Presented by
Ir John KL Chui (BIM Service Team)
Hong Kong Housing Authority 2
Agenda
Part 1: BIM in Housing Authority
Part 2: Project Showcases for BIM Applications
Part 3: Way Forward
Hong Kong Housing Authority
Statutory Submissions
Thermal Value Calculation
(RTTV)
Automated Foundation Design (SAFD)
Planning
Scheme Design
Detail Design
Statutory Submission
Construction
Post-completion
BIM & GIS Integration Daylight Analysis
Value Management
Facility Management
Construction & Safety Planning
5D BIM (QTO)
Lighting Simulation
BIM & RFID Integration
3
Part 1- BIM in Housing Authority
A. HA’s BIM Applications Encompass Full Design and Construction Cycle
Hong Kong Housing Authority
374353
364
302295
275
236220 227
248
198
150
114.6
85.268.1 60.3 59.9 64.3 60.6 61.4 54.6 52.1 49.7 44.3 40.8 41.9 39.1 34.5 32.9 31.4
206206221
195
160
8882
90
77
129109
86
5655.8
37.8 32.8 29.2 21.011.5 11.9 16.1
9.4 9.9 9.0 7.4 7.3 6.4 9.2 6.8 6.9 7.6
56.7
35.0 17.1
8.812.9 11.3 9.7 14.6
12.3 7.4 7.3 4.8 4.1 2.2 1.5 1.5 4.2
5.1 0
50
100
150
200
250
300
350
400
1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 20172018#
Accident Rate per 1000 Workers
HK Construction Industry HA New Works & Maintenance Works HA New Works HA Maintenance Works
2018# : Accident Rate per 1,000 workers
HA’s new works construction sites – 7.6Hong Kong’s construction sites – 31.42018 : Fatalities
HA’s construction sites – 4Hong Kong’s construction sites – 14
Source of information: Labour Department, Census & Statistics Department and Housing Department
# based on information up to 1st Three Quarters of 2018
4
The accident rate has been decreased from 86 nos. per 1,000 workers in 2000 to 7.6 nos. per 1,000 workers in 1st Three Quarters of 2018
Part 1- BIM in Housing Authority
B. Our Achievement on Safety
Hong Kong Housing Authority 5
BIM Project Steering Committee (BIM PSC)To plan strategically the implementation of BIM. The BIM PSC plays an important role at the management level giving direction and support to staff
BIM Working Group (BIM WG)To work on specific implementation and technical details. The BIM WG underpins the BIM PSC and is represented by all professional disciplines
BIM Service Team (BIMST)To act as central support to project teams on BIM implementation. The BIMST not only builds up in-house BIM experts, but also accelerates skill development within the department.
C. Our 3-Tier BIM Management Structure
Tier 1
Tier 2
Tier 3
Part 1- BIM in Housing Authority
Hong Kong Housing Authority 6
3D Printers
Setting up a BIM Centre at 12/F, Block 3, with meeting and training rooms to provide a dedicated venue for project teams to learn and apply BIM to their projects. The BIM Centre also serves as a showcase and meeting place for outside visitors.
Part 1- BIM in Housing Authority
D. Our BIM Centre
Hong Kong Housing Authority 7
2005
• BIM
2. PRH at Tung Tau Cottage Area East (TTCAE)
1. PRH at Tai Pak Tin Street
4. PRH at Kai Tak Site 1B
PRH at Kai Tak Site 1B
5. Footbridge at Shui Chuen O Ph.2
6. SSF at Sheung Lok Street
2019
Abbreviation: PRH stands for Public Rental Housing Development, SSF stands for Sale of Subsidized Flats Development
Part 2- Project Showcases
3. Redevelopment of Lower NgauTau Kok (II) Estate
Hong Kong Housing Authority
1. PRH at Tai Pak Tin Street, Kwai Chung Area 9H
8
Quick Facts:1. 1 no. 41-storey Domestic Block;2. 839 Flat nos; 3. Completed in 08/2013.
BIM Applications:1. 6-Day Construction Cycle
Simulation for Typical Floor;2. Safety Access Planning;3. Site Layout Planning; and4. 3D Printed ELS Model.
Part 2- Project Showcases
6-Day Construction Cycle for Typical Floor Site Layout Planning
BIM Modelling 3D Printed ELS Model
Lifting Zone Planning Safety Access Planning
Hong Kong Housing Authority
1. PRH at Tai Pak Tin Street, Kwai Chung Area 9H
9
Part 2- Project Showcases
Hong Kong Housing Authority
Part 2- Project Showcases
10
2. PRH at Tung Tau Cottage Area East (TTCAE)
Quick Facts:1. 1 no. Domestic Block;2. 990 Flats nos.; and3. Completed in 06/2014.
BIM Applications:1. 6-Day Construction Cycle
Simulation for Typical Floor;
2. Site Layout Planning; 3. ELS and its Safety
Planning; and4. 4D BIM Application and
Simulation.
The Photo View of the TTCAE Project under Construction (美東邨美德樓)
Hong Kong Housing Authority 11
2. PRH at Tung Tau Cottage Area East (TTCAE)
Part 2- Project Showcases
Hong Kong Housing Authority 12
Part 2- Project Showcases3. Redevelopment of Lower Ngau Tau Kok (II) Estate
Block 9
Block 10
Block 12
Hong Kong Housing Authority 13
Part 2- Project Showcases3. Redevelopment of Lower Ngau Tau Kok (II) Estate
Hong Kong Housing Authority 14
Refine demolition sequence & method;
Review safety measures of demolition sequence;
Workers familiarization of demolition sequence; and
Quantity of C&D wastes to be disposed of.
