Earned Value Management is forthe management of “projects”
• A contract or a budget is a “project”• A project has specific scope of work• A project requires authorized budget• A project requires a master schedule
![Page 2: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/2.jpg)
Earned Value is 3 dimensional
Planned Value1. What work has been authorized? (from PMS)2. What is the budget for the work authorized?
Earned Value3. What work has been accomplished? (from PMS)4. What was the budget for work accomplished?
Actual Costs5. What are the actual costs for the EV?
![Page 3: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/3.jpg)
1) Scope the entire project before...
You must define 100% of the project scope,using a Work Breakdown Structure (WBS).
![Page 4: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/4.jpg)
![Page 5: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/5.jpg)
3) Integrate all project processes
You must decompose the project scopeinto manageable cells which integrates
scope + schedule + resources
![Page 6: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/6.jpg)
4) Plan and schedule the project
Earned value management requires scheduling:1. A formal Project Master Schedule (PMS)2. Vertical traceability (PMS to all schedules)3. Horizontal relationships linked (CPM)
![Page 7: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/7.jpg)
5) Identify the measurement metrics
You must define how you will convertPlanned Value into Earned Value
![Page 8: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/8.jpg)
6) Plan and schedule the projectEarned value management requires scheduling:
1. A formal Project Master Schedule (PMS)2. Vertical traceability (PMS to all schedules)3. Horizontal relationships linked (CPM)
![Page 9: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/9.jpg)
7) Identify the measurement metrics
You must define how you will convertPlanned Value into Earned Value
![Page 10: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/10.jpg)
8) Form a project baseline
You must establish a time-phasedperformance measurement baselinemade up from CAPs, providing the basisfor measuring project performance.
![Page 11: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/11.jpg)
9) Record project direct costs
You must inform the project managerswhat they have spent…to compare against
the Earned Value
---the trend is to weekly measurement…of hours---
![Page 12: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/12.jpg)
10) Measure project performance
EVM requires 3 dimensional measurement:• Planned Value• Earned Value• Actual Costs• EV – PV = Schedule Variance (SV)• EV ÷ PV = Schedule Performance Index (SPI)• EV – AC = Cost Variance (CV)• EV ÷ AC = Cost Performance Index (CPI)
![Page 13: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/13.jpg)
11) Periodic estimates at completion
You must periodically estimatea statistical “range” of final cost results,
based on earned value performance data
---which provides the “early warning”---
![Page 14: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/14.jpg)
12) Manage all changes to the project
You must manage all changes to the project,either approving or rejecting each changeand incorporating the approved changes
into a revised project baseline.
![Page 15: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/15.jpg)
The “rewards” from the use ofEarned Value Management
![Page 16: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/16.jpg)
# 1 You join a select group of projectswhich are predicting their final resultsfrom the 15% 20% completion point...
...in time to make a difference.
![Page 17: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/17.jpg)
# 2 You will employ a “single”management control system
to provide enterprise-wide data onall capital projects
---the CPI is the common metric on any project---
![Page 18: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/18.jpg)
# 3 You will use an “integrated”management control system
to combine the project’s
technical + time + resources
![Page 19: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/19.jpg)
# 4You will employ
“Management by Exception” (MBE)principles to monitor performance
against the approved baseline
---the “CPI” and “SPI” constitute the exceptions---
![Page 20: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/20.jpg)
# 5 You will know your project’strue “cost efficiency”
the Cost Performance Index(e)based on actual performance
---the CPI never completely recovers!!!---
![Page 21: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/21.jpg)
# 6 You will know the project’sSchedule Performance Index (SPI) to
isolate & quantify & manage the workscheduled...but not performed
![Page 22: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/22.jpg)
# 7 You can useEarned Value Management datato monitor the remaining effort
within management’s expectations
![Page 23: Presentation Relating to Earned Value](https://reader033.vdocuments.net/reader033/viewer/2022061206/5482ed035906b59e158b45ed/html5/thumbnails/23.jpg)
Earned Value providesfundamental Project Management
You can practice goodproject management without EVM,
you cannot practice EVM effectivelywithout good project management”