MAINTENANCE SERVICE CONTRACT REVISION DETAILS A Issued for Review 11/02/14 Tanya Janjua Paul Andrews Hammad / John Bryce REV DESCRIPTION DATE PRPD CHKD APPD Electronic File Name: Doc Size: A4 DOCUMENT DETAILS EMPLOYER CONTRACT NO. : PROJECT TITLE :MAINTENANCE SERVICE CONTRACT EMPLOYER : CONTRACTOR : Petrofac International (UAE) LLC CONTRACTOR JOB NO. : PROJECT DOCUMENT NO. : CATEGORY : X REVISION NO.: A No. of pages (Incl. Cover Sheet) : 5 DOCUMENT DESCRIPTION : CTR 3 - I01-010A - PRESSURE SWITCH FUNCTION TEST

Upload: njenns

Post on 16-Nov-2015

6 views

Category:

Documents


1 download

DESCRIPTION

test

TRANSCRIPT

  • MAINTENANCE SERVICE

    CONTRACT

    REVISION DETAILS

    A Issued for Review 11/02/14 Tanya Janjua Paul Andrews Hammad / John Bryce

    REV DESCRIPTION DATE PRPD CHKD APPD

    Electronic File Name: Doc Size: A4

    DOCUMENT DETAILS

    EMPLOYER CONTRACT NO. :

    PROJECT TITLE :MAINTENANCE SERVICE CONTRACT

    EMPLOYER :

    CONTRACTOR : Petrofac International (UAE) LLC

    CONTRACTOR JOB NO. :

    PROJECT DOCUMENT NO. :

    CATEGORY : X REVISION NO.: A No. of pages (Incl. Cover Sheet) : 5

    DOCUMENT DESCRIPTION : CTR 3 - I01-010A - PRESSURE SWITCH

    FUNCTION TEST

  • Title : I01-010A - PRESSURE SWITCH FUNCTION TEST

    Rev : A

    Date : 11/02/14

    Page : 2 of 5

    REVISION DESCRIPTION SHEET

    Rev. Para. Revision Description

    A Issued for review

    Hold No.

    Para. Description of Hold

  • Title : I01-010A - PRESSURE SWITCH FUNCTION TEST

    Rev : A

    Date : 11/02/14

    Page : 3 of 5

    1.0 SCOPE

    The purpose/scope of this maintenance task is to conduct a function test of the device in order

    to assure its accuracy and verify the correct operation of the device and its loop components.

    The performance and condition of the device and its loop components will determine whether

    further maintenance or calibration is required.

    This task should be undertaken by trained personnel only.

    2.0 PRE-ROUTINE CHECKS

    Check the historical records, any repairs performed since the last maintenance and note any

    outstanding repair work.

    Check and ensure that the tag / equipment identification is in place, secure, correct and legible

    for the equipment under review and that it corresponds with the data in SAP.

    If the PM content is incorrect or changes to the frequency, technical content, resources and

    scheduling is required, raise SAP change request in accordance with procedures.

    Obtain applicable permit to work and carry out a tool box talk prior to commencement of work.

    3.0 EQUIPMENT REQUIRED

    Pressure calibrator of type appropriate to the instrument under test.

    Pressure switch operation and maintenance manual (O&M manual).

    4.0 FUNCTION TEST

    Notify the operations control centre (OCC) and/or other authorities of the activities to be

    performed.

    Precautions

    Where this instrument forms part of safety or trip system, refer to the appropriate cause and

    effect drawings prior to inhibiting all relevant trips. Initiate all relevant inhibits/overrides and

    confirm the correct input inhibits/overrides have been applied and logs updated prior to

    commencing work.

  • Title : I01-010A - PRESSURE SWITCH FUNCTION TEST

    Rev : A

    Date : 11/02/14

    Page : 4 of 5

    Inspection

    Inspect the device for evidence of damage, corrosion and contamination. Check cables and

    glands for security / damage and ensure identification is in place, secure, correct and legible.

    If equipment is Ex carry out Ex Close Inspection as per work instruction Ex-004A.

    Function Test

    As-found

    a. Isolate the switch from the process medium and depressurise through the vent / drain

    point, prior to carrying out calibration.

    b. Apply test pressure and verify that the switch trip point operates at the correct setting.

    c. On completion of calibration remove pressure test source and close calibration point,

    and any vent / drain isolation points.

    d. During Switch Calibration verify that the trip and alarm points operate at the correct

    settings and that any remote indications of alarms on the control system are correct.

    Note: Any differences found on tag number, range, set points etc, between field,

    control system and associated documentation needs to be resolved.

    e. If the error is within the range tolerance for the instrument then this test has passed

    and shall be recorded in SAP as OK.

    As-left

    f. If the error is outside the range tolerance then this test has failed. The instrument

    should then be adjusted and an as-left calibration recorded.

    g. Reset alarms, remove any inhibits and confirm that indication have returned to the

    healthy state.

    h. Ensure that the relevant personnel are informed that the test is complete.

    After Test

    Ensure equipment is left in a safe condition and cleanup worksite.

    Return all equipment to normal operating state, verify operation & notify the OCC and/or other

    authorities when tasks are complete.

    Close out any permits raised for the work.

  • Title : I01-010A - PRESSURE SWITCH FUNCTION TEST

    Rev : A

    Date : 11/02/14

    Page : 5 of 5

    5.0 REPORTING

    Complete the PM Work Order in SAP; raise a Notification for any follow up corrective work and

    flag the SAP Review for any proposed changes to the maintenance tasks or data all in

    accordance with the SAP process.

    Any serious defects must be reported to Line Management and the Instruments Support

    Engineer.