Part 2- Project Showcases3. Redevelopment of Lower Ngau Tau Kok (II) Estate
Installation of Supporting Props
Coring of Existing Floor Slab
Enclosing Screening during Demolition
Lifting of Precast Beams
Bay-by-Bay Demolition Simulation
Lifting of Wall Panels
Hong Kong Housing Authority
Removal of Non-structural Partition19
Part 2- Project Showcases3. Redevelopment of Lower Ngau Tau Kok (II) Estate
Lifting Frame for Removal of Precast Slabs (1 of 2)
Lifting Frame for Removal of Precast Slabs (2 of 2)
Temporary Scaffolding Supports to ensure Stability (1 of 2)
Temporary Scaffolding Supports to ensure Stability (2 of 2)
Hong Kong Housing Authority
Removal of Non-structural Partition19
Part 2- Project Showcases3. Redevelopment of Lower Ngau Tau Kok (II) Estate
Hong Kong Housing Authority 17
4. PRH Development at Kai Tak Site 1B
Quick Facts:1. 9 nos. Domestic Blocks;2. 8,164 Flat nos; and3. Completed in 09/2013.
BIM Applications:1. 6-Day Cycle Floor Construction;2. Installation and its Safety
Planning of Volumetric Precast Components; and
3. Maintenance Access Planning at Roof Level.
Part 2- Project Showcases
The Photo View of the Kai Tak Site 1B (德朗邨)
Maintenance Access Planning for PV Panels at Roof Level
Hong Kong Housing Authority 18
Part 2- Project Showcases
4. PRH Development at Kai Tak Site 1B
1. Lifting of Volumetric Precast Bathrooms
3. Installation of all other Precast Components
2. Base Connection of the Volumetric Precast Bathrooms
4. Wall Rebar Fixing and Erection of Large Panel Formworks
Hong Kong Housing Authority 19
Part 2- Project Showcases
4. PRH Development at Kai Tak Site 1B
Hong Kong Housing Authority
5. Footbridge of PRH Development at Shui Chuen O Ph. 2, Shatin Area 52
20
Quick Facts of the Footbridge:1. 78m Long Single-span;2. 51m Height Lift Tower;3. Natural Slope and Stream nearby; and4. Congested Construction Space.
BIM Applications:1. Footbridge Construction Sequence
Analysis; 2. Safety Measures Planning; and3. Clashing Analysis.
Part 2- Project Showcases
Hong Kong Housing Authority 21
5. Footbridge of PRH Development at Shui Chuen O Ph.2, Shatin Area 52
Part 2- Project Showcases
Hong Kong Housing Authority 22
78M
51M
Part 2- Project Showcases
BIM modelling of the Footbridges and its surrounding slopes and environment.
Photo showing the real environment
Photo showing the busy highways and congested site
5. Footbridge of PRH Development at Shui Chuen O Ph. 2, Shatin Area 52
Hong Kong Housing Authority 23
4D Construction Sequence Analysis
Part 2- Project Showcases
The Photo showing the Erection of Temporary Supporting Steel Structure
Simulation of Temporary Supporting Steel Structure.
The Photo showing the Erection of Temporary Supporting Steel Structure
5. Footbridge of PRH Development at Shui Chuen O Ph. 2, Shatin Area 52
Hong Kong Housing Authority 24
Part 2- Project Showcases
5. Footbridge of PRH Development at Shui Chuen O Ph. 2, Shatin Area 52
Hong Kong Housing Authority 25
Quick Facts:1. 3 nos. Domestic Blocks;2. 1 no. Carport Podium;3. 603 Flat nos; and4. Completed in 2019.
BIM Applications:1. 4D BIM Modelling and
Applications;2. Construction and Safety Planning
of Multiple Activities in a Congested Site;
3. Demonstration of Removal of an Existing Vertical “Soil-Nailed” Retaining Wall; and
4. ELS/Foundation Works Sequencing and its Safety Planning.
Part 2- Project Showcases6. Sale of Subsidized Flat (SSF) at Sheung Lok Street, Homantin
The Photo View of the Completed SSF Project, now named as “冠德苑”
Full BIM Modelling of the Project
Hong Kong Housing Authority 26
Part 2- Project Showcases6. Sale of Subsidized Flat (SSF) at Sheung Lok Street, Homantin
Hoarding and Gantry Planning
Tower Crane and other Machinery Positioning
Temporary Platform for Heavy Machinery for the Soldier-Piled Walls.
Existing Soil-Nailed Retaining Walls to be Removed and Re-constructed
Positioning of Single-boarded fencing
Recompaction of the Existing Filled Slope
Hong Kong Housing Authority 27
Part 2- Project Showcases6. Sale of Subsidized Flat (SSF) at Sheung Lok Street, Homantin
Demolition Sequencing of Existing Soil-nailed Retaining Walls
Hong Kong Housing Authority 28
Part 2- Project Showcases6. Sale of Subsidized Flat (SSF) at Sheung Lok Street, Homantin
Demolition Sequencing of Existing Soil-nailed Retaining Walls
1. Installation of push-pull adjustable props
2. Lower the level and frame cut the exposed soil nail
3. Hang the wall panel by Mobile Crane 4. Remove the separated wall panels.
Hong Kong Housing Authority 29
Part 2- Project Showcases6. Sale of Subsidized Flat (SSF) at Sheung Lok Street, Homantin
Hong Kong Housing Authority 30
1) There is imminency to do BIM ourselves. The time is right, things are ready. “Learn how to swim before the tide come.”
3) Cultivate the culture of using BIM for Safety in the Department; and
2) Encourage all stakeholders (i.e. Clients, Main Contractors, Consultants) to apply BIM in the field of Safety and Construction Planning.
4) Trainings.