis Final Presentation

Upload: others

Post on 20-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Thesis Final Presentation

Page 2: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline

•Introduction•Facility Information•Mechanical Information•Goals

•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Facility InformationSize: 186,000 SF 

Location:                                                            Fort George G. Meade, MD  

Owner:                                                                   Army Corps of Engineers

Architect:                                                                                                    HOK

Engineers:                                                                             AECOM |HSMM

Occupancy:                  24/7 Operation, Television Studios, Data Center

Completion Date:  September 2011

Page 3: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline

•Introduction•Facility Information•Mechanical Information•Goals

•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Mechanical InformationAir Delivery System:                                     Variable Air Volume

Chilled Water System:         (3) 500 Ton Water Cooled Chillers

Distribution System: Primary/Secondary Flow

Hot Water System: (3) 3000 MBH Condensing Boilers

Control System:                  Direct Digital Control using BACnet

Waterside Economizers:                          Used for Data Center 

Airside Economizers:  Used in AHU’s

Page 4: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline

•Introduction•Facility Information•Mechanical Information•Goals

•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Goal:

Minimize  Costs Spent on Energy Consumption, Making the Building Less Expensive and More Efficient to Operate

Page 5: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Electric•1.8 MW Base Load• 2.2 MW Peak Load

0

500

1000

1500

2000

2500

3000

3500

4000

122

645

167

690

111

2613

5115

7618

0120

2622

5124

7627

0129

2631

5133

7636

0138

2640

5142

7645

0147

2649

5151

7654

0156

2658

5160

7663

0165

2667

5169

7672

0174

2676

5178

7681

0183

2685

51

0

1000

2000

3000

4000

5000

6000

7000

8000

kW

Hours

MBH

Electrical vs. Thermal Loads

Thermal Load

Electric Load

Thermal (Heating & Cooling)• 4,900 MBH Base Load• 9,200 MBH Peak Load

Combined Heat & Power

Page 6: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Heating Loads

Cooling Loads

Electric Loads

Combined Heat & Power

Natural Gas

Waste Heat

Absorption Chiller

Prime Mover & Generator

Page 7: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

CHP OptionsSystem 

EngineType

 Options

Electric Production

Load Cooling Heat Source

A

Inte

rna

l Com

bu

stio

n

‐ 2390 kW 100% 800 Ton Absorption Chiller Waste Heat + Boiler

B ‐ 2390 kW 100% (2) 500 Ton Electric Chillers Waste Heat Only

C ‐ 2390 kW 100%700 Ton Absorption Chillerand a 300 ton Electric Chiller

Waste Heat Only

D ‐ 2390 kWLoad‐

Following800 Ton Absorption Chiller Waste Heat + Boiler

E ‐ 2390 kWLoad‐

Following700 Ton Absorption Chiller and a 300 ton Electric Chiller

Waste Heat Only

F ‐ 1801 kW 100% 800 Ton Absorption Chiller Waste Heat +Boiler

G

Turb

ine

‐ 1200 kW 100% 800 Ton Absorption Chiller Waste Heat Only

H Back‐Pressure Steam Turbine

1904 kW 100% 800 Ton Absorption Chiller Waste Heat +Boiler

I Back‐Pressure Steam Turbine

1904kW 100%400 Ton Absorption Chillerand a 500 ton Electric Chiller

Waste Heat +Boiler

Page 8: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Heating Loads

Cooling Loads

Electric Loads

System A

Natural Gas

Waste Heat

800 Ton Absorption ChillerBoiler

Jenbacher 2390 kW Natural Gas Engine & Generator At 100% Load

Page 9: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Heating Loads

Cooling Loads

Electric Loads

System B

Natural Gas

Waste Heat

Jenbacher 2390 kW Natural Gas Engine & Generator At 100% Load

(2) 500 Ton Electric Chillers

Page 10: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Natural Gas

Waste Heat

Heating Loads

Cooling Loads

Electric Loads

System E

650 Ton Absorption

Chiller300 Ton Electric Chiller

Jenbacher 2390 kW Natural Gas Engine & Generator Load Following

Page 11: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

$(100,000.00)

$‐

$100,000.00 

$200,000.00 

$300,000.00 

$400,000.00 

$500,000.00 

$600,000.00 

A B C D E F G H I

$438,363.29 

$408,300.27 

$465,215.87 

$504,490.46 

$578,552.11 

$359,540.85 

$(48,049.99)

$233,094.67 

$317,935.24 

Yearly Savings ($

)

System

Yearly Energy Cost Savings by System

Page 12: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

A B C D E F

11.2 11.5

9.18.4

6.0

12.4

Years

System

Payback Period

Page 13: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction

•CHP Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

0

1

2

3

4

5

6

0 10% 20% 30% 40% 50%

Years

% Increase in Electricity Costs

System E Payback with Increasing Electricity Costs Only

0.00

1.00

2.00

3.00

4.00

5.00

6.00

0 10% 20% 30% 40% 50%

Years

% Increase in Fuel and Electricity Costs

System E Payback with Increasing Electricity and Natural Gas Costs

Sensitivity Analysis

Page 14: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis

•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Electrical Interface for CHP•The generator switchboard and the breakers were sized based on current electrical design

