Presented April 16, 2009 at the ACG Annual Meeting in Chicago, IL. GAYLON RICHARDSON
Engineered Air Balance Co., Inc.Houston, Texas
04/18/23 1
DefinitionIntegrate- join two or more objects or make
something part of a larger whole, or be made part of a larger whole.
For commissioning an integrated system test can be defined as: a test that brings previously functionally tested systems together and simultaneously will test the designed control sequence for all associated systems as a whole in various modes.
04/18/23 2
Examples of Integrated System TestI have included 3 examples of types of integrated
system test.Stair pressurization system which could be in
most buildingsHospital considerations that could work for a
multitude of systemsLaboratory and/or vivarium considerations that
become more complex
04/18/23 3
Examples of Integrated System TestThis discussion is for only HVAC systems but the
same type of testing should be considered for life safety, security, lighting, plumbing, elevators, and any kind of special process systems.
04/18/23 4
Examples of Integrated System Test Stairwell PressurizationEmergency power system with stair well
pressurization system.In buildings that have floors 75 feet above grade a
stair pressurization is required. The system will be tested under normal power when originally tested. When the building looses power and the power is transferred to the emergency generator the stair pressurization system will be retested, which is an integration of the emergency power system with the stair pressurization system.
04/18/23 5
Examples of Integrated System Test Stairwell Pressurizati
This test will determine the stairwell pressurization fans start after emergency power has been established and they are operating with the correct rotation.
This test will also establish the dampers, alarms and smoke detectors are operational under emergency power.
The last part of this test will be to verify everything is operational after returning to normal power.
04/18/23 6
Examples of Integrated System Test HospitalsHVAC Systems with Emergency Power the IST
will verify the following:Air Handling Units (AHUs)
Start under emergency power with correct rotation
All control loops are operationalAll dampers are operationalAll terminal boxes are operational
04/18/23 7
Examples of Integrated System Test Hospitals
Systems returned to normal powerRestart under normal power, AHUs and fan
systems should follow the designed start sequence
All control loops are operationalAll systems back to their normal operationAll dampers are operational and are in the
correct position
04/18/23 8
Examples of Integrated System Test Hospitals
Exhaust Fans (EFs)Start under emergency power with correct
rotationAll control loops are operationalAll dampers are operationalAll terminal boxes are operational
04/18/23 9
Examples of Integrated System Test Hospitals
Return to normal powerRestart under normal powerAll control loops are operationalAll dampers are operationalAll terminal boxes are operational
04/18/23 10
Examples of Integrated System Test Hospitals
Chilled Water PumpsStart under emergency power with correct
rotationAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load
systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 11
Examples of Integrated System Test Hospitals
Return to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load
systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 12
Examples of Integrated System Test Hospitals
Hot Water PumpsStart under emergency power with correct
rotationAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load
systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 13
Examples of Integrated System Test Hospitalsst
Return to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load
systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 14
Examples of Integrated System Test Hospitals
Chillers and Heat ExchangersStart under emergency power with correct
rotationAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly
load systemTransfer switches for pumps and systems with
coils are sequenced properly
04/18/23 15
Examples of Integrated System Test Hospitals
Return to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly
load systemTransfer switches for pumps and systems with
coils may not transfer with the chiller’s transfer switch
04/18/23 16
Examples of Integrated System Test Hospitalst
Boilers and Heat ExchangersStart under emergency power with correct
rotationAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly
load systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 17
Examples of Integrated System Test Hospitals Test
Return to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly
load systemCaution systems with coils may not start at the
same time the pump starts.