•Redundant Automatic Transfer Switches were added to critical equipment

•Data Center•Fire Pump

Page 15: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis

•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Acoustical Analysis

Page 16: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis

•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

0

10

20

30

40

50

60

70

80

90

62.5 125 250 500 1000 2000 4000 8000

SPL (dB)

Frequency (Hz)

NC Analysis for Jenbacher 2390 kW IC Engine

Original 2390

2390 Two 8" CMU

2390 8" CMU and 8" concrete wall

2390 8" CMU with metal stud & insulation

2390 8" CMU with metal stud no insulation

NC‐15

NC‐20

NC‐25

NC‐30NC‐35

NC‐40

NC‐45

NC‐55

NC‐50

NC‐60

NC‐65

NC‐70

•Double 8” Concrete filled CMU wall

•8” CMU wall, and 8” Concrete wall

•8” CMU wall and a Metal Stud wall with insulation

8” CMU wall and a Metal Stud, with no insulation

Acoustical Analysis

Page 17: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis

•Thermal Storage Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

•Peak Shaving Strategy for:•Ice Storage Chilled•Water Storage

400

450

500

550

600

650

700

750

800

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Tons

Hours

Peak  Day Thermal Load

Constant Chiller Load

Peak Load Removed

Thermal Storage

Ice storage produced negative savings from this analysis due to inefficiency of making ice and low electric rates.

Page 18: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis

•Thermal Storage Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

• Peak demand was determined on a monthly basis.• On-Peak to Off-Peak shift was determined on a daily basis.

Chilled Water Storage Savings

Demand Savings: $3,617.22On-Peak Savings: $7,025.21Total Yearly Savings: $10,643.43

Thermal Storage

Page 19: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis

•Thermal Storage Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Simple Payback Period• Initial Investment was determined based on a 3,500 Ton-hr, 400,000 Gallon Tank and required accessories such as pumps, piping, etc.• Due to N+1 Redundancy requirements, one chiller/cooling tower could be removed and the remaining chillers/cooling towers have to be upsized to 600 tons.• Savings from one less chiller can be used to pay for the chilled water storage tank

Initial Investment: $173,666Simple Payback Period: 16.32 Years

Page 20: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis

•Thermal Storage Analysis•Concept•Energy Cost Savings•Payback Period•Sensitivity Analysis

•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

16.32

12.42

10.03

8.41

7.246.35

5.665.11 4.65

4.273.94

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

18.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Years

Percent  Electrical Cost Increase

Sensitivity Analysis

Thermal Storage• Exponential Decline in the payback period

• As Electricity Rates increase, the payback period decreases

16.3 years to 12.4 years at a 10% increase

Page 21: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis

•System Optimization Analysis•Thermal Storage & CHP

•Intro/Energy Cost Savings•Initial Investment/Payback Period

•Data Center Chiller•DOAS

•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

CHP Integrated with Thermal Storage

• CHP System A was used for this System Optimization AnalysisThis system had the largest amount of wasted heat, which

makes it a good candidate for integration with thermal storage.

• Integrating thermal storage into a CHP system produced slightly better results than thermal storage on its own.

Yearly Energy Cost Savings: $11,644

Page 22: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis

•System Optimization Analysis•Thermal Storage & CHP

•Intro/Energy Cost Savings•Initial Investment/Payback Period

•Data Center Chiller•DOAS

•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Initial Investment for Thermal Storage with CHP350,000 Gallon Tank $       354,200.00 300 Feet of 5" Pipe $         10,500.00 

300 Feet of 2" Insulation for 5" Pipe $            5,874.00 

(2) 15 HP Pumps  $         10,220.00 One Less (500 Ton) Chiller $     (293,062.50)

One Less (500 Ton) Cooling Tower $       (50,472.80)Increasing Size of Original Chiller (500 to 

650 tons)$         71,200.00 

Increasing Size of Original Towers (500 to 650 tons)

$         14,950.00 

Total $       123,408.70 

• Due to a smaller tank, and slightly larger yearly savings, the simple payback period for thermal storage was around

10.6 Years

Page 23: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis

•System Optimization Analysis•Thermal Storage & CHP•Data Center Chiller

•Concept•Energy Cost Savings/Payback Period

•DOAS•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Dedicating a Chiller to the Data Center

Chiller Efficiencies Evaporator Temperature 

(˚F)44 55 60

Condensing Water Temperature (˚F)

85 85 85

kW/ton 0.535 0.418 0.314

NPLV 0.314 0.256 0.2334

Page 24: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis

•System Optimization Analysis•Thermal Storage & CHP•Data Center Chiller

•Concept•Energy Cost Savings/Payback Period

•DOAS•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Cooling Cost of the Data Center

TemperatureMMBTU/yea

rSavings $/yr

44˚ F 15137.0 ‐

55˚ F 14065.4 $28,155.00

60˚ F 13046.8 $54,946.00

Even with higher pumping costs, the total energy savings from running a chiller at higher temps was substantial

• Initial Investment for dedicating a chiller only involved adding in a few valves, (2) pumps, and some piping.

•The simple payback period calculated for running a chiller at 55˚ F was less than a year.

Page 25: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis

•System Optimization Analysis•Thermal Storage & CHP•Data Center Chiller•DOAS

•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

DOAS• DOAS paralleled with Chilled Beams was modeled in TRACE 700 for annual energy and cost savings•Only lower energy density areas were modeled as DOAS with Chilled Beams

•Annual Energy Savings: 1,913 x 10^6 [BTU/yr]•Annual Cost Savings: $46,949

Page 26: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis

•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Conclusion

CHP System E Yearly Savings: $578,552

Dedicated Chiller to Data Center @ 55˚ F: $28,155

Chilled Water Storage W/CHP System A Savings: $11,644

Chilled Water Storage Yearly Savings: $10,643

DOAS (Office) Yearly Savings: $46,949

Page 27: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion

•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Acknowledgements:

Special Thanks To:All the AE Faculty 

&Family and Friends

Page 28: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements

•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Questions

Page 29: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

Initial Investment by  CHP System

System Cost

A $     2,754,407.05 

B $     2,483,717.55 

C $     2,478,387.55 

D $     2,800,156.55 

E $     2,439,842.55 

F $     2,381,676.53 

Initial Investment for Thermal Storage400,000 Gallon Tank $      382,800.00 300 Feet of 5" pipe $        10,500.00 

300 Feet of 2" Insulation for 5" Pipe

$           5,874.00 

(2) 15 HP pumps  $        10,220.00 One Less Chiller $    (293,062.50)

One Less Cooling Tower $      (50,472.80)Increasing size of original 

Chillers$        94,648.00 

Increasing size of original Towers

$        13,160.00 

Total $      173,666.70 

Initial Investment for Thermal Storage with CHP400,000 Gallon Tank $       354,200.00 300 Feet of 5" Pipe $         10,500.00 

300 Feet of 2" Insulation for 5" Pipe $            5,874.00 

(2) 15 HP Pumps  $         10,220.00 One Less Chiller $     (293,062.50)

One Less Cooling Tower $       (50,472.80)

Increasing Size of Original Chiller $         71,200.00 

Increasing Size of Original Towers $         14,950.00 

Total $       123,408.70 

Wall Type Total Cost

Total: Additional 8" Concrete $14,991.14

Total: Additional metal stud wall with insulation

$28,731.25

Total: Additional metal stud wall, no insulation

$14,498.80

Total: Additional block wall  $28,085.95

05

1015202530

0% 10% 20%

Years

% Increase in Fuel Costs

System E Payback with Increasing Natural Gas Costs Only

Page 30: Presentation Outline DMA Building Pavel Likhonin · 2010-05-05 · Presentation Outline •Introduction •CHP Analysis •Electrical Analy sis •Acoustical Analysis •Thermal Storage

Presentation Outline•Introduction•CHP Analysis•Electrical Analysis•Acoustical Analysis•Thermal Storage Analysis•System Optimization Analysis•Conclusion•Acknowledgements•Questions

DMA BuildingFort George G. Meade, MD

Pavel LikhoninMechanical Option       

CO2e Savings when compared to Grid

A B C D E F

IC Engine

kWh 20,936,400.00 20,982,933.93 20,936,400.00 16,673,858.17 17,305,591.92 15,776,760.00

BTU 74,893,389,355.47 71,635,736,437.02 71,476,869,600.00 70,082,301,286.29 59,081,290,819.32 53,861,858,640.00

CO2e (lb) 10,260,394.34 9,814,095.89 9,792,331.14 9,601,275.28 8,094,136.84 9,011,793.30

Grid kWh 18,602,443 18,602,443 18,602,443 18,602,443 18,602,443 18,602,443

CO2e (lb) 33,856,445.42 33,856,445.42 33,856,445.42 33,856,445.42 33,856,445.42 33,856,445.42

Savings (lb) 23,596,051.08 24,042,349.53 24,064,114.29 24,255,170.15 25,762,308.58 24,844,652.12

•Equivalent of removing 1,916 cars!•Spark Gap: $18.99•O&M costs from EPA.gov: $0.005/kWh•Assumed 40% Elect. Efficiency at 75% load. From manufacturer, full load electrical efficiency is 42.6%•System E never drops below 75% of the load, making load following very efficient•Thermal to Electric Ratio of 0.85 to 1.25 during the peak summer months

1% Δ