04/18/23 18
Examples of Integrated System Test Hospitals
Smoke Control Systems Under Emergency PowerAll fans and AHUs are off or operating as shown
on the smoke control matrix All fans start under emergency power with
correct rotation as shown on the smoke control matrix
All control loops are operationalAll dampers are operational and are in the
correct position as shown on the smoke control matrix
04/18/23 19
Examples of Integrated System Test Hospitals
All fans and AHUs stopping and starting meet NFPA 92 and the International Building Code time constraints
All damper opening and closing meet the standards mentioned above
All smoke barriers maintain the correct pressure relationships as shown on the smoke control matrix
04/18/23 20
Examples of Integrated System Test Hospitals
Smoke Control Systems Under Normal PowerAll fans and AHUs return to their normal
operation.All dampers return to their normal operation
04/18/23 21
Examples of Integrated System Test Laboratories and VivariumsAir Handling Units (AHUs) and Exhaust Systems integrated
at the lab or VivariumVerify all room pressures are stabilized
HVAC Systems with Emergency Power Air Handling Units (AHUs) and associated Exhaust
systemsStart under emergency power with correct rotation (If
the control system has UPS power the control program will require additional programming to avoid alarms and be able to start the systems)
Verify all control loops are operationalVerify all dampers are operationalVerify all valves are operational
04/18/23 22
Examples of Integrated System Test Laboratories and Vivariums
Verify startup follows the specified start procedure and how long it takes to establish all room pressuresReview the transfer switch time and which
systems are assigned to each transfer switchBe careful with rooms that are to be positive, when
the sequence requires the exhaust system to be operational before the supply systems are allowed to start
On large manifold systems (both supply and exhaust) trending may be required on all AHUs, EFs, room pressurization, alarms, and control loops
04/18/23 23
Examples of Integrated System Test Laboratories and Vivariums
Return to normal powerRestart under normal power (If the control
system has UPS power the control program will require additional programming to avoid alarms and start the systems)
All control loops are operationalAll dampers are operationalAll valves are operational
04/18/23 24
Examples of Integrated System Test Laboratories and Vivariums
Chilled Water PumpsStart under emergency power with correct rotationAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load systemReturn to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load system
04/18/23 25
Examples of Integrated System Test Laboratories and Vivariums
Hot Water PumpsStart under emergency power with correct rotationAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load system ,
because transfer switch timing and restartReturn to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient coils are operational to properly load system ,
because transfer switch timing and restart
04/18/23 26
Examples of Integrated System Test Laboratories and Vivariums
Chillers and Heat ExchangersStart under emergency power with correct rotationAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly load
system , because transfer switch timing and restartReturn to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly load
system , because transfer switch timing and restart
04/18/23 27
Examples of Integrated System Test Laboratories and Vivariums
Boilers and Heat ExchangersStart under emergency power with correct rotationAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly load
system, because transfer switch timing and restartReturn to normal powerRestart under normal powerAll control loops are operationalAll valves are operationalSufficient pumps are operational to properly load
system, because transfer switch timing and restart
04/18/23 28
Examples of Integrated System Test Laboratories and Vivariums
Smoke Control Systems in Labs and Vivariums are usually passive, if an AHU goes down because of an internal smoke detector the exhaust will remain operational but this test should consider the negative pressures created in the building
If there is a smoke controlVerify which fans and AHUs are off or operating as
shown on the smoke control matrix All control loops are operationalAll dampers are operational and are in the correct
position as shown on the smoke control matrix
04/18/23 29
Examples of Integrated System Test Laboratories and Vivariums
All fan stopping and starting and damper opening and closing meet NFPA 92 time constraints
All smoke barriers maintain the correct pressure relationships as shown on the smoke control matrix
Verify fans and AHUs remain operational under emergency power with correct rotation as shown on the smoke control matrix
04/18/23 30
Examples of Integrated System Test Laboratories and Vivariums
Verify all control loops remain operationalVerify dampers are operational and are in the
correct position as shown on the smoke control matrix
Verify all fan stopping and starting and damper opening and closing meet NFPA 92 time constraints
Verify all smoke barriers maintain the correct pressure relationships as shown on the smoke control matrix and meet the laboratory and Vivarium pressure requirements